1. Replacement of Sand and Salt Shed Canopies Fort Devens, MA
2. The NAICS Code for this project is 236220. The small business size standard is $39.5 million.
3. The estimated magnitude of this project is betw een $25,000 and $100,000.
4. All w ork is to be completed w ithin 60 days after issuance of notice to proceed.
5. Set Aside Status - This requirement shall be set aside 100% for small business concerns.
EMILY G. SCHLEE 609-562-6462
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
13-Dec-2019
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________60 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________27 Dec 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY CONTRACTING COMMAND
5418 S. SCOTT PLAZA
JOINT BASE MDL NJ 08640
W15QKN
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
02:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W15QKN20Q5020 63
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
W15QKN20Q5020
Section SF 30 - Block 14 Continuation Page (SF 30)
CONTRACT ADMINISTRATION
Inquiries concerning all contractual actions after award shall be directed first to the contract administrator. In her absence, please contact the contracting officer. Subject line must reference the solicitation/contract number.
CONTRACT ADMINISTRATOR: Emily Schlee 609-562-3774(office) Emily.schlee.civ@mail.mil
CONTRACTING OFFICER: Julie Cameron
(609)562-7026 (office) Julie.a.cameron.civ@mail.mil
CUSTOMER: USAG Fort Devens POC: George Markt Chief, Engineering Division
Devens Reserve Forces Training Area Office - (978) 615-6098 george.h.markt.civ@mail.mil
INSTRUCTIONS TO OFFERORS
1. This is a 100% Small Business Set-Aside. All questions shall be in writing. Questions shall be e-mailed to Contract Specialist Emily Schlee at emily.schlee.civ@mail.mil
2. All proposals are due no later than the date and time specified in Block 13 A of the SF1442. No offer will be accepted if received after this date and time. All quotes/offers shall be in writing. Quotes / offers may be e-mailed to Contract Specialist Emily Schlee at emily.schlee.civ@mail.mil
3. Mailed offers should be sent to the following address:
Department of the Army
ACC-NJ-WS
Attn: Emily Schlee Building 5418 South Scott Plaza Joint Base - MDL, New Jersey 08641
4. Anywhere in this solicitation where the term “offer” is used, it is hereby changed to read “quote”.
5. Anywhere in this solicitation where the term “offeror” is used, it is hereby changed to read “quoter”.
6. It is the offeror’ s responsibility that all offers submitted, regardless of method of submission, are received in this office prior to the time and date for receipt of the offer. All quotes/offers are due no later than the date specified in the solicitation.
7. Basis of Award: The Government intends to award a firm fixed-price (FFP) contract resulting from this solicitation. Award will be made on all or none basis. Award shall be made to a single contractor. Quotes must include prices for each item listed in order that quotes may be properly evaluated. Failure to do so shall be cause for the offeror to be considered non-responsive. Award shall be made to that responsive, responsible offeror, and will be based on lowest price meeting technical specification.
8. FOB Destination, Vendors must include CAGE code, Duns number, TIN, warranty terms. Quote should include FOB Destination pricing; freight should not be listed separately.
9. A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party. Before the offer's specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
10. Quotes must include the following information: Price: pricing for each Line Item. Pricing must be submitted in the proper format. The proper format consists of QUANTITY * UNIT AMOUNT = NET AMT. In the event there is a difference between a unit price and the extended total, the unit price will be held to the intended price. If the offeror shows only the total price but fails to enter a unit price, the total divided by the estimated quantity will be held to be the intended price.
11. The contractor shall provide all personnel, equipment, tools, materials, supervision, and other items necessary to provide the contracted supplies.
12. Contractors shall quote on all CLINS. CLIN pricing should be all inclusive of labor, labor burden, other direct cost (material, equipment, fees, licenses, etc), G&A and profit.
13. Line Item pricing should include all applicable taxes, fees, gratuities, commissions, services charges, etc.
The federal government is tax exempt.
