SLEEPY HOLLOW ROAD WATER MAIN IMPROVEMENTS
Solicitation number
2141029
Issued by
Westchester County, Brookhaven CDP, New York

About this file

This document is the Project Manual Rider (Volume 2) for the Village of Briarcliff Manor, Westchester County, New York, containing standardized bid documentation, contract conditions, and general construction contract terms. The Project Manual Rider serves as supplemental documentation to the main Project Manual (Volume 1) and establishes the procedural and contractual framework for construction projects undertaken by the Village. The document specifies that proposals must be submitted in sealed envelopes on forms prepared by the Engineer, with all original forms included in the Contract Documents booklet. Bidders are required to conduct site visits and familiarize themselves with existing conditions prior to submission. Proposals received after the scheduled deadline will be returned unopened, and no bidder may withdraw a proposal for 45 days after the bid opening. The contract will be awarded to the lowest and/or best-qualified responsible bidder who complies with all instructions and legal requirements. The Village reserves the right to reject any or all proposals or waive any formality or technicality in the interest of the Village. The Standard Construction Contract General Conditions establish time-of-essence performance requirements, with the Contractor obligated to commence work on the date specified in the Notice to Proceed and prosecute the work diligently to completion by the specified date.

A certified check or bid bond equal to 5% of the bid price must accompany sealed bids, with unsuccessful bidders' checks returned within 30 days of bid opening. The successful bidder must furnish a Performance Bond, Labor and Material Payment Bond, and Maintenance Bond, each in an amount equal to 100% of the contract price within ten days of notification of award acceptance. The Contractor must provide comprehensive insurance coverage including Commercial General Liability, Automobile Liability, Workers' Compensation, Employers' Liability, and NYS Disability Insurance from companies licensed in New York State. Liquidated damages are assessed for each calendar day of delay beyond the completion date as specified in the Special Conditions. The contract incorporates prevailing wage rate requirements in accordance with New York State Labor Law Section 220. Extensions of time may be granted only by the Village under specific circumstances including acts or omissions of the Village, acts or omissions of other contractors, or supervening conditions beyond the control of either party, provided the Contractor has strictly complied with progress schedule and information request requirements. The document includes detailed provisions regarding subcontracts, payment procedures, final completion and acceptance processes, indemnification obligations, and dispute resolution mechanisms, establishing comprehensive terms and conditions for public works construction projects.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LAST UPDATED: AUGUST 2026

VILLAGE OF BRIARCLIFF MANOR

1111 Pleasantville Road

Briarcliff Manor, NY 10510

VILLAGE OF BRIARCLIFF MANOR

WESTCHESTER COUNTY, NY

PROJECT MANUAL RIDER

Vol. 2

Mayor Deputy Mayor Trustee Trustee Trustee

Village Manager

Steven Vescio Peter Chatzky Kevin Hunt Rhea Mallett Robert Mayer

Josh Ringel Greg McCann DPW Superintendent

THIS RIDER SUPPLEMENTS THE PROJECT MANUAL. PLEASE REFER TO

PROJECT MANUAL (VOL 1) FOR BID DOCUMENTATION TO BE COMPLETED,

SIGNED AND SUBMITTED.

VOL 2 of 2 VBM PROJECT MANUAL RIDER R-1

INFORMATION FOR BIDDERS

Each Proposal shall be made on a form prepared by the Engineer and included as one of the Contract Documents; and shall be submitted in a sealed envelope bearing the title of work and name of the Bidder. The Contractor's Bid shall be submitted in the Contract Documents booklet including all original forms. Any deviation shall be grounds for disqualification of bid.

In case of a difference between the stipulated amount of the Proposal written in words and the stipulated amount written in figures, the stipulated amount stated in words shall govern.

Proposals shall not contain any recapitulations of the work to be done. Alternate proposals will not be considered unless called for. Oral proposals or modifications will not be considered.

Before submitting a Proposal, Bidders shall carefully read the Specifications, including the Special Conditions and other contract Documents, shall visit the site, and shall fully inform themselves as to all existing conditions and limitations, and shall include in the Proposal a sum to cover the cost of all items included in the Contract Drawings and Documents. A mandatory walk through is only required if stated in the Notice to Bidders.

Proposals shall be delivered by the time and to the place stipulated in the advertisement.

It is the sole responsibility of the Bidder to see that his Proposal is received in proper time.

Any Proposal received after the scheduled time for receipt of Proposals shall be returned to the Bidder unopened.

Any Bidder may withdraw his Proposal, either personally or by written request, at any time prior to the scheduled bid time for receipt of Proposals.

Proposals will be opened and publicly read aloud at the time and place set forth in the Notice to Bidders.

The contract will be awarded to the lowest and/or best-qualified responsible Bidder who complies with these instructions and with the Legal Notice. The Village reserves the right to reject any or all Proposals or to waive any formality or technicality in any Proposal in the interest of the Village. No Bidder may withdraw his Proposal for a period of 45 days after the date of opening thereof.

If any person contemplating submitting a Proposal is in doubt to the true meaning of any part of the Drawings, Specifications or other Contract Documents, or finds discrepancies in, or omissions from, the Drawings or Specifications, he may submit to the Engineer a written request for an interpretation or correction thereof, the person submitting the request will be responsible for its prompt delivery. Any interpretation or correction of the documents will be made only by Addendum duly issued and a copy of the Addendum will be mailed or delivered to each person receiving a set of the Contract Documents. Neither the Village nor the Engineer will be responsible for any other explanations or interpretations of the Contract Documents.

