S02 - 36C10A24Q0087 - AITC Generators Maintenance 6.5.24 (Clean DRAFT).pdf
PDF 1 MB Posted
- Solicitation number
- VA-24-00051954
About this file
This document is a draft Performance Work Statement (PWS) related to a federal contract opportunity for AITC Emergency/Non-Emergency Generators Repairs and Parts. The PWS outlines the scope of work, which includes project management, weekly testing, load testing, inspections, emergency and non-emergency repairs, and procurement and installation of required parts for the generators and associated equipment at the Austin Information Technology Center (AITC) facility.
The contract will be a single-award, firm-fixed-price contract with time-and-materials contract line items. The period of performance is from June 17, 2024 through June 16, 2025, with four 12-month option periods. The work will be performed at the AITC facility in Austin, Texas. The PWS provides detailed requirements for the various maintenance tasks, testing, reporting, and emergency/non-emergency repairs that the contractor must perform. It also includes general requirements related to enterprise architecture, information security, accessibility, and physical security.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PAGE 1 OF 1. REQUISITION NO.
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NO. 5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
a. NAME b. TELEPHONE NO. (No Collect Calls) 8. OFFER DUE DATE/LOCAL
TIME
9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: % FOR:
SMALL BUSINESS
HUBZONE SMALL
BUSINESS
SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
WOMEN-OWNED SMALL BUSINESS
(WOSB) ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
8(A)
NAICS:
SIZE STANDARD:
11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
12. DISCOUNT TERMS
13a. THIS CONTRACT IS A
RATED ORDER UNDER
DPAS (15 CFR 700)
13b. RATING
14. METHOD OF SOLICITATION
RFQ IFB RFP
15. DELIVER TO CODE 16. ADMINISTERED BY CODE
17a. CONTRACTOR/OFFEROR CODE FACILITY CODE 18a. PAYMENT WILL BE MADE BY CODE
TELEPHONE NO. UEI: EFT:
PHONE: FAX:
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN OFFER
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW IS CHECKED
SEE ADDENDUM
19. 20. 21. 22. 23. 24.
ITEM NO. SCHEDULE OF SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA 26. TOTAL AWARD AMOUNT (For Govt. Use Only)
27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED.
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _______________ 29. AWARD OF CONTRACT: REF. ___________________________________ OFFER COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DATED ________________________________. YOUR OFFER ON SOLICITATION DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED SET FORTH HEREIN IS ACCEPTED AS TO ITEMS:
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)
30b. NAME AND TITLE OF SIGNER (TYPE OR PRINT) 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER (TYPE OR PRINT) 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION (REV. NOV 2021)
PREVIOUS EDITION IS NOT USABLE Prescribed by GSA - FAR (48 CFR) 53.212
7. FOR SOLICITATION
INFORMATION CALL:
STANDARD FORM 1449
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30
TAC
F367449-24-0000208
36C10A24Q0087 06-5-2024
Marcus Rivers 512-981-4119 06-11-2024
12:00 PM EDT
36C10A Department of Veterans Affairs Technology Acquisition Center Procurement Services G 23 Christopher Way Eatontown NJ 07724
X 100
X
811310
$12.5 Million
N/A
X
See Schedule
36C10A
Department of Veterans Affairs Technology Acquisition Center Procurement Services G
Y
Department of Veteran Affairs Financial Services Center P.O. Box 149971
Austin TX 78714-8971
(877) 353-9791
See CONTINUATION Page
Austin Information Technology Center (AITC) Emergency/Non- Emergency Generators Repairs and Parts
See Section B.1 - Schedule of Supplies and Services
See Continuation Pages
F367449-24-0000208 Obligation Number: TBD
X X
LORI L. WALKER
AITC Generator Maintenance Request for Quotation No.: 36C10A24Q0087
SECTION B – CONTINUATION OF SF 1449 BLOCKS
B.1 SCHEDULE OF SUPPLIES AND SERVICES
19.
ITEM
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
Base Period: AITC Emergency/Non-Emergency Generators Services, Repairs and Parts for the AITC, located in Austin, Texas (TX).
FOB/Inspection/Acceptance:
Destination Period of Performance:
June 17, 2024 through June 16, 2025 PSC: J028 (Applies to All CLINs) iFAMS Obligation No.: TBD Service Address:
1615 Woodward Street Austin, TX 78748 Contracting Officer Representative (COR):
Will be provided at time of award.
Alternate Point of Contact:
Will be provided at time of award.
NSP – Not Separately Priced NTE – Not to Exceed Firm-Fixed-Price (FFP) Tasks – Base Year
0001 Project Management
IAW PWS Tasks: 5.1 through 5.6
12 MO $________ $________
0001AA Monthly Progress Report IAW PWS Task: 5.1.1 Delivery: Monthly
12 EA NSP NSP
0001AB Contractor Personnel Emergency Contact List IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
0001AC Technician Certificates IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
0002 Preventative Annual Maintenance – Generators 1-8 IAW PWS Tasks: 5.6 through 5.9
- Includes Labor and Materials
1 YR $________ $________
0002AA Preventative Maintenance Inspection Report IAW PWS Task: 5.8 Delivery: Quarterly
4 EA NSP NSP
19.
