BLACKFIN_(WPB_87)_DS_FQ3_LKT_18R1.doc

DOC document 354 KB Posted

Attached to
USCGC BLACKFIN DOCKSIDE REPAIRS FY18 - 70Z080-18-Q-P4511700
Solicitation number
USCGC_BLACKFIN_DS_FY18
Issued by

About this file

Specification

View the file

Other files

File Type Posted
BLACKFIN_(WPB_87)_DS_FQ3_LKT_18ED0_BLANK.xls XLS spreadsheet
FINAL_Combined_Synopsis_Solicitation_Dockside_-_BLACKFIN_FY18.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC BLACKFIN (WPB 87317)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2018

Developed By: Lindsay K Taylor (Rev-1, 5 December 2017)

TABLE OF CONTENTS

Revisions Record This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE
REV#
WORK ITEM#
CHANGES MADE
12/5/2017
1
2
Corrected compartment number for rack renewal, 2-6-1-L.
12/5/2017
1
3
Add recommended source of supply and included exterior surfaces to touch-up preservation.

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

Consolidated List of References

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 87 WPB 167-002, Rev B, CG Schedule of Doors, Manholes, Windows & Hatches

Coast Guard Drawing 87 WPB 184-001, Rev -, Foundations for Install of Jets Vacuum System

Coast Guard Drawing 87 WPB 302-003, Rev -, Jets Vacuum Toilet Electrical Details

Coast Guard Drawing 87 WPB 310-001, Rev H, Ship's Service One-Line Diagram

Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping System

Coast Guard Drawing 87 WPB 593-004, Rev -, Sewage System Modifications Jets Vacuum System

Coast Guard Drawing 87 WPB 640-001, Rev N, Interior Furnishings

Coast Guard Drawing 87WPB 185-001, Rev AN, Sheet 1 and 2, Auxiliary Foundation Booklet

Coast Guard Drawing 87-WPB 185-001, Rev AN, Sht 57, Auxiliary Foundation Booklet

Coast Guard Drawing 87-WPB 302-001, Rev W, Misc. Controls Wiring Diagram

Coast Guard Drawing 87-WPB 310-001, Rev H, Ship’s Service One-Line Drawing

Coast Guard Drawing 87-WPB-201-001, Rev F, Machinery Arrangement

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Coast Guard Technical Publication (TP) 4583B, MAR 2003, Pump, Fire / Bilge Centrifugal - Series Crn32-4

Coast Guard Technical Publication (TP), 9115, Jets Vacuum Sewage System

Engineering Change Approval (EC) 087-C-042 AM1, JUN 2009, Fire/Bilge Pump Replacement

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0341 (SFLC Std Spec 0341) 2014, Shipboard Electrical Cable Test

Surface Forces Logistics Center Standard Specification 0342 (SFLC Std Spec 0342) 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Coast Guard Technical Publication 4540, Pump, Chilled Water- Model KC2.

Coast Guard TP 4542, Pump, Lube Oil Evacuation-Model 01SS1PTYDJHLW

Coast Guard TP 4570, Pump, Waste Oil

Coast Guard TP 4988, Ventilation Fan, Engine Room Circulating-Model YM-18

Consolidated List of Government-furnished Property

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK ITEM
MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/Unit)

2
N
***Rack, upper, berthing
P/N: 4000-109
1 ea
735.00
2
N
***Drawer
P/N: 4000-114
1 ea
75.00
2
N
***Drawer pull
P/N: 4000-113
1 ea
25.00
4
Y
Sewage installation kit: Jets 610SS Toilets, Vacuum Pump, controller and Vacuum Accumulator
NSN: 4510-01-F16-4844 PN: CUSTVU15-TO610
1 ea.
13,957
6
Y
Fire Pump
NSN: 4320-01-477-8625 PN: CRN 32-40
1
6068.31
6
N
Adaptor Kit
NSN: 4320-01-543-3949 PN: 290843
1
117.46

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter

Consolidated List of Critical Inspection Items The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5 (Inspection report particulars)):

Work Item
Title

This section is not applicable to this package.

