W15QKN-24-X-10AE ERAP Questions 1.docx

DOCX document 21 KB Posted

Attached to
Extended Range Artillery Projectile (ERAP)
Solicitation number
W15QKN-24-X-10AE
Issued by

About this file

This document is a set of questions and answers related to the Extended Range Artillery Projectile (ERAP) procurement opportunity. The key details are:

The government is requesting Rough Order of Magnitude (ROM) pricing for the development, qualification, low-rate initial production (LRIP), and production phases over multiple fiscal years, with planned production quantities of 300 in FY#1, 500 in FY#3, 1000 in FY#5, ramping up to a minimum of 1500 by FY#6. The production start date is intended to indicate the beginning of assembling the rounds, not the contract award date. Interested parties must provide information on their capabilities, technology readiness levels, development/production schedules and costs, supply chain, manufacturing processes, and experience with 155mm guided projectiles. Responses will be held confidential and are for planning purposes only, with no obligation on the government's part. No award will result from this market survey.

View the file

Other files

File Type Posted
W15QKN-24-X-10AE ERAP Questions 2.docx DOCX document
DD2345 Military Critical Technical Data Agreement.pdf PDF
Non Disclosure Agreement ERAP.docx DOCX document
TDR Questionaire.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W15QKN-24-X-10AE ERAP Questions #1

1. For Task #4, Is the Government requesting ROM pricing for Development, Qual, LRIP and Production by GFY for the quantities in #6 in total by GFY or does the Government only want the AUPP (Average Unit Production Price) per each production quantity?

Answer: Intent is to receive the expected funding amount in total by GFY – this is intended to inform POM planning in those timeframes.

1. Is the Jan 2029 production start intended to indicate the start of assembling hardware or is that the intended contract award date?

Answer: The Jan 2029 production start is intended to indicate the beginning of assembling the rounds.