This is a Statement of Work (SOW) for a federal construction project at the VA Medical Center in Fresno, California (Project Number 570-20-308). The Department of Veterans Affairs seeks to replace undersized chilled water infrastructure in Building 1 and the Outpatient Clinic (OPC) that cannot accommodate required cooling capacity during summer months exceeding 110 degrees Fahrenheit. This is the third and final phase of a critical mechanical upgrade, with new chillers and main building infrastructure already completed.
The project scope encompasses replacement of chilled water piping, pumps, and undersized fan coils in both areas; demolition and consolidation of scattered risers into two main sets serving the north wing of Building 1 and the OPC/south wing; installation of new control valves for seasonal hot water and chilled water switchover; and all associated civil, architectural, and mechanical-electrical-plumbing work. Civil work includes direct-burial exterior piping at appropriate frost depth (4 inches in Fresno), a precast concrete vault with manually operated gate valves, jack-and-bore installation beneath the existing patio using a steel casing sleeve, and restoration of all concrete, landscaping, and irrigation within the limits of disturbance. The project requires 31 new risers served by three or more new 10-horsepower chilled water pumps with automated controls, replacement of fan coils and ductwork-mounted reheat coils, NETA acceptance testing, infection control risk assessments (ICRA Type D and E), and compliance with VA specifications and applicable codes including NFPA 13 for fire protection systems. The contractor must provide a phasing schedule minimizing downtime with two weeks' advance notice to the Contracting Officer Representative (COR) before starting work in each area. The period of performance is 915 calendar days after Notice to Proceed, with performance and payment bonds, proof of insurance, and a Contractor Quality Control Plan due within 10 and 30 days respectively of Notice of Award. Deliverables include a comprehensive safety plan, operations and maintenance training with video documentation, record drawings in CAD format, O&M manuals, and a minimum one-year warranty from both manufacturer and installer covering parts and labor. A mandatory site visit is required prior to bidding.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Form 36C26126R0028.docx | DOCX document | |
| 36C26126R0028.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 1 of 9 January 30, 2026
Statement of Work
Replace and Expand Chilled Water Infrastructure 570-20-308
1. PROJECT OVERVIEW
1.1 PURPOSE:
The Department of Veterans Affairs (VA) intends to replace undersized chilled water infrastructure in our main facility and associated mechanical systems. The old pipes are considered too small and unable to handle the chilled water volume needed to meet our 110 plus degree temperatures during the summer months. This project constitutes the third and final phase of this critical mechanical upgrade to our main building, the new chillers and infrastructure to the main building are complete.
2. SCOPE OF WORK
This project involves the replacement of the chilled water piping in the OPC and building 1, the chilled water pumps currently serving these areas, and any undersized fan coils in these areas. The existing pipes are too small to accommodate the required chilled water flow that is required in the summer months, and their associated risers are scattered throughout various locations in the building. These risers will be demolished and consolidated to two sets of risers, one serving the north wing of building 1 and one serving the OPC and south wing of building 1. The new piping system will be used for chilled water as well as hot water; new control valves will be provided on the hot and chilled water lines to allow for switchover during summer/ winter months.
2.1 GENERAL:
Provide all labor, materials, supplies, tools and equipment, supervision, excavation, demolition, temporary utilities, temporary services, project management and construction services necessary for the project. All work detailed in drawings and specifications shall be performed. The contractor shall submit a Request for Information to clarify any work or unforeseen issues. Construction will comply with plans, specifications and applicable VA design guides.
2.2 WORK REQUIRED – CIVIL:
Work to be done as part of the scope of this project will include:
The proposed exterior routing of the CHW will be a direct route from the proposed point of connection to the proposed point of entry back into the building. The supply and return lines will be directly buried per the requirements of the plans, specifications and VA Design Manuals. The lines will be spaced adequately to facilitate proper soil compaction and at an elevation deep enough to meet the requirements of the frost depth in Fresno California which is 4”. Additionally, a precast concrete vault and manually operated gate valves will be installed prior to re-entering the building to facilitate line isolation should it be needed.