Principal Characteristics

87' WPB

Physical

Length overall
87'
Length between perpendiculars
81' 7"
Depth
10' 11"
Maximum beam
19.4'
Draft, mean to design waterline
5' 9"
Height of highest projection
50.2'
Full load displacement
93.5 long tons
Minimum operating displacement
83.9 long tons
Displacement, light ship
77.9 long tons
Framing
Longitudinal
Bulkheads
Four watertight bulkheads located below the Main Deck
Anchor
40 lb Fortress with 480 ft. 3 strand 5/8" dia. Line stayset

Hull

Hull/main weatherdeck material
ABS Grade AH 36
Superstructure
5086 Aluminum

Machinery

Main propulsion
Two MTU 8V396TE94, sequential turbo-charged diesels
Reduction gears
Two ZF Type BW 255
Propulsion shaft
Two AQUAMET 22, 101.6mm
Shaft diameter
4"
Shaft seal
Two John Crane mechanical seals
Shaft bearing, intermediate
Thordon Elastomeric Bearing
Shaft bearing, aft
Thordon Elastomeric Bearing
Number of propellers
2
Number of blades
5
Diameter of propeller
1040mm
Pitch
1230 mm fixed
Shaft RPM
828
Rudders
Two 316L Stainless Steel
Ship's service generators
Two Man Model D08241F01 diesel with Stanford 60KW Generator

Tank Capacities

3-9-1-f (fuel oil)
1402 gal
3-9-2-f (fuel oil)
1402 gal
3-12-2-f (waste oil)
86 gal
3-12-1-f (oily water)
86 gal
3-7-0-q (sewage collection)
352 gal
3-7-1-q (grey water)
52 gal
3-12-1-w (fresh water)
200 gal
3-12-2-w (fresh water)
200 gal

00000_1216_FLT

REC_00000_FLT_Commercial Project @ CG Facility (1212)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

Coast Guard Drawings

None

Coast Guard Publications

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General. The Contractor shall conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability.

NOTE

The requirements of paragraph 3.1 (General) applies to all work under the scope of this contract, whether explicitly stated in work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

3.2 Contractor-provided fire watch personnel. The Contractor shall provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor shall accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. Ensure that all colors and color coat/paint schemes are in accordance with COMDTINST M10360.3, Chapter 6 (Cutter and Boat Colors Exterior and Interior).

NOTE

Unless a waiver has been granted (in writing) by the KO, deviations from authorized coatings (listed in Appendix C of SFLC Std Spec 6310) and colors and color schemes (provided in Chapter 6 of COMDTINST M10360.3) are strictly prohibited.

3.4 Welding and brazing requirements. The Contractor shall perform all welding and allied processes, and NDI in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor shall adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor shall provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor shall plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor shall comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item shall not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility will be provided upon award of contract.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

· Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

· National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

· Air Emission Permit: Unit has a Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor shall be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work shall be done by qualified laboratories; and where required by law, the laboratories shall be certified.

3.5.3 Regulatory notifications. The Contractor shall be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The Contractor shall submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications shall be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor shall appoint in writing an Environmental Manager for the project, and shall be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager shall ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor shall comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor shall be aware of the following:

3.5.6.1 No Contractor or Subcontractor shall have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor shall prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor shall furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. None.

3.7 SFLC standard specification approved changes. The Contractor shall be aware that the following are approved changes to published SFLC 2014 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 6310, Requirements for Preservation of Ship Structures.

3.7.1.1 SFLC Std Spec 6310, page C-2, Section C1.5.1. Change from "lead-containing paint as 0.06%" to "lead-containing paint as 0.009%".

3.7.1.2 SFLC Std Spec 6310, page 4, Section 2 References, Group- Other References. Add “The Society for Protective Coatings (SSPC) Paint Application Guide No. 11, 2008, Protecting Edges, Crevices, and Irregular Steel Surfaces by Stripe Coating”

3.7.1.3 SFLC Std Spec 6310, page Appendix C-6, add "Hempel Hempadur Multi-Strength GF 35870" with FED-STD-595 color "Black/Red" under ANTI-ABRASION COATING, ICE BREAKING CAPABLE VESSELS, <235’.

3.7.1.4 Standard Spec 6310, page Appendix A-7, Under "UNDERWATER (U/W) BODY/BOOT-TOP", Add line Column 1: Option for U/W Body and Boot-Top, Steel Hulls, <154', in Salt Water. Column 2: Blank. Column 3: SSPC-SP 10/NACE NO. 2 using grit conforming to MIL-A-22262 / (1.5-3.5) - or - SSPC-SP WJ-2(M)/NACE WJ-2(M). Columns 4 and 5: Same as "U/W Body and Boot-Top, Aluminum Hull, High Speed (>30 knots)".

3.7.2 SFLC Standard Specification 0000 General Requirements.

3.7.2.1 SFLC Std Spec 0000, paragraph 1.3 ‘Acronyms and term definitions’, page 5, “PCL (Paint Containing Lead)” definition replaced by, “Any paint or coating containing lead in excess of 0.009 percent by weight (1.0 mg/cm2 or 90 ppm). Lead Based Paint (LBP) is an interchangeable term with PCL.”

