Text version

Government Responses to Industry Questions 9/27/2012

Reference Question Government Response

PRD 3.12.1 and 3.12.3

Requirement to operate at -25F which is the same temperature requirement for storage. The storage requirement is not a problem. But the operating temperature requirement appears to be difficult to meet (most ruggedized COTS RCUs will guarantee operation no lower than -22F). Please consider revising the min operating temperature requirement.

The operating requirement for the SI1A RCU has been changed to -5F based on user input.

PRD

3.14.1Embedded Training:

How is the ICBT related to Embedded Training? Interactive Computer Based Training (ICBT) is a characteristic of embedded training but the only standard is SCORM if the embedded training is to be web enabled.

PRD

3.14.1Embedded Training:

Is there a requirement document for ICBT? Interactive Computer Based Training (ICBT) is a characteristic of embedded training but the only standard is SCORM if the embedded training is to be web enabled.

Government Responses to Industry Questions 9/27/2012

Reference Question Government Response

SOW 3.2.1.2

Software Reliability Demonstration:

As part of the developmental test program, the contractor shall conduct a software reliability demonstration and deliver a report. (DI-TMSS-81586A) The contractor shall support the Test and Evaluation IPT in establishing the scope and success criteria of this test. Testing shall conform to the test requirements listed in the PRD.

The SOW paragraph 3.2.1.2 states that the testing shall conform to the test requirements listed in the PRD.

However, the PRD does not list test requirements.

Please clarify.

SOW will be changed to read as follows: "Testing shall conform to the command and control (C2) requirements in the PRD."

PRD 3.7 Reliability: PRD paragraph states Essential Function Failures are those failures as defined by the Spider Increment 1A

FDSC.

When will the SI1A Failure Definition and Scoring Criteria (FDSC) be available?

FDSC will be available after contract award.

Controller Assessment

Request a copy of the Joint Battle Command JBC (JBC) Platform Development Kit (PDK), which was referred to in the Network Munitions Controller Assessment.

JBC PDK interface documentation will be provided to cleared potential offerors that submit a request to procurement.

Contractor