This is a VA CWM Utility Shutdown Request form and instructions document used to request and manage utility service interruptions at VA medical center facilities.

The form requires contractors to submit shutdown requests with detailed information including project number, company name, shutdown point of contact with phone number, requested shutdown date(s) with expected start and stop times, location of shutdown, location of work, location of LOTO equipment, competent person(s) performing the work, required PPE, reason for shutdown, and description of work. Contractors must identify all buildings and areas impacted by the shutdown, including downstream and upstream systems affected. The form requires identification of which services are being shut down (steam, HVAC, power, domestic water, heating hot water, chilled water, sanitary system, nurse call, fire alarm, sprinkler system, IT, emergency power, or other) and which services are affected during the work period. Contractors must provide photos of all affected panels and panel schedules with the request.

The document establishes notification timelines: minor shutdowns require seven calendar days' notice while major shutdowns (those affecting medical center operations) require 21 calendar days' notice. All fire alarm and sprinkler shutdowns require coordination with VA Fire Alarm Technician. VA M&O shops require 72-hour notice from VA Contracting Officers Representatives (COR) for all shutdowns. LOTO equipment and mandatory PPE must be on site; failure to have proper equipment results in cancellation. The form includes sections for COR approval/denial and Operations & Maintenance shop acknowledgment, with specified responsibilities for contractors, VA COR, and M&O shops throughout the shutdown coordination and execution process.

View the file

Other files

File Type Posted
Photos of SW1.pdf PDF
36C24126Q0444.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA CWM UTILITY SHUTDOWN REQUEST

Project Number: Company/Name:

Shutdown POC: POC Phone Number:

Requested Shutdown Date(s):

Expected Start Time:

Expected Stop Time:

Location of Shutdown:

Location of Work:

Location of

LOTO:

Competent Person(s):

PPE

Required:

Reason for Shutdown:

Description of Work:

All Building(s)/Area(s) Impacted (include downstream and upstream systems affected):

SERVICES AFFECTED BY SHUTDOWN

Service(s) being shut down during the requested work period: ✔ Service(s) affected during the requested work period: X ☐ Steam ☐ Domestic Cold Water ☐ Chilled Water ☐ Fire Alarm ☐ IT ☐ HVAC ☐ Domestic Hot Water ☐ Sanitary System ☐ Sprinkler System ☐ Other:

☐ Normal Power ☐ Heating Hot Water ☐ Nurse Call ☐ Emergency Power

WRITTEN NOTIFCATION REQUIRED

• Requests for utility shutdown must be conducted per 01 00 00 GENERAL REQUIREMENTS. Type of shutdown (major/minor) are the discretion of COR.

• Minor shutdowns require a 7-calendar day notification.

• Major shutdowns require a 21-calendar day notification. Major shutdowns are any interruptions that affect Medical Center operations.

• All Fire Alarm and Sprinkler shutdowns and outages require coordination with VA Fire Alarm Technician.

• All LOTO (Lock Out Tag Out) equipment and mandatory PPE must be on site and is required to shut down utilities. Failure to have proper

PPE and equipment will result in the shutdown being cancelled.

Requestor (Signature and Date):

VA ONLY-COR COMMENTS AND CONSIDERATIONS

Is shop support required for the shutdown? (i.e. investigating systems) YES NO If yes, specify support needed for shutdown:

Additional Comments:

COR Acknowledged (Signature and Date): APPROVED DENIED

VA ONLY-OPERATIONS AND MAINTENANCE

Is shop presence support required for the shutdown? YES NO Comments:

O&M Shop Acknowledged (Signature and Date):

VA CWM UTILITY SHUTDOWN REQUEST INSTRUCTIONS

CONTRACTORS RESPONIBILTIES

1. Requests need to be made in enough advance for investigation of affected systems by VA.

2. VA M&O shops require 72-hour notice from VA CORs for all shutdowns.

3. The below needs to be provided for the corresponding section:

• Shutdown POC/POC Phone Number: Provide the person onsite for the shutdown that will be coordinating all work and communicating with VA and appropriate parties. This contact will be provided to appropriate VA parties.