To enter the basement, a steel casing sleeve will be Jack-and-bored beneath the existing patio area to avoid any structural disturbances. All concrete required to be removed due to the CHW installation will be replaced in-kind. Additionally, all landscaping and irrigation will be replaced within the limits of disturbance.
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 2 of 9 January 30, 2026
Due to the tight nature of the site as well as limited access, the excavation will likely need to be performed by a mini excavator which can come in widths as narrow as 3’. Although the excavation will take longer with the smaller equipment, it will allow for access to the site without damaging the adjacent flatwork.
Construction will comply with plans, specifications and applicable VA design guides.
The Contractor shall furnish the COR with a schedule of extensive phasing dates to minimize downtime as required by the drawings on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
2.3 WORK REQUIRED – ARCHITECTURAL:
Where the chilled water infrastructure is routed from the fifth-floor roof to the sixth floor on the outside of the building materials and the assembly methodology will be selected such that the exterior envelope is long lasting and provides many years of trouble-free service to the VA Fresno medical center. The exterior envelope will control moisture, air, vapor, and thermal transfer.
Materials and finishes will blend in with recent renovation projects at the Fresno VA medical center. As is good practice and complying with code references including ASHRAE 90.1 the appropriate level of exterior insulation will be provided. A continuous air, vapor, and moisture barrier on sheathing on cold formed metal framing will complete the building envelope.
Where the chilled water infrastructure is routed above existing ceiling finishes, the existing ceiling finish will need to be removed in its entirety. Once the new chilled water infrastructure is installed a new ceiling finish can be installed in the existing’s place and matching the existing layout. Existing ceiling mounted MEP fixtures will need to be supported during demolition and then reinstalled in the new ceiling finish.
Where existing interior walls need to be demoed to allow for demolition and reconstruction of the chilled water infrastructure, the new work plans will designate new wall construction that matches in-kind. To meet a two-hour rating, and where access is only possible from the room side a shaft wall construction will be most appropriate.
Non-rated interior walls will be constructed of metal studs spaced a maximum of 16” on center with 5/8” gypsum board and sound batt insulation. Full height and partial height partitions could be selected depending on adjacent room functions and sound transfer considerations.
Rated interior walls will be constructed with the appropriate UL assembly and where required within the hospital.
Renovation and construction work within an active hospital requires special considerations be made and properly accounted for by the Contractors. An Infection Control Risk Assessment (ICRA) will need to be completed, with considerations from the Sheet Metal and Air Conditioning National Association (SMACNA) indoor air quality guidelines for occupied buildings. ICRA Type D and Type E are currently anticipated to be the type of construction activities encountered. In addition, the patients likely to be encountered fall within the low, medium and high-risk group.
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 3 of 9 January 30, 2026
• During construction the following activities are anticipated to be included:
o Provide active means to prevent airborne dust from dispersing into atmosphere.
o Water mist work surfaces to control dust while cutting.
o Seal unused doors with duct tape.
o Block off and seal air vents.
o Place dust mat at entrance and exit of work area.
o Remove or isolate the HVAC system in areas where work is being performed.
o Contain construction waste before transport in tightly covered containers.
• Upon completion of construction the following activities are anticipated to be included:
o Wipe work surfaces with disinfectant.
o Contain any remaining construction waste before transport in tightly covered containers.
o Wet mop and/or vacuum with HEPA filtered vacuum before leaving work area.
o Remove isolation of HVAC system in areas where work is being performed.
Construction will comply with plans, specifications and applicable VA design guides.