R-2

Any Addenda issued during the time of the bidding, or forming a part of the Contract Documents received by the Bidder for the preparation of a Bid shall be covered in the Proposal and shall be made a part of the Contract. Receipt of each Addendum shall be acknowledged in the Proposal.

No person, firm or corporation shall be allowed to make, file or be interested in more than one Proposal for the same Contact as the prime bidder. A person, firm or corporation who has submitted a sub-proposal to a Bidder, or who has quoted prices on materials to a Bidder, is not hereby disqualified from submitting a sub-proposal or quoting prices to other Bidders.

The work under this contract shall be completed within the timeframe indicated in the Special Conditions, unless the Village waives adherence to this date in writing. The Contractor will be required to pay as liquidated damages, the sum of which is indicated in the Special Conditions for each calendar day beyond said time that is required to satisfactorily complete the work of this project.

The attention of persons intending to submit proposals is specifically called to the fact that no plea will be accepted in which a Contractor pleads misunderstanding or deception of estimates of quantities, character, scope of work, location or other conditions surrounding same. Permission will not be given to withdraw, modify or explain any proposal or bid after it has been deposited.

To be entitled to consideration, a Certified Check or Bid Bond payable to the Village of Briarcliff Manor, New York shall accompany the sealed bid, for the sum equal to 5% of the bid price. The checks of the unsuccessful bidders shall be returned within 30 days of the bid opening. Within ten (10) days of notification of acceptance and approval of the proposal, the successful bidder shall furnish the performance bond described herein, at which time the 5% check will be returned. Should the bidder neglect to or refuse to furnish the aforesaid bond, the 5% shall be retained by the Village of Briarcliff Manor, New York.

The Performance Bond that the Contractor is to provide, shall be issued by a solvent insurance company authorized to do business in the State of New York and which will indemnify and insure the Village of Briarcliff Manor, New York, so that all work herein required to be performed and all material to be furnished, will be satisfactorily completed in accordance with this proposal. The amount of the bond shall be 100% of the amount of the contract price. The form of this bond is included herein.

The Contractor shall also pay for and furnish a separate Labor and Material Bond payment, guaranteeing prompt payment of monies due to all persons supplying the Contractor or any Sub-contractor with work, labor or materials employed and used in carrying out the Contract. The amount of such bond shall be 100% of the amount of the contract price. The form of this bond is included herein.

In addition, at the time of final payment, a Maintenance Bond guaranteeing against defective materials and workmanship will be required in an amount equal to one hundred percent (100%) of the contract amount. The Maintenance Bond shall be in effect for a

R-3 period of two-year from the date of final acceptance of the project. The form of this bond is included herein.

The Contractor, prior to signing of the contract, shall provide to the Village of Briarcliff Manor and maintain throughout the life of the contract, at his own cost and expense, proof of the following insurance by insurance companies licensed in the State of New York; Commercial General Liability Insurance; Automobile Liability; Workers' Compensation; Employers’ Liability and NYS Disability Insurance; Excess Insurance.

Only if indicated in the Special Conditions the following insurances may be required;

Owners Contractors Protective Insurance (OCP); Builders Risk Insurance or Installation Floater. Refer to Section I, Insurance and Special Conditions for specific insurance requirements.

The Contractor shall comply with all local, state, and federal laws, rules and regulations applicable and with the New York State Labor Law.

All costs and expenses for obtaining and providing required shop drawings, submittals, Insurances and Bonds shall be deemed included in all items of this contract and therefore no separate payment item is provided.

Before submitting a proposal, each bidder shall examine the premises which the work is to be done, and shall thoroughly familiarize himself/herself with the existing conditions and any difficulties which may present themselves in the execution of the contract.

R-4

INDEMNIFICATION AGREEMENT

The Contractor, including any Subcontractor or any other firm or entity related thereto, agrees to protect, defend, indemnify and hold the Village of Briarcliff Manor, and any agents, officers, employees and consultants of any of them, free and harmless from and against any and all losses, penalties, damages, settlements, costs, charges, professional fees or other expenses or liabilities of every kind and character arising out of or relating to any and all claims, liens, demands, obligations, actions, proceedings or causes of action of every kind and character in connection with or arising directly or indirectly out of this agreement and/or the performance hereof: without limiting the generality of the foregoing, any and all such claims, etc., relating to personal injury, death, damage to property, defects in materials or workmanship, actual or alleged infringement of any patent, trademark, copyright (or application for any thereof) or of any other tangible or intangible personal or property right, or any actual or alleged violation of any applicable statute, ordinance, administrative order, rule or regulation, decree of any court, shall be included in the indemnity hereunder. The Contractor further agrees to investigate, handle, respond to, provide defense for and defend any such claims, etc., at his sole expense and agrees to bear all other costs and expenses related thereto, even if it (claims, etc.), is groundless, false or fraudulent. In any case in which such indemnification would violate Section 5-322.l of the New York General Obligations Law, or any other applicable legal prohibition, the foregoing provisions concerning indemnification shall not be construed to indemnify the Owner for damage arising out of bodily injury to persons or damage to property caused by or resulting from the sole negligence of the Owner, or its employees.

