- W50RAJ24S0001-EnduringDE
- Issued by
-
Department of the Army
About this file
This document is a Broad Agency Announcement (BAA) for a federal contract opportunity related to Enduring Directed Energy (DE) weapons systems. The U.S. Army Rapid Capabilities and Critical Technologies Office (RCCTO) is seeking white paper submissions for a High Energy Laser (HEL) weapon system capable of fixed site defense or integration onto an existing Army platform, such as a Joint Light Tactical Vehicle (JLTV). Key requirements include demonstrating lethality against Groups 1-3 Unmanned Aircraft Systems (UAS) threats, providing interoperability with the Army's Forward Area Air Defense Command and Control (FAAD C2) system, and ensuring sustainability and producibility. White papers are due by 5:00 pm CT on 07 August 2024. RCCTO intends to award an Other Transaction Authority (OTA) prototype in early FY25, conduct field testing in FY25, and select a prime contractor for a production OTA in 3QFY26 to produce up to 20 HEL weapon systems. Respondents must provide a Rough Order of Magnitude (ROM) cost estimate with their white paper submission per the provided format.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Enduring HEL Qs and As_Final.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| (DRAFT) DE Enduring WBS - Enhanced White Paper ROM Cost_COMPANY NAME | |||||
| (Company Marking) | |||||
| WBS/CES | Hours | Materials | Dollars (Burdened) | Estimated Duration |
=Weeks( Working Days)
| 1.0 | RDT&E (OTA for Improvement/ Test/Qualification of Proven DE Prototype) |
| 1.1 | Development Engineering/ Non Recurring Engineering |
| 1.2 | Producibility Engineering and Planning |
| 1.3 | Delopment Tooling(if Required) |
| 1.4 | Prototype Manufacturing |
| 1.4.1 | Prime Mission Product Integration, Assemby and Test |
| 1.4.2 | Platform Integration, Assembly and Test |
| 1.5 | Systems Engineering/Program Management |
| 1.6 | System Test and Evaluation ( Planned Government Test Events Listed) |
| 1.6.1 | Sensor Test (Assume WSMR) |
| 1.6.2 | Lab Demo( Vendor Facitlity with BASH) |
| 1.6.3 | Integrated System Test Event (IFRCO WSMR) |
| 1.6.4 | Safety Test Event ( Automotive, EMI/EMC) for Safety Assessment |
| 1.6.5 | Soldier Touch Point ( Vendor Facility) |
| 1.6.6 | Transportability Test (TBD) |
| 1.7 | Training |
| 1.8 | Data |
| Fee | |
| Totals |
Instructions:
- A ROM cost breakout by WBS is required to understand the Contractor estimate to ensure prototype readiness for transition to Production.
- Contractors may also include a ROM Cost Estimate in their own format
- If Cost Estimate is for other than labor, please identify hardware or software costs as sub- elements to existing cost estimating structure.
- If available, please provide Prototype Unit Costs and Subsystem Unit Costs (See WBS Below) -Army Cost Analysis Manual(2020) CES Definitions(Section II- Cost Element Definitions) for each WBS Based on MIL STD 881-F( 13-May-2022)
| Assume 1980 per year | *Total Effort~12-15 Months | ||
| Prototype Unit Cost( ROM) | |||
| 1.1 | Prime Mission Product | Cost ($) | Description (Optional) |
| 1.1.1 | (RESERVED) | ||
| 1.1.2 | HEL Subsystem | ||
| 1.1.2.1 | Hardware 1..n (Specify) | ||
| 1.1.2.2 | Laser SW Release | ||
| 1.1.3 | Beam Control and Steering | ||
| 1.1.3.1 | Hardware 1..n(Specify) | ||
| 1.1.3.2 | Laser SW Release | ||
| 1.1.4 | Beam Director | ||
| 1.1.4.1 | Hardware 1..n(Specify) | ||
| 1.1.4.2 | Laser SW Release | ||
| 1.1.5 | Optical | ||
| 1.1.5.1 | Hardware 1..n(Specify) | ||
| 1.1.5.2 | Laser SW Release | ||
| 1.1.6 | Power and Cooling | ||
| 1.1.6.1 | Hardware 1..n(Specify) | ||
| 1.1.6.2 | Laser SW Release | ||
| 1.1.7 | Targeting and Tracking | ||
| 1.1.7.1 | Hardware 1..n(Specify) | ||
| 1.1.7.2 | Laser SW Release | ||
| 1.1.8 | Other Subsystem Components 1…n (Specify) | ||
| (Company Marking) | |||
| Prepared By: Company POC - Name- Email- Phone | |||
| Date Prepared: DD/MM/YYYY |