SINK-DRYWALL RFI’s
What is the length of each wall in the area described in ITEM number 0001?
A. 18 Feet and 24 feet
Is there a preferred brand for the floor molding, Johnsonite or Roppe?
A. The color is Burnt Umber
The solicitation requests a trim for the ceiling and 2.2.5 states to verify with COR and project manager. Is there a preferred brand, piece, or color? Are you just requesting, and L-type trim painted in the same color as the wall or not painted and left white?
A. There is no preferred brand or piece. L-type trim painted in white would be good. To be settled on site.
What is the height of the ceiling in the first and second buildings?
A. B2100 CE = 9’0” / B1120 LRS = 9’0”
Does the 800SF of wall encompass the wall space for both buildings or only the first?
A. This is only for the CE Building, Bldg 2100
The laminate countertop is 8’ long but the wall where it is to be installed is only 6’4” should cutting the countertop be included in the bid or will this be done prior?
A. Yes