14. The offeror is reminded it must offer on any issued plans, drawings, and specifications as amended. Any deviations, conditions or attachments made by the offeror itself may render the offer non-responsive and may be cause for its rejection.
15. All representations and certifications to include provision of Dun & Bradstreet number are to be returned with the quote. Dun and Bradstreet information can be found by calling (800)-333-0505. A contractor that is receiving an award resulting from this request for quotation must be registered in the System for Award Management (SAM. To register, offerors may log onto: https://www.sam.gov/portal/public/SAM/.
16. Dun and Bradstreet #__________________________
17. CAGE(commercial and government entity)code___________________
18. Federal Tax ID __________________
19. Due to restricted access to Fort Dix, contractors that will be hand carrying their quote are required to submit to the contracting officer a list of personnel planning to deliver the package not later than 24 hours prior to the due date. Contractors must also furnish the approximate time of arrival and the gate they will utilize.
Contractors are cautioned that there may be delays at the gates and should allow adequate time for entering the installation to ensure packages are received prior to the time and date for receipt of quote. All individuals must have a picture id and no substitutions are authorized. Vehicles are also subject to search.
20. This project falls under NAICS 236220 with the business size standard of $39,500,000.00.
21. Quotes shall be valid for 120 days unless specified.
STATEMENT OF WORK
SECTION 01 11 01
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
A. Where references (e.g. ASTM, ACI, etc.) are noted for compliance throughout any Section, Contractor shall use the most current and up to date copy at time of actual construction.
B. Contractor shall be responsible for providing their own copies of references.
1.2 RELATED SECTIONS
A. Section 01 57 20 – Environmental Protection (Fort Devens) B. Section 02 41 00 - Demolition C. Section 12 93 00 – Site Furnishings
1.3 DEFINITIONS
A. Drawings – That part of the Contract Documents which graphically shows the scope, extent, and character of the Work to be performed by the Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined.
B. Existing Conditions - Including but not limited to, all existing buildings and interior utilities (HVAC, electricity, plumbing, etc.), structures, fences, roads, sidewalks, pavement, curbs, above and underground utilities and equipment, existing improvements, vegetation (trees, shrubs, grass, etc.), and underground facilities.
C. Furnish – When used in connection with services, materials, or equipment, shall mean to supply and deliver said services, materials, or equipment to the Site (or some other specified location) ready for use or installation and in usable or operable condition.
D. Install, Perform or Provide – When used in conjunction with services, materials, or equipment, shall mean to put into use or place in final position said services, materials, or equipment complete and ready for intended use.
E. Repair or Replace – Shall mean to remove existing, damaged material and install new material in its place
F. Shop Drawings – All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for the Contractor and submitted by Contractor to illustrate some portion of the Work.
G. Site – Including but not limited to land, buildings, structures and or areas indicated in the Contract Documents as being furnished by the Government upon which the Work is to be performed, including rights-of-way and easements for access thereto, and such other lands furnished by the Government which are designated for use by the Contractor.
H. Underground Facilities – All underground pipelines, conduits, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.
I. Work – The entire construction, on- and off-site, or the various separate identifiable parts thereof required to be provided under this Contract. Work includes and is the result of performing or providing all labor, services, submittals, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by this Contract.
J. Unless stated otherwise in the Contract, words or phrases which have a well-known technical or construction industry or trade meaning shall be used in the Contract in accordance with such recognized meaning.
1.4 WORK COVERED BY THE CONTRACT DOCUMENTS
A. Project Location: DPW equipment yard, 11 Feinberg Street, Fort Devens MA.
B. General:
1. Although such work may not be specifically indicated in Contract, furnish and install all supplementary or miscellaneous items, appurtenances and devices incidental to and or necessary to complete the Work as required by the Contract.
2. Prior to start of construction:
a. Contractor shall meet with contracting and engineering to discuss project schedule
b. Work areas shall be cordoned off.
