VCT Cleaning Contract Schedule of Items.docx

DOCX document 17 KB Posted

Attached to
Virginia Creeper Trailhead Vault toilet Cleaning
Solicitation number
12443921Q0023
Issued by

View the file

Other files

File Type Posted
VCT Contract Cleaning Scope of Work 2021.docx DOCX document
VCT Cleaning Contract Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOUNT ROGERS NATIONAL RECREATION AREA

VIRGINIA CREEPER TRAIL CONTRACT CLEANING

SCHEDULE OF ITEMS

1. Straight Branch Trailhead (Start date – May 1st, 2021, End date – September 30th, 2021, which is 22 weeks)

a) Vault Toilet – 56 sq. ft., 1 Toilet; clean once daily Monday, Tuesday, Wednesday, Thursday, and Friday, clean twice daily Saturday and Sunday (morning and afternoon)

b) 1 Double Trash Receptacle – Garbage Collection, same as cleaning schedule

2. Creek Junction Trailhead (Start date – May 1st, 2021, End date – September 30th, 2021)

c) Vault Toilet – 56 sq. ft., 1 Toilet; clean once daily Monday, Tuesday, Wednesday, Thursday, and Friday, clean twice daily Saturday and Sunday (morning and afternoon)

d) 1 Double Trash Receptacle – Garbage Collection, same as cleaning schedule

1.

2.

3. Green Cove Station (Start date – May 1st, 2021, End date – September 30th, 2021)

a) Vault Toilet – 120 sq. ft., 2 Toilets - clean once daily Monday, Tuesday, Wednesday, Thursday, and Friday, clean twice daily Saturday and Sunday (morning and afternoon)

b) 1 Double Trash Receptacle, 1 Single Trash Receptacle – Garbage Collection, same as cleaning schedule

3.

4. Whitetop Station (Start date – May 1st, 2021, End date – September 30th, 2021)

c) Vault Toilet – 120 sq. ft., 2 Toilets - clean once daily Monday, Tuesday, Wednesday, Thursday, and Friday, clean twice daily Saturday and Sunday (morning and afternoon)

d) 1 Double Trash Receptacle, 1 Single Trash Receptacle – Garbage Collection, same as cleaning schedule

9 cleaning per week for 22 weeks equals 198 cleanings during performance period

Recreation Site
Cost per cleaning
Total cost of 198 cleanings

Straight Branch Trailhead

Creek Junction Trailhead

Green Cove Station

Whitetop Station