This document is a Technical Requirements specification for the acquisition of one (1) TensileTurn CNC IU system and associated shipping insurance. The system must meet several technical requirements, including the ability to machine a variety of tensile test specimens, a stainless steel enclosure, a granite frame, and the capability to run at high travel speeds. The contractor must also provide on-site installation and training. The equipment is required to support mechanical testing efforts associated with additive manufacturing properties and evaluation database generation. The related federal contract opportunity is a Pre-Solicitation seeking capabilities statements from interested parties. The capabilities statement must address the offeror's past performance on similar work, company information including size and socioeconomic status, and be submitted electronically to the Contracting Officer. This is an informational notice only and is not a request for proposal.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TDD RMAC 24-12 TECHNICAL REQUIREMENTS
1.0 Description of Requirement:
The contractor shall provide the following items as specified in the table below:
| Item Number |
| Part Description |
| Quantity |
| 1 |
| TensileTurn CNC IU System |
| 1 |
| 2 |
| Shipping and Insurance |
| 1 |
Additionally, this equipment must meet the requirements stated below:
· The system must contain a library of preprogrammed ASTM, ISO, JIS and DIN specimen sizes for machining tensile samples.
· In the X and Z axis be capable of running travel speeds of 500 in/min.
· System must have a stainless steel enclosure for corrosion prevention.
· Must have a 3 jaw scroll chuck for gripping cylindrical bar stock
· System frame should be made of granite to reduce vibrational effects and improve machined surface.
· The chuck must hold 4” diameter specimens.
· Company must provide on-site installation and training
· Parts must be able to be machined to standard, sub-size, threaded, button-head, fatigue and other round testing specimens.
· Must have 8 position turrets.
· Must have 4 Boring tool holders.
2.0 Travel:
Travel is not required in the performance of this contract.
3.0 Deliverables:
The above items shall be delivered to the following:
US ARMY CCDC AvMC FCDD-AMT-MPA (Attn.) Sean Thompson Building 7631 Bat Road, Redstone, Arsenal, AL 35898 CONTRACTORS THAT DO NOT REQUIRE CAC, BUT REQUIRE ACCESS TO A DOD FACILITY OR INSTALLATION: Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
ACCESS AND GENERAL PROTECTION / SECURITY POLICY AND PROCEDURES: This standard language text is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include associated sub-contractors employees shall comply with applicable installation, facility and area Commander Installation and facility access and local security policies and procedures (provided by the Government representative). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor workforce shall comply with all personal identity verification requirements (CFR clause 52.204-9, Personal Identity Verification of Contract Personnel) as directed by DoD, Department of the Army Headquarters, and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. The prime contractor Human Resources/ Security Officer is responsible for the collection of all Redstone Badges and CAC cards issued to their employees. The Human Resources/Security Officer will then turn over these credentials to the COR. This applies when the contract expires; as well as, when a contractor resigns or is terminated. After accounting for all badges/ CACs, the COR will turn in the credentials at the One Stop Badging Office or CAC Office (MILPO). All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.