ITEM
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
0002AB Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.8 Delivery: Upon Request
1 EA NSP NSP
0002AC Odd Year Biennial Preventative Maintenance Generators 1 thru. 8 Occurs once every two years, includes labor and materials
1 EA NSP NSP
0002AD Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.9 Delivery: Upon Request
1 EA NSP NSP
0003 Generators 1-4 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
0003AA Generators 5-8 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
0003AB Inspection Report Weekly Maintenance IAW PWS Task: 5.10.1 Delivery: Weekly
52 WK $________ $________
0003AC Estimate of Repair Cost Report IAW PWS Task: 5.10.1 Delivery: Upon Request
1 EA NSP NSP
0003AD Annual Early-Year & Mid-Year Load Test Report IAW PWS Task: 5.10.3 & 5.10.4 Delivery: Due after Early-Year Load Test is complete
2 EA NSP NSP
0003AE Crankcase Oil and Coolant Lab Analysis Test Result Report IAW PWS Task: 5.10.3.1 Delivery: Due after Analysis Test is complete
1 EA NSP NSP
0003AF IR Scanning Test Result Report IAW PWS Task: 5.10.3.2 Delivery: Due after IR Scanning Test is complete
1 EA NSP NSP
Subtotal Firm-Fixed-Price Line Items for Base Period: $________
ITEM
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
Time and Materials (T&M) Tasks – Base Year 0004 Project Supervisor – Hourly Rate
IAW PWS Task 5.11 -Not to Exceed 300 Hours
250 HR $________ $________
0005 Technician – Hourly Rate IAW PWS Task 5.11 -Not to Exceed 600 Hours
600 HR $________ $________
0006 Cummins – Hourly Rate Standard Working Hours IAW PWS Task 5.11 -Not to Exceed 600 Hours
600 HR $________ $________
0007 Corrective Action Report
IAW PWS Task 5.11 Delivery: Due prior to repair for VA PM, COR, and CO approval. Final report due after repair
1 EA NSP NSP
0008 Parts IAW PWS Task 5.12
NTE $30,000.00
Subtotal Time and Material Line Items: $________ Total Amount Base Year: $________
ITEM
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
Option Period One: AITC Emergency/Non-Emergency Generators Services, Repairs and Parts for the AITC, located in Austin, TX.
FOB/Inspection/Acceptance:
Destination Period of Performance:
June 17, 2025 – June 16, 2026 PSC: J028 (Applies to All CLINs) iFAMS Obligation No.: TBD Service Address:
1615 Woodward Street Austin, TX 78748 Contracting Officer Representative (COR):
Will be provided at time of award.
Alternate Point of Contact:
Will be provided at time of award.
NSP – Not Separately Priced NTE – Not to Exceed
Option Period One: Option for an additional 12-months of AITC Emergency/Non-Emergency Generators Services, Repairs and Parts IAW FAR 52.217-9, “Option to Extend the Term of the
Contract” 1001 Project Management
IAW PWS Tasks: 5.1 through 5.6
12 MO $________ $________
1001AA Monthly Progress Report IAW PWS Task: 5.1.1 Delivery: Monthly
12 EA NSP NSP
1001AB Contractor Personnel Emergency Contact List IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
1001AC Technician Certificates IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
1002 Preventative Annual Maintenance – Generators 1-8 IAW PWS Tasks: 5.6 through 5.9
- Includes Labor and Materials
1 YR $________ $________
1002AA MCS Preventative Maintenance Inspection Report IAW PWS Task: 5.8 Delivery: Quarterly
4 EA NSP NSP
1002AB Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.8 Delivery: Upon Request
1 EA NSP NSP
1002AC Odd Year Biennial Preventative Maintenance Generators 1 thru. 8 Occurs once every two years, includes labor and materials
1 EA $________ $________
1002AD Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.9 Delivery: Upon Request
1 EA NSP NSP
1003 Generators 1-4 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
1003AA Generators 5-8 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
1003AB Inspection Report Weekly Maintenance IAW PWS Task: 5.9 & 5.10.1
52 WK $________ $________
Delivery: Weekly 1003AC Estimate of Repair Cost Report
IAW PWS Task: 5.10.1 Delivery: Upon Request
1 EA NSP NSP
1003AD Annual Early-Year & Mid-Year Load Test Report IAW PWS Task: 5.10.3 & 5.10.4 Delivery: Due after Early-Year Load Test is complete
2 EA NSP NSP
1003AE Crankcase Oil and Coolant Lab Analysis Test Result Report IAW PWS Task: 5.10.3.1 Delivery: Due after Analysis Test is complete
1 EA NSP NSP
1003AF IR Scanning Test Result Report IAW PWS Task: 5.10.3.2 Delivery: Due after IR Scanning Test is
Subtotal Firm-Fixed-Price Line Items for Option Period One: $________
Time and Materials (T&M) Tasks – Option Period One 1004 Project Supervisor – Hourly Rate
IAW PWS Task 5.11 -Not to Exceed 300 Hours
250 HR $________ $________
1005 Technician – Hourly Rate IAW PWS Task 5.11 -Not to Exceed 600 Hours
600 HR $________ $________
1006 Cummins – Hourly Rate Standard Working Hours IAW PWS Task 5.11
1007 Corrective Action Report
Delivery: Due prior to repair for VA PM, COR, and CO approval. Final report due after repair
1 EA NSP NSP
1008 Parts IAW PWS Task 5.12
NTE $30,000.00
Total Amount Option Period One: $________
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
Option Period Two: AITC Emergency/Non-Emergency Generators Services, Repairs and Parts for the AITC, located in Austin, TX.
FOB/Inspection/Acceptance:
Destination Period of Performance:
June 17, 2026 – June 16, 2027 PSC: J028 (Applies to All CLINs) iFAMS Obligation No.: TBD Service Address:
1615 Woodward Street Austin, TX 78748 Contracting Officer Representative (COR):
Will be provided at time of award.
Alternate Point of Contact:
Will be provided at time of award.
