This solicitation seeks proposals for a construction project. The Alaska Air National Guard is soliciting bids to construct a 70' x 50' x 15' metal canopy near Hangar 18 at Joint Base Elmendorf-Richardson in Alaska. An optional bid item also requests removal and replacement of an existing backflow preventer and fire water supply lines in an adjacent pump room. Bids are due no later than September 1, 2021, with original bid bonds and powers of attorney due by September 10, 2021. The total estimated value of the project, including options, is between $100,000 and $250,000. The contract will have a 120 day performance period for the base bid and a 150 day period if the optional item is exercised. This is a total small business set-aside for firms with average annual revenue under $39.5 million. Bidders must perform at least 15% of the work with their own employees. An in-person site visit will be held on August 2, 2021 to review the project details. The solicitation and supporting documents are available on SAM.gov and require registration in the System for Award Management.

View the file

Other files for this federal contract opportunity

Other files attached to Construct ISO Canopy, newest first.
File Type Posted
Bid Abstract - 21B0002.pdf PDF
W50S6L21B0002 Amendment 1 (SAM).pdf PDF
Section 01000 General Requirements.pdf PDF
Site Visit Sign-in Sheet.pdf PDF
Attachment 2 - Backflow Drawing - H18.pdf PDF
SOW - Construct ISO Canopy H18.pdf PDF
Attachment 1 - Canopy Drawing - H18.pdf PDF
W50S6L21B0002.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FXSB210279

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to incorporate questions and answ ers after bidders' review of the solicitation, SOW, and supporting documentation. The solicitation close date remains 1 September 2021 @ 2:00PM AKST.

All other solicitation terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 12-Aug-2021

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W50S6L21B0002

X 9B. DATED (SEE ITEM 11)

01-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

12-Aug-2021

CODE

USPFO AK 176 MSC

7252 GIBSON AVE.

ANCHORAGE AK 99506-2959

W50S6L 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

CONNER VAN FOSSEN, Maj, AKANG

X

W50S6L21B0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

W50S6L-21-B-0002, Amendment 2 – Questions and Answers

1. “You just released amendment 1 for projects W50S6L21B0001 THROUGH B0004, on page 1 you have the bid date extended to September 1, 2021 at 2pm but on page 2 (where it is yellow highlighted) you have the date as September 10, 2021, which one are you wanting?

a. The highlighted text stating “10 September 2021 @ 12:00 AKST” on page 2 of Amendment 1 is referring to the due date for original bid bonds and the Power of Attorney. This allows for copies to be submitted as part of the complete bid package, but not requiring originals until September 10th 2021. This is meant to provide relief due to a higher instance of people teleworking or otherwise experiencing longer lead times getting originals. In summary, a complete bid package is due NLT 1 September 2021 at 2:00PM AKST. That bid package may contain copies of bid bonds and POA, originals must be provided to the 176WG Contracting Office by 10 September at 12:00PM AKST

2021-08-12T14:49:54-0800
VANFOSSEN.CONNER.JAMES.1291424046

File details come from the government source that posted it. Updated .