W50S7523Q0006_Expand_Restrooms_SOW.pdf
PDF 10 MB Posted
- Attached to
- 146 AW Expand Bldg 701 Women's Restroom
- Solicitation number
- W50S7523Q0006
- Issued by
-
Department of the Army National Guard
About this file
This Scope of Work document outlines requirements for expanding an existing women's restroom at Building 701 for Solicitation Number W50S7523Q0006 issued by the Department of the Army National Guard. The contractor will be responsible for renovating approximately 150 square feet of existing space to add three additional stalls, modifying plumbing lines, installing new fixtures and finishes, and repainting the restroom. The work must be completed within 90 calendar days of award. Bids are due by April 15, 2023, with award anticipated by May 1 and work to start no later than June 1. The contractor will be responsible for all associated labor, materials, equipment, and permits to complete the project in accordance with the specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W50S7523Q0006_Expand_Restroom_Sign_In.pdf | ||
| W50S7523Q0006_Expand_Restrooms_1442.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Expand Women’s Restroom B701
PROJECT NO.: DJCF232539
12 April 2023
146TH AIRLIFT WING
CHANNEL ISLANDS AIR NATIONAL GUARD, PORT HUENEME, CA
CALIFORNIA AIR NATIONAL GUARD
TECHNICAL PROVISIONS
TABLE OF CONTENTS:
1. DESCRIPTION OF SERVICES
2. SITUS OF WORK
3. PROJECT SPECIFIC REQUIREMENTS
4. GENERAL REQUIREMENTS
5. SUBMITTALS
1. DESCRIPTION OF SERVICES
1.1. Objectives: The purpose of this project is to expand the Women’s Restroom in Building 701 on Channel Islands ANG Station, CA.
1.2. This Statement of Work describes Contractor requirements for the project titled “Expand Women’s Restroom B701.” The Contractor is responsible for work required to complete all items listed in this Statement of Work to include but not limited to all necessary labor, furnishing and installation of parts/materials, tools, equipment, planning, scheduling, and coordination. The Contractor shall comply with current NEC, NFPA, California Universal Plumbing Code, and applicable United Facilities Criteria (UFC). The Contractor shall provide the Government a complete and usable product at the completion of the project.
All information included in this document, along with the instructions and standards referenced in the document, should be considered as part of the Statement of Work.
2. SITUS OF WORK
2.1. All work will occur at Channel Islands Air National Guard Station, 4146 Naval Air Road Port Hueneme, CA 93041, Building 901
3. PROJECT SPECIFIC REQUIREMENTS
3.1. The Contractor shall:
3.1.1. Attend a Pre-Construction Site-Visit to assess scope of work prior to bidding on this project. All work under this division shall be executed in a thorough professional manner by competent and experienced workmen licensed to perform the work specified. All work shall be installed in strict conformance with manufacturer’s requirements and recommendations. Equipment and materials shall be installed in a neat and professional manner and shall be aligned, leveled, and adjusted for satisfactory operation. Material and equipment shall be new, shall be of the best quality and design, shall be current model of the manufacturer, shall be free from defects and imperfections and shall have markings or a nameplate identifying the manufacturer and providing sufficient reference to establish quality, size, and capacity. Material and equipment of the same type shall be made by the same manufacturer and be Underwriters Laboratory (UL) Listed.
3.1.2. Remove and dispose of existing wall tile, sink, countertop, cabinet, electrical outlet back to the originating source, and place a blank cover where existing outlet was, floor tile, carpet, plumbing to point of connection with wall, and wall-mounted white board. Remove and dispose of two (2) existing 2’x 2’ HVAC ventilation: one
(1) supply and one (1) return vent covers.
WALL/DOOR/ HARDWARE
3.1.3. Construct metal stud wall with 5/8” gypsum board double sided sheetrock
(Waterproof Drywall for Bathroom(s)) with constructed wall height that extends beyond existing acoustic ceiling grid by 2 feet. COR must approve material(s) selection prior to installation. Wall shall be flush with existing adjacent wall office room. Provide and install insulation within wall in accordance with Title 24 code requirements.