NSP – Not Separately Priced NTE – Not to Exceed
Option Period Two: Option for an additional 12-months of AITC Emergency/Non-Emergency Generators Services, Repairs and Parts IAW FAR 52.217-9, “Option to Extend the Term of the
2001 Project Management
2001AA Monthly Progress Report IAW PWS Task: 5.1.1 Delivery: Monthly
12 EA NSP NSP
2001AB Contractor Personnel Emergency Contact List IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
2001AC Technician Certificates IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
2002 Preventative Annual Maintenance – Generators 1-8 IAW PWS Tasks: 5.6 through 5.9
- Includes Labor and Materials
1 YR $________ $________
2002AA MCS Preventative Maintenance Inspection Report IAW PWS Task: 5.8 Delivery: Quarterly
4 EA NSP NSP
2002AB Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.8 Delivery: Upon Request
1 EA NSP NSP
2002AC Odd Year Biennial Preventative Maintenance Generators 1 thru. 8
Occurs once every two years, includes labor and materials
2002AD Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.9 Delivery: Upon Request
1 EA NSP NSP
2003 Generators 1-4 Early Year & Mid-Year Testing IAW PWS Task: 5.10
2 EA $________ $________
2003AA Generators 5-8 Early Year & Mid-Year Testing IAW PWS Task: 5.10
2 EA $________ $________
2003AB Inspection Report Weekly Maintenance IAW PWS Task: 5.10.1 Delivery: Weekly
52 WK $________ $________
2003AC Estimate of Repair Cost Report IAW PWS Task: 5.10.1 Delivery: Upon Request
1 EA NSP NSP
2003AD Annual Early-Year Load & Mid-Year Test Report IAW PWS Task: 5.10.3 & 5.10.4 Delivery: Due after Early-Year Load Test is complete
2 EA NSP NSP
2003AE Cranckcase Oil and Coolant Lab Analysis Test Result Report IAW PWS Task: 5.10.3.1 Delivery: Due after Analysis Test is complete
1 EA NSP NSP
2003AF IR Scanning Test Result Report IAW PWS Task: 5.10.3.2 Delivery: Due after IR Scanning Test is
Subtotal Firm-Fixed-Price Line Items for Option Period Two: $________
Time and Materials (T&M) Tasks – Option Period Two 2004 Project Supervisor – Hourly Rate
IAW PWS Task 5.11 -Not to Exceed 300 Hours
250 HR $________ $________
2005 Technician – Hourly Rate IAW PWS Task 5.11 -Not to Exceed 600 Hours
600 HR $________ $________
2006 Cummins – Hourly Rate Standard Working Hours IAW PWS Task 5.11
2007 Corrective Action Report IAW PWS Task 5.11 Delivery: Due prior to repair for VA PM, COR, and CO approval. Final report due after repair
1 EA NSP NSP
2008 Parts IAW PWS Task 5.12
NTE $30,000.00
Total Amount Option Period Two: $________
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
Option Period Three: AITC Emergency/Non-Emergency Generators Services, Repairs and Parts for the AITC, located in Austin, TX.
FOB/Inspection/Acceptance:
Destination Period of Performance:
June 17, 2027 – June 16, 2028 PSC: J028 (Applies to All CLINs) iFAMS Obligation No.: TBD Service Address:
1615 Woodward Street Austin, TX 78748 Contracting Officer Representative (COR):
Will be provided at time of award.
Alternate Point of Contact:
Will be provided at time of award.
NSP – Not Separately Priced NTE – Not to Exceed Option Period Three: Option for an additional 12-months of AITC Emergency/Non-Emergency Generators Services, Repairs and Parts IAW FAR 52.217-9, “Option to Extend the Term of the
3001 Project Management
3001AA Monthly Progress Report IAW PWS Task: 5.1.1 Delivery: Monthly
12 EA NSP NSP
3001AB Contractor Personnel Emergency Contact List IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
3001AC Technician Certificates IAW PWS Task: 5.5 Delivery: Two weeks, ARO
3002 Preventative Annual Maintenance – Generators 1-8 IAW PWS Tasks: 5.6 through 5.9
- Includes Labor and Materials
1 YR $________ $________
3002AA MCS Preventative Maintenance Inspection Report IAW PWS Task: 5.8 Delivery: Quarterly
4 EA NSP NSP
3002AB Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.8 Delivery: Upon Request
1 EA NSP NSP
3002AC Odd Year Biennial Preventative Maintenance Generators 1 thru. 8 Occurs once every two years, includes labor and materials
1 EA NSP NSP
3002AD Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.9 Delivery: Upon Request
1 EA NSP NSP
3003 Generators 1-4 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
3003AA Generators 5-8 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
3003AB Inspection Report Weekly Maintenance IAW PWS Task: 5.8 & 5.10.1 Delivery: Weekly
52 WK $________ $________
3003AC Estimate of Repair Cost Report IAW PWS Task: 5.10.1 Delivery: Upon Request
1 EA NSP NSP
3003AD Annual Early-Year & Mid-Year Load Test Report IAW PWS Task: 5.10.3 Delivery: Due after Early-Year Load Test is complete
1 EA NSP NSP
3003AE Cranckcase Oil and Coolant Lab Analysis Test Result Report IAW PWS Task: 5.10.3.1 Delivery: Due after Analysis Test is complete
1 EA NSP NSP
3003AF IR Scanning Test Result Report IAW PWS Task: 5.10.3.2
Delivery: Due after IR Scanning Test is
Subtotal Firm-Fixed-Price Line Items for Option Period Three: $________
Time and Materials (T&M) Tasks – Option Period Three 3004 Project Supervisor – Hourly Rate
IAW PWS Task 5.11 -Not to Exceed 300 Hours
250 HR $________ $________
3005 Technician – Hourly Rate IAW PWS Task 5.11 -Not to Exceed 600 Hours
600 HR $________ $________
3006 Cummins – Hourly Rate Standard Working Hours IAW PWS Task 5.11
3007 Corrective Action Report
Delivery: Due prior to repair for VA PM, COR, and CO approval. Final report due after repair
1 EA NSP NSP
3008 Parts IAW PWS Task 5.12
NTE $30,000.00
Total Amount Option Period Three: $________
NO.
20. SCHEDULE OF
SUPPLIES/SERVICES
21.
QTY
22.
UNIT
23. UNIT
PRICE
24. NTE
AMOUNT
Option Period Four: AITC Emergency/Non-Emergency Generators Services, Repairs and Parts for the AITC, located in Austin, TX.
FOB/Inspection/Acceptance:
Destination Period of Performance:
June 17, 2028 – June 16, 2029 PSC: J028 (Applies to All CLINs) iFAMS Obligation No.: TBD Service Address:
1615 Woodward Street Austin, TX 78748 Contracting Officer Representative (COR):
Will be provided at time of award.
Alternate Point of Contact:
Will be provided at time of award.