C. Scope of Work D. The Contractor shall furnish all plant, labor and material, equipment, supervision, incidentals, and services necessary to demolish and dispose of the existing canopy covers installed over the sand and salt bins located within the DPW equipment yard. The existing canopies consist of synthetic fabric coverings stretched over galvanized steel arches attached to concrete foundation walls that are approximately 3.5 feet high. The back of the openings of the canopies are covered by plywood walls.
The Contractor shall disassemble the canopies completely leaving the concrete foundation walls intact. All canopy materials shall be removed from the installation and disposed of off-site.
E. The Contractor shall furnish all plant, labor and material, equipment, supervision, incidentals, and services necessary to supply and install two new canopy covers over the existing sand and salt bins.
The structures shall be fastened to the tops of the concrete bin walls and allow for a minimum of 12 feet vertical clearance in the front and back. The support structures and all hardware shall be fabricated of galvanized steel capable of withstanding a severe moisture and salt environment. The fabric covering shall be of a fire resistant material and shall cover the back of the structures as well as the top. The structures shall be able to withstand heavy snow and wind loads.
1.5 SUBMITTALS
A. General
1. Units of weights and measures used on all submittals are to be the same as those used in the Contract Documents.
2. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.
3. Prior to submission to Contracting Officer, all submittals shall be checked and approved by the Contractor as stated in the Contract. Each item shall be stamped, signed, and dated by the Contractor indicating action taken.
4. Proposed deviations from the Contract requirements are to be clearly identified. Include within submittal items such as: Contractor's, manufacturer's, or fabricator's drawings;
descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list);
certifications; warranties; and other such required submittals.
5. Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby.
6. Samples remaining upon completion of the Work shall be picked up and disposed of in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.
7. The Contractor shall also comply with Special Contract Requirements as required based on procurement type and total cost of this Contract.
8. All submittals shall be forwarded to, Directorate of Public Works Engineering Division, 30 Quebec Street, Building 666, Fort Devens, MA 01434-4429. Four copies each shall be submitted for all submittals.
B. Submittal Classification
1. Government Approved
Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer.
Within the terms of the Contract Clause entitled "Specifications and Drawings for Construction," they are considered to be "shop drawings."
2. Information Only C. Submittals not requiring Government approval will be for information only. For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.
D. Approved/Accepted Submittals
1. The Contracting Officer's approval or acceptance of submittals is not be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.
2. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist. The Contractor under the Contractor’s quality control program requirements of this Contract is responsible for dimensions, details, and the satisfactory construction of all work, etc.
3. After submittals have been approved or accepted by the Contracting Officer, no re-submittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
E. Disapproved/Rejected Submittals
1. Contractor shall make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the clause entitled, "Changes" is to be given to the Contracting Officer.
2. Contractor is responsible for the dimensions, details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.
3. If changes are necessary to submittals, the Contractor shall make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
F. Withholding of Payment
1. Payment for materials incorporated in the Work will not be made if required approvals have not been obtained.
2. No payment will be made for any materials incorporated into the Work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.
G. Scheduling
1. Submittals covering component items forming a system or items that are interrelated shall be submitted concurrently and scheduled to be coordinated. Certifications to be submitted with the pertinent drawings shall be so scheduled. Adequate time (a minimum of 14 calendar days exclusive of mailing time) shall be allowed and shown on the register for review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.
H. Transmittal Form
1. Transmittal Form (ENG Form 4025) shall be used for submitting both Government
Approved and Information Only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor during the pre-construction meeting. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
2. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the Work covered in this Contract.
I. Submittal Procedure
1. Quantity of Submittals
a. The Contractor shall submit four (4) copies for each submittal specified in the Contract.
2. Variations from contract requirements require government approval pursuant to the Contract Clauses and will be considered where advantageous to the government.
a. Considering Variations J. Discussions with the Contracting Officer prior to submission will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP). Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the government requiring rejection and removal of such work at no additional cost to the government.
a. Proposing Variations K. When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to government. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item. Clearly mark the proposed variation in all documentation.
a. Warranting That Variations Are Compatible L. When delivering a variation for approval, Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
M. 3. Government Approved Submittals
a. Upon completion of review of submittals requiring government approval, the submittals will be identified as having received approval by being so stamped and dated. Two (2) copies of the submittal will be retained by the Contracting Officer and two (2) copies of the submittal will be returned to the Contractor.