• Shutdown Date and Times: These times are a reflection of the time the utility will be shutdown which may differ from the overall time for the rest of the work to be completed.

• Location of Shutdown: Building(s), Floor(s), and Room Numbers(s), directly affected by the shutdown.

• Location of Work: Building(s), Floor(s), and Room Numbers(s) where the work is being performed.

• Location of LOTO: Include a Primary Panel Number(s)/Circuit Number(s) or Pipe(s) Tagged.

• Competent Person(s): Provide the name of the CP that will be performing the shutdown & LOTO for the shutdown.

• PPE Required: List all PPE required for shutdown. Failure to have proper PPE and equipment will result in the shutdown being cancelled.

• Reason for Shutdown: Specify work being performed that requires the shutdown.

• Description of Work: Provide all work to be completed during the shutdown. Ensure required permits are obtained as applicable.

• Impacted Area(s): All impacted/affected areas are determined by investigating panel schedules, tracing down stream piping, etc. VA COR assistance may be necessary to determine impacts, so it is recommended to involve the COR as early as possible to investigate the shutdown. Submit a photo of all panels and panel schedules affected by the shut down with this request form.

• Services Affected by Shutdown: Mark both the utility being shut down as well as utilities impacted by the shutdown.

(i.e. electrical shut downs may affect HVAC, IT Systems, Nurse Call)

• A copy of the fully executed request form is required for shutdown.

VA (COR) RESPONIBILTIES

1. Review request for accuracy. In the comments, specify whether an investigation will need to occur to ensure all interrupted services are listed. Email request to Greg and applicable M&O Shop Supervisor(s).

2. Notify the M&O Shops and Projects Team of shutdown to avoid conflicting shutdowns or interrupt work on other projects.

3. Review shutdown with Shops. Confirm what systems will be affected and ensure critical functions (phone, medication fridges, etc.) are not interrupted or have a contingency plan.

4. Communicate with affected Supervisors and Staff to ensure Medical Center operations can be maintained. Address concerns as necessary.

5. Meet with the Contractor to confirm shutdown schedule, duration and ensure VA is prepared for additional investigation if required.

6. Ensure that adequate temporary measures are in place that Medical Center Operations remain unaffected/mitigated.

7. Ensure if shop presence is required that shop personnel is available and present for shutdown.

8. Once request has been signed by all parties, provide general notification including End Users, Engineering, Police, and

Greg. Return completed form to the Contractor.

M&O (SHOPS) RESPONIBILTIES

1. Review request for accuracy-ensure all impacted systems are listed. If impacted systems are missing, notify COR.

2. Report any known issues to COR, ensure to provide follow-up tasks/actions if needed. (i.e. checking breakers after shutdown, checking specific affected systems etc.)

3. If shop support is required for shutdown, specify in the “Comments” section. Notify COR to coordinate. Communicate all

Shop requirements to COR.

4. Return completed form to COR.

Project Number:
Additional Comments:
Comments:
COMPANY:
SHUTDOWN LOCATION:
LOTO LOCATION:
WORK LOCATION:
CP:
PPE:
REASON FOR SHUTDOWN:
DESCRIPTION OF WORK:
EXPECTED START:
EXPECTED STOP:
POC PHONE NUMBER:
SHUTDOWN POC:
EXPECTED DATES:
ALL BLDs/AREAs IMPACTED:
COR SHOP SUPPORT:
OTHER DESCRIPTION:
CORSHOPSUPPORT: Off
FORMAPPROVED: Off
SHOPPRESENCE: Off
HVAC: [nothing selected]
STEAM: [nothing selected]
NORMAL POWER: [nothing selected]
DOMESTIC COLD WATER: [nothing selected]
DOMESTIC HOT WATER: [nothing selected]
HEATING HOT WATER: [nothing selected]
CHILLED WATER: [nothing selected]
SANITARY SYSTEM: [nothing selected]
NURSE CALL: [nothing selected]
FIRE ALARM: [nothing selected]
SPRINKLER SYSTEM: [nothing selected]
EMERGENCY POWER: [nothing selected]
IT: [nothing selected]