Specifications
FOR CONSTRUCTION
LAD Project No. 046-10034-000
April 20, 2016
Bldg 126/126OP Outpatient Clinics
VA Long Beach Healthcare System
VA PROJECT NUMBER #600-402
VOLUME 2
BLDG 126/ B126OP Outpatient Clinics VA PROJECT NO.600-402
VA LONG BEACH HEALTHCARE SYSTEM REVISED: 4/20/2016
00 01 10-1
TABLE OF CONTENTS
Section 00 01 10
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-12 01 25 00 Substitution Procedures 01 26 00 Contract Modification Procedures 01 31 00 Project Management and Coordination 01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 04-10 01 33 23 Shop Drawings, Product Data, and Samples 11-08 01 42 19 Reference Standards 09-11 01 45 29 Testing Laboratory Services 10-12 01 57 19 Temporary Environmental Controls 01-11 01 58 16 Temporary Interior Signage 08-11 01 74 19 Construction Waste Management 05-12 01 81 11 Sustainable Design Requirements 12-11
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 06-10 02 82 11 Traditional Asbestos Abatement 07-11 02 82 13.13 Glovebag Asbestos Abatement 07-11 02 82 13.19 Asbestos Floor Tile and Mastic Abatement 07-11 02 82 13.21 Asbestos Roofing Abatement 07-11 02 82 13.31 Asbestos Transite Abatement 07-11 02 82 13.41 Asbestos Abatement for Total Demolition Project 07-11 02 83 33.13 Lead-Based Paint Removal and Disposal 08-11
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 10-01
DIVISION 04 – MASONRY
Not used
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-12 05 31 00 Steel Decking 10-12 05 50 00 Metal Fabrications 09-11
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
06 64 00 Plastic Fabrication
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Re-Roofing 10-10
00 01 10-2
07 21 13 Thermal Insulation 03-09 07 22 00 Roof and Deck Insulation 10-10 07 54 19 Polyvinyl-Chloride (PVC) Roofing 11-12 07 60 00 Flashing and Sheet Metal 10-10 07 84 00 Firestopping 10-11 07 92 00 Joint Sealants 12-11 07 95 13 Expansion Joint Cover Assemblies 10-11
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 02-09 08 14 00 Interior Wood Doors 10-12 08 14 23 Impact Resistant Wood Door 08 17 10 Integrated Door Assemblies 02-12 08 31 13 Access Doors and Frames 10-11 08 33 13 Coiling Counter Doors 10-11 08 33 14 Solid Panel Folding Closure 08 41 13 Aluminum-Framed Entrances and Storefronts 10-11 08 71 00 Door Hardware 09-11 08 80 00 Glazing 10-12 08 84 00 Plastic Glazing
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 10-11 09 22 16 Non-Structural Metal Framing 07-10 09 29 00 Gypsum Board 02-12 09 30 13 Ceramic/Porcelain Tiling 05-12 09 51 00 Acoustical Ceilings 10-10 09 65 13 Resilient Base and Accessories 10-11 09 65 16 Resilient Sheet Flooring 07-10 09 65 19 Resilient Tile Flooring 03-11 09 67 23.30 Resinous (Epoxy Resin Composition)Mortar Flooring (RES-
3) 05-11
09 67 23.50 Resinous (Epoxy Terrazzo) Flooring (RES-5) 10-10 09 68 00 Carpeting 10-11 09 72 31 Wall Covering 11-11 09 77 00 Decorative Wall Panel System 09 91 00 Painting 04-09
DIVISION 10 – SPECIALTIES
10 11 13 Chalkboards and Markerboards 10-11 10 11 23 Tackboards 11-11 10 13 00 Directories 11-11 10 14 00 Signage 11-11 10 21 13 Toilet Compartments 05-12 10 21 23 Cubicle Curtain Tracks 11-11 10 22 19 Demountable Partitions 10 26 00 Wall and Door Protection 01-11 10 28 00 Toilet, Bath, and Laundry Accessories 11-11 10 44 13 Fire Extinguisher Cabinets 11-11
00 01 10-3
DIVISION 11 – EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 07-10
DIVISION 12 – FURNISHINGS
12 24 00 Window Shades 11-11 12 31 00 Manufactured Metal Casework 04-11 12 32 00 Manufactured Wood Casework 11-11 12 36 00 Solid Surface Countertops 05-10 12 48 40 Entrance Mat
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components 08-11
13 34 23 Audiological Rooms
DIVISION 14– CONVEYING EQUIPEMENT
Not used
DIVISION 21- FIRE SUPPRESSION
21 05 11 Common Work Results for Fire Suppression 11-09 21 08 00 Commissioning of Fire Suppression System 07-10 21 13 13 Wet-Pipe Sprinkler Systems 05-08
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 04-11 22 05 12 General Motor Requirements for Plumbing Equipment 12-09 22 05 19 Meters and Gages for Plumbing Piping 02-10 22 05 23 General-Duty Valves for Plumbing Piping 12-09 22 07 11 Plumbing Insulation 05-11 22 11 00 Facility Water Distribution 05-11 22 11 23 Domestic Water Pumps 11-10 22 35 00 Domestic Water Heat Exchangers 02-10 22 40 00 Plumbing Fixtures 03-11
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 11-10 23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment 11-10
23 05 41 Noise and Vibration Control for HVAC and Steam Gen 23 05 93 Testing, Adjusting, and Balancing for HVAC 05-11 23 07 11 HVAC and Boiler Plant Insulation 05-11 23 09 23 Direct-Digital Control System for HVAC 09-11 23 21 13 Hydronic Piping 09-12 23 21 23 Hydronic Pumps 02-10 23 22 13 Steam and Condensate Heating Piping 03-10 23 25 00 HVAC Water Treatment 02-10
00 01 10-4
23 31 00 HVAC Ducts and Casings 04-11 23 34 00 HVAC Fans 11-09 23 36 00 Air Terminal Units 03-10 23 37 00 Air Outlets and Inlets 11-09 23 73 00 Indoor Central-Station Air-Handling Units 04-11 23 74 13 Packaged, Outdoor, Central-Station Air-Handling Units 04-11 23 81 00 Decentralized Unitary HVAC Equipment 02-11 23 82 16 Air Coils 04-11
DIVISION 25 – INTEGRATED AUTOMATION
Not used
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 09-10 26 05 19 Low-Voltage Electrical Power Conductors and Cables (600
Volts and Below) 09-10