N. 4. Information Only Submittals
a. Normally submittals for information only will not be returned. Approval of the
Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the drawings and specifications; it will not prevent the Contracting Officer from requiring removal and replacement of non-conforming material incorporated in the work;
and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
O. Stamps P. Stamps used by the Contractor on all Submittals, to certify that the submittal meets contract requirements, shall be similar to the following:
1.6 PROJECT/SITE CONDITIONS
A. Work Under Other Contracts
1. During the performance period of this Contract, other contracts may be in force for the construction of other features of work on or adjacent to the site of Work. In addition, members of the U.S. Armed Forces may be performing work or occupying facilities on or adjacent to the area;
2. Contractor shall arrange his plan and shall schedule and perform this Work so as to fully cooperate with all Contractors and Government agencies. No direct or extra compensation will be allowed on account of the coordination or cooperation required.
B. Coordination Between Contractors
1. It shall be the responsibility of the prime contractor to fully coordinate with other contractors, or with utility or subcontractor’s forces engaged in collateral work;
2. In case of disputes, the decision of the Contracting Officer shall be final and binding upon the parties affected;
3. Delays resulting from a lack of proper coordination shall not be grounds for a time extension, direct or extra compensation, or affect the requirements for a timely completion.
1.7 CONTRACTOR USE OF PREMISES
1. Storage Areas
1. Construction staging, equipment, and material storage shall be located in an area as directed by the Contracting Officer.
2. Work Limits
a. As instructed by the Contracting Officer, the Contractor shall restrict Contractor’s employees to the immediate Work areas on the job-site and in no way go beyond the Work limits as indicated by the Contracting Officer.
3. Contractor’s Receipt of Supplies:
a. The Contractor shall be responsible for all arrangements for the receipt of materials and supplies at the job site;
b. Government personnel are not permitted to receive or sign for items delivered to the site.
4. Utility Interruptions:
a. To the extent practicable, make utility interruptions after normal working hours or on
Saturdays, Sundays, and Government holidays;
b. Coordinate all utility cutovers and interruptions with the Contracting Officer;
c. Permission to interrupt any building utility services shall be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
5. Identification of Employees
a. The Contractor shall be responsible for furnishing the Contracting Officer with a list of all the names of employees prior to employees work on-site; each employee shall be required to carry on their person some sort of identification;
b. The Contractor shall become acquainted with all Post Regulations in advance.
Compliance with the provisions of this paragraph by the Contractor’s subcontractors and their employees will be the responsibility of the Contractor.
1.8 EXISTING WORK
A. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
B. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.9 EXAMINATION OF SITE
A. It is HIGHLY recommended that the Contractor visit the Site and become familiar with general, local, and Site conditions which may affect cost, progress, or performance of the Work. A site visit shall be scheduled through the Army Contracting Command, New Jersey.
1.10 PROTECTION
1. Provide and maintain protection for all existing conditions on or adjacent to the Site, as well as nearby third party property which is not part of the Work; this also includes parts of the Contract which do not unreasonably interfere with the Work. It is recommended that the Contractor become very familiar with the Site and any adjacent property.
2. Upon discovery of unknown utility or concealed conditions, notify the Contracting Officer immediately and re-direct work to avoid delay.
3. Avoid damage to existing vegetation to remain in place and only remove vegetation when specifically authorized to do so.
4. Any damage to existing conditions, including third party property, as a result of failure to comply with the requirements of the Contract or failure to exercise reasonable care in conducting the Work shall be immediately repaired. If Contractor fails or refuses to promptly repair the damage, the Contracting Officer shall exercise its rights to repair the damage at the expense of the Contractor.
