Q and A- Bldg 41 Compressor.pdf

PDF 100 KB Posted

Attached to
BLDG 41 Compressor
Solicitation number
W50S6S24Q0026
Issued by

About this file

This document is a Questions and Answers (Q&A) session related to a Request for Quote (RFQ) for a compressor replacement at Building 41. The RFQ, numbered W50S6S24Q0026, is being issued by the Department of the Army Arizona Army National Guard.

The key details are: The RFQ is seeking to replace an existing compressor, and the new compressor should match the size and capacity of the existing unit. Offerors are required to provide a proposed compressor specification sheet, technical narrative/warranty information, and vendor details. The replacement should include an air dryer/water separator, but the existing facility air lines do not need to be replaced. The new compressor should use isolation/anti-vibration pads but does not need to be anchored to the concrete. A downtime of up to 2 days is acceptable. This is not a brand name or equal requirement - all proposed products must adhere to the updated Statement of Need specifications. Quotes are due by the date and time listed on SAM.gov and should be emailed to the provided address. This requirement is 100% set-aside for Small Businesses under NAICS code 333912 with a 1,000 employee size standard.

View the file

Other files

File Type Posted
20240531_103844.jpg JPG image
W50S6S24Q0026-Statement of Need-BLDG 41 Compressor-REV1.pdf PDF
20240531_103500.jpg JPG image
20240531_103850.jpg JPG image
20240531_103839.jpg JPG image
20240531_103547.jpg JPG image
20240531_103522.jpg JPG image
20240531_103515.jpg JPG image
20240531_103512.jpg JPG image
20240531_103626.jpg JPG image
20240531_103617.jpg JPG image
20240531_103614.jpg JPG image
20240531_103607.jpg JPG image
20240531_103603.jpg JPG image
20240531_103556.jpg JPG image
20240531_103550.jpg JPG image
RFQ W50S6S24Q0026 - BLDG 41-Compressor-Amendment 1.docx DOCX document
RFQ W50S6S24Q0026 - BLDG 41-Compressor.pdf PDF
W50S6S24Q0026-Statement of Need-BLDG 41 Compressor.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bldg. 41 Compressor Q&A

RFQ W50S6S240026

1. Can we get pictures of the compressor (model number, placement location, electrical connection)?

A. Pictures posted with amendment.

2. Match the size and capacity of the existing compressor?

A. All submissions shall match what is stated in the Statement of Need.

3. Should we add an air dryer as an option?

A. The requirement has been updated to include an air dryer/ water separator.

4. Replace the 3/8” stainless steel lines?

A. Not replacing existing facility lines. Contract should include air line from the unit to existing facility lines.

5. Should the new compressor be anchored to the concrete with isolation pads?

A. New compressor doesn’t need to be anchored to the concrete but should include isolation/anti-vibration pads.

6. How long downtime is acceptable?

A. 2-day downtime is acceptable.

7. Is there a particular brand name we need to match?

A. This is not a brand name or equal requirement. All proposed products shall adhere to the specifications provided.

8. Are there any additional features you would like the compressor itself to have?

A. Salient characteristics have been updated to Statement of Need doc Rev1.