26 05 26 Grounding and Bonding for Electrical Systems 09-10 26 05 33 Raceway and Boxes for Electrical Systems 09-10 26 05 73 Overcurrent Protective Device Coordination Study 26 08 00 Commissioning of Electrical Systems 07-10 26 09 23 Lighting Controls 09-10 26 22 00 Low-Voltage Transformers 09-10 26 24 16 Panelboards 09-10 26 24 19 Motor-Control Centers 09-10 26 27 26 Wiring Devices 04-09 26 29 11 Motor Starters 09-10 26 29 21 Disconnect Switches 09-10 26 51 00 Interior Lighting 04-09
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 11-09 27 05 26 Grounding and Bonding for Communications Systems 10-06 27 05 33 Raceways and Boxes for Communications Systems 12-05 27 05 61 Leased Space, Communication Equipment and Systems 02-09 27 08 00 Commissioning of Communications Systems 07-10 27 10 00 Structured Cabling 12-05 27 11 00 Communications Equipment Room Fittings 10-06 27 15 00 Communications Horizontal Cabling 10-06 27 31 00 Voice Communications Switching and Routing Equipment 10-06 27 41 31 Master Antenna Television Equipment and Systems 08-09 27 51 16 Public Address and Mass Notification Systems 01-10 27 52 23 Nurse Call and Code Blue Systems 01-10 27 52 31 Security Emergency Call, Duress Alarm, and
Telecommunications 02-09
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 09-11 28 08 00 Commissioning of Electronic Safety and Security Systems 09-11 28 13 00 Physical Access Control Systems 10-11 28 13 53 Security Access Detection 09-11 28 16 00 Intrusion Detection System 10-11
00 01 10-5
28 23 00 Video Surveillance 09-11 28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
Not used
DIVISION 32 – EXTERIOR IMPROVEMENTS
Not used
DIVISION 33 – UTILITIES
Not used
DIVISION 34 – TRANSPORTATION
Not used
21 05 11 - 1
SECTION 21 05 11
COMMON WORK RESULTS FOR FIRE SUPPRESSION
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section apply to all sections of Division 21.
B. Definitions:
1. Exposed: Piping and equipment exposed to view in finished rooms.
2. Option or optional: Contractor's choice of an alternate material or method.
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
C. Excavation and Backfill: Section 31 20 00, EARTH MOVING.
D. Concrete and Grout: Section 03 30 00, CAST-IN-PLACE CONCRETE.
E. Building Components for Attachment of Hangers: Section 05 31 00, STEEL
DECKING. Section 05 36 00, COMPOSITE METAL DECKING.
F. Section 05 50 00, METAL FABRICATIONS.
G. Section 07 84 00, FIRESTOPPING.
H. Flashing for Wall and Roof Penetrations: Section 07 60 00, FLASHING AND
SHEET METAL.
I. Section 07 92 00, JOINT SEALANTS.
J. Section 09 91 00, PAINTING.
K. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS
L. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS
M. Section 21 05 12, GENERAL MOTOR REQUIREMENTS FOR FIRE-SUPPRESSION
EQUIPMENT.
N. Section 26 29 11, LOW-VOLTAGE MOTOR STARTERS.
1.3 QUALITY ASSURANCE
A. Products Criteria:
1. Standard Products: Material and equipment shall be the standard products of a manufacturer regularly engaged in the manufacture of the products for at least 3 years. See other specification sections for any exceptions.
2. Equipment Service: Products shall be supported by a service organization which maintains a complete inventory of repair parts and is located reasonably close to the site.
21 05 11 - 2
3. Multiple Units: When two or more units of materials or equipment of the same type or class are required, these units shall be products of one manufacturer.
4. Assembled Units: Manufacturers of equipment assemblies, which use components made by others, assume complete responsibility for the final assembled product.
5. Nameplates: Nameplate bearing manufacturer's name or identifiable trademark shall be securely affixed in a conspicuous place on equipment, or name or trademark cast integrally with equipment, stamped or otherwise permanently marked on each item of equipment.
6. Asbestos products or equipment or materials containing asbestos shall not be used.
B. Manufacturer's Recommendations: Where installation procedures or any part thereof are required to be in accordance with the recommendations of the manufacturer of the material being installed, printed copies of these recommendations shall be furnished to the Resident Engineer prior to installation. Installation of the item will not be allowed to proceed until the recommendations are received. Failure to furnish these recommendations can be cause for rejection of the material.
C. Supports for sprinkler piping shall be in conformance with NFPA 13.
D. Supports for standpipe shall be in conformance with NFPA 14.
1.4 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Manufacturer's Literature and Data: Submit under the pertinent section rather than under this section.
1. Equipment and materials identification.
2. Fire-stopping materials.
3. Hangers, inserts, supports and bracing. Provide load calculations for variable spring and constant support hangers.
4. Wall, floor, and ceiling plates.
C. Coordination Drawings: Provide detailed layout drawings of all piping systems. Provide details of the following.
1. Mechanical equipment rooms.
2. Interstitial space.
3. Hangers, inserts, supports, and bracing.
4. Pipe sleeves.
5. Equipment penetrations of floors, walls, ceilings, or roofs.
D. Maintenance Data and Operating Instructions:
21 05 11 - 3
1. Maintenance and operating manuals in accordance with Section 01 00
00, GENERAL REQUIREMENTS, Article, INSTRUCTIONS, for systems and equipment.