NSP – Not Separately Priced
NTE – Not to Exceed Option Period Four: Option for an additional 12-months of AITC Emergency/Non-Emergency Generators Services, Repairs and Parts IAW FAR 52.217-9, “Option to Extend the Term of the
4001 Project Management
4001AA Monthly Progress Report IAW PWS Task: 5.1.1 Delivery: Monthly
12 EA NSP NSP
4001AB Contractor Personnel Emergency Contact List IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
4001AC Technician Certificates IAW PWS Task: 5.5 Delivery: Two weeks, ARO
1 EA NSP NSP
4002 Preventative Annual Maintenance – Generators 1-8 IAW PWS Tasks: 5.6 through 5.9
- Includes Labor and Materials
1 YR $________ $________
4002AA MCS Preventative Maintenance Inspection Report IAW PWS Task: 5.8 Delivery: Quarterly
4 EA NSP NSP
4002AB Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.8 Delivery: Upon Request
1 EA NSP NSP
4002AC Odd Year Biennial Preventative Maintenance Generators 1 thru. 8 Occurs once every two years, includes labor and materials
1 EA NSP NSP
4002AD Provide contract hours for Cummins, Square D and other specialized trades for Maintenance/Emergency Equipment, repair Support IAW PWS Task: 5.9 Delivery: Upon Request
1 EA NSP NSP
4003 Generators 1-4 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
4003AA Generators 5-8 Early Year & Mid-Year Load Testing IAW PWS Task: 5.10
2 EA $________ $________
4003AB Inspection Report Weekly Maintenance
52 WK $________ $________
IAW PWS Task: 5.9 & 5.10.1 Delivery: Weekly
4003AC Estimate of Repair Cost Report IAW PWS Task: 5.10.1 Delivery: Upon Request
1 EA NSP NSP
4003AD Annual Early-Year & Mid-Year Load Test Report IAW PWS Task: 5.10.3 & 5.10.4 Delivery: Due after Early-Year Load Test is complete
1 EA NSP NSP
4003AE Crankcase Oil and Coolant Lab Analysis Test Result Report IAW PWS Task: 5.10.3.1 Delivery: Due after Analysis Test is complete
1 EA NSP NSP
4003AF IR Scanning Test Result Report IAW PWS Task: 5.10.3.2 Delivery: Due after IR Scanning Test is
Subtotal Firm-Fixed-Price Line Items for Option Period Four: $________
Time and Materials (T&M) Tasks – Option Period Four 4004 Project Supervisor – Hourly Rate
IAW PWS Task 5.11 -Not to Exceed 300 Hours
250 HR $________ $________
4005 Technician – Hourly Rate IAW PWS Task 5.11 -Not to Exceed 600 Hours
600 HR $________ $________
4006 Cummins – Hourly Rate Standard Working Hours IAW PWS Task 5.11
4007 Corrective Action Report
Delivery: Due prior to repair for VA PM, COR, and CO approval. Final report due after repair
1 EA NSP NSP
4008 Parts IAW PWS Task 5.12
NTE $30,000.00
Subtotal Time and Material Line Items: $________ Total Amount Option Period Four: $________
Total Order Value, Inclusive of all Options: $________
Governing Law (continuation of Schedule of Supplies and Services above):
Federal law and regulations, including the Federal Acquisition Regulations (FAR), shall govern this Contract/Order. Commercial license agreements may be made a part of this Contract/Order but only if both parties expressly make them an addendum hereto, as permitted by FAR 12.212. If the commercial license agreement is not made an addendum, it shall not apply, govern, be a part of or have any effect whatsoever on the Contract/Order; this includes, but is not limited to, any agreement embedded in the computer software (clickwrap), any agreement that is otherwise delivered with or provided to the Government with the commercial computer software or documentation (shrinkwrap), or any other license agreement otherwise referred to in any document. If a commercial license agreement is made an addendum, only those provisions addressing data rights regarding the Government’s use, duplication and disclosure of data (e.g., restricted computer software) are included and made a part of this Contract/Order, and only to the extent that those provisions are not duplicative or inconsistent with Federal law, Federal regulation, the incorporated FAR clauses and the provisions of this Contract/Order; those provisions in the commercial license agreement that do not address data rights regarding the Government’s use, duplication and disclosure of data shall not be included or made a part of the Contract/Order. Federal law and regulation including, without limitation, the Contract Disputes Act (41 U.S.C. § 7101 et seq.), the Anti-Deficiency Act (31 U.S.C. § 1341 et seq.), the Competition in Contracting Act (41 U.S.C. § 3301 et seq.), the Prompt Payment Act (31 U.S.C. §3901 et seq.), Contracts for Data Processing or Maintenance (38 USC § 5725), and FAR clauses 52.212-4, 52.227-14, 52.227-19 shall supersede, control, and render ineffective any inconsistent, conflicting, or duplicative provision in any commercial license agreement. In the event of conflict between this clause and any provision in the Contract/Order or the commercial license agreement or elsewhere, the terms of this clause shall prevail. The Contractor shall deliver to the Government all data first produced under this Contract/Order with unlimited rights as defined by FAR 52.227-
14. Claims of patent or copyright infringement brought against the Government as a party shall be defended by the U.S. Department of Justice (DOJ in accordance with 28 U.S.C. § 516; at the discretion of DOJ, the Contractor may be allowed reasonable participation in the defense of the litigation. Any additional changes to the Contract/Order must be made by contract/order modification (Standard Form 30) and shall only be made by a warranted Contracting Officer. Nothing in this Contract/Order or any commercial license agreement shall be construed as a waiver of sovereign immunity.
SOFTWARE LICENSE, MAINTENANCE AND TECHNICAL SUPPORT:
(1) Definitions.
(a) Licensee. The term “licensee” shall mean the U.S. Department of Veterans Affairs (“VA”) and is synonymous with “Government.”
(b) Licensor. The term “licensor” shall mean the contractor having the necessary license or ownership rights to deliver license, software maintenance and support of the computer software being acquired. The term “contractor” is the party identified in Block 17a on the SF1449. If the contractor is a reseller and not the Licensor, the contractor remains responsible for performance under this order.
(c) Software. The term “software” shall mean the licensed computer software product(s) cited in the Schedule of Supplies/Services.
(d) Maintenance. The term “maintenance” is the process of enhancing and optimizing software, as well as remedying defects. It shall include all new fixes, patches, releases, updates, versions and upgrades, as further defined below.