3.1.4. Finish drywall paint and trim at door to match appearance of existing adjacent walls. Repair interior wall(s) surface(s) damage stemming from removal of existing items. Prepare, patch, and paint. COR must approve materials and color selection prior to installation.
3.1.5. Furnish and install an exterior floor mounted door-stopper and door sweep.
3.1.6. Install matching cove base on opposite side of the newly constructed wall
3.1.7. Apply one coat of primer and two coats of paint to walls. Contractor will take all necessary precautions to protect adjacent areas and all existing installed equipment while painting.
CEILING TILE/LED LIGHTING/EXIT SIGN
3.1.8. Contractor is responsible for taking all necessary actions to install the ceiling tiles in a neat, leveled, and professional manner within Room 211 and on the other side of constructed wall Room 210.
3.1.9. Furnish and install (1) new battery backup exit sign located at door. Contractor shall conduct field survey to determine available power capabilities, and comply with the latest version of the National Electrical Code (NEC). Contractor shall ensure that all outlets inside of the newly constructed bathroom are Ground Fault Circuit Interrupters (GFCI) and comply with the latest version of the NEC. COR must approve materials and color selection prior to installation.
3.1.10. Furnish and install three (3) new recessed mounted 2’ x 2’ LED lights to match existing lighting plan. Contractor shall conduct field survey to determine available power capabilities.
3.1.11. Furnish and install a new bathroom exhaust fan where the existing HVAC return was located, and all necessary ducting for venting to the outside of the building.
Penetrate the side of the building to exhaust bathroom fumes, reference Attachment
1. COR must approve materials prior to installation.
FLOORING/PLUMBING
3.1.12. Replace carpeted area with slip resistant quartz flooring with 4” high integral cove base. Color to be approved by the COR. Contractor will take necessary precaution to preserve the pre-construction condition of the existing flooring. COR must approve materials and color selection prior to installation.
3.1.13. Install doorway transition strip. COR must approve materials and color selection prior to installation.
3.1.14. Install waterproof bathroom wall tile for area that will cover newly added urinal, toilet, and pedestal sink. COR must approve materials and color selection prior to installation.
3.1.15. Furnish and install one (1) new toilet with associated fixtures, and urinal with associated fixtures in accordance with the most current United Facilities Criteria (UFC) 3-420-01 Plumbing Systems Code, and International Plumbing Code (IPC).
Conduct field survey to determine available plumbing/sewer capabilities (See Attachment 1 for reference) and ensure compliance with current IPC. Contractor shall provide new bathroom floor drain, and sewer line in accordance with UFC 3- 420-01 Plumbing Systems, and IPC for new toilet and urinal. Contractor shall intercept 4” Sewer Drain shown in Attachment 1. COR must approve materials and color selection prior to installation. Note: Contractor will have to penetrate existing walls, and trench concrete flooring in order to accomplish installation of new floor drain and connection/interception to existing 4” Sewer Line.
3.1.16. Contractor shall provide Pedestal Bathroom Sink with fixtures, and wall mounted mirror. COR must approve materials and color selection prior to installation.
3.1.17. Install new sanitary sewer vent pipes behind walls in accordance with most current UFC 3-420-01 Plumbing Systems, and International Plumbing Code (IPC).
Conduct field survey to determine is current sewer vent pipes can be intercepted and used; ensure compliance with current UFC 3-420-01 Plumbing Systems, and IPC.
3.1.18. Provide ½’ Hot and Cold Water Stub-outs with isolation valves for Room 211, and a 2” Sewer line as shown in Attachment 1. Contractor shall ensure compliance with current UFC 3-420-01 Plumbing Systems, and IPC.
3.1.19. Contractor shall thoroughly clean all surfaces to remain, replace/repair damaged gypsum board/concrete from tile removal and installation of new floor drain.
