Exhibit A CDRLs Inert Warheads 11.26.2025.docx

DOCX document 527 KB Posted

Attached to
Inert Warhead for Reduced Range Practice Rocket (RRPR) FY26-FY28
Solicitation number
W31P4Q-26-R-0013
Issued by

About this file

This document is an Exhibit A listing Contract Data Requirements Lists (CDRLs) for the Inert Warhead for the Reduced Range Practice Rocket (RRPR) M28A2 contract (W31P4Q-26-R-00XX). The CDRL matrix specifies ten required data deliverables that the contractor must submit throughout contract performance, with submission requirements, approval timelines, and distribution classifications for each item.

The ten CDRLs include: Engineering Change Proposals (ECP), Notices of Revision (NOR), Requests for Variance (RFV), Data Accession Lists (DAL), supporting documentation for data accessions, a Quality Program Plan (QPP), First Article Inspection Report, Hazardous Materials Management Program (HMMP) Plan, HMMP Report, and Special Packaging Instructions (SPI). Each CDRL specifies the SOW paragraph reference, responsible office (primarily SFAE-MSL-STE or SFAE-MSL-STV), and submission procedures. Key timelines include: QPP draft submission 30 days after contract award with government comments within 30 days and final submission within 5 days thereafter; First Article Inspection Report submission 15 days after completion with government approval within 15 working days; HMMP Plan approval within 30 days of receipt; HMMP Report submission 30 days after the contractor's accounting year end; and SPI delivery no later than 120 days prior to shipment. All technical data must be marked with Distribution Statements in accordance with DoDI 5230.24 and include export control warnings as applicable. Electronic delivery of all data items shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil in searchable PDF or MS Office format.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A SESS

INERT WARHEAD FOR THE REDUCED RANGE PRACTICE ROCKET: M28A2

W31P4Q-26-R-00XX

A001 Engineering Change Proposal (ECP)

DI-SESS-80639 E SOW Para 4.1 SFAE-MSL-STV

LT ASREQ

D A N/A

ASREQ SEE BLK 16

SFAE-MSL-STV 0 1 0

Block 9:

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, 12 and 13: The contractor shall submit RFVs for temporary changes to Government controlled documents as required. Government will provide approval/disapproval of the first submission within 15 days. If disapproved, the contractor shall resubmit 15 days after receipt of Government comments.

Block 14: RFVs shall be delivered to the Government in searchable PDF format. Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil.

0 1 0

1 10

A SESS

A002 Notice of Revision (NOR)

DI-SESS-80642 E SOW Para 4.1 SFAE-MSL-STV

LT ASREQ

A N/A

SFAE-MSL-STV 0 1 0

Block 9:

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, 12 and 13: The contractor shall submit RFVs for temporary changes to Government controlled documents as required. Government will provide approval/disapproval of the first submission within 15 days. If disapproved, the contractor shall resubmit 15 days after receipt of Government comments.

Block 14: RFVs shall be delivered to the Government in searchable PDF format. Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil.

0 1 0

2 10

A SESS

A003 Request for Variance (RFV)

DI-SESS-80640 E SOW Para 4.2 SFAE-MSL-STE

LT

A

Block 9:

ASREQ

N/A

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, 12 and 13: The contractor shall submit RFVs for temporary changes to Government controlled documents as required. Government will provide approval/disapproval of the first submission within 15 days. If disapproved, the contractor shall resubmit 15 days after receipt of Government comments.

Block 14: RFVs shall be delivered to the Government in searchable PDF format. Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil.

0 1 0

3 10

A MGMT

A004 Data Accession List (DAL)

DI-MGMT-81453 B SOW Para 4.3.2 SFAE-MSL-STE

N/A

Block 9:

SEMIA

180 DAC SEMIA

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Block 14: Data Accession List shall be delivered to the Government in searchable PDF format. Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil.

0 1 0

4 10

A MISC

A005 Technical Report - Study/Services Data Accessions List Supporting Documentation

DI-MISC-80508 B SOW Para 4.3.2 SFAE-MSL-STE

N/A

Block 9:

SEE BLK 16

N/A

SEE BLK 16

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 10, 12, and 13: The contractor shall submit documentation within 15 working days after notification from the Procuring Contracting Officer.

Block 14: Data Accession List supporting documentation shall be delivered to the Government in one or more of the MS Office document searchable PDF formats. Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil.