(e) Technical Support. The term “technical support” refers to the range of services providing assistance for the software via the telephone, email, a website or otherwise.
(f) Release or Update. The term “release” or “update” are terms that refer to a revision of software that contains defect corrections, minor enhancements or improvements of the software’s functionality. This is usually designated by a change in the number to the right of the decimal point (e.g., from Version 5.3 to 5.4). An example of an update is the addition of new hardware.
(g) Version or Upgrade. The term “version” or “upgrade” are terms that refer to a revision of software that contains new or improved functionality. This is usually designated by a change in the number to the left of the decimal point (e.g., from Version
5.4 to 6).
(2) Software License
(a) Unless otherwise stated in the Schedule of Supplies/Services, the Performance
Work Statement or Product Description, the software license provided to the Government is a perpetual, nonexclusive license to use the software.
(b)The Government may use the software in a networked environment.
(c) Any dispute regarding the license grant or usage limitations shall be resolved in accordance with the Disputes Clause incorporated in FAR 52.212-4(d).
(d) All limitations of software usage are expressly stated in the Schedule of Supplies/Services and the Performance Work Statement/Product Description.
(3) Software Maintenance and Technical Support
(a) If the Government desires to continue software maintenance and support beyond the period of performance identified in this contract or order, the Government will issue a separate contract or order for maintenance and support. Conversely, if a contract or order for continuing software maintenance and technical support is not received the contractor is neither authorized nor permitted to renew any of the previously furnished services.
(b) The contractor shall provide software support services, which includes periodic updates, enhancements and corrections to the software, and reasonable technical support, all of which are customarily provided by the contractor to its commercial customers so as to cause the software to perform according to its specifications, documentation or demonstrated claims.
(c) Any telephone support provided by contractor shall be at no additional cost.
(d) The contractor shall provide all maintenance services in a timely manner in accordance with the contractor’s customary practice or as defined in the Performance Work Statement/Product Description. However, prolonged delay (exceeding 2 business days) in resolving software problems will be noted in the Government’s various past performance records on the contractor (e.g., www.ppirs.gov).
(e) If the Government allows the maintenance and support to lapse and subsequently wishes to reinstate it, any reinstatement fee charged shall not exceed the amounts that would have been charged if the Government had not allowed the subscription to lapse.
(4) Disabling Software Code. The Government requires delivery of computer software that does not contain any code that will, upon the occurrence or the nonoccurrence of any event, disable the software. Such code includes but is not limited to a computer virus, restrictive key, node lock, time-out or other function, whether implemented by electronic, mechanical, or other means, which limits or hinders the use or access to any computer software based on residency on a specific hardware configuration, frequency of duration of use, or other limiting criteria. If any such disabling code is present, the contractor agrees to indemnify the Government for all damages suffered as a result of a disabling caused by such code, and the contractor agrees to remove such code upon the Government’s request at no extra cost to the Government. Inability of the contractor to remove the disabling software code will be considered an inexcusable delay and a material breach of contract, and the Government may exercise its right to terminate for cause. In addition, the Government is permitted to remove the code as it deems appropriate and charge the Contractor for consideration for the time and effort expended in removing the code.
Manuals and Publications. Upon Government request, the contractor shall furnish the most current version of the user manual and publications for all products/services provided under this contract or order at no cost.
http://www.ppirs.gov/
B.2 CONTRACT ADMINISTRATION DATA
1. Contract Administration: All contract administration matters will be handled by the following individuals:
a. CONTRACTOR: To Be Determined
b. GOVERNMENT: Contracting Officer 36C10A
Department of Veterans Affairs Technology Acquisition Center Procurement Services G
2. CONTRACTOR REMITTANCE ADDRESS: All payments by the Government to the contractor will be made in accordance with:
[X] 52.232-33, Payment by Electronic Funds Transfer—System For Award Management, or
[] 52.232-36, Payment by Third Party
3. INVOICES: Invoices shall be submitted in arrears:
a. Quarterly []
b. Semi-Annually []
c. Other [X] Upon Completion of Services, Repairs and Parts Installation
4. GOVERNMENT INVOICE ADDRESS: All Invoices from the contractor shall be submitted electronically in accordance with VAAR Clause 852.232-72 Electronic Submission of Payment Requests.
See website at: http://www.fsc.va.gov/einvoice.asp
ACKNOWLEDGMENT OF AMENDMENTS: The offeror acknowledges receipt of amendments to the Solicitation numbered and dated as follows:
AMENDMENT NO DATE
B.3 ACCOUNTING AND APPROPRIATION DATA
Funds in the amount of $TBD are obligated on iFAMS Obligation Number TBD to pay for services on Contract Line Item Numbers (CLINs) 0001 through 0009. The Contractor shall reference iFAMS Obligation Number TBD, the CLIN(s) and/or Sub-Line Item Number on all invoices submitted for CLINs 0001 through 0009.
http://www.fsc.va.gov/einvoice.asp
B.4 PERFORMANCE WORK STATEMENT
PERFORMANCE WORK STATEMENT (PWS)
DEPARTMENT OF VETERANS AFFAIRS (VA)
Office of Information & Technology (OI&T) Austin Information Technology Center (AITC)
AITC EMERGENCY/NON-EMERGENCY GENERATORS
REPAIRS and PARTS
CONTRACT
Date: May 30, 2024
VA-24-00051954
PWS Version Number: 1.0
1.0 BACKGROUND AND SCOPE
BACKGROUND
The mission of the Department of Veterans Affairs (VA), Office of Information & Technology (OI&T), Austin Information Technology Center (AITC) is to provide benefits and services to Veterans of the United States. In meeting these goals, OI&T strives to provide high quality, effective, and efficient Information Technology (IT) services to those responsible for providing care to the Veterans at the point-of-care as well as throughout all the points of the Veterans’ health care in an effective, timely and compassionate manner. VA depends on Information Management/Information Technology (IM/IT) systems to meet mission goals.
The AITC processes data that is considered a lifeline to Veterans. As such, the AITC has a responsibility to ensure the Data Center will not experience any power loss or outage under any circumstance, twenty-four hours a day and seven days a week. The Contractor services are required to remotely monitor the system twenty-four hours a day and seven days a week and provide maintenance, repair and on-call services.