Contractor shall prepare surfaces for either tile/painting or floor installation, and return facility to its pre-construction condition. Contractor shall remove all debris and protective material. Repair any damage caused by construction per COR’s direction.
3.2. The Government must approve all materials and execution plans prior to implementation.
3.3. Performance Period: The Contractor has 120 Days from the Notice-to-Proceed (NTP) to complete all work on the project. The NTP will be issued at the Pre-Construction Conference.
4. GENERAL REQUIREMENTS
4.1. The Contractor shall attend a Pre-Construction Conference that will be scheduled after award. At a minimum, the Contractor shall have the Project Manager and Site Superintendent attend the meeting. The Contractor shall provide the following documents at the Pre-Construction Conference.
4.1.1. Project Construction Schedule
4.1.2. Contract Schedule of Values
4.1.3. Safety Plan
4.1.4. Quality Control Plan
4.2. The Contractor shall provide all labor, tools, materials, equipment, transportation, removal of debris and trash, supervision, and management (except as specified as Government Furnished) necessary to install/repair and test the requirements identified in the Statement of Work as located at Channel Islands Air National Guard Station, Port Hueneme, California.
4.2.1. Any waste of excess material resulting from any contract requirement shall be removed and disposed of by Contractor at a proper disposal site off Channel Islands Air National Guard Station. Disposal, discharge, deposit, dumping, spilling, leaking, or placing of any materials, wastes, effluents, trash, garbage, oil, grease, paint, chemicals, etc. must be notified to and coordinated with the installation Environmental Office. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material, restore the area to the condition of the adjacent undisturbed site at Contractor’s expense.
4.2.2. The Contractor shall comply with all Air Force, OSHA, and building code requirements that are abiding by the Federal Government and State of California.
4.2.3. Any additional work completed by the Contractor without approval by the Contracting Officer Representative (COR) shall be at the Contractor expense.
4.2.4. The Contractor shall submit material approval form to the COR within 10 days of contract NTP date. No materials shall be ordered without material approval of the Contracting Officer and the COR.
4.3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. The Government will provide water, sewer and electrical connections. Unsecure outdoor storage area at the base is available and must be requested through the COR prior to utilizing. Secured storage is the responsibility of the Contractor.
4.4. QUALITY CONTROL. Contractor shall develop and maintain a quality control program to ensure work is performed as described in this Statement of Work and in accordance with all local, State, and Federal rules.
4.5. PROGRESS REPORTING. As work progresses, the Contractor will enter the actual progress on the progress report, (NGB Contract Progress Report, AF Form 3065 or similar) and submit to the COR on a weekly basis. For modifications that result in price increases and will affect the progress schedule and report, a separate NGB Contract Progress Report (or similar form) is used for each modification since they are normally individual line items and invoicing must be by CLIN to properly distribute funding.
4.6. QUALITY ASSURANCE. The Government will maintain a Quality Assurance Program to ensure work is performed as described in this Statement of Work and in accordance with all local, State, and Federal rules. The Government Project Manager will manage the Government’s QA program.
4.6.1. Periodic inspection of the work in progress will be accomplished by a representative of the Government for the purpose of ensuring the Contractor is conforming to the requirements of the Statement of Work as well as verification of conformance with all safety, environmental, and employment regulations, practices and guidelines.
4.6.2. A one hundred percent (100%) inspection of the finished product will be accomplished. This inspection will be a two-part inspection consisting of a pre-final and a final inspection walkthrough by the Contracting Officer, Contracting Officer Representative, safety, environmental, fire department, security, anti-terrorism officer, user, contract manager and a representative of the associated trades to be inspected.
4.6.3. Upon completion of the pre-final inspection, a pre-final inspection report will be prepared by the COR and forwarded to the Contractor. All discrepancies noted in the pre-final inspection report must be corrected by the Contractor to the satisfaction of the Contracting Officer within 10 days of receipt of the report.