2. Provide a listing of recommended replacement parts for keeping in stock supply, including sources of supply, for equipment. Include in the listing belts for equipment.
1.5 APPLICABLE PUBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. American Society for Testing and Materials (ASTM):
A36/A36M-2001...........Carbon Structural Steel
A575-96.................Steel Bars, Carbon, Merchant Quality, M-Grades R
(2002)
E84-2003................Standard Test Method for Burning Characteristics of Building Materials
E119-2000...............Standard Test Method for Fire Tests of Building
Construction and Materials
C. National Fire Protection Association (NFPA):
90A-2012................Standard for the Installation of Air
Conditioning and Ventilating Systems
101-2012................Life Safety Code
PART 2 - PRODUCTS
2.1 LIFTING ATTACHMENTS
Provide equipment with suitable lifting attachments to enable equipment to be lifted in its normal position. Lifting attachments shall withstand any handling conditions that might be encountered, without bending or distortion of shape, such as rapid lowering and braking of load.
2.2 EQUIPMENT AND MATERIALS IDENTIFICATION
A. Use symbols, nomenclature and equipment numbers specified, shown on the drawings and shown in the maintenance manuals. Identification for piping is specified in Section 09 91 00, PAINTING.
B. Interior (Indoor) Equipment: Engraved nameplates, with letters not less than 48 mm (3/16-inch) high of brass with black-filled letters, or rigid black plastic with white letters specified in Section 09 91 00, PAINTING permanently fastened to the equipment. Identify unit components such as coils, filters, fans, etc.
21 05 11 - 4
C. Exterior (Outdoor) Equipment: Brass nameplates, with engraved black filled letters, not less than 48 mm (3/16-inch) high riveted or bolted to the equipment.
D. Control Items: Label all temperature and humidity sensors, controllers and control dampers. Identify and label each item as they appear on the control diagrams.
E. Valve Tags and Lists:
1. Valve tags: Engraved black filled numbers and letters not less than
13 mm (1/2-inch) high for number designation, and not less than 6.4 mm(1/4-inch) for service designation on 19 gage 38 mm (1-1/2 inches) round brass disc, attached with brass "S" hook or brass chain.
2. Valve lists: Typed or printed plastic coated card(s), sized 216 mm
(8-1/2 inches) by 280 mm (11 inches) showing tag number, valve function and area of control, for each service or system. Punch sheets for a 3-ring notebook.
3. Provide detailed plan for each floor of the building indicating the location and valve number for each valve. Identify location of each valve with a color coded thumb tack in ceiling.
2.3 FIRESTOPPING
Section 07 84 00, FIRESTOPPING specifies an effective barrier against the spread of fire, smoke and gases where penetrations occur for piping.
2.4 GALVANIZED REPAIR COMPOUND
Mil. Spec. DOD-P-21035B, paint form.
2.5 PIPE PENETRATIONS
A. Install sleeves during construction for other than blocked out floor openings for risers in mechanical bays.
B. To prevent accidental liquid spills from passing to a lower level, provide the following:
1. For sleeves: Extend sleeve 25 mm (one inch) above finished floor and provide sealant for watertight joint.
2. For blocked out floor openings: Provide 40 mm (1-1/2 inch) angle set in silicone adhesive around opening.
3. For drilled penetrations: Provide 40 mm (1-1/2 inch) angle ring or square set in silicone adhesive around penetration.
C. Penetrations are not allowed through beams or ribs, but may be installed in concrete beam flanges. Any deviation from this requirement must receive prior approval of Resident Engineer.
21 05 11 - 5
D. Sheet Metal, Plastic, or Moisture-resistant Fiber Sleeves: Provide for pipe passing through floors, interior walls, and partitions, unless brass or steel pipe sleeves are specifically called for below.
E. Cast Iron or Zinc Coated Pipe Sleeves: Provide for pipe passing through exterior walls below grade. Make space between sleeve and pipe watertight with a modular or link rubber seal. Seal shall be applied at both ends of sleeve.
F. Galvanized Steel or an alternate Black Iron Pipe with asphalt coating
Sleeves: Provide for pipe passing through concrete beam flanges, except where brass pipe sleeves are called for. Provide sleeve for pipe passing through floor of mechanical rooms, laundry work rooms, and animal rooms above basement. Except in mechanical rooms, connect sleeve with floor plate.
G. Brass Pipe Sleeves: Provide for pipe passing through quarry tile, terrazzo or ceramic tile floors. Connect sleeve with floor plate.
H. Sleeves are not required for wall hydrants for fire department connections or in drywall construction.
I. Sleeve Clearance: Sleeve through floors, walls, partitions, and beam flanges shall be one inch greater in diameter than external diameter of pipe. Sleeve for pipe with insulation shall be large enough to accommodate the insulation. Interior openings shall be caulked tight with fire stopping material and sealant to prevent the spread of fire, smoke, and gases.
J. Sealant and Adhesives: Shall be as specified in Section 07 92 00, JOINT
SEALANTS.
2.6 TOOLS AND LUBRICANTS
A. Furnish, and turn over to the Resident Engineer, special tools not readily available commercially, that are required for disassembly or adjustment of equipment and machinery furnished.
B. Grease Guns with Attachments for Applicable Fittings: One for each type of grease required for each motor or other equipment.
C. Tool Containers: Hardwood or metal, permanently identified for in tended service and mounted, or located, where directed by the Resident
Engineer.
D. Lubricants: A minimum of 0.95 L (one quart) of oil, and 0.45 kg (one pound) of grease, of equipment manufacturer's recommended grade and type, in unopened containers and properly identified as to use for each different application.
21 05 11 - 6
2.7 WALL, FLOOR AND CEILING PLATES
A. Material and Type: Chrome plated brass or chrome plated steel, one piece or split type with concealed hinge, with set screw for fastening to pipe, or sleeve. Use plates that fit tight around pipes, cover openings around pipes and cover the entire pipe sleeve projection.