The Contractor shall furnish the COR with a schedule of extensive phasing dates to minimize downtime as required by the drawings on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed
2.4 WORK REQUIRED – MEP (MECHANICAL):
31 new risers will be served by three or more new 10-hp chill water pumps connected in a common header, along with additional controls to operate the pumps and automate the seasonal changeover between hot water and chilled water. The existing system is manually switched over in the subbasement of Building 1. The existing Building 1 subbasement hot water and chilled water pumps will be demolished.
From these main risers, branches will run down the corridors and to each of the fan coil units that required piping throughout the entire building, avoiding existing items located in the ceiling spaces. This routing will allow for the minimum impact to essential rooms of the hospital during construction and will be phased to reduce impact as well. Additionally, the condensate risers, branch piping to fan coil units, distribution piping, duct mounted coils, and chilled water coils throughout building 1 and the OPC will need to be replaced.
In addition to updating the entire chilled water infrastructure of the building, the fan coils will also be replaced, as most of them are old and not performing efficiently, thus causing the chilled water pumps to overwork, and the environments affected to not meet temperature requirements. Existing duct mounted reheat coils will be replaced with coils that will receive chilled and heating hot water throughout the building. VAV terminal units are to remain, and replacement of these units are not in the scope of this project. All existing VAV terminal unit valves, strainers, etc. are to remain.
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 4 of 9 January 30, 2026
Construction will comply with plans, specifications and applicable VA design guides.
The Contractor shall furnish the COR with a schedule of extensive phasing dates to minimize downtime as required by the drawings on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed
2.5 WORK REQUIRED – MEP (ELECTRICAL):
This project shall upgrade the existing electrical infrastructure and equipment to comply with VA electrical systems requirements. Provide power to the three new distribution pumps located in the sub-basement in mechanical equipment room B203, drawings will also include the new VFDs, and control panel associated with the new pumps. Lighting fixtures will be reused in each corridor. Contractor to notify VA of any existing electrical code issues found and not noted on this project.
Construction will comply with plans, specifications and applicable VA design guides.
The Contractor shall furnish the COR with a schedule of extensive phasing dates to minimize downtime as required by the drawings on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
2.6 WORK REQUIRED – FIRE PROTECTION):
The primary fire life safety goal of this project is to provide an environment for occupants that is reasonably safe from the effects of fire and products of combustion. Applicable features of fire life safety, means of egress, fire resistive construction, site fire protection, fire protection system design, and other pertinent requirements of the VA Fire Protection Design Manual (VA FPDM), International Building Code (IBC), Health Care Facilities Code (NFPA 99), Life Safety Code (NFPA 101), and other referenced Codes and Standards are summarized herein.
Modify the existing automatic wet-pipe sprinkler system to provide complete coverage throughout the areas of work to include upturned sprinkler heads. All materials and methods shall conform to the requirements of 2022 NFPA 13, except where specially modified by the 2021 VA FPDG. The system shall be designed using the area/ density method, hydraulically calculated for light hazard as noted on the drawings and shall include allowance per 2022 NFPA 13. The Fire Sprinkler Contractor shall perform required acceptance testing in accordance with Division 21 Specifications, including hydrostatic testing, main drain test and alarm tests in accordance with 2022 NFPA 13.
The Contractor shall furnish the COR with a schedule of extensive phasing dates to minimize downtime as required by the drawings on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
2.7 Work Shall Include
The base portion of the project will include all labor, material, equipment and supervision to perform the required construction work on this project as shown in the drawings and specifications. Project also provides for all the necessary tie-in points to existing infrastructure. Refer to the attached drawings and specs.
A site visit is required prior to bidding.
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 5 of 9 January 30, 2026
All numbers are approximate. Contractor needs to verify all amounts. If there is a discrepancy in the amounts provided and or any condition affecting work shall be brought to the attention of the VA Representative before proceeding with the work.
The Contractor shall furnish the COR with a schedule of extensive phasing dates to minimize downtime as required by the drawings on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
The Contractor shall be responsible for obtaining and coordinating the services of any and all third-party Contractors performing other services on site and other entities as part of the contract to ensure the expected quality, timely delivery, and documented final product.