3.7.2.2 Change Std Spec 0000 paragraph 3.2.4.2.3(QP 1 inspector or tech rep duties) bullet, “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.19 of SFLC Std Spec 6310 (Critical drying time requirements)).” to “Determine when applied coats have sufficiently cured for overcoating or for system service resumption (see paragraph 3.1.17 of SFLC Std Spec 6310 (Critical drying time requirements)).”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfgr.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfgr.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

Vessel Name
Hull #
Work Item #
Work Item Title

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE & TIME
ACTIVITY (Surface preparation, primer coat, barrier coat, top coat, etc…)
LOCATION (Frame & Deck, relation to equipment, etc.)
TEMPERATURE
% REL. HUMID-ITY
DEW PT.
SURFACE
AMBIENT
ΔT

| DP - Surface |

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Place surface profile replica tapes in the spaces provided below, to serve as permanent QA record. Maintain a separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Place Surface Profile

Place Surface Profile Replica Tape Here Place Surface Profile Replica Tape Here

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mil Reading (IAW ASTM D4417-Method C) for above 15 readings:

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)
SURFACE PREPARATION METHOD
PROFILE ACHIEVED (mils)
Min
Max
Mean

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

Abrasive Manufacturer:

Abrasive Sieve Size:

Record measurements taken in the spaces provided below, to serve as permanent QA record. Maintain separate log for each location. When an area is divided into separate sections, maintain a separate log for each section.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading (mils)

Mean Reading (mils) IAW ASTM DD4417).

Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

Vessel Name
Hull #
Work Item #
Work Item Title
Location of Work (incl. frame #’s)
Area (sqft)

SOLUBLE SALT CONDUCTIVITY Measurements IAW SSPC-GUIDE 15.

Date
Test Locations
Conductivity (Microsiemens/CM)
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

Vessel Name
Hull #
Work Item #
Work Item Title
Coating Mfg
Product Name
Batch #
Induction Time
Coating System Sequence (Primer/Touchup/3rd Coat, etc.)

Dry Film Thickness (DFT) Measurements IAW SSPC-PA 2.

SPOT
1
2
3
4
5
AVERAGE VALUE

*BASE METAL READING (BMR) Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Location (Frame Reference):

SPOT
1
2
3
4
5
Overall Avg. DFT
ADJUSTMENTS
Avg. BMR
Deviation
Before Adjustments
After Adjustments

Avg.

Application Method (Airless, Conventional Spray, Rolled)
Average DFT
Name of QP-1/NACE Inspector
Signature
Cert. #
Date / Time

S17_002_16710_FJL_0617_87317

WORK ITEM 1: Lazarette Hatch, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the port lazarette flush hatch 1-22-2.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 87 WPB 167-002, Rev B, CG Schedule of Doors, Manholes, Windows & Hatches

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Renewal. Using Coast Guard Drawing 87 WPB 167-002, the Contractor shall renew hatch 1-22-2 (indicated on sheet of the drawing as “A” enclosed in an inverted triangle), Freeman Marine Equipment part number 2464-USCG, accessing the port lazarette.

NOTE

The Contractor shall notify and permit the Coast Guard Inspector to witness all chalk tests for watertight doors as required by SFLC Std Spec 0740 (paragraph 3.16).

3.3 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs).

NOTE

Do not preserve the knife edge of the new hatch coamings.

Do not preserve any moving parts on the hatches.

3.4 Closure. The Contractor shall demonstrate 100 percent gasket contact and proper dog operation by means of a chalk test. Ensure that initial contact between gasket and knife edge occurs throughout extent of gasket before final securing of dogs, and without use of excessive closing force. If the mark on the gasket is not uniform, adjust as necessary to achieve uniform contact and retest.

3.5 Water hose test. The Contractor shall inspect and perform a water hose test of all affected boundaries in accordance with SFLC Std Spec 0740, Appendix C. Submit a CFR.

3.6 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

4. NOTES

This section is not applicable to this work item.

S17_001_64000_FJL_0617_87317

WORK ITEM 2: Interior Rack, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew the upper berthing rack and associated drawer in the forward berthing space, 2-6-1-L.