B. Thickness: Not less than 2.4 mm (3/32-inch) for floor plates. For wall and ceiling plates, not less than 0.64 mm (0.025-inch) for up to 80 mm
(3-inch pipe), 0.89 mm (0.035-inch) for larger pipe.
C. Locations: Use where pipe penetrates floors, walls and ceilings in exposed locations, in finished areas only. Use also where insulation ends on exposed water supply pipe drop from overhead. Provide a watertight joint in spaces where brass or steel pipe sleeves are specified.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Coordinate location of piping, sleeves, inserts, hangers, and equipment.
Locate piping, sleeves, inserts, hangers, and equipment clear of windows, doors, openings, light outlets, and other services and utilities. Follow manufacturer's published recommendations for installation methods not otherwise specified.
B. Protection and Cleaning:
1. Equipment and materials shall be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations and as approved by the Resident Engineer. Damaged or defective items in the opinion of the Resident Engineer, shall be replaced.
2. Protect all finished parts of equipment, such as shafts and bearings where accessible, from rust prior to operation by means of protective grease coating and wrapping. Close pipe openings with caps or plugs during installation. Tightly cover and protect equipment against dirt, water chemical, or mechanical injury. At completion of all work thoroughly exposed materials and equipment.
C. Concrete and Grout: Use concrete and shrink compensating grout 25 MPa
(3000 psi) minimum, specified in Section 03 30 00, CAST-IN-PLACE
CONCRETE.
D. Install gages, valves, and other devices with due regard for ease in reading or operating and maintaining said devices. Locate and position gages to be easily read by operator or staff standing on floor or
21 05 11 - 7 walkway provided. Servicing shall not require dismantling adjacent equipment or pipe work.
E. Work in Existing Building:
1. Perform as specified in Article, OPERATIONS AND STORAGE AREAS, Article, ALTERATIONS, and Article, RESTORATION of the Section 01 00
00, GENERAL REQUIREMENTS for relocation of existing equipment, alterations and restoration of existing building(s).
2. As specified in Section 01 00 00, GENERAL REQUIREMENTS, Article, OPERATIONS AND STORAGE AREAS, make alterations to existing service piping at times that will least interfere with normal operation of the facility.
3. Cut required openings through existing masonry and reinforced concrete using diamond core drills. Use of pneumatic hammer type drills, impact type electric drills, and hand or manual hammer type drills, will be permitted only with approval of the Resident
Engineer. Locate openings that will least effect structural slabs, columns, ribs or beams. Refer to the Resident Engineer for determination of proper design for openings through structural sections and opening layouts approval, prior to cutting or drilling into structure. After Resident Engineer's approval, carefully cut opening through construction no larger than absolutely necessary for the required installation.
F. Switchgear Drip Protection: Every effort shall be made to eliminate the installation of pipe above electrical and telephone switchgear. If this is not possible, encase pipe in a second pipe with a minimum of joints.
G. Inaccessible Equipment:
1. Where the Government determines that the Contractor has installed equipment not conveniently accessible for operation and maintenance, equipment shall be removed and reinstalled or remedial action performed as directed at no additional cost to the Government.
2. The term "conveniently accessible" is defined as capable of being reached without the use of ladders, or without climbing or crawling under or over obstacles such as motors, fans, pumps, belt guards, transformers, high voltage lines, piping, and ductwork.
3.2 OPERATING AND PERFORMANCE TESTS
A. Prior to the final inspection, perform required tests as specified in
Section 01 00 00, GENERAL REQUIREMENTS, Article, TESTS and submit the test reports and records to the Resident Engineer.
21 05 11 - 8
B. Should evidence of malfunction in any tested system, or piece of equipment or component part thereof, occur during or as a result of tests, make proper corrections, repairs or replacements, and repeat tests at no additional cost to the Government.
C. When completion of certain work or system occurs at a time when final control settings and adjustments cannot be properly made to make performance tests, then make performance tests for heating systems and for cooling systems respectively during first actual seasonal use of respective systems following completion of work.
3.3 INSTRUCTIONS TO VA PERSONNEL
Provide in accordance with Article, INSTRUCTIONS, of Section 01 00 00, GENERAL REQUIREMENTS.
- - - E N D - - -
21 08 00 - 1
SECTION 21 08 00
COMMISSIONING OF FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section apply to all sections of Division 21.
B. This project will have selected building systems commissioned. The complete list of equipment and systems to be commissioned is specified in Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS. The commissioning process, which the Contractor is responsible to execute, is defined in Section 01 91 00 GENERAL COMMISSIONING REQUIRMENTS. A
Commissioning Agent (CxA) appointed by the VA will manage the commissioning process.
1.2 RELATED WORK
A. Section 01 00 00 GENERAL REQUIREMENTS.
B. Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS.
C. Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
1.3 SUMMARY
A. This Section includes requirements for commissioning the Fire
Suppression systems, subsystems and equipment. This Section supplements the general requirements specified in Section 01 91 00
General Commissioning Requirements.
B. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for more details regarding processes and procedures as well as roles and responsibilities for all Commissioning Team members.
1.4 DEFINITIONS
A. Refer to Section 01 91 00 GENERAL COMMISSIONING REQUIREMENTS for definitions.
1.5 COMMISSIONED SYSTEMS
A. Commissioning of a system or systems specified in Division 21 is part of the construction process. Documentation and testing of these systems, as well as training of the VA’s Operation and Maintenance personnel in accordance with the requirements of Section 01 91 00 and of Division 21, is required in cooperation with the VA and the
Commissioning Agent.
B. The Fire Suppression systems commissioning will include the systems listed in Section 01 19 00 General Commissioning Requirements:
21 08 00 - 2
1.6 SUBMITTALS
A. The commissioning process requires review of selected Submittals. The
Commissioning Agent will provide a list of submittals that will be reviewed by the Commissioning Agent. This list will be reviewed and approved by the VA prior to forwarding to the Contractor. Refer to
Section 01 33 23 SHOP DRAWINGS, PRODUCT DATA, and SAMPLES for further details.