5. During the Work, the Contractor shall provide temporary protection at all times for:
1. Damaged portions of existing structures and land where materials are handled and equipment is moved and or relocated.
2. The interior of existing structures for the prevention of damage and the intrusion of dust and inclement weather. Prior to the starting any phases or work, all surfaces that are to remain in place and intact shall be adequately protected; this protection shall be maintained until all associated work in the area is completed and accepted by Government.
1.11 RESTORATION
A. All existing conditions which are disturbed, damaged and or removed as a result of the Work, shall be fully restored (restored shall mean, but not be limited to, repaired, put back into service, replaced, etc). Restorations shall match elevations, conditions prior to the start of the Work.
Except as otherwise noted, materials and workmanship used in restoring the damaged work shall conform in type and quality to that of original existing conditions. All restorations shall be at the expense of the Contractor.
B. The Contractor shall not cut, alter or remove any structural components, nor disturb any plumbing, steam, gas, or electric utilities without prior approval from the Contracting Officer.
C. Prior to any disturbance to existing conditions, the Contracting Officer shall be notified immediately when conditions which are to be altered and or extended are found to be defective in any way.
D. Changes in contract price and or time as a result of restoration to damaged existing conditions which were not shown in the Contract Documents or were unknown to the Government will be covered by the clauses entitled “CHANGES” (FAR 52.243-5) and “DIFFERING SITE
CONDITIONS” (FAR 52.236-2).
1.12 PHYSICAL DATA
A. Data and information furnished or referred to is for the Contractor’s information only. The
Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
B. The indications of physical conditions on the drawings are the result of As-Built Drawings. The Contractor by his own site investigations shall determine actual field conditions and measurements.
C. The Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by the drawings. Bidders are expected to examine site of work and, after investigation, decide for themselves character of materials and make their bids accordingly.
1.13 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall reasonably make existing utilities available to the Contractor. The
Contractor shall carefully conserve any utilities which are furnished without charge.
B. At the expense of the Contractor and the satisfaction of the Contracting Officer, all necessary temporary facilities (electricity, heating, cooling, telephone, controls, distribution lines, etc.), shall be installed and maintained.
C. Prior to final acceptance of the Work, the Contractor shall remove all temporary facilities and any associated appurtenances, and clean and repair damage caused by installation or use of temporary facilities.
1.14 MATERIALS AND EQUIPMENT TO BE SALVAGED
A. Items designated by the Contracting Officer to be salvaged shall remain the property of the
Government. The salvaged property shall be segregated, itemized, delivered, and off-loaded at the a Government designated storage area located within 5 miles of the construction site.
B. Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer.
C. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
1.15 PRECONSTRUCTION CONFERENCE
A. After award of the Contract, but prior to commencement of any work at the site, a meeting with the Contracting Officer shall be held to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
1.16 CLEANUP
A. On a daily basis, Contractor shall remove and properly dispose of all waste material and other debris generated by the Work. It shall be removed off the Site in a manner as to prevent spillage on streets and adjacent roads. Do not allow the materials to accumulate on the Site.
B. Removal, as indicated above, shall be in accordance with all Federal, State, and Local Regulations and Laws.
C. Do not burn or bury materials and or debris on site. Leave site in clean condition.
1.17 CONTRACTOR MANPOWER REPORTING
A. The Office of Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the contractor will report contractor manpower information (including subcontractor manpower information) required for performance of this contract. The contractor shall submit all the information required in the format specified at the following web address https://cmra.army.mil/default.aspx.
B. The required information includes:
• Contract Number
• Delivery Order Number (if applicable)
• Task Order Number (if applicable)
• Requiring Activity Unit Identification Code (UIC)
• Command
• Contractor Contact Information
• Federal Service Code
• Direct Labor Hours
• Direct Labor Dollars
• Location information [where contractor and subcontractors (if applicable) performed the services Contractors shall fill in the above fields on the website.