SIGNED AND SEALED this _________ day of _____________ A.D. 20______

In the presence of: {_______________________________(Seal)

PRINCIPAL

WITNESS TITLE

R-5

AGREEMENT

THIS AGREEMENT, made this day of , 20 , by and between , (a corporation organized and existing under the state of

)*(a LLC consisting of )*(a partnership consisting of )*(an individual trading as )*(hereinafter called the

“Contractor” and Village of Briarcliff Manor, New York hereinafter called the “Owner”

WITNESSETH, that the Contractor and the Owner for the considerations stated herein mutually agree as follows:

Article 1. Statement of Work. The Contractor shall furnish all supervision, technical personnel, labor, materials, machinery, tools, appurtenances, equipment and services, including utility and transportation services and perform and complete all work and required supplemental work for the completion of this Contract in strict accordance with the hereinafter referenced Contract Documents, including all Addenda thereto, numbered

Article 2. The Contract Price. The Owner will pay the Contractor for the performance of the Contract in current funds, for the total quantities of work performed at the unit prices stipulated in the bid for the respective items of work completed subject to additions and deduction as provided in the Section-Changes in the work in the General Conditions.

* Strike out the two terms not applicable.

R-6

Article 3. Contract Documents. The Contract Documents shall consist of the following (included or otherwise referenced therein as attachments and exhibits). The below items are listed in no particular order with each document being equally relevant:

• Agreement

• Project Manual Rider

• Addenda (if any)

• Notice to Bidders

• Information to Bidders

• Sign copy of Bid, with all attachments required for the bidding

• Special Conditions

• Any Standard Specifications issued by any Local, County, State or Federal entities i.e.

NYSDOT

• Standard Construction Contract, General Conditions

• Technical Specifications

• Drawings (as listed in the

Schedule of Drawings)

• Payment & Bonds

• Certificates of Insurance

• Supplemental Information

This Agreement, together with other Documents enumerated in the Article 3, which said other Documents are as fully a part of the Contract as if hereto attached or herein repeated, forms the Contract between the parties hereto. In the event that any provision in any component part of this Contract conflicts with any provision of any other component, the part first enumerated in this Article 3 shall govern, except as otherwise specifically stated.

IN WITNESS WHEREOF, the parties hereto have caused this AGREEMENT to be executed in five (5) original copies on the day and year first above written.

ATTEST:

(Contractor)

By:

(Name of Contractor)

Title:

Village of Briarcliff Manor, New York

By:

Title

R-7

PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS that

(Here insert the name and address or legal title of the Contractor) as Principal, hereinafter called the Contractor, and

(Here insert the legal title of Surety) as Surety, hereinafter called Surety, are held and firmly bound unto

(Here insert the name and address or legal title of the Owner)

_______________________________________ as Obligee hereinafter called Owner, in the amount of_____________________________________________ Dollars ($___________) for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, Contractor has by written agreement dated

20____ entered into a Contract with Owner for in accordance with drawings and specifications prepared by

(Here insert full name and title)

R-8 which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, the Contractor shall promptly and faithfully perform said Contract, then this obligation shall be null and void; otherwise shall remain in full force and effect.

A. The Surety hereby waives notice of any alteration or extension of time made by the Owner.

B. Whenever Contractor shall be, and declared by Owner to be in default under the Contract, the Owner having performed Owner’s obligations thereunder, the Surety may promptly remedy the default, or shall promptly

C. Complete the Contract in accordance with its terms and conditions, or

1. Obtain a bid or bids for submission to Owner for completing the Contract in accordance with terms and conditions, and upon determination by Owner and Surety of the lowest responsible bidder, arrange for a contract between such bidder and Owner, and make available as work progresses (even though there should be a default or a succession of defaults under the contract or contracts of completion arranged under this paragraph) sufficient funds to pay the cost of completion less the balance of the Contract price; but the exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount forth in the first paragraph hereof. The term “balance of the Contract price,” as used in this paragraph, shall mean the total amount payable by Owner to Contractor under the Contract and any amendments thereof less the amount properly paid by Owner to Contractor.

2. Any suit under this bond must be instituted before the expiration of two (2) years from the date which final payment under the Contract fails due.

D. No right of action shall accrue on this bond to or for the use of any person or corporation other than the Owner named herein or the heirs, executors, administrators or successors of Owner.

R-9

SIGNED AND SEALED this _________ day of _____________ A.D. 20______

In the presence of: {_______________________________(Seal)

PRINCIPAL

{_________________________(Seal)

SURETY

R-10

LABOR AND MATERIAL PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS that ________________________________

(Here insert the name and address or legal title of the Contractor) as Principal, hereinafter called Principal, and

(Here insert the legal title of Surety) as Surety, hereinafter called Surety, are held and firmly bound unto

(Here insert the name and address or legal title of the Owner) as Obligee, hereinafter called Owner, for the use and benefit of claimants as herein below defined, in the amount of

____________________________________________Dollars for the payment whereof Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

WHEREAS, Principal has by written agreement dated _____________________, 20____ entered into a contract with Owner for ____________________________________ in accordance with the drawings and specifications prepared by

(Here insert full name and title) which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.

R-11

NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that if the Principal shall promptly make payment to all claimants as hereinafter defined, for all labor and material used or reasonably for use in the performance of the Contract, then this obligation shall be void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:

A. A claimant is defined as one having a direct contract with the Principal or with a subcontractor of the Principal for labor, material, or both, used or reasonably required for use in the performance of the Contract labor and material being construed to include that part of water, gas, power, light, heat, oil, gasoline, telephone service or rental of equipment directly applicable to the Contract.

B. The above named Principal and Surety hereby jointly and severally agree with the Owner that every claimant as herein defined, who has not been paid in full before the expiration of a period of ninety (90) days after the date on which the last of such claimant’s work or labor was done or performed, or materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due claimant, and have execution thereon. The Owner shall not be liable for the payment of any costs or expenses of any such suit.

