W31P4Q-24-R-0024 LIDAS Requirment USG Response 20 Feb 2024.xlsx

XLSX spreadsheet 12 KB Posted

Attached to
Launcher Instrumentation Data Acquisition System (LIDAS)
Solicitation number
W31P4Q24R0024
Issued by

About this file

This document contains questions and answers regarding solicitation number W31P4Q24R0024 for engineering services in support of the Launcher Instrumentation Data Acquisition System and Operational Rockets and Missiles Project Office. The U.S. Army Materiel Command Contracting Command at Redstone Arsenal is seeking feedback on the draft solicitation prior to official release of the request for proposal. The solicitation will require proposed pricing for a five-year overarching contract to provide engineering support for the LIDAS Family of Test Equipment, including the MLRS Family of Munitions Weapons Simulator. Individual task order costs will be determined on an as-needed basis after contract award. Labor hours will be provided in the solicitation to facilitate cost estimation, though final task orders are not predefined at this time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

W31P4Q-24-R-0024 RFP Q/A for LIDAS Requirement
QuestionsUSG Response
1For the response requested by 20 Feb is USG just requesting/soliciting interest only or are they requesting a certified cost estmated?USG is requesting feedbacks/comments from industry on the draft, prior to solicit officially RFP.
2If a cost estimate is required, is the USG planning to distribute max Labor Hours/Materials $ by year for Industry to price to for establishment of a ceiling price line?The labor hours will be provided in the soliciation.
3If a cost estimate is required, will/should it include both the overarching 5 year PWS (based on provided hours) and a separate single base year estimate for a Government Work Authorizatoin (GWA)?The contractor can propose to the 5 year overarching contract because the GWAs are not defined until a particular need arises. The GWA cost will be determined on an as needed basis at a later date post award.
4Or, is the RFP only specific to the overarching contract with a GWA cost estmate response to be requested at a later date post award of the 5 year contract?The contractor can propose to the 5 year overarching contract because the GWAs are not defined until a particular need arises. The GWA cost will be determined on an as needed basis at a later date post award.
5