2.0 APPLICABLE DOCUMENTS
The Contractor shall comply with the documents listed below. Additional documents may be listed in individual TOs.
1. 44 U.S.C. § 3541, “Federal Information Security Management Act (FISMA) of 2002”
2. Federal Information Processing Standards (FIPS) Publication 140-2, “Security Requirements For Cryptographic Modules”
3. FIPS Pub 201-2, “Personal Identity Verification of Federal Employees and Contractors,” August 2013
4. 5 U.S.C. § 552a, as amended, “The Privacy Act of 1974”
5. 42 U.S.C. § 2000d “Title VI of the Civil Rights Act of 1964”
6. VA Directive 0710, “Personnel Suitability and Security Program,” June 4, 2010, http://www.va.gov/vapubs/
7. VA Handbook 0710, Personnel Suitability and Security Program, September
10, 2004, http://www.va.gov/vapubs
8. VA Directive and Handbook 6102, “Internet/Intranet Services,” July 15, 2008
9. 36 C.F.R. Part 1194 “Electronic and Information Technology Accessibility
Standards,” July 1, 2003
10. Office of Management and Budget (OMB) Circular A-130, “Management of
Federal Information Resources,” November 28, 2000
11. Sections 504 and 508 of the Rehabilitation Act (29 U.S.C. § 794d), as amended by the Workforce Investment Act of 1998 (P.L. 105-220), August 7, 1998
12. Homeland Security Presidential Directive (12) (HSPD-12), August 27, 2004 http://www.va.gov/vapubs/ http://www.va.gov/vapubs http://www.va.gov/vapubs
13. VA Directive 6500, “Managing Information Security Risk: VA Information Security Program,” September 20, 2012
14. VA Handbook 6500, “Risk Management Framework for VA Information Systems – Tier 3: VA Information Security Program,” March 10, 2015
15. VA Handbook 6500.1, “Electronic Media Sanitization,” November 03, 2008
16. VA Handbook 6500.3, “Assessment, Authorization, And Continuous
Monitoring Of VA Information Systems,” February 3, 2014
17. VA Handbook 6500.5, “Incorporating Security and Privacy in System
Development Lifecycle” March 22, 2010
18. VA Handbook 6500.6, “Contract Security,” March 12, 2010
19. VA Directive 6508, VA Privacy Impact Assessment, October 3, 2008
20. VA Directive 0735, Homeland Security Presidential Directive 12 (HSPD-12)
Program, February 17, 2011
21. VA Handbook 0735, Homeland Security Presidential Directive 12 (HSPD-
12) Program, March 20, 2014OMB Memorandum M-06-18, Acquisition of Products and Services for Implementation of HSPD-12, June 30, 2006
22. OMB Memorandum 05-24, Implementation of Homeland Security Presidential Directive (HSPD) 12 – Policy for a Common Identification Standard for Federal Employees and Contractors, August 5, 2005
23. OMB memorandum M-11-11, “Continued Implementation of Homeland Security Presidential Directive (HSPD) 12 – Policy for a Common Identification Standard for Federal Employees and Contractors, February 3, 2011OMB Memorandum, Guidance for Homeland Security Presidential Directive (HSPD) 12 Implementation, May 23, 2008
24. NIST SP 800-116, A Recommendation for the Use of Personal Identity Verification (PIV) Credentials in Physical Access Control Systems, November 20, 2008
25. OMB Memorandum M-07-16, Safeguarding Against and Responding to the Breach of Personally Identifiable Information, May 22, 2007
26. NIST SP 800-63-2, Electronic Authentication Guideline, August 2013
27. Draft NIST Special Publication 800-157, Guidelines for Derived PIV
Credentials, March 2014
28. Draft National Institute of Standards and Technology Interagency Report
(NISTIR) 7981 Mobile, PIV, and Authentication, March 2014
29. VA Memorandum, VAIQ #7100147, Continued Implementation of Homeland
Security Presidential Directive 12 (HSPD-12), April 29, 2011 (reference https://www.voa.va.gov/documentlistpublic.aspx?NodeID=514)
30. IAM Identity Management Business Requirements Guidance document, May 2013, (reference Enterprise Architecture Section, PIV/IAM (reference https://www.voa.va.gov/documentlistpublic.aspx?NodeID=514)
31. Trusted Internet Connections (TIC) Reference Architecture Document, Version 2.0, Federal Interagency Technical Reference Architectures, https://www.voa.va.gov/documentlistpublic.aspx?NodeID=514 https://www.voa.va.gov/documentlistpublic.aspx?NodeID=514
Department of Homeland Security, October 1, 2013, https://www.fedramp.gov/files/2015/04/TIC_Ref_Arch_v2-0_2013.pdf
32. VA Memorandum, VAIQ #7497987, Compliance – Electronic Product Environmental Assessment Tool (EPEAT) – IT Electronic Equipment, August 11, 2014 (reference Document Libraries, EPEAT/Green Purchasing Section, https://www.voa.va.gov/documentlistpublic.aspx?NodeID=552)
33. Sections 524 and 525 of the Energy Independence and Security Act of 2007, (Public Law 110–140), December 19, 2007
34. Section 104 of the Energy Policy Act of 2005, (Public Law 109–58), August 8, 2005
35. Executive Order 13514, “Federal Leadership in Environmental, Energy, and Economic Performance,” October 5, 2009
36. Executive Order 13423, “Strengthening Federal Environmental, Energy, and Transportation Management,” January 24, 2007
37. Executive Order 13221, “Energy-Efficient Standby Power Devices,” August 2, 2001
38. VA Directive 0058, “VA Green Purchasing Program”, July 19, 2013
39. VA Handbook 0058, “VA Green Purchasing Program”, July 19, 2013
40. Clinger-Cohen Act of 1996, 40 U.S.C. §11101 and §11103
41. NFPA (National Fire Protection Association) 110, “Standard for Emergency and Standby Power Systems”, January 1, 2013
42. Cummins Power Generation Warranty Statements, Generator Sets, and
Commercial Standby Extended Warranty Statements
3.0 SCOPE of WORK
The Contractor shall provide VA generator maintenance to include project management, weekly testing, load testing, inspection, emergency and non-emergency repairs, associated reports, and the procurement and installation of required parts.