C. No suit or action shall be commenced hereunder by any claimant,

1. Unless claimant, other than one having a direct contract with the Principal, shall have given written notice to any two of the following:

The Principal, the Owner, or the Surety above named, within ninety

(90) days after such claimant did or performed the last of the work or labor, or furnished the last of the material for which said claim is made, stating with substantial accuracy the amount claimed and the name of the part to whom the materials were furnished, or for whom the work or labor was done or performed. Such notice shall be served by mailing the same by registered mail or certified mail, postage prepaid, in an envelope addressed to the Principal, Owner or Surety, at any place where an office is regularly maintained for the transaction of business, or served in any manner which is legal process may be served in the state in which the aforesaid project is located, save that such service need not be made by a public officer.

2. After the expiration of one (1) year following the date on which the

Principal ceased work on such Contract, it being understood, however, that if any limitation embodied in this bond is prohibited by any law controlling the construction hereof such limitation shall be

R-12 deemed to be amended so as to be equal to the minimum period of limitation permitted by such law.

3. Other than in a state court of competent jurisdiction in and for the county or other political subdivision of the state in which the project, or any part thereof, is situated, or in the United States District Court for the district in which the project, or any part thereof, is situated, and not elsewhere.

D. The amount of this bond shall be reduced by and to the extent of any payment or payments made in good faith hereunder, inclusive of the payment by Surety of mechanics’ liens which may be filed of record against said improvement, whether or not claim for the amount of such lien be presented under and again this bond.

SIGNED AND SEALED this ______________day of ___________A.D.20_____

In the presence of: {____________________________________(Seal)

PRINCIPAL

WITNESS

TITLE

{______________________________(Seal)

SURETY

R-13

SUBMITTAL FORM

SUBMITTALS:

All submittals prepared by or for the Contractor, shall be thoroughly checked by the

Contractor for accuracy and conformance to the intent of the Contract Documents before being submitted to the Engineer and shall bear the Contractor's signature certifying that they have been so checked. Before submitting them to the Engineer, all submittals shall be properly labeled and consecutively numbered. Contractor shall attach this completed sheet to all submittals. The Contractor shall note, in writing, if there are any deviations from the Contract drawings and specifications.

CONTRACT NO.: VM – XXXX-X DATE:

NAME OF PROJECT: XXXXX XXXXX

SPECIFICATION SECTION:

MANUFACTURER:

ITEM/MODEL NO.:

This document has been reviewed, coordinated and checked for accuracy of content and for compliance with the Contract Documents. The information contained herein has been coordinated with all other Contract Work.

CONTRACTOR:

SIGNATURE:

DO NOT WRITE BELOW THIS LINE

□ NO EXCEPTION TAKEN □ MAKE CORRECTIONS NOTED

□ REJECTED □ REVISE AND RESUBMIT

Checking is only for general conformance with the design concept of the project and general compliance with the information given in the contract documents. Any action shown is subject to the requirements of the plans and specifications. Contractor is responsible for; dimensions which shall be confirmed and correlated at the job site; Fabrication processes and techniques of construction; Coordination of his work with that of all other trades; and the satisfactory performance of his work.

DATE BY

R-14

PAYMENT SUBMISSION FORM

PROJECT:

Village of Briarcliff Manor

VM – XXXX-XX

PAYMENT ESTIMATE NO.

DATE

Work Credited Under Unit Prices

Change Orders

Total Work Credited To Date

5% Retained

Sub-Total

PREVIOUS PAYMENTS

TOTAL DUE THIS PAYMENT

I have reviewed the estimate and certify that the quantities are correct and that I know that there are no claims for additional work.

DATE:

(CONTRACTOR)

I hereby certify that the above is the total amount of work completed, and the foregoing payment is due under the contract.

(ENGINEER)

VBM PROJECT MANUAL RIDER

R-15

GENERAL RELEASE

(TO-BE SUBMITTED WITH REQUISITION FOR ANY AND ALL PAYMENTS)

KNOW ALL MEN BY THESE PRESENTS, that

Contractor for and in consideration of the sum of lawful money of the United States of America, to it in hand paid by

Village of Briarcliff Manor (Owner/Contracting Agency) have remised, released, quit-claimed, and forever discharged, and by these presents do for its successors and assigns remise, release, quit-claim, and forever discharge the said

Village of Briarcliff Manor (Owner/Contracting Agency) and its successors and assigns and administrators, of and from and all manner of action and actions, caused and causes of action, suits, debts, dues, sum and sums of money, accounts, reckonings, bonds, bills, specialties, covenants, contracts, controversies, agreements, promises, variances, trespasses, damages, judgements, patents, extents, executions, claims and demands whatsoever in law and unity which against the said

Village of Briarcliff Manor (Owner/Contracting Agency) now have or which heirs, executors, or administrator hereafter can, shall, or may have, for upon or by reason of any matter, cause or thing whatsoever, from the beginning of the world to the day of the date of these presents rising out of the construction, in accordance with contract entered into between parties hereto, dated _________________________________________________ two thousand and ___________________________ , any admittance or supplements thereto.

IN WITNESS WHEREOF, the undersigned corporation has caused this agreement to be signed by its _____________________________________________and its corporate seal to be hereto affixed and duly attested by its_________________________________ this ____day of ____________________, 20___.