C. The Contractor shall have sole authority and responsibility for all management, supervision and personnel quality controls over its employees. The government will not exercise any supervision or control over Contractor employees while performing work under the contract. Such employees shall be accountable solely to the Contractor. Furthermore, contractor personnel will not be subject to the relatively continuous supervision or control of any Government officer or employee, nor will any contractor employee be issued "ad hoc" or "administrative support" tasks by any Government personnel.
ATTACHMENT(S):
1. Aerial map of existing bin canopies
2. CADD site plan of bins with dimensions shown
SECTION 01 57 20
ENVIRONMENTAL PROTECTION (FORT DEVENS)
PART 1 GENERAL
1.1 REFERENCES (NOT USED)
1.2 DEFINITIONS
A. Contractor Generated Hazardous Waste - Contractor generated hazardous waste means materials that, if abandoned or disposed of, may meet the definition of a hazardous waste. These waste streams would typically consist of material brought on site by the Contractor to execute work, but are not fully consumed during the course of construction. Examples include, but are not limited to, excess paint thinners (i.e. methyl ethyl ketone, toluene etc.), waste thinners, excess paints, excess solvents, waste solvents, and excess pesticides, and contaminated pesticide equipment rinse water.
B. Environmental Pollution and Damage - Environmental pollution and damage is the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life; affect other species of importance to humankind; or degrade the environment aesthetically, culturally and/or historically.
C. Environmental Protection - Environmental protection is the prevention/control of pollution and habitat disruption that may occur to the environment during construction. The control of environmental pollution and damage requires consideration of land, water, and air; biological and cultural resources; and includes management of visual aesthetics; noise; solid, chemical, gaseous, and liquid waste; radiant energy and radioactive material as well as other pollutants.
D. Hazardous Materials - As defined by the Environmental Protection Agency (EPA) or State Hazardous Control Authority. Hazardous material is any material that is regulated as a hazardous material by the EPA or requires a Material Safety Data Sheet (MSDS), or during end use, treatment, handling, packaging, storage, transpiration, or disposal meets or has components that meet or have potential to meet the definition of a hazardous waste. Such material include ammunition, weapons, explosive actuated devices, propellants, pyrotechnics, chemical and biological warfare materials, medical and pharmaceutical supplies, medical waste and infectious materials, bulk fuels, radioactive materials, and other materials such as asbestos, mercury, and polychlorinated biphenyls (PCBs). Nonetheless, the exposure may occur incident to manufacture, storage, use and demilitarization of these items.
E. Hazardous Waste - Any discarded material, liquid, solid, or gas, which meets the definition of hazardous material or is designated hazardous waste by the Environmental Protection Agency or State Hazardous Control Authority.
F. Land Application for Discharge Water - The term "Land Application" for discharge water implies that the Contractor must discharge water at a rate which allows the water to percolate into the soil. No sheeting action, soil erosion, discharge into storm sewers, discharge into defined drainage areas, or discharge into the "Waters of the United States" must occur. Land Application must be in compliance with all applicable Federal, State, and local laws and regulations.
G. Oily Waste - Those materials which are, or were, mixed with used oil and have become separated from that used oil. Oily wastes also means materials, including wastewaters, centrifuge solids, filter residues or sludges, bottom sediments, tank bottoms, and sorbents which have come into contact with and have been contaminated by, used oil and may be appropriately tested and discarded in a manner which is in compliance with Federal, State and local requirements.
H. Pesticide - Pesticide is defined as any substance or mixture of substances intended for preventing, destroying, repelling, or mitigating any pest, or intended for use as a plant regulator, defoliant or desiccant.
I. Solid Waste - Garbage, refuse, debris, sludge, or other discharged material, including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.
J. Surface Discharge - The term implies that the water is discharged with possible sheeting action and subsequent soil erosion may occur. Waters that are surface discharged may terminate in drainage ditches, storm sewers, c reeks, and/or "Waters of the United States" and would require a permit to discharge water from the governing agency.