Normal hours of operation for VA sites are 7:00 AM to 4:00 PM Monday through Friday except for Federal Holidays. Work on Saturday, Sunday, holidays, or outside the project site’s normal working hours may be required by the contractor per phasing dates and must coordinate approval by submitting a written request to the VA- COR at least two weeks prior to the proposed start of such work.
2.8 DESCRIPTION OF WORK
A. Existing Conditions
a. Before disabling any of the following systems, the contractor needs to coordinate with COR at least 10 working days in advance. Contractor shall be responsible for relocating and temporary installing all utilities and controls, including, but not limited to, telephone, data, electrical, med/gas, emergency power, AV alarms, smoke detectors, sprinklers heads, speakers, nurse call, card readers, isolation monitor, phone booster, WIFI boosters, pull stations, etc. It is the contractor’s responsibility to immediately repair any tampered with system at no additional cost to the government.
b. Phasing plan shall be due 30 calendar days after NTP.
c. Contractor will coordinate all work with existing work to remain and existing conditions.
d. Contractor shall be responsible for complying with all the construction documents and applicable Department of Veterans Affairs Master Specifications as part of this project.
e. Contractor must also comply with all applicable city, county, state, and federal regulations / codes and applicable OSHA standards project. Construction shall also comply with Infection Control Risk Assessment (ICRA), attached, and IC standards delineated in the specifications.
f. On-site staging WILL NOT be provided in VA premises.
g. There will be NO contractor parking allowed on the VA campus.
h. Demolition and renovation shall take place with minimal disruption to adjacent workspaces.
i. Demolition debris shall be recycled to the best ability of the contractor. Reports of weight and deposition of all waste are to accompany the monthly progress payments (C&D Waste Form attached). Form also included in corresponding specification.
j. Any item damaged during removal is the contractor’s responsibility to replace with no additional cost to the government.
k. All work shall be in accordance with VA specifications. All costs shall be included in the base
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 6 of 9 January 30, 2026 bid. All work shall be coordinated with the VA prior to any demolition work being performed.
B. Additional Requirements
a. Housekeeping - Accumulation of trash, paper, wood shavings, sawdust, excelsior, boxes and other packing materials will be cleaned up as often as necessary and at the end of each workday.
b. False Alarms – Fire Department response fees for false alarms caused by the contractor will be paid by the contractor. To avoid this, dust covers for smoke detectors and alarms are required to be used while construction work is ongoing. These covers shall be removed at the end of the construction work shift to keep them operational.
c. Fire Watch - Provide fire watch for impairments more than 4 hours in a 24-hour period. Request interruptions in accordance with Article, OPERATIONS AND STORAGE AREAS, and coordinate with COR and facility safety officer. All existing or temporary fire protection systems (fire alarms, sprinklers) located in construction areas shall be tested as coordinated with the medical center.
Parameters for the testing and results of any tests performed shall be recorded by the medical center and copies provided to the COR.
d. Smoking is strictly prohibited in all facilities, near flammable liquids and highly combustible materials. Smoking is only authorized in designated smoking areas.
e. Security – Contractors will wear security badge in plain sight above the waist at all times.
Contractors found without a badge will be immediately removed from VA property by VA Police.
f. Parking – Contractor vehicles found parked in VA parking lots will be issued a United States
District Court Violation Notice and immediately removed and banned from VA property.
g. Tuberculosis (TB) – Contractor is responsible for ensuring that if contracted construction worker(s) have been determined to be at risk for transmission of TB based upon the TB pre-construction risk assessment. The contractor must provide written certification, within 24 hours upon request, to the COR that all contract employees assigned to the work site have had a pre-placement tuberculin screening within 90 days prior to assignment to the work site and been found to be free of active TB. Refer to the contract documents for this requirement.
