- Machinery Ventilation System, Clean AND HVAC Duct System, Clean on vessel at USCG Base Boston, Boston, MA
- Solicitation number
- 70Z02426Q0000275
About this file
This is a Statement of Work (SOW) for HVAC and machinery ventilation system cleaning services aboard the USCG Boat 1153 (CGC John Patterson) located at 427 Commercial Street, Boston, MA. The contractor must be certified by the National Air Duct Cleaners Association (NADCA) and technically competent with Novenco FRC-515-P1 marine ventilation systems or equivalent. The scope of work includes site preparation with lock-out/tag-out procedures, removal of registers and ceiling sections, creation of access ports to ductwork, agitation and brushing using industrial equipment, compressed air washing, and HEPA filtration vacuuming to remove contaminants. Specific components requiring cleaning include Variable Air Velocity (VAV) boxes, reheat coils treated with EPA-approved cleaners, and Air Handling Units (AHUs) with thorough interior surface cleaning. Post-cleaning operations require sealing access ports with airtight plates, reinstallation of all components, complete cleanup, and a final walk-through inspection with before-and-after photographs.
The contractor must comply with NADCA ACR 2021 standards and OSHA requirements including hazard communication, lock-out/tag-out, respirator protection, and confined space procedures. Required insurance includes Commercial General Liability of $2,000,000 aggregate, Excess Liability (Umbrella) of $5,000,000 aggregate, and statutory Worker's Compensation. Work is scheduled Monday through Friday between 0600-1430 hours with site access coordination through Mr. Curtis LeFever at 508-596-2474. The Contracting Officer Representative is LT Colin Cashin. The period of performance will be mutually agreed upon based on vessel availability and contractor scheduling, with all work performed when service areas are unoccupied. The USCG will provide vessel access, water, and electricity as customer responsibilities.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Vent Cleaning 2 WD.pdf | ||
| DEI FAR Clause.docx | DOCX document | |
| Vent Cleaning 2 Clauses.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF HOMELAND SECURITY
UNITED STATES COAST GUARD
STATEMENT OF WORK (SOW) FOR
Machinery Ventilation System, Clean
AND
HVAC Duct System, Clean CGC John Patterson
REQUEST FOR QUOTE (RFQ) 70Z02426Q0000275
427 COMMERCIAL ST.
BOSTON, MA 02109
STATEMENT OF WORK (SOW)
FOR AIR CONVEYANCE SYSTEM CLEANING
UNITED STATES COAST GUARD BOAT 1153 CGC J. PATTERSON
1. Introduction/Background This Statement of Work (SOW) outlines the requirements for the cleaning of the air conveyance system(s) aboard the United States Coast Guard Boat 1153, located at 427 Commercial St, Boston, MA. The work will be performed by a certified member of the National Air Duct Cleaners Association (NADCA). The purpose of this work is to ensure the cleanliness and operational efficiency of the vessel's HVAC systems.
2. Scope of Work The contractor shall provide all necessary labor, materials, and equipment to perform the cleaning of the vessel's air conveyance systems. Technically competent with experience with Novenco FRC-515-P1, single piping, ABS, 3 phase X 450 V, 60HZ marine ventilation system or equivalent. The scope includes, but is not limited to, the following procedures:
2.1. Site Preparation:
Lock-Out/Tag-Out: Exhaust fans will be locked out by the Ships Engineering Watchstander and the Customer.
· Protective Covering: Cover all machinery, office equipment, furniture, and other components with plastic or drop cloths.
2.2. Gaining Access to Ductwork:
· Removal of all registers, vents, grilles, and diffusers.
· Removal of drop ceiling sections as needed.
· Cutting off exterior insulation where necessary.
· Cutting of various sized access ports into the ductwork in adherence with industry standards (NFPA, NAIMA, NADCA, SMACNA, UL).
2.3. Cleaning Process:
· Agitation and Brushing: Use of industrial brushes (hard and soft bristle) and other agitation devices to loosen dust and dirt build-up within the ductwork.
· Compressed Air Washing: Use of compressed air to loosen and move debris.
· Vacuum Collection: Employ High Efficiency Particulate Air (H.E.P.A.) filtration vacuum systems to remove contaminants. H.E.P.A. filters are rated as removing 99.97% of particles down to 0.3 microns.
· Specific Components:
· Variable Air Velocity (VAV) Boxes: Accessed via ports, HEPA vacuumed.
· Reheat Coils: Accessed via ports, fins HEPA vacuumed or brushed, treated with EPA approved coil cleaner, and rinsed.
· Air Handling Unit (AHU): Thorough cleaning of interior surfaces, plenum, condensing coils, filter racks, blower chamber and blades, dampers, and louvers.
2.4. Post-Cleaning Operations:
· Sealing Access Ports: All access ports created will be covered with removable airtight plates or doors in accordance with industry standards.
· Reinstallation: Reinstall all registers, grilles, diffusers, and ceiling tiles.
· Clean-Up: Remove all protective coverings, sweep floors, and vacuum carpets.
· Final Inspection: A walk-through of the service area with the customer and service coordinator to ensure completion and satisfaction.
· ELECTRONIC COPY OF BEFORE AND AFTER PHOTGRAPHS DOCUMENTING THE WORK
3. Administrative and Safety Requirements
· Standards Compliance: All work shall be performed in strict adherence to industry standard NADCA ACR 2021, Assessment, Cleaning & Restoration of HVAC Systems.
· Safety Program: The contractor will follow a comprehensive safety program in accordance with OSHA standards, including:
· Hazard Communication (OSHA 3111)
· Lock-out / Tag-out (OSHA 3120)
· Respirator Protection (OSHA 29CFR 1910.134)
· Confined Space Program (OSHA 3138)
· Use of Personal Protective Equipment (PPE) such as eye, head, and hearing protection.
· Insurance: The contractor shall maintain the following insurance coverage:
· Commercial General Liability: $2,000,000 Aggregate
· Excess Liability (Umbrella): $5,000,000 Aggregate
· Worker's Compensation: Statutory limits On-site Coordination:
Site visit:
Monday through Friday 0700-1300. Contact POC Mr. Curtis LeFever at 508-596-2474 or curtis.d.lefever@uscg.mil to schedule a site visit. A service coordinator will always be on the job site.
Contracting Officer Representative (COR): LT Colin Cashin @ 603-714-1778 or Colin.P.Cashin@uscg.mil
Workers will be escorted on Base. Passport or real id required
Work Hours: 0600 to 1430
4.The period of Period of Performance for this work shall be mutually agreed upon by the United States Coast Guard and The Awarded Vendor. The schedule will be based on the availability of the vessel and the contractor. All service work will be performed when the serviced areas are unoccupied.
5. Miscellaneous
• Customer Responsibilities: The USCG will be responsible for providing access to the vessel and for supplying shipboard services such as water and electricity.