Functional area requirements are described in PWS Section 5.0. Requirements may fall within one specific functional area but in many cases, the requirements will encompass and apply across multiple functional areas to provide the total life cycle solution.
The Contractor shall provide only Cummins manufactured parts. When an issue with the VA generator is beyond the Contractor technician’s technical expertise, the Contractor shall be responsible for bringing in a Cummins manufacturer technician.
3.1 CONTRACT TYPE
This is a single award Firm-Fixed-Price (FFP) contract with Time-and-Materials (T&M) Contract Line Item Numbers.
https://www.fedramp.gov/files/2015/04/TIC_Ref_Arch_v2-0_2013.pdf https://www.voa.va.gov/documentlistpublic.aspx?NodeID=552
4.0 PERFORMANCE Details
4.1 PERFORMANCE PERIOD
The period of performance shall be June 17, 2024 through June 16, 2025, plus four 12-month option periods.
Work at a Government site shall not take place on Federal holidays or weekends (but may require off-hour work due to network loading or other disruptions that could occur) unless directed by the Contracting Officer (CO).
There are 11 Federal holidays set by law (USC Title 5 Section 6103) that VA follows:
Under current definitions, five are set by date:
New Year's Day January 1 Juneteenth June 19 Independence Day July 4 Veterans Day November 11 Christmas Day December 25
If any of the above falls on a Saturday, then Friday shall be observed as a holiday.
Similarly, if one falls on a Sunday, then Monday shall be observed as a holiday.
The other six are set by a day of the week and month:
Martin Luther King's Birthday Third Monday in January Washington's Birthday Third Monday in February Memorial Day Last Monday in May Labor Day First Monday in September Columbus Day Second Monday in October Thanksgiving Fourth Thursday in November
4.2 PLACE OF PERFORMANCE
The equipment under maintenance is located in the VA AITC facility at 1615 Woodward Street, Austin, TX 78748.
4.3 TRAVEL
The Government anticipates travel under this effort to perform the tasks associated with the effort, as well as to attend program-related meetings or conferences throughout the period of performance. All estimated travel costs shall be included within the priced line items. These costs will not be directly reimbursed by the Government.
The total estimated number of trips in support of the program related meetings for this effort is fifty-two (52) weekly maintenance and load test. All work to be performed at 1615 Woodward Street, Austin, TX 78748, estimated at one to four hours per weekly maintenance visit.
5.0 SPECIFIC TASKS AND DELIVERABLES
The Contractor shall perform the following:
5.1 PROJECT MANAGEMENT
5.1.1 REPORTING REQUIREMENTS
The Contractor shall provide the Contracting Officer’s Representative (COR) with monthly Progress Reports in electronic form in Microsoft Word and Project formats. The report shall include detailed instructions/explanations for each required data element, to ensure that data is accurate and consistent. These reports shall reflect data as of the last day of the preceding month.
The Monthly Progress Reports shall cover all work completed during the reporting period and work planned for the subsequent reporting period. The report shall also identify any problems that arose and a description of how the problems were resolved. If problems have not been completely resolved, the Contractor shall provide an explanation including their plan and timeframe for resolving the issue. The report shall also include an itemized list of all Information and Communication Technology (ICT) deliverables and their current Section 508 conformance status. The Contractor shall monitor performance against the Contractor Program Management Plan (CPMP) and report any deviations. It is expected that the Contractor will keep in communication with VA accordingly so that issues that arise are transparent to both parties to prevent escalation of outstanding issues.
Deliverable:
A. Monthly Progress Report
5.2 MATERIALS AND EQUIPMENT
5.2.1 GOVERNMENT-FURNISHED
Government Furnished Property (GFP), which includes Government Furnished Material (GFM), and Government Furnished Equipment, may be provided The Contractor shall be responsible for conducting all necessary examinations, inspections, maintenance, and tests upon receipt. The Contractor shall be responsible for reporting all inspection results, maintenance actions, losses, and damage to the Government through the Contracting Officer (CO), Contract Specialist (CS) or COR.
The Contractor may utilize VA provided documents and requirements repositories as required for the development, storage, maintenance and delivery of products.
Contractors shall comply with VA security policies and procedures with respect to protecting sensitive data. The Contractor will need to be familiar with VA policies and processes regarding requirements development, maintenance, and storage.
Reference PWS Section 6.0 for detailed security requirements.
5.2.2 CONTRACTOR-ACQUIRED
The Contractor shall acquire and/or provide any hardware and/or software required.
Software integrity shall be maintained by the Contractor within the licensing agreement of the producer until such software is delivered to the Government, or otherwise disposed of in accordance with Government direction. Reference PWS Section 6.0 for detailed security requirements.
5.2.3 NON-DEVELOPMENTAL ITEMS AND COMMERCIAL PROCESSES
Non-Developmental Items (NDI), Commercially-Available-Off-The-Shelf (COTS) and Government-Off-The-Shelf products shall be used to the maximum extent. The Contractor shall apply commercially available and industry best processes, standards and technologies to the maximum extent.
5.2.4 CONNECTIVITY
N/A
5.2.5 WARRANTY
Items acquired under this contract may require warranty protection. Commercial warranties shall be transferred to the Government.
5.2.6 MARKING, HANDLING, STORAGE, PRESERVATION, PACKAGING, &
SHIPPING
The Contractor shall establish/maintain procedures for handling, storage, preservation, packaging, and shipping to protect the quality of products and prevent damage, loss, deterioration, degradation or substitution of products.
5.3 TRANSITION AND ORIENTATION SUPPORT
The Contractor shall perform transition and orientation services (e.g. develop Phase- In/Phase-Out Transition Plan) to insure continuity of services.
5.4 FUNCTIONAL AREAS
Functional area requirements are not mutually exclusive and may apply across multiple functional areas.
5.5 CONTRACTOR PROGRAM MANAGEMENT SUPPORT
The Contractor shall provide project and/or program management support to accomplish the administrative, managerial, logistical, integration and financial aspects..