B. The commissioning process requires Submittal review simultaneously with engineering review. Specific submittal requirements related to the commissioning process are specified in Section 01 91 00 GENERAL
COMMISSIONING REQUIREMENTS.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 CONSTRUCTION INSPECTIONS
A. Commissioning of the building fire suppression systems will require inspection of individual elements of the fire suppression construction throughout the construction period. The Contractor shall coordinate with the Commissioning Agent in accordance with Section 01 19 00 and the Commissioning plan to schedule inspections as required to support the Commissioning Process.
3.2 PRE-FUNCTIONAL CHECKLISTS
A. The Contractor shall complete Pre-Functional Checklists to verify systems, subsystems, and equipment installation is complete and systems are ready for Systems Functional Performance Testing. The
Commissioning Agent will prepare Pre-Functional Checklists to be used to document equipment installation. The Contractor shall complete the checklists. Completed checklists shall be submitted to the VA and to the Commissioning Agent for review. The Commissioning Agent may spot check a sample of completed checklists. If the Commissioning Agent determines that the information provided on the checklist is not accurate, the Commissioning Agent will return the marked-up checklist to the Contractor for correction and resubmission. If the
Commissioning Agent determines that a significant number of completed checklists for similar equipment are not accurate, the Commissioning
Agent will select a broader sample of checklists for review. If the
Commissioning Agent determines that a significant number of the broader sample of checklists is also inaccurate, all the checklists for the
21 08 00 - 3 type of equipment will be returned to the Contractor for correction and resubmission. Refer to SECTION 01 91 00 GENERAL COMMISSIONING
REQUIREMENTS for submittal requirements for Pre-Functional Checklists, Equipment Startup Reports, and other commissioning documents.
3.3 CONTRACTORS TESTS
A. Contractor tests as required by other sections of Division 21 shall be scheduled and documented in accordance with Section 01 00 00 GENERAL
REQUIREMENTS. All testing shall be incorporated into the project schedule. Contractor shall provide no less than 7 calendar days’ notice of testing. The Commissioning Agent will witness selected
Contractor tests at the sole discretion of the Commissioning Agent.
Contractor tests shall be completed prior to scheduling Systems
Functional Performance Testing.
3.4 SYSTEMS FUNCTIONAL PERFORMANCE TESTING
A. The Commissioning Process includes Systems Functional Performance
Testing that is intended to test systems functional performance under steady state conditions, to test system reaction to changes in operating conditions, and system performance under emergency conditions. The Commissioning Agent will prepare detailed Systems
Functional Performance Test procedures for review and approval by the
Resident Engineer. The Contractor shall review and comment on the tests prior to approval. The Contractor shall provide the required labor, materials, and test equipment identified in the test procedure to perform the tests. The Commissioning Agent will witness and document the testing. The Contractor shall sign the test reports to verify tests were performed. See Section 01 91 00 GENERAL
COMMISSIONING REQUIREMENTS, for additional details.
3.5 TRAINING OF VA PERSONNEL
A. Training of the VA operation and maintenance personnel is required in cooperation with the Resident Engineer and Commissioning Agent.
Provide competent, factory authorized personnel to provide instruction to operation and maintenance personnel concerning the location, operation, and troubleshooting of the installed systems. Contractor shall submit training agendas and trainer resumes in accordance with the requirements of Section 01 19 00. The instruction shall be scheduled in coordination with the VA Resident Engineer after submission and approval of formal training plans. Refer to Section 01
21 08 00 - 4
91 00 GENERAL COMMISSIONING REQUIREMENTS and Division 21 Sections for additional Contractor training requirements.
----- END -----
21 13 13 - 1
SECTION 21 13 13
WET-PIPE SPRINKLER SYSTEMS
PART 1 - GENERAL
1.1 SCOPE OF WORK
A. Design, installation and testing shall be in accordance with NFPA 13 except for specified exceptions.
B. The design and installation of a hydraulically calculated automatic wet system complete and ready for operation, as indicated on the design drawings.
C. Modification of the existing sprinkler system as indicated on the drawings and as further required by these specifications.
1.2 RELATED WORK
A. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Section 07 84 00, FIRESTOPPING, Treatment of penetrations through rated enclosures.
C. Section 09 91 00, PAINTING.
D. Section 28 31 00, FIRE DETECTION AND ALARM, Connection to fire alarm of flow switches, pressure switches and valve supervisory switches.
E. Section 21 05 11 COMMON WORK RESULTS FOR FIRE SUPPRESSION
1.3 QUALITY ASSURANCE
A. Installer Reliability: The installer shall possess a valid State of
California fire sprinkler contractor's license. The installer shall have been actively and successfully engaged in the installation of commercial automatic sprinkler systems for the past ten years.
B. Materials and Equipment: All equipment and devices shall be of a make and type listed by UL and approved by FM, or other nationally recognized testing laboratory for the specific purpose for which it is used. All materials, devices, and equipment shall be approved by the VA.
C. Submittals: Submit as one package in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES. Prepare detailed working drawings that are signed by a NICET Level III or Level IV Sprinkler
Technician or stamped by a Registered Professional Engineer practicing in the field of Fire Protection Engineering. As Government review is for technical adequacy only, the installer remains responsible for correcting any conflicts with other trades and building construction that arise during installation. Partial submittals will not be accepted. Material submittals shall be approved prior to the purchase or delivery to the job site. Suitably bind submittals in notebooks or
21 13 13 - 2 binders and provide index referencing the appropriate specification section. Submittals shall include, but not be limited to, the following:
1. Qualifications:
a. Provide a copy of the installing contractor’s fire sprinkler and state contractor’s license.
b. Provide a copy of the NICET certification for the NICET Level III or Level IV Sprinkler Technician who prepared and signed the detailed working drawings unless the drawings are stamped by a
Registered Professional Engineer practicing in the field of Fire
Protection Engineering.