K. Waste Hazardous Material (WHM) - Any waste material which because of its quantity, concentration, or physical, chemical, or infectious characteristics may pose a substantial hazard to human health or the environment and which has been so designated. Used oil not containing any hazardous waste, as defined above, falls under this definition.
L. Waters of the United States - All waters which are under the jurisdiction of the Clean Water Act, as defined in 33 CFR 328.
M. Wetlands - Those areas that are inundated or saturated by surface or ground water at a frequency and duration sufficient to support, and that under normal circumstances do support, a prevalence of vegetation typically adapted for life in saturated soil conditions. Wetlands generally include swamps, marshes, and bogs.
1.3 NOTIFICATION
The Contracting Officer will notify the Contractor in writing of any observed noncompliance with Federal, State or local environmental laws or regulations, and permits. After receipt of such notice, the Contractor will inform the Contracting Officer of the proposed corrective action and take such action when approved by the Contracting Officer. The Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No time extensions will be granted or equitable adjustments allowed for any such suspensions. This is in addition to any other actions the Contracting Officer may take under the contract, or in accordance with the Federal Acquisition Regulation or Federal Law.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION
3.1 PROTECTION OF NATURAL RESOURCES
A. Preserve the natural resources within the project boundaries and outside the limits of permanent work. Restore to an equivalent or improved condition upon completion of work. Confine construction activities to within the limits of the work indicated or specified. If the work is near streams, lakes, or other waterways, conform to the national permitting requirements of the Clean Water Act.
B. Do not disturb fish and wildlife. Do not alter water flows or otherwise significantly disturb the native habitat adjacent to the project and critical to the survival of fish and wildlife, except as indicated or specified.
C. Except in areas to be cleared, do not remove, cut, deface, injure, or destroy trees or shrubs without the Contracting Officer's permission. Do not fasten or attach ropes, cables, or guys to existing nearby trees for anchorages unless authorized by the Contracting Officer. Where such use of attached ropes, cables, or guys is authorized, the Contractor will be responsible for any resultant damage.
D. Protect existing trees which are to remain and which may be injured, bruised, defaced, or otherwise damaged by construction operations. Remove displaced rocks from uncleared areas. By approved excavation, remove trees with 30 percent or more of their root systems destroyed.
Remove trees and other landscape features scarred or damaged by equipment operations, and replace with equivalent, undamaged trees and landscape features. Obtain Contracting Officer's approval before replacement.
E. The Contracting Officer's approval is required before any equipment will be permitted to ford live streams. In areas where frequent crossings are required, install temporary culverts or bridges.
Obtain Contracting Officer's approval prior to installation. Remove temporary culverts or bridges upon completion of work, and repair the area to its original condition unless otherwise required by the Contracting Officer.
3.2 WORK AREA LIMITS
Mark the areas that need not be disturbed under this Contract prior to commencing construction activities.
Mark or fence isolated areas within the general work area which are not to be disturbed. Protect monuments and markers before construction operations commence. Where construction operations are to be conducted during darkness, any markers must be visible in the dark. The Contractor's personnel must be knowledgeable of the purpose for marking and/or protecting particular objects.
3.3 LANDSCAPE
Trees, shrubs, vines, grasses, land forms and other landscape features to be preserved as indicated and or defined in the Contract must be clearly identified by marking, fencing, or wrapping with boards, or any other approved techniques. Restore landscape features damaged or destroyed during construction operations outside the limits of the approved work area.
3.4 EROSION AND SEDIMENT CONTROLS
A. If required by the Contract, the Contractor shall responsible for providing erosion and sediment control measures in accordance with Federal, State, and local laws and regulations.
B. The erosion and sediment controls selected and maintained by the Contractor shall be such that water quality standards are not violated as a result of construction activities.
C. The area of bare soil exposed at any one time by construction operations should be kept to a minimum. Construct or install temporary and permanent erosion and sediment control best management practices (BMPs) as may be indicated in the Contract.
D. Erosion and sediment controls must be provided for onsite borrow and spoil areas to prevent sediment from entering any nearby waters.