4.6.4. The Contractor will be held accountable for the successful execution of the project in accordance with the contract documents. Failure to meet the requirements of the contract may result in liquidated damages charged to the Contractor at a pre-determined rate.
4.7. HOURS OF OPERATION. The hours of work shall be between 7:00 a.m. and 5:00 p.m.
Monday through Friday unless otherwise prescribed by this Statement of Work. Work shall not be performed on Weekends (except during RSDs) and Federal Holidays without prior coordination from the COR. NOTE: No work shall commence without prior coordination with the Base Facility Manager and the COR. Work within each project location shall not commence without prior coordination of the applicable building manger, the Contractor, and COR.
4.8. The Contractor shall schedule and arrange work with each Building Manager or end user representative at least five (5) working days before beginning work in each building or project location. The Contractor shall make every effort to minimize the interference and effect on the Government mission.
4.9. PRIOR TO ANY WORK STARTING ON A FACILITY OR SITE LOCATION, A
MANDATORY WALK THROUGH SHALL BE SCHEDULED AND
ACCOMPLISHED WITH THE COR OR CONSTRUCTION INSPECTOR FOR
EXPLANATION AND REQUIREMENTS OF WORK WITHIN EACH BUILDING OR
SITE LOCATION.
4.10. ANTITERRORISM/OPERATIONS SECURITY/INFORMATION PROTECTION.
This standard language is for Contractor employees with an area of performance within Government controlled installation, facility, or area.
4.10.1. Access and General Protection/Security Policy and Procedures. Base security personnel require that all personnel entering the installation are cleared for access.
The Contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The Contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The Contractor will provide first name, last name, driver’s license number and applicable vehicle data for all personnel accessing the base. The Contractor shall submit this information to the COR NLT ten (10) working days prior to the date of required access. The Contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Personnel must maintain a valid driver’s license, vehicle registration and proof of insurance always while on the base. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
4.10.2. For Contractors that do not require Common Access Card (CAC) but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors' employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 10-245, AFI 31-101 and AFMAN 31- 113), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by Government representative).
4.11. MATERIAL SAFETY DATA SHEETS, AND LABELS. The Contractor shall maintain a copy of the Environmental Protection Agency or State Registered Labels, plus Material Data Sheets for all paints, primers, solvents, inhibitors, or solutions used in connection with this contract; Material Data Sheets are also required for all hazardous materials defined in Federal Standard 313c. Identical back-up copies of these documents shall be given to the Base Safety Officer, Environmental Office, and the Contracting Officer prior to the start of any work.
4.12. TECHNICAL COMPETENCE AND ABILITY. If requested by the Government, the Contractor shall provide proof of technical competence and experience in the area of expertise required by this Statement of Work. The Contractor shall be prepared to submit documents providing proof of successful competence such as training certificate or accreditations from recognized industry leaders. Contractors shall also be prepared to provide proof of successful project experience through references of former clients in related project types.
4.13. DIMENSIONS AND QUANTITY. All dimensions and quantities provided in the Statement of Work are estimates only. They are provided as a courtesy for Contractors to estimate the magnitude of work or materials necessary to complete a task. They are not intended to be final measurements. The Contractor is responsible for verifying all dimensions and quantities in the field prior to starting work.
4.14. WARRANTY. The Contractor shall guarantee all workmanship and materials covered under this Statement of Work for a period of no less than 1 year from the date of project acceptance. This Contractor’s warranty shall be included with any manufacturer’s warranties that accompany materials or systems installed as part of this Statement of Work.
4.15. CONTRACTOR PAYMENT. Contractor shall submit an application and certificate for payment every 30 days or at the end of the performance period, whichever comes first.
4.15.1. The payment request shall include the following:
4.15.1.1. Contractor’s application for payment
4.15.1.2. Schedule of values
4.15.1.3. Contract progress report
4.15.1.4. Contract progress schedule
5. SUBMITTALS
5.1. All material approval submittals shall be forwarded to the COR and transmitted with an AF Form 3000. When submitting on a finish, texture or other material characteristic where a photograph is unacceptable, the Contractor shall provide a sample of the material for review and approval along with the product cut-sheet.