2. Drawings: Submit detailed 1:100 (1/8 inch) scale (minimum) working drawings conforming to NFPA 13. Include a site plan showing the piping to the water supply test location.
3. Manufacturers Data Sheets:
a. Provide for materials and equipment proposed for use on the system. Include listing information and installation instructions in data sheets. Where data sheet describes items in addition to that item being submitted, clearly identify proposed item on the sheet.
4. Calculation Sheets: Submit hydraulic calculation sheets in tabular form conforming to the requirements and recommendations of NFPA 13.
5. Final Document Submittals: Provide as-built drawings, testing and maintenance instructions in accordance with the requirements in
Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
Submittals shall include, but not be limited to, the following:
a. One complete set of reproducible as-built drawings showing the installed system with the specific interconnections between the waterflow switch and the fire alarm equipment.
b. Complete, simple, understandable, step-by-step, testing instructions giving recommended and required testing frequency of all equipment, methods for testing all equipment, and a complete trouble shooting manual. Provide maintenance instructions on replacing any components of the system including internal parts, periodic cleaning and adjustment of the equipment and components with information as to the address and telephone number of both the manufacturer and the local supplier of each item.
c. Material and Testing Certificate: Upon completion of the sprinkler system installation or any partial section of the system, including testing and flushing, provide a copy of a completed
Material and Testing Certificate as indicated in NFPA 13.
21 13 13 - 3
d. Certificates shall document all parts of the installation.
e. Instruction Manual: Provide one copy of the instruction manual covering the system in a flexible protective cover and mount in an accessible location adjacent to the riser.
D. Design Basis Information: Provide design, materials, equipment, installation, inspection, and testing of the automatic sprinkler system in accordance with the requirements of NFPA 13. Recommendations in appendices shall be treated as requirements.
1. Perform hydraulic calculations in accordance with NFPA 13 utilizing the Area/Density method. Do not restrict design area reductions permitted for using quick response sprinklers throughout by the required use of standard response sprinklers in the areas identified in this section.
2. Sprinkler Protection: To determining spacing and sizing, apply the following coverage classifications and those indicated on the drawings:
a. Light Hazard Occupancies: Patient care, treatment, and customary access areas.
b. Ordinary Hazard Group 1 Occupancies: Laboratories, Mechanical
Equipment Rooms, Transformer Rooms, Electrical Switchgear Rooms, Electric Closets, Elevator Shafts, Elevator Machine Rooms, and
Repair Shops.
c. Ordinary Hazard Group 2 Occupancies: Storage rooms, trash rooms, clean and soiled linen rooms, pharmacy and associated storage, laundry, kitchens, kitchen storage areas, retail stores, retail store storage rooms, storage areas, building management storage, boiler plants, energy centers, warehouse spaces, file storage areas for the entire area of the space up to 140 square meters
(1500 square feet) and Supply Processing and Distribution (SPD).
d. Request clarification from the Government for any hazard classification not identified.
3. Hydraulic Calculations: Calculated demand including hose stream requirements shall fall no less than 10 percent below the available water supply curve.
4. Water Supply: Base water supply on a flow test of discharge of fire pumps.
5. Zoning:
a. For each sprinkler zone provide a control valve, flow switch and a test and drain assembly with pressure gauge.
21 13 13 - 4
b. Sprinkler zones shall conform to the smoke barrier zones shown on the drawings.
c. Provide seismic protection in accordance with NFPA 13.
1.4 APPLICABLE PUIBLICATIONS
A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. National Fire Protection Association (NFPA):
13-2010.................Installation of Sprinkler Systems
101-2012................Safety to Life from Fire in Buildings and
Structures (Life Safety Code)
170-2012................Fire Safety Symbols
C. Underwriters Laboratories, Inc. (UL):
Fire Protection Equipment Directory – 2012
D. Factory Mutual Engineering Corporation (FM):
Approval Guide – 2012
PART 2 PRODUCTS
2.1 PIPING & FITTINGS
A. Sprinkler systems in accordance with NFPA 13. Use nonferrous piping in
MRI Scanning Rooms.
2.2 VALVES
A. Valves in accordance with NFPA 13.
B. Do not use quarter turn ball valves for 50 mm (2 inch) or larger drain valves.
C. The wet system control valve shall be a listed indicating type valve.
Control valve shall be UL Listed and FM Approved for fire protection installations. System control valve shall be rated for normal system pressure but in no case less than 175 PSI. (No Substitutions Allowed).
D. Automatic Ball Drips: Cast brass 20 mm (3/4 inch) in-line automatic ball drip with both ends threaded with iron pipe threads.
2.3 FIRE DEPARTMENT SIAMESE CONNECTION
A. Brass, flush wall type, and a minimum of two 65 mm (2-1/2 inch) connections threaded to match those on the local fire protection service, with polished brass caps and chains. Provide escutcheon with integral raised letters "Standpipe and Automatic Sprinkler". Install an automatic ball drip between fire department connection and check valve with drain piping routed to the exterior of the building or a floor drain.
21 13 13 - 5
2.4 SPRINKLERS
A. All sprinklers except “institutional” type sprinklers shall be FM approved. “Institutional” type sprinklers in Mental Health and Behavior
Units shall be UL listed or FM approved quick response type. Maximum break away strength shall be certified by the manufacturer to be no more than 39 kPa (85 pounds). Provide quick response sprinklers in all areas, except where specifically prohibited by their listing or approval.
1. Elevator pit: sidewall sprinklers.
B. Temperature Ratings: In accordance with NFPA 13, except as follows:
1. Sprinklers in elevator pits: Intermediate temperature rated.
2.5 SPRINKLER CABINET
Provide sprinkler cabinet with the required number of sprinkler heads of all ratings and types installed, and a sprinkler wrench for each system.
Locate adjacent to the riser. Sprinkler heads shall be installed in center of tile or center to center.
2.6 IDENTIFICATION SIGNS/HYDRAULIC PLACARDS
Plastic, steel or aluminum signs with white lettering on a red background with holes for easy attachment. Enter pertinent data for each system on the hydraulic placard.