ATTEST: PRINCIPAL:

R-16

MAINTENANCE BOND

KNOW ALL MEN BY THESE PRESENTS:

That We, ______________________________________________________________

______________________________________________(hereinafter called the Principal) as Principal and the _________________, a ___________________ Corporation with an office and place of business for the State of New York at ________________, New York, (hereinafter called the Surety) as Surety, are held and firmly bound unto the

(hereinafter called the Obligee) as Obligee in the sum of __________________________

_________________________________________ ($_________________) DOLLARS,

lawful money of the United States of America, for the payment whereof the Principal and

Surety bind themselves, their successors and assigns, jointly and severally, firmly by these presents.

Signed, sealed and dated this _________ day of _____________, 20 ____.

WHEREAS, the Principal heretofore entered into a written contract with the Obligee for _____________________________________________________________

WHEREAS, said Contract provides that the Principal shall guarantee __________

NOW, THEREFORE, the condition of this obligation is such, that if the above Principal shall indemnify the Obligee against loss by reason of his failure to make good at his own expense any defects or deficiencies in materials or workmanship which may appear in the work under said contract with the period of two years from the date of acceptance of the work, then this obligation shall be void; otherwise to remain in full force and effect.

Principal

By: ________________________________

By: ________________________________

R-17

STATE OF __________________)

COUNTY OF ________________)

On this____________ day of ________________________ 20 ______ before me personally appeared the within named ________________________________________ to me known, and known to me to be _________________________________________, the individual described in and who executed the within bond, and __________________

___________________ acknowledged to me that he _____________________________ executed the same.

NOTARY PUBLIC

R-18

WAGE RATES

The Labor Law requires public work contractors and subcontractors to pay laborers, workers, or mechanics employed in the performance of a public work contract not less than the prevailing rate of wage and supplements (fringe benefits) in the locality where the work is performed.

Prevailing wage rates are attached herein.

R-19

VILLAGE OF BRIARCLIFF MANOR

STANDARD CONSTRUCTION CONTRACT

GENERAL CONDITIONS

WITNESSETH:

The parties, in consideration of the mutual agreements contained herein, agree as follows:

CHAPTER I: THE CONTRACT AND DEFINITIONS ARTICLE 1. THE CONTRACT

1.1 Except for titles, subtitles, headings, running headlines, tables of contents and indices (all of which are printed herein merely for convenience), the following, except for such portions thereof as may be specifically excluded, shall be deemed to be part of this Contract.

1.1.1 All provisions required by law to be inserted in this Contract, whether actually inserted or not;

1.1.2 The Contract Drawings, Specifications including any Standard Specifications issued by any Local, County, State or Federal entities i.e. NYSDOT.

1.1.3 The General Conditions and Special Conditions, if any;

1.1.4 The Contract;

1.1.5 The Information for Bidders; Request for Proposals; Notice to Bidders and Proposal for Bids; Bid or Proposal, and, if used, the Bid Documents;

1.1.6 All Addenda issued prior to the receipt of the bids; the Notice of Award;

Performance and Payment Bonds, if required; and the Notice to Proceed or the Order to Work.

1.2 Should any conflict occur in or between the Drawings and Specifications, the Contractor shall be deemed to have estimated the most expensive way of doing the Work, unless the Contractor shall have asked for and obtained a decision in writing from the Village, before the submission of its bid, as to what shall govern.

ARTICLE 2. DEFINITIONS

2.1 The following words and expressions, or pronouns used in their stead, shall, wherever they appear in this Contract, be construed as follows, unless a different meaning is clear from the context:

2.1.1 “Addendum” or “Addenda” shall mean the additional Contract provisions and/or technical clarifications issued in writing by the Village prior to the receipt of bids.

R-20

2.1.2 “Agency” shall mean the Village or other office, position, department, Board, or agency of government, the expenses of which are paid in whole or in part from the Village Treasury.

2.1.3 INTENTIONALLY OMITTED

2.1.4 “Owner’s Contingency Allowance” shall mean a sum of money which the Village may include in the total amount of the Contract for such specific contingencies as the Village believes may be necessary to complete the Work, e.g., lead or asbestos remediation, and for which the Contractor will be paid on the basis of stipulated unit prices or a formula set forth in the Contract or negotiated between the parties provided, however, that if the Contractor is not directed to use the Allowance, the Contractor shall have no right to such money and it shall be deducted from the total amount of the Contract.

2.1.5 INTENTIONALLY OMITTED

2.1.6 INTENTIONALLY OMITTED

2.1.7 “Village” shall mean the Agency that has entered into this Contract, or it’s duly authorized representative; or otherwise the Village of Briarcliff Manor, 1111 Pleasantville Road, Briarcliff Manor, NY 10510.

2.1.8 INTENTIONALLY OMITTED

2.1.9 “Contract” or “Contract Documents” shall mean each of the various parts of the contract referred to in Article 1 hereof, both as a whole and severally.

2.1.10 “Contract Drawings” shall mean only those drawings specifically entitled as such and listed in the Specifications or in any Addendum, or any drawings furnished by the Village, pertaining or supplemental thereto.

2.1.11 “Contract Work” shall mean everything required to be furnished and done by the Contractor by any one or more of the parts of the Contract referred to in Article 1, except Extra Work as hereinafter defined.

2.1.12 “Contractor” shall mean the entity which executed this Contract, whether a corporation, firm, partnership, joint venture, individual, or any combination thereof, and its, their, his/her successors, personal representatives, executors, administrators, and assigns, and any person, firm, partnership, joint venture, individual, or corporation which shall at any time be substituted in the place of the Contractor under this Contract.