5.1.1. Architectural/Mechanical
5.1.1.1. Tile
5.1.1.2. Drywall/Gypsum
5.1.1.3. LED Lights
5.1.1.4. Toilet/Urinal
5.1.1.5. Paint
5.1.1.6. Flooring
5.1.1.7. Piping
5.1.1.8. Drain(s)
5.1.1.9. Sink
5.1.1.10. Faucets
5.1.1.11. Vents
5.1.1.12. Exit Sign
5.1.1.13. GFCI’s
6. CLOSEOUT DOCUMENTATION
6.1. 10% Retainage will be released upon receipt of the following items:
6.1.1. Contractor workmanship letter of warranty up to one year.
6.1.2. Letter of Warranty.
6.1.3. Beneficial occupancy/usable completion date (if applicable).
6.1.4. Operating Tests performed and witnessed.
6.1.5. Pre-Final/Final inspections and completion of punchlist.
6.1.6. Training Sessions scheduled and user notified.
6.1.7. Certificates of no debts to suppliers and vendors.
6.1.8. As-Built Documentation (as needed) and O&M Documentation.
6.1.9. Electronic pictures showing the area before and after repair.
6.1.10. Recycling or Landfill proof of disposition document (if available).
1258283879N Highlight
Rectangle
1258283879N Callout
WOMEN'S BATHROOM
1258283879N Line
1258283879N Line
1258283879N Callout Men's Locke Room
1258283879N Rectangle
1258283879N Rectangle
1258283879N Rectangle
1258283879N Callout Men's Restroom
1258283879N Highlight
1258283879N Highlight
Polygon
1258283879N Rectangle
1258283879N Callout Proposed Restroom Location Room 211, approximately 10'x10' room.
1258283879N Callout Provide Stub-out for hot and cold water lines with isolation valves. Provide Stub-out for sewer line per SOW.
1258283879N Callout Provide restroom exhaust vent. Penetrate side of building and route exhaust plenum outside.
1258283879N Highlight
1258283879N Highlight
1258283879N Callout Route new sewer line to existing 4" sewer line in compliance with regulations/codes outlined in SOW.
1258283879N Rectangle
Line
Text Box Women's Rest Room. See drawing P-2 for reference.
Room 211. See drawing P-3 for reference.
Room 211. See drawing P-3 for reference.
1258283879N Callout Remove and replace with exhaust fan per SOW.
Below Room 211. See drawing P-3, P-5, and M-2 for reference.
| Expand Women's Restroom B701_2.pdf |
| Binder6.pdf |
| image000000 |
| image000001 |
| image000002 |
| Expand Women's Restroom B701_1.pdf |
| Expand Women's Restroom B701_1.pdf |
| image.pdf |
| Binder3.pdf |
| image000003 |
| image000004 |
| image000005 |
| image000006 |
| image000007 |
| image000008 |
| image000009 |
| Expand Women's Restroom B701.pdf |
| 701 M-2.pdf |
| 701 M-3.pdf |
| Expand Women's Restroom B701.pdf |
| Expand Women's Restroom B701.pdf |
| 701 P-1.pdf |
| 701 P-5.pdf |
| 701 P-2 first floor.pdf |
| 701 P-3.pdf |
| 6 - SOW (Expand Women's Restroom) 20230608 Rev.2.pdf |
| 1. DESCRIPTION OF SERVICES |
| 1.1. Objectives: The purpose of this project is to expand the Women’s Restroom in Building 701 on Channel Islands ANG Station, CA. |
| 1.2. This Statement of Work describes Contractor requirements for the project titled “Expand Women’s Restroom B701.” The Contractor is responsible for work required to complete all items listed in this Statement of Work to include but not limited to ... |
| 2. SITUS OF WORK |
| 2.1. All work will occur at Channel Islands Air National Guard Station, 4146 Naval Air Road Port Hueneme, CA 93041, Building 901 |
| 3. PROJECT SPECIFIC REQUIREMENTS |
| 3.1. The Contractor shall: |
| FLOORING/PLUMBING |
| 3.1.19. Contractor shall thoroughly clean all surfaces to remain, replace/repair damaged gypsum board/concrete from tile removal and installation of new floor drain. Contractor shall prepare surfaces for either tile/painting or floor installation, and... |
| 3.2. The Government must approve all materials and execution plans prior to implementation. |
| 3.3. Performance Period: The Contractor has 120 Days from the Notice-to-Proceed (NTP) to complete all work on the project. The NTP will be issued at the Pre-Construction Conference. |
