A02 PWS B250 Fire Restoration.docx
DOCX document 1 MB Posted
- Attached to
- B250 Fire Restoration
- Solicitation number
- W50S7F24Q0011
About this file
This performance work statement and related federal contract opportunity request fire restoration and cleaning services for Building 250 at the 148th Fighter Wing in Duluth, Minnesota. Services include inspecting and assessing fire damage, removing smoke odor and soot from all surfaces, and cleaning ducted HVAC systems. Quotes are due by March 7, 2024 and the contract is a 100% small business set-aside under NAICS 236220 with a $45 million size standard. The selected contractor must have a SAM registration and past performance is desired.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Visitor Request Form 66.pdf | ||
| SCA WD 2015-4939.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT
FOR
B250 FIRE RESTORATION SERVICES
Contents
| 1. | Scope of Work | 2 |
| 2. | Background | 2 |
| 3. | Performance of Services | 2 |
| 4. | Government Personnel | 3 |
| 5. | General Responsibilities | 3 |
| 6. | Fire Damage Restoration Services | 4 |
1. Scope of Work
1.1 The contractor shall provide all personnel, equipment, tools, materials, supervision and quality control necessary to perform fire restoration and cleaning services as defined in this Performance Work Statement (PWS). Location of services provided is Building 250 (B250) at the 148th Fighter Wing in Duluth, MN.
1.2 The objective is to restore B250 to pre-fire condition to include the following:
· Inspection and assessment of facility to determine degree and extent of damage
· Removal of smoke odor and soot from all surfaces including walls, ceilings, floors, and other surfaces
· Cleaning of the ducted HVAC systems
2. Background
In the early morning hours on 14 Feb 24, smoke was reported coming from the medical wing of B250. Firefighter personnel extinguished the fire without water and started building ventilation procedures. The fire alarm system did not activate immediately as there was only heat detectors in the immediate area. Therefore, the HVAC systems were ventilating smoke and soot for some time. The cause of the fire was a faulty mobile device charging station.
3. Performance of Services
3.1 The contractor shall provide services between the hours of 0700-1600 on Monday through Friday, excluding federal holidays. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential.
3.2 The contractor shall develop and submit a work schedule to the Contracting Officer (KO) for approval no later than seven calendar days prior to the start of this contract. The schedule shall indicate as a minimum, dates and times the work shall be performed.
3.3 All contractor personnel will be required to pass a background check for Base access. All contractor personnel shall carry proper identification at all times and shall be subject to security checks as deemed necessary. The contractor shall ensure compliance with all regulations and orders of the installation, which may affect performance. The Government reserves the right to direct the removal of an employee for misconduct or security reasons. Removal of contractor employees for any reason does not relieve the contractor from responsibility of total performance of this contract.
3.4 All contractor employees, to include subcontractor employees, requiring access to US Government installations, facilities and controlled access areas shall complete AT Level I training within 15 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. AT Level I may be accomplished by a Level I qualified instructor; completing the Force Protection computer-based training (CBT) course on the Advanced Distributed Learning System (ADLS) or Joint Knowledge Online at http://jko.jten.mil.
3.5 The contactor shall designate a contract manager (CM) who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the Contracting Officer’s Representative (COR) to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
3.6 All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4. Government Personnel
The COR assigned to this PWS and contract will be Maj Ben Hayes, benjamin.hayes.6@us.af.mil, 218-788-7885, 148th Civil Engineer Squadron.
5. General Responsibilities
5.1 The contractor shall be responsible for safeguarding all government property. Damages incurred due to contractor negligence shall be repaired or replaced with the approval of the KO, at no cost to the government. Damages to real property shall be corrected within seven working days with materials of like type, quality, and finish by skilled craftsmen of the trades required. The contractor shall report all damages incurred immediately to the KO or COR.
5.2 The contractor shall maintain the work area in a neat and orderly fashion. All debris must be disposed of in an approved location. The contractor must leave the workspace in a broom clean condition upon completion of the project.
5.3 The contractor shall be responsible for the vehicles required in the performance of the requirement of this contract. All vehicles shall be in operable condition and meet all local and Base registration and safety requirements.
5.4 Any materials used shall be new and installed as per manufacturer’s recommendations as well as state, federal, and local regulations. A list of chemicals used on the project shall be furnished to the COR at the completion of the project. The list must include cleaning agents, lubricants, oils, and extinguishing agents.
6. Fire Damage Restoration Services
6.1 Inspect and evaluate the entirety of B250 for potential damage as a result of fire and smoke to identify surfaces, facility components, and equipment that may need treatment.
6.2 At a minimum, the contractor shall complete the following surface cleaning and restoration services in areas C and D, as depicted in Figure 1:
· Evaluate sensitive materials and equipment (i.e. IT assets, medical equipment, etc.) that may be damaged as a result of smoke and soot particles. Provide recommendations to COR for restoration options.
· If required, remove contents from the building for cleaning and restoration.
· If possible, salvage all product stock, equipment, and machinery and return to government.
· Remove any charred contents that may seal in smoke such as insulation or wood. Remove and replace acoustic ceiling tiles and clean grid.
· Clean all flooring surfaces. Evaluate carpets and floor coverings that may be unsalvageable and need to be removed. Provide recommendations to the government for restoration.
· Treat all affected surfaces for smoke odors and seal to keep any leftover odors from leaking back into the building.
· Clean, eliminate odors, and deodorize surfaces to pre-fire condition.
· Return government items that were removed for cleaning to their original location and help restore normal operation in the building.
· Provide recommendations to government for required repairs outside the scope of this PWS.
Figure 1: Approximate Scope of Surface Cleaning Services (19,000 SF)
6.3 The contractor shall complete comprehensive cleaning and restoration of ducted HVAC systems depicted in the figures below. Clean all ductwork and associated components from diffusers to air handling units (AHU). Government personnel will replace AHU filters.
Figure 2: Area A HVAC Layout
Figure 3: Area B HVAC Layout
Figure 4: Area C HVAC Layout
Figure 5: Area D HVAC Layout image2.png image3.png image4.png image5.png image6.png image1.emf