h. OSHA 10 & 30 -Hour Training Course – All construction workers are required to have the OSHA
10-hour Construction Safety training certification. The construction safety manager and/or superintendent shall have the 30-hour Construction Safety course certification. Proof of certification shall be on site at all times.
i. Infection Control (IC) and Safety– All contractors, construction workers and COR’s must attend the Infection Prevention training every fiscal year. All construction workers shall have a current IC training sticker attached to their badges at all times. If this requirement is not met, workers will be removed from construction site. Refer to construction documents for additional information.
j. Construction sign and copy of IC permit (attached) shall be posted in project site at all times. AllIC and dust control measures shall be implemented at all times.
k. Renovation and construction work within an active hospital requires special considerations be made and properly accounted for by the Contractors. An Infection Control Risk Assessment (ICRA) will need to be completed, with considerations from the Sheet Metal and Air Conditioning
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 7 of 9 January 30, 2026
National Association (SMACNA) indoor air quality guidelines for occupied buildings. ICRA Type D and Type E are currently anticipated to be the type of construction activities encountered. In addition, the patients likely to be encountered fall within the low, medium and high-risk group.
l. All fire and smoke wall penetrations shall be fireproofed according to corresponding wall rating.
These shall be through a sleeve and sealed with fire barrier compound to be approved by VA.
m. All construction and installation work shall comply with VA specifications for material and workmanship, NEC, NFPA and all applicable city, county, state, and federal regulations and codes and OSHA standards. Refer construction drawings and specs for requirements.
n. All incidental work associated with the installation and construction works in the exterior and interior of the building shall be included in the base bid.
o. Conduct work as to interfere as least as possible with facility operations. All coordination for utilities shutdown shall be coordinated at least 72 hours prior to event with COR. For major utility system shutdowns, coordination shall be done at least 2 weeks in advance.
2.9 OTHER DELIVERABLES
A. Period of Performance: 915 Calendar days after Notice to Proceed
B. Performance and Payment bonds: Due 10 Calendar days after Notice of Award
C. Proof of Insurance: Due 10 Calendar days after Notice of Award
D. Project Schedule: Project schedule shall be provided and approved 30 days after NTP
E. Contractor Quality Control Plan (CQCP): The contractor shall develop a quality control plan and shall furnish to VA for review no later than 30 calendar days after the receipt of notice to proceed. The plan shall identify personnel, procedures, control, instructions, tests, records, and forms to be used. VA will consider an interim plan for the first 45 calendar days of operation. Installation will be allowed to begin only after acceptance of the CQCP or acceptance of an interim plan applicable to the particular feature of the work to be started. Work outside of the features of the work included in an accepted interim plan will not be permitted to begin until acceptance of a CQCP or another interim plan containing the additional features of the work to be started. After acceptance of the CQCP, the Contractor shall notify the Contracting Officer Representative (COR) in writing of any proposed change. Proposed changes are subject to acceptance by the Contracting Officer.
F. Safety Plan: Contractor shall develop and implement a Comprehensive safety plan to eliminate injuries occurring relative to providing the design and installation services for this project. Contractor shall furnish to VA for review no later than 15 calendar days after the receipt of notice to proceed. The plan shall also describe how final system installation will meet all applicable requirements of NFPA30 and NFPA30A.
Construction/Renovation work will be allowed to begin only after VA’s acceptance of the Safety Plan.
Contractor is responsible for providing enough project lead time to allow for VA review of Safety Plan before acceptance. The Department of Labor OSHA requires that all Contractors involved in installation on VA owned or leased property comply with the Incorporation of General Industry Safety and Health Standards applicable to Installation Work and Technical Amendments, Final Rule 29 CFR Parts 1910 and 1926 as published in the Federal Register Volume 58, No. 124, June 30, 1993. In addition, any Contractor that performs construction type work on any VA project as defined by the Scope of the referenced
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 8 of 9 January 30, 2026 regulation is required to; (1) Provide and maintain his own protective equipment and devices, etc.; and (2) Require all sub- contractors used on site to follow these same provisions in the regulation.