The Contractor shall provide and maintain a Contractor Personnel Emergency Contact List to include contact phone numbers. This list may be periodically checked for response. In addition, the Contractor shall provide the stationary diesel generator repair technician certificates for personnel performing the maintenance and repair tasks below.
Deliverable:
A. Contractor Personnel Emergency Contact List
B. Technician Certificates
5.6 GENERATOR MAINTENANCE EQUIPMENT
The Contractor shall provide maintenance solutions for the following generator equipment and associated wiring, as follows:
A. One Cummins (Generator #1) 750kW diesel generator set Model KTA38GS1 (with on-board Power Command digital paralleling system) with lead-acid starting batteries and charger, and other attached components including dampers.
B. Two Cummins (Generators #2 and #3) 900kW diesel generator set Model 900DFJC (with on-board Power Command digital paralleling system) with lead-acid starting batteries and charger, and other attached components including dampers.
C. One Cummins (Generator #4) 1000kW diesel generator set Model 1000DQFAD (with on-board Power Command digital paralleling system) with lead-acid starting batteries, battery charger, generator enclosure and other attached components including dampers.
D. Three 400 amp Onan Model BT400 automatic transfer switches
E. One 1000 amp Onan Model BT1000 automatic transfer
F. One 3000 amp Onan BI automatic transfer switch
G. Two emergency generator switchboards EDAB and Power Switch Board (PSBD)
H. One 3000 amp emergency power system disconnects
I. One 3000 amp utility power system disconnects
J. Six 300-gallon day tanks with dual pumps, three aboveground fuel storage tanks and all related fuel pumps and piping.
K. Hydrogen Gas Detector, located in the Uninterruptible Power Supply (UPS) Battery Room (note – limited to testing only)
L. One Cummins power command center, which accesses the on-board power command system of each of the generators #1 through #4.
M. Four Cummins (Generators #5 thru. #8) 2250kW diesel generator set Model DQKAF-1332787, DQKAF-1332805, DQKAF-209070 & DQKAF-209070 (with on-board Power Command digital paralleling system) with lead-acid starting batteries, battery charger, generator enclosure and other attached components including dampers. Also, generators are controlled by Square D switch gear with Programmable Logic Controllers.
N. One Cummins Power Command Paralleling Digital Master Control Station (MCS) and remote computer (equipment located in room 160D).
5.7 GENERATOR & SWITCHGEAR SUPPORT
Contractor maintenance for Cummins generators under warranty shall be performed in accordance with the Cummins and Square D Maintenance Specifications. The Contractor shall ensure all replacement parts are Cummins Original Equipment Manufacturer (OEM) parts. Generator & Switchgear build dates at the time of this writing are:
• Generator #5: 8/1/13
• Generator #6: 8/5/13
• Generator #7: 3/7/21
• Generator #8: 3/18/21
• Square D Switchgear: 2015
5.8 MASTER CONTROL STATIONS (MCS) SUPPORT
The MCS contains Cummins developed software that allows a VA technician to monitor the health of each of the generators from the MCS position. In addition, it is used to run the tests (e.g., weekly test). Further, the MCS performs automatic transfer (switchover) during a power outage to prevent interruption of electrical services to maintain data center functions.
The MCS software communicates to the Emergency Diesel Generators (EDGS) via a Cummins proprietary protocol. Failure to maintain the MCS may result in the inability to monitor or run required tests, which would place the generators at greater risk of power outages.
Prior to performing any work on the MCS, the Contractor shall consult with Cummins to confirm that any MCS work is performed in a manner (i.e., Cummins performs software upgrade) that will not result in the proprietary software being compromised. The Contractor shall consult with the COR for VA approval before proceeding with any MCS maintenance or repair work e.g., software patch. The Contractor shall ensure quarterly preventative maintenance is performed on the MCS and software system. The quarterly preventative maintenance work shall be captured (test results, repair, etc.) and provided to the COR in a Preventative Maintenance Inspection Report.
Deliverable:
A. Preventive Maintenance Inspection Report B. Provide contract hours for Cummins, Square D and other specialized trades for
Maintenance/emergency Equipment, repair Support.
5.9 GENERATOR MAINTENANCE
The Contractor shall perform a level of maintenance and load testing on the AITC EDGS generators over the course of the period of performance as specified in the following subparagraphs to ensure that the generators are available and capable of performing at required load levels. In addition, the Contractor maintenance shall include facility electrical infrastructure (e.g., Electrical feeders, breakers, Data Center Critical Load Panel (CLP) Electrical Panels, Electrical Feeder/Electrical Breakers to Power Distribution Units/Remote Power Panels (PDUs/RPPs), Electrical Panel PBCCM in Rm.
160B, and misc. switch gear). All maintenance and repair/replacement work shall be performed by stationary diesel generator repair/maintenance certified technicians.
The following subsections define the type of maintenance and load testing, as well as the frequency of the functions to be performed by the Contractor. In addition, the Contractor shall record the status of the generators based on the maintenance and load testing performed. The Contractor shall document the maintenance activity performed in the following subtasks in a weekly Maintenance Report.
Details regarding Contractor maintenance activities, scheduling of maintenance tasks with the VA, and identification of specific generators to be maintained shall be specified in the Maintenance Report.
Deliverable:
A. Maintenance Report B. Provide contract hours for Cummins, Square D and other specialized trades for
Maintenance/emergency Equipment, repair Support.
5.9.1 PREVENTIVE MAINTENANCE
The Contractor shall perform generator maintenance activities consisting of:
A. Oil
1. Drained and Replaced with New Oil and Dispose of old oil off-site.
B. Replacement of Filters (Dispose of old filters off-site)
1. Fuel Filter
2. Air Filters
3. Water Filters
4. Oil Filters
The Contractor shall capture all the work performed (e.g., date oil and filter replaced on which generator) in the Maintenance Report specified in Section 5.9.1 “Preventive Maintenance”. The Contractor shall comply with Environment Protection Agency (EPA) regulations and Hazardous Waste Recycling Regulations
5.9.2 ODD-YEAR MAINTENANCE
On years ending in an odd number (e.g.
This is the start of the file's text. The full file is on GovTribe.