2.1.13 “Days” shall mean calendar days, except where otherwise specified.

2.1.14 “Engineer” or “Architect” or “Project Manager” shall mean the person so designated by the Village in the Notice to Proceed or the Order to Work to act as such in relation to this Contract, including a private Architect or Engineer or Project Manager, as the case may be.

Subject to written approval by the Village, the Engineer, Architect or Project Manager may designate an authorized representative.

R-21

2.1.15 INTENTIONALLY OMITTED

2.1.16 “Extra Work” shall mean Work other than that required by the Contract at the time of award which is authorized by the Village pursuant to Chapter VI of this Contract.

2.1.17 “Federal-Aid Contract” shall mean a contract in which the United States (federal) Government provides financial funding as so designated in the Information for Bidders.

2.1.18 “Final Acceptance” shall mean final written acceptance of all the Work by the Village, a copy of which shall be sent to the Contractor.

2.1.19 “Final Approved Punch List” shall mean a list, approved pursuant to Article 14.2.2, specifying those items of Work to be completed by the Contractor after Substantial Completion and dates for the completion of each item of Work.

2.1.20 “Law” or “Laws” shall mean the Constitution of the State of New York, the New York State Administrative Code, a statute of the United States or of the State of New York, a local law of the Village, any ordinance, rule or regulation having the force of law, or common law.

2.1.21 “Materialman” shall mean any corporation, firm, partnership, joint venture, or individual, other than employees of the Contractor, who or which contracts with the Contractor or any Subcontractor, to fabricate or deliver, or who actually fabricates or delivers, plant, materials or equipment to be incorporated in the Work.

2.1.22 “Means and Methods of Construction” shall mean the labor, materials, temporary structures, tools, plant, and construction equipment, and the manner and time of their use, necessary to accomplish the result intended by this Contract.

2.1.23 “Notice to Proceed” or “Order to Work” shall mean the written notice issued by the Village specifying the time for commencement of the Work and the Engineer, Architect or Project Manager.

2.1.24 “Other Contractor(s)” shall mean any contractor (other than the entity which executed this Contract or its Subcontractors) who or which has a contract with the Village for work on or adjacent to the building or Site of the Work.

2.1.25 “Payroll Taxes” shall mean State Unemployment Insurance (SUI), Federal Unemployment Insurance (FUI), and payments pursuant to the Federal Insurance Contributions Act (FICA).

2.1.26 “Project” shall mean the public improvement to which this Contract relates.

2.1.27 INTENTIONALLY OMITTED

2.1.28 “Required Quantity” in a unit price Contract shall mean the actual quantity of any item of Work or materials which is required to be performed or furnished in order to comply with the Contract.

2.1.29 INTENTIONALLY OMITTED

R-22

2.1.30 “Site” shall mean the area upon or in which the Contractor’s operations are carried on, and such other areas adjacent thereto as may be designated as such by the Engineer.

2.1.31 “Small Tools” shall mean items that are ordinarily required for a worker’s job function, including but not limited to, equipment that ordinarily has no licensing, insurance or substantive storage costs associated with it; such as circular and chain saws, impact drills, threaders, benders, wrenches, socket tools, etc.

2.1.32 “Specifications” shall mean all of the directions, requirements, and standards of performance applying to the Work as hereinafter detailed and designated under the Specifications.

2.1.33 “Subcontractor” shall mean any person, firm or corporation, other than employees of the Contractor, who or which contracts with the Contractor or with its subcontractors to furnish, or actually furnishes labor, or labor and materials, or labor and equipment, or superintendence, supervision and/or management at the Site. Wherever the word Subcontractor appears, it shall also mean sub-Subcontractor.

2.1.34 “Substantial Completion” shall mean the written determination by the Engineer that the Work required under this Contract is substantially, but not entirely, complete and the approval of the Final Approved Punch List.

2.1.35 “Work” shall mean all services required to complete the Project in accordance with the Contract Documents, including without limitation, labor, material, superintendence, management, administration, equipment, and incidentals, and obtaining any and all permits, certifications and licenses as may be necessary and required to complete the Work, and shall include both Contract Work and Extra Work.

CHAPTER II: THE WORK AND ITS PERFORMANCE

ARTICLE 3. CHARACTER OF THE WORK

3.1 Unless otherwise expressly provided in the Contract Drawings, Specifications, and Addenda, The Work shall be performed in accordance with the best modern practice, utilizing, unless otherwise specified in writing, new and unused materials of standard first grade quality and workmanship and design of the highest quality, to the satisfaction of the Village.

ARTICLE 4. MEANS AND METHODS OF CONSTRUCTION

4.1 Unless otherwise expressly provided in the Contract Drawings, Specifications, and Addenda, the Means and Methods of Construction shall be such as the Contractor may choose; subject, however, to the Engineer’s right to reject the Means and Methods of Construction proposed by the Contractor which in the opinion of the Engineer:

4.1.1 Will constitute or create a hazard to the Work, or to persons or property;

or

4.1.2 Will not produce finished Work in accordance with the terms of the

R-23

Contract; or

4.1.3 Will be detrimental to the overall progress of the Project.

4.2 The Engineer’s approval of the Contractor’s Means and Methods of Construction, or his/her failure to exercise his/her right to reject such means or methods, shall not relieve the Contractor of its obligation to complete the Work as provided in this Contract; nor shall the exercise of such right to reject create a cause of action for damages.