| 4. GENERAL REQUIREMENTS |
| 4.1. The Contractor shall attend a Pre-Construction Conference that will be scheduled after award. At a minimum, the Contractor shall have the Project Manager and Site Superintendent attend the meeting. The Contractor shall provide the following doc... |
| 4.1.1. Project Construction Schedule |
| 4.1.2. Contract Schedule of Values |
| 4.1.3. Safety Plan |
| 4.1.4. Quality Control Plan |
| 4.2. The Contractor shall provide all labor, tools, materials, equipment, transportation, removal of debris and trash, supervision, and management (except as specified as Government Furnished) necessary to install/repair and test the requirements iden... |
| 4.2.1. Any waste of excess material resulting from any contract requirement shall be removed and disposed of by Contractor at a proper disposal site off Channel Islands Air National Guard Station. Disposal, discharge, deposit, dumping, spilling, leak... |
| 4.2.2. The Contractor shall comply with all Air Force, OSHA, and building code requirements that are abiding by the Federal Government and State of California. |
| 4.2.3. Any additional work completed by the Contractor without approval by the Contracting Officer Representative (COR) shall be at the Contractor expense. |
| 4.2.4. The Contractor shall submit material approval form to the COR within 10 days of contract NTP date. No materials shall be ordered without material approval of the Contracting Officer and the COR. |
| 4.3. GOVERNMENT FURNISHED PROPERTY AND SERVICES. The Government will provide water, sewer and electrical connections. Unsecure outdoor storage area at the base is available and must be requested through the COR prior to utilizing. Secured storage i... |
| 4.4. QUALITY CONTROL. Contractor shall develop and maintain a quality control program to ensure work is performed as described in this Statement of Work and in accordance with all local, State, and Federal rules. |
| 4.5. PROGRESS REPORTING. As work progresses, the Contractor will enter the actual progress on the progress report, (NGB Contract Progress Report, AF Form 3065 or similar) and submit to the COR on a weekly basis. For modifications that result in price ... |
| 4.6. QUALITY ASSURANCE. The Government will maintain a Quality Assurance Program to ensure work is performed as described in this Statement of Work and in accordance with all local, State, and Federal rules. The Government Project Manager will manag... |
| 4.6.1. Periodic inspection of the work in progress will be accomplished by a representative of the Government for the purpose of ensuring the Contractor is conforming to the requirements of the Statement of Work as well as verification of conformance ... |
| 4.6.2. A one hundred percent (100%) inspection of the finished product will be accomplished. This inspection will be a two-part inspection consisting of a pre-final and a final inspection walkthrough by the Contracting Officer, Contracting Officer Rep... |
| 4.6.3. Upon completion of the pre-final inspection, a pre-final inspection report will be prepared by the COR and forwarded to the Contractor. All discrepancies noted in the pre-final inspection report must be corrected by the Contractor to the satisf... |
| 4.6.4. The Contractor will be held accountable for the successful execution of the project in accordance with the contract documents. Failure to meet the requirements of the contract may result in liquidated damages charged to the Contractor at a pre... |
| 4.7. HOURS OF OPERATION. The hours of work shall be between 7:00 a.m. and 5:00 p.m. Monday through Friday unless otherwise prescribed by this Statement of Work. Work shall not be performed on Weekends (except during RSDs) and Federal Holidays withou... |
