Request for Proposal W25G1V-22-Q-0161 Project Title: Brand name or Equal, Blast Cabinet

Attachment 01 - Questions and Answers Version 1

Date: September 28, 2022

This Question and Answer document is incorporated into the solicitation and any resultant contract.

Question #1: Who is responsible for connecting the 120V 1PH power supply to the unit?

Answer #1: The vendor

Question #2: How far away is the above supply?

Answer #2: Within five feet

Question #3: Who is responsible for connecting the 10" dust hose to the central dust collection system?

Answer #3: The vendor

Question #4: How far away is the above supply?

Answer #4: Approximately 15 feet straight up

Question #5: Who is responsible for connecting the 1" pneumatic airline to the unit?

Answer #5: The vendor

Question #6: How far away is the above supply?

Answer #6: Within five feet

Question #7: How far away is the nearest parking lot for unloading the units to the first entry point of the building they will be installed in?

Answer #7: Approximately 100 feet, Also doors and aisles are wide and high enough for access to the installation site.

Question #8: Will there be an indoor or outdoor staging area available for our use while unloading and moving equipment?

Answer #8: It is outdoors.

Question #9: What floor of the building will the units be installed in?

Answer #9: First floor.

Question #10: What is the composition AND thickness of the floor the units will be directly installed on? Will we need to drill and supply a ground rod as well as anchor the units?

Answer #10: N/A. There is a grounding wire coming up from the floor servicing the machines that the Government is removing that will be reused. Machines will not be required to be anchored, only leveled.

Question #11: Will there be a prior floor study done before holes are drilled into the floor to rule out underground piping, gas, electrical, etc or a guarantee of such not being there?

Answer #11: N/A. No drilling required.

Question #12: Measurements and weight limits of all doorways, ramps, elevators, etc.

the equipment will have to pass through in order to move it to its final install location Answer #12: Overhead doors are approximately 12 feet by 12 feet. The Government has had many of the same machines installed in the same manner is past several years without issue.