0 1 0

5 10

A QCIC

A006 Quality Program Plan (QPP)

DI-QCIC-81722 SOW Para 5.0 SFAE-MSL-STE

A

Block 9:

SEE BLK 16

N/A

SFAE-MSL-STE 1 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, 12, and 13: The contractor shall submit draft 30 days after contract award. The Government will provide comments within 30 days. The contractor shall submit final with incorporation of comments within 5 days after receiving comments. The Government will provide approval/disapproval of final within 5 days. Resubmit as required for program changes. Contractor format is acceptable.

Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil. The data item shall be delivered in one or more of the MS Office documents or searchable PDF format.

1 1 0

6 10

A MISC

A007 Technical Report-Study/Services First Article Inspection Report

DI-MISC-80508 B SOW Para 5.1 SFAE-MSL-STE

A

Block 9:

SEE BLK 16

SEE BLK 16 ASREQ

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, 12, and 13: The contractor shall submit 15 days after First Article Inspection completion. The Government will provide approval/disapproval NLT 15 working days after receipt. The contractor shall resubmit within 15 days after disapproval. Subsequent submissions as required.

Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil. This data item shall be delivered in one or more of the MS Office document or searchable PDF formats.

0 1 0

7 10

A MGMT

A008 Hazardous Materials Management Program (HMMP) Plan

DI-MGMT-81398 D SOW Para 7.0 SFAE-MSL-STE

A

Block 9:

See BLK 16

120 DAC ASGEN

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, and 13: Government will provide approval/disapproval 30 days after receipt. If disapproved, the contractor shall resubmit 30 days after receipt of the government disapproval. Contractor format is acceptable. Update with major changes to the program.

Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil. The data item shall be delivered in one or more of the MS Office documents or searchable PDF format.

0 1 0

8 10

A MISC

A009 Hazardous Materials Management Program (HMMP) Report

DI-MISC-81397 D SOW Para 7.0 SFAE-MSL-STE

C A

Block 9:

ANNLY

N/A

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 12, and 13: The contractor shall submit the first submission 30 days after end of contractor’s accounting year. Government will provide approval/disapproval 30 days after receipt. If disapproved, the contractor shall resubmit 15 days after receipt of the government disapproval.

Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil. The data item shall be delivered in one or more of the MS Office documents or searchable PDF format.

0 1 0

9 10

A PACK

A010 Special Packaging Instructions (SPI)

DI-PACK-80121 C SOW Para 8.0 SFAE-MSL-SFL

A

Block 9:

SEE BLK 16

N/A

SFAE-MSL-STE 0 1 0

(A) The contractor shall mark all technical data with a Distribution Statement IAW DODI 5230.24 dated 10 Jan 2023; The contractor shall use the language below for Date of Determination and Controlling DoD Office when using Distributions B, C, D and E. Unlimited Rights technical data shall be marked A, C, or D. Technical Data delivered with less than Unlimited Rights shall be marked with either B or E. Distribution F may not be used unless prior written authorization is given by STORM CM.

Date of determination shall be determined by the contractor.

Other requests for this document must be referred to the STORM Project, ATTN: SFAE-MSL-STE, Huntsville, AL 35808-8000.

(B) All printed and electronic, including digital, technical documents that are determined to contain export-controlled technical data shall be protected IAW DoDD 5230.25, DoDI 2040.02, the ITAR, and EAR and shall be marked with Export Control Warning IAW DoDI 5230.24 which is shown below:

WARNING - This document contains technical data whose export is restricted by the Arms Export Control Act (Section 2751 of Title 22, United States Code) or the Export Control Reform Act of 2018 (Chapter 58 Sections 4801-4852 of Title 50, United States Code). Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25 and DoD Instruction 2040.02.

Blocks 8, 10, 12, and 13: The contractor shall deliver the Inert Warhead SPI NLT 120 days prior to shipment from the production facility. Government will provide approval/disapproval within 30 days after receipt. If disapproved, the contractor shall resubmit 14 days after receipt of Government disapproval. The same approval cycle applies.

Block 14: Electronic delivery of this data item shall be submitted to usarmy.redstone.peo-ms.mbx.pf-pdm@army.mil. The data item shall be delivered in one or more of the MS Office documents or searchable PDF format.

0 1 0

10 10 image3.png image4.png image1.png image2.png

File details come from the government source that posted it. Updated .