| 4.8. The Contractor shall schedule and arrange work with each Building Manager or end user representative at least five (5) working days before beginning work in each building or project location. The Contractor shall make every effort to minimize th... |
| 4.9. PRIOR TO ANY WORK STARTING ON A FACILITY OR SITE LOCATION, A MANDATORY WALK THROUGH SHALL BE SCHEDULED AND ACCOMPLISHED WITH THE COR OR CONSTRUCTION INSPECTOR FOR EXPLANATION AND REQUIREMENTS OF WORK WITHIN EACH BUILDING OR SITE LOCATION. |
| 4.10. ANTITERRORISM/OPERATIONS SECURITY/INFORMATION PROTECTION. This standard language is for Contractor employees with an area of performance within Government controlled installation, facility, or area. |
| 4.10.1. Access and General Protection/Security Policy and Procedures. Base security personnel require that all personnel entering the installation are cleared for access. The Contractor shall comply with all applicable installation/facility access a... |
| 4.10.2. For Contractors that do not require Common Access Card (CAC) but require access to a DoD Facility and/or Installation. Contractor and all associated sub-contractors' employees shall comply with adjudication standards and procedures using the N... |
| 4.11. MATERIAL SAFETY DATA SHEETS, AND LABELS. The Contractor shall maintain a copy of the Environmental Protection Agency or State Registered Labels, plus Material Data Sheets for all paints, primers, solvents, inhibitors, or solutions used in connec... |
| 4.12. TECHNICAL COMPETENCE AND ABILITY. If requested by the Government, the Contractor shall provide proof of technical competence and experience in the area of expertise required by this Statement of Work. The Contractor shall be prepared to submit... |
| 4.13. DIMENSIONS AND QUANTITY. All dimensions and quantities provided in the Statement of Work are estimates only. They are provided as a courtesy for Contractors to estimate the magnitude of work or materials necessary to complete a task. They are... |
| 4.14. WARRANTY. The Contractor shall guarantee all workmanship and materials covered under this Statement of Work for a period of no less than 1 year from the date of project acceptance. This Contractor’s warranty shall be included with any manufact... |
| 4.15. CONTRACTOR PAYMENT. Contractor shall submit an application and certificate for payment every 30 days or at the end of the performance period, whichever comes first. |
| 4.15.1. The payment request shall include the following: |
| 4.15.1.1. Contractor’s application for payment |
| 4.15.1.2. Schedule of values |
| 4.15.1.3. Contract progress report |
| 4.15.1.4. Contract progress schedule |
| 5. SUBMITTALS |
| 5.1. All material approval submittals shall be forwarded to the COR and transmitted with an AF Form 3000. When submitting on a finish, texture or other material characteristic where a photograph is unacceptable, the Contractor shall provide a sample ... |
| 5.1.1. Architectural/Mechanical |
| 5.1.1.1. Tile |
| 5.1.1.2. Drywall/Gypsum |
| 5.1.1.3. LED Lights |
| 6. CLOSEOUT DOCUMENTATION |
| 6.1. 10% Retainage will be released upon receipt of the following items: |
| 6.1.1. Contractor workmanship letter of warranty up to one year. |
| 6.1.2. Letter of Warranty. |
| 6.1.3. Beneficial occupancy/usable completion date (if applicable). |
| 6.1.4. Operating Tests performed and witnessed. |
| 6.1.5. Pre-Final/Final inspections and completion of punchlist. |
| 6.1.6. Training Sessions scheduled and user notified. |
| 6.1.7. Certificates of no debts to suppliers and vendors. |
| 6.1.8. As-Built Documentation (as needed) and O&M Documentation. |
| 6.1.9. Electronic pictures showing the area before and after repair. |
| 6.1.10. Recycling or Landfill proof of disposition document (if available). |