22Q5017 QA DOC AS OF 20220513 COM CLOSET UPGRADE.pdf
PDF 74 KB Posted
- Solicitation number
- W50S6R22Q5017
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 22Q5017 WDOL RATES 15-5469 COM CLOSET UPGRADES.pdf | ||
| 22Q5017 SITE VISIT LIST COM CLOSET UPGRADE.pdf | ||
| 22Q5017 PD COM CLOSET UPGRADE.pdf | ||
| 22Q5017 PWS COM CLOSET UPGRADE.pdf | ||
| 22Q5017 RFQ DOC COM CLOSET UPGRADES.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ W50S6R22Q6017
COM CLOSET UPGRADED
QUESTIONS AND ANSWERS
(IN NO PARTICULAR ORDER)
CURRENT AS OF 10 MAY 2022
1. Q: Purchase Description document in the original solicitation calls for:
i. c. labeling of all Ethernet cables utilized and returned to current position on new rack
ii. d. Cable management for all fiber and Ethernet connections to the new rack.
iii. e. 144 20’ cables for building 6 room 23 cable management
iv. f. Two 100’ 2 strand LC/LC Fiber cables installed in Buidling 26 Room 153 from mounted equipment rack to new locations.
Based on the information revealed at the site visit, are c., d., e., and f. still required?
A: No.
2. Q: What are the basic objectives for the three separate Communications Closets A: These are the basic objectives:
B6 ROOM 23:
- No cut sheet / no tags on patch cords/jumpers.
- No station cabling
- Remove 1 rack and replace with new (Government supplies new)
- Fiber only
- 6” span minimum between rack which remains and the new rack
- Minimum 24” standoff from back wall to the rack
- “SC” and “LC” terminations
- Re-use ladder rack
- Re-use patch cord/jumpers
- Bring replacement cable in case existing needs replacement
- “LC” is single mode
- Use grounding bar on wall
- Fiber boxes can go in back or front as best suited to perform under contract, as determined by length of available cabling, to optimize installed cable performance inside new racks and to mitigate against breakage, kinking, attenuation, degradation of signal and rate, etc. (uniformity is not required)
B10 ROOM 118:
- No cut sheet / no tags on patch cords/jumpers.
- No station cabling
- Move fiber cabling on left rack to “A2”
- Vendor installs A1 cooling rack (GOV supplies new)
- No new cooling rack on RIGHT
- “SC” and “LC” terminations
- Re-use ladder rack
- Re-use patch cord/jumpers
RFQ W50S6R22Q6017
COM CLOSET UPGRADED
QUESTIONS AND ANSWERS
(IN NO PARTICULAR ORDER)
CURRENT AS OF 10 MAY 2022
- Bring replacement cable in case existing needs replacement
- “LC” is single mode
- Us grounding bar on wall
- Fiber boxes can go in back or front as best suited to perform under contract, as determined by length of available cabling, to optimize installed cable performance inside new racks and to mitigate against breakage, kinking, attenuation, degradation of signal and rate, etc. (uniformity is not required)
B10 ROOM 204
- No cut sheet / no tags on patch cords/jumpers.
- No station cabling
- Remove and replace “A2” with cooling rack (Gov supplies new)
- No new cooling rack on right
- Fiber only
- Minimum 24” standoff from back wall to the rack
- “LC” only terminations
- Re-use ladder rack
- Re-use patch cord/jumpers
- Bring replacement cable in case existing needs replacement
- “LC” is single mode
- Use grounding bar on wall
- Fiber boxes can go in back or front as best suited to perform under contract, as determined by length of available cabling, to optimize installed cable performance inside new racks and to mitigate against breakage, kinking, attenuation, degradation of signal and rate, etc. (uniformity is not required)