This is a Justification for Other than Full and Open Competition (JOFOC) memorandum dated February 14, 2025, for repair services on a stern ramp due to wire rope jumping sheaves. The procurement is being conducted under simplified acquisition procedures with Trident Maritime Systems - Heavy Equipment Group as the sole source contractor.
The justification cites three main reasons for limiting competition: 1) standardization/brand name requirements for Model F113533 Stern Ramp, 2) form, fit, and function compatibility requirements with existing equipment, and 3) the vendor's proprietary drawings and specialized expertise with wire rope connections and sheave assembly inspection. The required delivery date is February 24, 2025. The contractor, located in Kingsford, MI, is deemed the only source capable of performing the repairs since they are the OEM with proprietary technical data and are responsible for ensuring the stern ramp remains operational for mission readiness.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| COMBINED SYNOPSIS SOLICITATION N3220525Q2182.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 Ver 2.0 (01 July 2018)
Date: 14 Feb 2025
MEMORANDUM
Subj: USE OF OTHER THAN FULL AND OPEN COMPETITION FOR AN ACQUISITION UNDER
THE SIMPLIFIED ACQUISITION THRESHOLD
Ref: (a) PR Number(s)/PD: 1301230281
I. BACKGROUND:
1. In considering the references, FAR 13.106-1(b)(1)(i) states for purchases not exceeding the simplified acquisition threshold, Contacting Officers may solicit from one source if the
Contracting Officer determines that, under the circumstances of the contract action, only one source is reasonably available (e.g., urgency, exclusive licensing, brand-name, or industrial mobilization).
2. As required by FAR 13.106-3(b)(3)(i), this memorandum explains the absence of competition for this acquisition because only one source will be solicited for this requirement (or for a portion of the requirement) and the requirement is not expected to exceed the simplified acquisition threshold.
II. DESCRIPTION OF ITEM OR SERVICE:
1. Provide a description of the item or service required, to include
a) the name of the required source or brand name
Trident
b) the required delivery date/period of performance and
RDD: 2/24/2025
c) its intended use.
OEM required to repair ramp due to wire rope jumping sheaves.
2. List the source(s) or known vendor(s) who are able to provide the above described item or service.
Trident Maritime Systems - Heavy Equipment
Group
2141 WOODWARD AVENUE
KINGSFORD, MI 49802
906-774-1500 FAX:906-774-15
III. THE DETERMINATION FOR USE OF OTHER THAN FULL AND OPEN COMPETITION IS BASED
ON THE FOLLOWING (select all that apply):
A. _____ Only one responsible source (select all that apply):
2 Ver 2.0 (01 July 2018)
1. _ _ RESTRICTIVE RIGHTS: the source has established proprietary rights, limited rights in data, patent rights, copyrights, or secret processes in the item or service.
a. Explain what is subject to the restrictive rights.
b. If drawings are included, who is identified as “owning” the drawings.
2. _____ EXCLUSIVE LICENSING AGREEMENTS: The item or service is only available from the Original Equipment Manufacturer (OEM), or there is ONLY ONE authorized distributor or technical representative for the OEM.
a. Identify the OEM and explain the circumstances surrounding why the item or service is only available from the OEM.
b. Identify the distributor / authorized technical representative for the item or service. Provide evidence of the exclusive licensing agreement as an attachment to this document.
(NOTE: If there is more than one distributor / authorized technical representative, then use Part
B – Brand Name.)
3. _ X__ OTHER REASON:
a. _____ CRITICAL SHIP EQUIPMENT: The required item is critical ship equipment, the failure of which poses a hazard to the ship, the crew or the environment.
i. SMS Procedure Number: ___________________________
b. _X_ STANDARDIZATION / BRAND NAME: Per MSCs standardization initiative, only the specified make/model of the equipment/parts will satisfy the Government’s needs for additional units or replacement items.
i. Identify Make / Model Number(s):
ii. Identify other vessels with this Make / Model:
_ ___Model F113533 Stern Ramp_______________
c. _X_ FORM, FIT, AND FUNCTION: Item is direct replacement parts / components for existing equipment and must be compatible in terms of form, fit, and function with existing equipment / configurations.
3 Ver 2.0 (01 July 2018)
i. Identify Make / Model of existing equipment: Trident Stern Ramp
Model F113533
ii. Describe how the equipment must be compatible with the existing configuration.
OEM has specific drawings which are proprietary. OEM is responsible that the
Stern Ramp is operational and is essential to mission executions and readiness.
d. __X__ OTHER:
Vendor holds proprietary drawings in accordance to wire rope connection. OEM has knowledge and extensive experience in untangling the wire rope and inspection of the condition of the wire ripe and sheave assembly.
4. _____ UNUSUAL AND COMPELLING URGENCY: The supplies or services are of such unusual and compelling urgency that the Government would be seriously injured unless the agency is permitted to limit the number of sources from which it solicits. Urgent requirements are supplies or services that will result in work stoppage, or are mission critical and the routine processing time would injure the Government. The determination that the procurement for the above is an urgent and compelling requirement is based on the following:
a. Date on which the requirement was identified:
b. Required delivery date / Period of Performance:
c. If the difference between a. and b. is more than one week, explain the delay in submitting the requirement.
d. Estimated production lead time: _ _____________________________
e. Explanation of why delivery / commencement of services by the date required is needed: (explain the impact to the mission, any special circumstances or conditions, etc.)
4 Ver 2.0 (01 July 2018)
f. CASREP Number: _________________________________________
IV. ANTICIPATED DOLLAR VALUE OF PROCURMENT:
V. CERTIFICATIONS AND APPROVALS:
Technical / Requirement Certification: I certify that the facts and representation under my cognizance which are included in this justification are complete and accurate to the best of my knowledge and belief.
Requester Signature / Date
Level Higher (Suppo / SPE / ASPE) / Date
Contract Specialist / Date
Contracting Officer / Date
File details come from the government source that posted it. Updated .