2.7 SWITCHES:
A. Contain in a weatherproof die cast/red baked enamel, oil resistant, aluminum housing with tamper resistant screws, 13 mm (1/2 inch) conduit entrance and necessary facilities for attachment to the valves. Provide two SPDT switches rated at 2.5 amps at 24 VDC.
B. Water flow Alarm Switches: Mechanical, non-coded, non-accumulative retard and adjustable from 0 to 60 seconds minimum. Set flow switches at an initial setting between 20 and 30 seconds.
C. Valve Supervisory Switches for Ball and Butterfly Valves: May be integral with the valve.
2.8 GAUGES
Provide gauges as required by NFPA 13.
2.9 PIPE HANGERS AND SUPPORTS
Supports, hangers, etc., of an approved pattern placement to conform to
NFPA 13. System piping shall be substantially supported to the building structure. The installation of hangers and supports shall adhere to the requirements set forth in NFPA 13, Standard for Installation of
Sprinkler Systems. Materials used in the installation or construction of hangers and supports shall be listed and approved for such application.
21 13 13 - 6
Hangers or supports not specifically listed for service shall be designed and bear the seal of a professional engineer.
2.10 WALL, FLOOR AND CEILING PLATES
Provide chrome plated steel escutcheon plates for exposed piping passing though walls, floors or ceilings.
PART 3 - EXECUTION
3.1 INSTALLATION
A. Installation shall be accomplished by the licensed contractor. Provide a qualified technician, experienced in the installation and operation of the type of system being installed, to supervise the installation and testing of the system.
B. Installation of Piping: Accurately cut pipe to measurements established by the installer and work into place without springing or forcing. In any situation where bending of the pipe is required, use a standard pipe-bending template. Install concealed piping in spaces that have finished ceilings. Where ceiling mounted equipment exists, such as in operating and radiology rooms, install sprinklers so as not to obstruct the movement or operation of the equipment. Sidewall heads may need to be utilized. Locate piping in stairways as near to the ceiling as possible to prevent tampering by unauthorized personnel, and to provide a minimum headroom clearance of 2250 mm (seven feet six inches). To prevent an obstruction to egress, provide piping clearances in accordance with NFPA 101.
C. Welding: Conform to the requirements and recommendations of NFPA 13.
D. Drains: Pipe drains to discharge at safe points outside of the building or to sight cones attached to drains of adequate size to readily carry the full flow from each drain under maximum pressure. Do not provide a direct drain connection to sewer system or discharge into sinks. Install drips and drains where necessary and required by NFPA 13.
E. Supervisory Switches: Provide supervisory switches for sprinkler control valves.
F. Waterflow Alarm Switches: Install waterflow switch and adjacent valves in easily accessible locations.
G. Inspector's Test Connection: Install and supply in conformance with NFPA
13, locate in a secured area, and discharge to the exterior of the building.
H. Affix cutout disks, which are created by cutting holes in the walls of pipe for flow switches and non-threaded pipe connections to the
21 13 13 - 7 respective waterflow switch or pipe connection near to the pipe from where they were cut.
I. Sleeves: Provide for pipes passing through masonry or concrete. Provide space between the pipe and the sleeve in accordance with NFPA 13. Seal this space with a UL Listed through penetration fire stop material in accordance with Section 07 84 00, FIRESTOPPING. Where core drilling is used in lieu of sleeves, also seal space. Seal penetrations of walls, floors and ceilings of other types of construction, in accordance with
Section 07 84 00, FIRESTOPPING.
J. Provide pressure gauge at each water flow alarm switch location and at each main drain connection.
K. For each fire department connection, provide the symbolic sign given in
NFPA 170 and locate 2400 to 3000 mm (8 to 10 feet) above each connection location. Size the sign to 450 by 450 mm (18 by 18 inches) with the symbol being at least 350 by 350 mm (14 by 14 inches).
L. Firestopping shall comply with Section 07 84 00, FIRESTOPPING.
M. Securely attach identification signs to control valves, drain valves, and test valves. Locate hydraulic placard information signs at each sectional control valve where there is a zone water flow switch.
N. Repairs: Repair damage to the building or equipment resulting from the installation of the sprinkler system by the installer at no additional expense to the Government.
O. Interruption of Service: There shall be no interruption of the existing sprinkler protection, water, electric, or fire alarm services without prior permission of the Contracting Officer. Contractor shall develop an interim fire protection program where interruptions involve in occupied spaces. Request in writing at least one week prior to the planned interruption.
3.2 INSPECTION AND TEST
A. Preliminary Testing: Flush newly installed systems prior to performing hydrostatic tests in order to remove any debris which may have been left as well as ensuring piping is unobstructed. Hydrostatically test system, including the fire department connections, as specified in NFPA 13, in the presence of the Contracting Officers Technical Representative (COTR) or his designated representative. Test and flush underground water line prior to performing these hydrostatic tests.
B. Final Inspection and Testing: Subject system to tests in accordance with
NFPA 13, and when all necessary corrections have been accomplished, advise COTR/Resident Engineer to schedule a final inspection and test.
21 13 13 - 8
Connection to the fire alarm system shall have been in service for at least ten days prior to the final inspection, with adjustments made to prevent false alarms. Furnish all instruments, labor and materials required for the tests and provide the services of the installation foreman or other competent representative of the installer to perform the tests. Correct deficiencies and retest system as necessary, prior to the final acceptance. Include the operation of all features of the systems under normal operations in test.
3.3 INSTRUCTIONS
Furnish the services of a competent instructor for not less than two hours for instructing personnel in the operation and maintenance of the system, on the dates requested by the COTR/Resident Engineer.
- - - E N D - - -
VA LONG BEACH HEALTHCARE SYSTEM REVISED: 04/20/2016
22 05 11 - 1
SECTION 22 05 11
COMMON WORK RESULTS FOR PLUMBING
PART 1 - GENERAL
1.1 DESCRIPTION
A. The requirements of this Section shall apply to all sections of
Division 22.