G. Submittals CD: As part of the closeout documentation, the contractor shall provide the COR:
a. 4 CDs containing all the approved submittals.
b. 2 Full Sets of full-size laminated drawings of the SLD Package
H. Operations and Maintenance Training: The Contractor shall provide on-site O&M training for the location which will consist of two (2) formal on-site training sessions during a 30 day period to including but not limited to system operation, corrective and preventive maintenance and inspections.
The contractor shall provide training manuals that include the hands-on exercises, O&M data and troubleshooting guides necessary for personnel to assume full O&M responsibility for the system after completion of the training. The contractor shall provide a written training syllabus for the topics and detailed training content for review and approval by the COR at least 30 days prior to the scheduled training. The contractor will coordinate with the COR the scheduling of any training classes in advance.
The COR may require the classes to be provided on non-consecutive days at the convenience of the VA Staff. The Contractor shall video tape this training for official use and forward CD (4 copies) including those training videos.
I. Warranty: Contractor shall provide a minimum one (1) year warranty, unless specified otherwise in the specs, from both the manufacturer and installer including parts and labor to include normal, premium or holidays hours. The Warranty period shall start on the date of Substantial Completion.
2.10 ACCEPTANCE
A. For the purposes of Warranty and payment for the work performed at a location, government “Acceptance” will be provided by the VA upon the completion of all of the following:
a. The Contractor has demonstrated/ verified acceptance tests per NETA Acceptance Testing
Requirements and performed by a recognized NETA or Original Equipment Manufacture equivalent shop. Successful Test and Balance (TAB) and Direct Digital Controls (DDC) integration have been verified. All punch list items identified during the commissioning have been resolved.
b. The Contractor has provided O&M manuals.
c. The Contractor has provided Record drawings to include a CD with all as builds CAD files, one full set, one half set and one Mylar full set.
d. The Contractor has placed and installed one set of the SLD drawings in the appropriate electrical room. The SLD drawings in each room reflect the equipment located in the room. A table will be provided at the end to list which sheets are in each room to allow for future updates of the SLDs.
2.11 CONFIDENTIALITY AND NONDISCLOSURE
A. The preliminary and final deliverables and all associated working papers, application source code, and other material deemed relevant by the VA which has been generated by the contractor in the performance of this Order are the exclusive property of the U.S. Government and shall be submitted to the VA-COR at the conclusion of the contract.
B. The Contracting Officer will be the sole authorized official to release verbally or in writing any data, the draft deliverables, the final deliverables, or any other written or printed materials pertaining to this contract.
Replace and Expand Chilled Water Infrastructure, Building 1 and OPC Fresno, CA VAMC Client Project Number: 570-20-308 Page 9 of 9 January 30, 2026
No information shall be released by the contractor. Any request for information relating to this contract presented to the contractor shall be submitted to the CO for response.
C. Press releases, marketing material or any other printed or electronic documentation related to this project, shall not be publicized without the written approval of the CO.
D. To the extent that the work under this contract requires that the contractor be given access to proprietary business, technical or financial information belonging to the Government or other companies, the contractor shall treat such information as proprietary business sensitive and agrees not to appropriate such information to its own use or to disclose such information to third parties unless specifically authorized by the CO in writing. A mutually agreed to agreement for exchange of sensitive information or nondisclosure agreement may be required.
E. General Requirements for Privacy Information:
• Information Systems Officer, Information Protection: The contractor will not have access to VA Desktop computers, nor will they have access to online resources belonging to the government while conducting services.
• Privacy Officer: The contractor will not have access to Patient Health Information (PHI) nor will they have the capability of accessing patient information during the services provided to the VA.
• Records Manager: There will be no federal records created, maintained, used or dispositioned with this contract; regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.].