E. Temporary excavation and embankments for work areas must be controlled to protect adjacent areas.
F. Remove all temporary measures after the area has been fully stabilized.
3.5 WATER RESOURCES
Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated. For construction activities immediately adjacent to impaired surface waters, the Contractor must be capable of quantifying sediment or pollutant loading to that surface water when required by Federal or State issued Clean Water Act permits.
3.6 WETLANDS
Do not enter, disturb, destroy, or allow discharge of contaminants into any wetlands. The protection of wetlands is the Contractor's responsibility. Authorization to enter specific wetlands identified will not relieve the Contractor from any obligation to protect other wetlands within, adjacent to, or in the vicinity of the construction site and associated boundaries.
3.7 AIR RESOURCES
Equipment operation, activities, or processes will be in accordance with all Federal and State air emission and performance laws and standards.
3.8 DUST CONTROL
A. Keep dust down at all times, including during nonworking periods. Sprinkle or treat, with dust suppressants, the soil at the site, haul roads, and other areas disturbed by operations.
B. Dry power brooming will not be permitted. Instead, use vacuuming, wet mopping, wet sweeping, or wet power brooming.
C. Air blowing will be permitted only for cleaning nonparticulate debris such as steel reinforcing bars.
D. Only wet cutting will be permitted for cutting concrete blocks, concrete, and bituminous concrete.
Do not unnecessarily shake bags of cement, concrete mortar, or plaster.
3.9 BURNING
Burning is prohibited and will not be allowed on government property.
3.10 SOLID WASTES
A. Place solid wastes (excluding clearing debris) in containers which are emptied on a regular schedule. Handling, storage, and disposal must be conducted to prevent contamination. Employ segregation measures so that no hazardous or toxic waste will become co-mingled with solid waste.
B. Transport solid waste off Government property and dispose of it in compliance with Federal, State, and local requirements for solid waste disposal.
C. Verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate.
3.11 CHEMICALS AND CHEMICAL WASTES
Dispense chemicals ensuring no spillage to the ground or water. Perform and document periodic inspections of dispensing areas to identify leakage and initiate corrective action. This documentation will be periodically reviewed by the Government. Collect chemical waste in corrosion resistant, compatible containers. Collection drums must be monitored and removed to a staging or storage area when contents are within 6 inches of the top. Wastes will be classified, managed, stored, and disposed of in accordance with Federal, State, and local laws and regulations.
3.12 WASTE WATER
A. Waste water from construction activities, such as onsite material processing, concrete curing, foundation and concrete clean-up, water used in concrete trucks, forms, etc. will not be allowed to enter water ways or to be discharged prior to being treated to remove pollutants. Dispose of the construction related waste water off-Government property in accordance with all Federal, State, Regional and Local laws and regulations.
B. Water generated from the flushing of lines after disinfection or disinfection, and hydrostatic testing will be land applied in accordance with all Federal, State, and local laws and regulations for land application.
3.13 FUEL AND LUBRICANTS
A. Storage, fueling and lubrication of equipment and motor vehicles must be conducted in a manner that affords the maximum protection against spill and evaporation. Manage and store fuel, lubricants and oil in accordance with all Federal, State, Regional, and local laws and regulations.
Used lubricants and used oil to be discarded must be stored in marked corrosion-resistant containers and recycled or disposed in accordance all Federal, State, and local laws and regulations.
B. Contractor shall coordinate the disposition of hazardous waste with Fort Devens Environmental Coordinator and the Contracting Officer.
C. Storage of fuel on the project site is not allowed. Fuel must be brought to the project site each day that work is performed.
3.14 BIOLOGICAL RESOURCES
A. Minimize interference with, disturbance to, and damage to fish, wildlife, and plants including their habitat.
B. The protection of threatened and endangered animal and plant species, including their habitat, is the Contractor's responsibility in accordance with Federal, State, Regional, and local laws and regulations.
3.15 PREVIOUSLY USED EQUIPMENT
A. Clean all previously used…