ARTICLE 5. COMPLIANCE WITH LAWS

5.1 The Contractor shall comply with all Laws applicable to this Contract and to the Work to be done hereunder.

5.2 INTENTIONALLY OMITTED

5.3 Noise Control Code provisions.

5.3.1 The Contractor to the maximum extent possible comply with Chapter 146, Noise of the Code of Briarcliff Manor.

5.3.2 INTENTIONALLY OMITTED

5.4 INTENTIONALLY OMITTED

5.5 INTENTIONALLY OMITTED

5.6 INTENTIONALLY OMITTED

5.7 INTENTIONALLY OMITTED

5.8 INTENTIONALLY OMITTED

ARTICLE 6. INSPECTION

6.1 During the progress of the Work and up to the date of Final Acceptance, the Contractor shall at all times afford the representatives of the Village of Briarcliff Manor every reasonable, safe, and proper facility for inspecting all Work done or being done at the Site and also for inspecting the manufacture or preparation of materials and equipment at the place of such manufacture or preparation.

6.2 The Contractor’s obligation hereunder shall include the uncovering or taking down of finished Work and its restoration thereafter; provided, however, that the order to uncover, take down and restore shall be in writing, and further provided that if Work thus exposed proves satisfactory, and if the Contractor has complied with Article 6.1, such uncovering or taking down and restoration shall be considered an item of Extra Work to be paid for in accordance with the provisions of Article 26. If the Work thus exposed proves unsatisfactory, the Village of Briarcliff Manor has no obligation to compensate the Contractor for the uncovering, taking down or restoration.

6.3 Inspection and approval by the Village, the Engineer or Project Manager of finished Work or of Work being performed, or of materials and equipment at the place of manufacture or preparation, shall not relieve the Contractor of its obligation to perform the Work in strict accordance with the Contract. Finished or unfinished Work not found to be in strict accordance with the Contract shall be replaced as directed by the Engineer, even though

R-24 such Work may have been previously approved and paid for. Such corrective Work is Contract Work and shall not be deemed Extra Work.

6.4 Rejected Work and materials shall be promptly taken down and removed from the Site at Contractor’s sole cost and expense, which must at all times be kept in a reasonably clean and neat condition.

ARTICLE 7. PROTECTION OF WORK AND OF PERSONS AND PROPERTY; NOTICES

AND INDEMNIFICATION

7.1 During the performance of the Work and up to the date of Final Acceptance, the Contractor shall be under an absolute obligation to protect the finished and unfinished Work against any damage, loss, injury, theft and/or vandalism and in the event of such damage, loss, injury, theft and/or vandalism, it shall promptly replace and/or repair such Work at the Contractor’s sole cost and expense, as directed by the Engineer. The obligation to deliver finished Work in strict accordance with the Contract prior to Final Acceptance shall be absolute and shall not be affected by the Engineer’s approval of, or failure to prohibit, the Means and Methods of Construction used by the Contractor.

7.2 During the performance of the Work and up to the date of Final Acceptance, the Contractor shall take all reasonable precautions to protect all persons and the property of the Village of Briarcliff Manor and of others from damage, loss or injury resulting from the Contractor’s, and/or its Subcontractors’ operations under this Contract. The Contractor’s obligation to protect shall include the duty to provide, place or replace, and adequately maintain at or about the Site suitable and sufficient protection such as lights, barricades, and enclosures.

7.3 The Contractor shall comply with the notification requirements set forth below in the event of any loss, damage or injury to Work, persons or property, or any accidents arising out of the operations of the Contractor and/or its Subcontractors under this Contract.

7.3.1 The Contractor shall make a full and complete report in writing to the Engineer within three (3) Days after the occurrence.

7.3.2 The Contractor shall also send written notice of any such event to all insurance carriers that issued potentially responsive policies (including commercial general liability insurance carriers for events relating to the Contractor’s own employees) no later than twenty (20) days after such event and again no later than twenty (20) days after the initiation of any claim and/or action resulting therefrom. Such notice shall contain the following information: the number of the insurance policy, the name of the Named Insured, the date and location of the incident, and the identity of the persons injured or property damaged. For any policy on which the Village of Briarcliff Manor and/or the Engineer, Architect, or Project Manager are Additional Insureds, such notice shall expressly specify that “this notice is being given on behalf of the Village as Additional Insured, such other Additional Insureds, as well as the Named Insured.”

7.3.2(a) Whenever such notice is sent under a policy on which the Village of Briarcliff Manor is an Additional Insured, the Contractor shall provide copies of the notice to the Village and

R-25 the Village of Briarcliff Manor Counsel. The copy to the Village shall be sent to the Village Clerk, 1111 Pleasantville Road, Briarcliff Manor, NY 10510.

7.3.2(b) If the Contractor fails to provide any of the foregoing notices to any appropriate insurance carrier(s) in a timely and complete manner, the Contractor shall indemnify the Village of Briarcliff Manor for all losses, judgments, settlements, and expenses, including reasonable attorneys’ fees, arising from an insurer’s disclaimer of coverage citing late notice by or on behalf of the Village of Briarcliff Manor.