B. Definitions:
1. Exposed: Piping and equipment exposed to view in finished rooms.
C. Abbreviations/Acronyms:
1. ABS: Acrylonitrile Butadiene Styrene
2. AISI: American Iron and Steel Institute
3. AWG: American Wire Gauge
4. BACnet: Building Automation and Control Network
5. BSG: Borosilicate Glass Pipe
6. CDA: Copper Development Association
7. CO: Carbon Monoxide
8. COR: Contracting Officer’s Representative
9. CPVC: Chlorinated Polyvinyl Chloride
10. CR: Chloroprene
11. CWP: Cold Working Pressure
12. db(A): Decibels (A weighted)
13. DDC: Direct Digital Control
14. DISS: Diameter Index Safety System
15. DWV: Drainage, Waste and Vent
16. ECC: Engineering Control Center
17. EPDM: Ethylene Propylene Diene Monomer
18. EPT: Ethylene Propylene Terpolymer
19. ETO: Ethylene Oxide
20. FAR: Federal Acquisition Regulations
21. FD: Floor Drain
22. FG: Fiberglass
23. FNPT: Female National Pipe Thread
24. FPM: Fluoroelastomer Polymer
25. HDPE: High Density Polyethylene
26. HOA: Hands-Off-Automatic
27. HP: Horsepower
22 05 11 - 2
28. ID: Inside Diameter
29. MAWP: Maximum Allowable Working Pressure
30. NPTF: National Pipe Thread Female
31. NPS: Nominal Pipe Size
32. NPT: National Pipe Thread
33. OD: Outside Diameter
34. OSD: Open Sight Drain
35. OS&Y: Outside Stem and Yoke
36. PP: Polypropylene
37. PTFE: Polytetrafluoroethylene
38. PVC: Polyvinyl Chloride
39. PVDF: Polyvinylidene Fluoride
40. RTRP: Reinforced Thermosetting Resin Pipe
41. SPS: Sterile Processing Services
42. SUS: Saybolt Universal Second
43. SWP: Steam Working Pressure
44. TFE: Tetrafluoroethylene
45. THHN: Thermoplastic High-Heat Resistant Nylon Coated Wire
46. THWN: Thermoplastic Heat & Water Resistant Nylon Coated Wire
47. USDA: U.S. Department of Agriculture
48. VAC: Voltage in Alternating Current
49. WOG: Water, Oil, Gas
1.2 RELATED WORK
A. Section 01 00 00, GENERAL REQUIREMENTS.
B. Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
C. Section 01 74 19, CONSTRUCTION WASTE MANAGEMENT.
D. Section 01 81 11, SUSTAINABLE DESIGN REQUIREMENTS.
E. Section 01 91 00, GENERAL COMMISSIONING REQUIREMENTS.
F. Section 02 82 11, TRADITIONAL ASBESTOS ABATEMENT.
G. Section 03 30 00, CAST-IN-PLACE CONCRETE: Concrete and Grout.
H. Section 05 31 00, STEEL DECKING: Building Components for Attachment of
Hangers.
I. Section 05 36 00, COMPOSITE METAL DECKING: Building Components for
Attachment of Hangers.
J. Section 05 50 00, METAL FABRICATIONS.
K. Section 07 60 00, FLASHING AND SHEET METAL: Flashing for Wall and Roof
Penetrations.
22 05 11 - 3
L. Section 07 84 00, FIRESTOPPING.
M. Section 07 92 00, JOINT SEALANTS.
N. Section 09 91 00, PAINTING.
O. Section 13 05 41, SEISMIC RESTRAINT REQUIREMENTS FOR NON-STRUCTURAL
COMPONENTS.
P. Section 22 05 12, GENERAL MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT.
Q. Section 22 07 11, PLUMBING INSULATION.
R. Section 22 08 00, COMMISSIONING OF PLUMBING SYSTEMS.
S. Section 23 09 23, DIRECT-DIGITAL CONTROL SYSTEM FOR HVAC.
T. Section 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS.
U. Section 26 05 19, LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES.
V. Section 26 29 11, MOTOR CONTROLLERS.
1.3 APPLICABLE PUBLICATIONS
A. The publications listed below shall form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only.
B. American Society of Mechanical Engineers (ASME):
ASME Boiler and Pressure Vessel Code -
BPVC Section IX-2013....Welding, Brazing, and Fusing Qualifications
B31.1-2012..............Power Piping
C. American Society for Testing and Materials (ASTM):
A36/A36M-2012...........Standard Specification for Carbon Structural
Steel
A575-96(R2013)e1........Standard Specification for Steel Bars, Carbon, Merchant Quality, M-Grades
E84-2013a...............Standard Test Method for Surface Burning
Characteristics of Building Materials
E119-2012a..............Standard Test Methods for Fire Tests of
Building Construction and Materials
F1760-01(R2011).........Standard Specification for Coextruded
Poly(Vinyl Chloride) (PVC) Non-Pressure Plastic
Pipe Having Reprocessed-Recycled Content
D. International Code Council, (ICC):
IBC-2012................International Building Code
IPC-2012................International Plumbing Code
22 05 11 - 4
E. Manufacturers Standardization Society (MSS) of the Valve and Fittings
Industry, Inc:
SP-58-2009..............Pipe Hangers and Supports - Materials, Design, Manufacture, Selection, Application and
Installation
SP-69-2003..............Pipe Hangers and Supports - Selection and
Application
F. Military Specifications (MIL):
P-21035B................Paint High Zinc Dust Content, Galvanizing
Repair (Metric)
G. National Electrical Manufacturers Association (NEMA):
MG 1-2011...............Motors and Generators
H. National Fire Protection Association (NFPA):
51B-2014................Standard for Fire Prevention During Welding, Cutting and Other Hot Work
54-2012.................National Fuel Gas Code
70-2011.................National Electrical Code (NEC)