7.4 To the fullest extent permitted by law, the Contractor shall defend, indemnify, and hold the Village of Briarcliff Manor, its employees, and officials (the “Indemnitees”) harmless against any and all claims (including but not limited to claims asserted by any employee of the Contractor and/or its Subcontractors) and costs and expenses of whatever kind (including but not limited to payment or reimbursement of attorneys’ fees and disbursements) allegedly arising out of or in any way related to the operations of the Contractor and/or its Subcontractors in the performance of this Contract or from the Contractor’s and/or its Subcontractors’ failure to comply with any of the provisions of this Contract or of the Law. Such costs and expenses shall include all those incurred in defending the underlying claim and those incurred in connection with the enforcement of this Article

7.4 by way of cross-claim, third-party claim, declaratory action or otherwise. The parties expressly agree that the indemnification obligation hereunder contemplates (1) full indemnity in the event of liability imposed against the Indemnitees without negligence and solely by reason of statute, operation of Law or otherwise; and (2) partial indemnity in the event of any actual negligence on the part of the Indemnitees either causing or contributing to the underlying claim (in which case, indemnification will be limited to any liability imposed over and above that percentage attributable to actual fault whether by statute, by operation of Law, or otherwise). Where partial indemnity is provided hereunder, all costs and expenses shall be indemnified on a pro rata basis.

7.4.1 Indemnification under Article 7.4 or any other provision of the Contract shall operate whether or not Contractor or its Subcontractors have placed and maintained the insurance specified under Article 22.

7.5 The provisions of this Article 7 shall not be deemed to create any new right of action in favor of third parties against the Contractor or the Village of Briarcliff Manor.

CHAPTER III: TIME PROVISIONS

ARTICLE 8. COMMENCEMENT AND PROSECUTION OF THE WORK

8.1 The Contractor shall commence the Work on the date specified in the Notice to Proceed or the Order to Work. The time for performance of the Work under the Contract shall be computed from the date specified in the Notice to Proceed or the Order to Work.

TIME BEING OF THE ESSENCE to the Village of Briarcliff Manor, the Contractor shall thereafter prosecute the Work diligently, using such Means and Methods of Construction as are in accord with Article 4 herein and as will assure its completion not later than the date specified in this Contract, or on the date to which the time for completion may be extended.

R-26

ARTICLE 9. PROGRESS SCHEDULES

9.1 Within 15 days of Contract execution, to enable the work to be performed in an orderly and expeditious manner, the Contractor, shall submit to the Engineer a proposed progress schedule based on the Critical Path Method in the form of a bar graph or in such other form as specified by the Engineer, and monthly cash flow requirements, showing:

9.1.1 The anticipated time of commencement and completion of each of the various operations to be performed under this Contract; and

9.1.2 The sequence and interrelation of each of these operations with the others and with those of other related contracts; and

9.1.3 The estimated time required for fabrication or delivery, or both, of all materials and equipment required for the Work, including the anticipated time for obtaining required approvals pursuant to Article 10; and

9.1.4 The estimated amount in dollars the Contractor will claim on a monthly basis.

9.2 The proposed schedule shall be revised as directed by the Engineer, until finally approved by the Engineer, and after such approval, subject to the provisions of Article 11, shall be strictly adhered to by the Contractor.

9.3 If the Contractor shall fail to adhere to the approved progress schedule, or to the schedule as revised pursuant to Article 11, it shall promptly adopt such other or additional Means and Methods of Construction, at its sole cost and expense, as will make up for the time lost and will assure completion in accordance with the approved progress schedule.

The approval by the Village of Briarcliff Manor of a progress schedule which is shorter than the time allotted under the Contract shall not create any liability for the Village of Briarcliff Manor if the approved progress schedule is not met.

9.4 The Contractor will not receive any payments until the proposed progress schedule is submitted and approved.

ARTICLE 10. REQUESTS FOR INFORMATION OR APPROVAL

10.1 From time to time as the Work progresses and, in the sequence, indicated by the approved progress schedule, the Contractor shall submit to the Engineer a specific request in writing for each item of information or approval required by the Contractor. These requests shall state the latest date upon which the information or approval is actually required by the Contractor, and shall be submitted in a reasonable time in advance thereof to provide the Engineer a sufficient time to act upon such submissions, or any necessary re-submissions

R-27 thereof.

10.2 The Contractor shall not have any right to an extension of time on account of delays due to the Contractor’s failure to submit requests for the required information or the required approval in accordance with the above requirements.

ARTICLE 11. NOTICE OF CONDITIONS CAUSING DELAY AND DOCUMENTATION OF

DAMAGES CAUSED BY DELAY

11.1 After the commencement of any condition which is causing or may cause a delay in completion of the Work, including conditions for which the Contractor may be entitled to an extension of time, the following notifications and submittals are required:

11.1.1 Within fifteen (15) Days after the Contractor becomes aware or reasonably should be aware of each such condition, the Contractor must notify Engineer, as directed by the Village, in writing of the existence, nature and effect of such condition upon the approved progress schedule and the Work, and must state why and in what respects, if any, the condition is causing or may cause a delay. Such notice shall include a description of the construction activities that are or could be affected by the condition and may include any recommendations the Contractor may have to address the delay condition and any activities the Contractor may take to avoid or minimize the delay.

11.1.2 If the Contractor shall claim to be sustaining damages for delay as provided for in this Article 11,within forty-five (45) Days from the time such damages are first incurred for each such condition, the Contractor shall submit to the Village a verified written statement of the details and estimates of the amounts of such damages, including categories of damages together with documentary evidence of such damages as the Contractor may have at the time of submission (“statement of delay damages”), as further detailed in Article

11.6. The Contractor may submit the above statement within such additional time as may be granted by the Village in writing upon written request therefor. The contractor shall resubmit the statement of delay damages updates every 30 days.

11.1.3 Articles 11.1.1 and 11.1.2 do not relieve the Contractor of its obligation to comply with the provisions of Article 44.

11.2 Failure…