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/UNIT)

N
***Rack, upper, berthing
P/N: 4000-109
1 ea
735.00
N
***Drawer
P/N: 4000-114
1 ea
75.00
N
***Drawer pull
P/N: 4000-113
1 ea
25.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 87 WPB 640-001, Rev N, Interior Furnishings

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.1.5 Operational test, initial. Prior to commencement of work, the Contractor shall witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Renewal particulars. Using Coast Guard Drawing 87 WPB 640-001 as guidance, the Contractor shall renew the upper berthing rack and drawer located in the compartment 2-6-1-L. Use government-furnished property provided in paragraph 1.2 above.

3.3 Operational test, post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310.

4. NOTES

This section is not applicable to this work item.

TCTO_TD7000_30300_RJL_0616_87WPB(01-50)

WORK ITEM 3: Motor Controller, Install

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to install new motor controllers and associated components.

NOTE

This work item is applicable to hulls 87301-87350 only.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 87-WPB 185-001, Rev AN, Sht 57, Auxiliary Foundation Booklet

Coast Guard Drawing 87-WPB-201-001, Rev F, Machinery Arrangement

Coast Guard Drawing 87-WPB 302-001, Rev W, Misc. Controls Wiring Diagram

Coast Guard Drawing 87-WPB 310-001, Rev H, Ship’s Service One-Line Drawing

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 0341 (SFLC Std Spec 0341) 2014, Shipboard Electrical Cable Test

Surface Forces Logistics Center Standard Specification 0342 (SFLC Std Spec 0342) 2014, Shipboard Electrical Cable Removal, Relocation, Splice, Repair, and Installation Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2014, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures Other References

Coast Guard Technical Publication 4540, Pump, Chilled Water- Model KC2.

Coast Guard TP 4542, Pump, Lube Oil Evacuation-Model 01SS1PTYDJHLW

Coast Guard TP 4570, Pump, Waste Oil

Coast Guard TP 4988, Ventilation Fan, Engine Room Circulating-Model YM-18

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not Applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.3.1 Protect non-affected vessel’s equipment, components, and spaces during surface preparation and coating application procedures, as specified in SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

· Bulkhead insulation

· Motor access covers

· Cable straps

· Cable hangers

· Coating systems

· Electrical wiring

· Insulation

3.2 Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.3. Controller install. The Contractor shall install pieces 126 and 127 on drawing 87-WPB-302-001 in accordance with Coast Guard Drawings 87 WPB 185-001, 87 WPB-201-001, 87 WPB 302-001, and 87 WPB 310-001.

3.3.2 Electrical requirements. The Contractor shall accomplish all electrical work in accordance with SFLC Std Spec 3042, and test cables in accordance with SFLC Std Spec 3041

3.4 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed interior and exterior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310, Requirements for Preservation of Ship Structures.

3.5 Operational test – post repairs. After completion of work, the Contractor shall, in the presence of the Coast Guard Inspector, thoroughly test and prove all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

4. NOTES

4.1 Recommended source of supply. Recommended source for motor controllers: WESCO Distribution Inc. 2011 Lausat ST. Metarie, LA. 70001. POC Fred Florek, (504) 835-8888

TCTO_TQ4010.0_33000_RJL_0617_87WPB

WORK ITEM 4: Sewage System (Toilet), Modify

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to remove two existing toilets and associated components and install the Jets vacuum sewage system.

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/UNIT)

Y
Sewage installation kit: Jets 610SS Toilets, Vacuum Pump, controller and Vacuum Accumulator
NSN: 4510-01-F16-4844

PN: CUSTVU15-TO610

1 ea.
13,957

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 87 WPB 184-001, Rev -, Foundations for Install of Jets Vacuum System

Coast Guard Drawing 87 WPB 302-003, Rev -, Jets Vacuum Toilet Electrical Details

Coast Guard Drawing 87 WPB 593-004, Rev -, Sewage System Modifications Jets Vacuum System Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Coast Guard Technical Publication (TP), 9115, Jets Vacuum Sewage System

Other References

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

· Piping

· One-step decking system

· Electrical wiring

· Carpet

· Bulkhead sheathing

· Insulation

· Sewage

· Grey water

· Sink vanity

CAUTION

Empty sewage and grey water tanks, gas free all spaces between Frames 5 and 9 from the bilge to the main deck prior to hot work.

warning

Do not perform any welding evolutions until all steps pertaining to welding isolation (MPC B00000.0) are completed or severe damage to electronic equipment may occur.

3.1.5 Temporary Sanitary and Sewage Facilities. Whenever sewage or grey water collection service is disrupted due to contractor repairs, the Contractor shall provide temporary facilities in accordance with SFLC Standard Spec 0000 par 3.2.11.

3.2 Removal. The Contractor shall remove existing toilets (2) and associated components (e.g. piping, etc.) in accordance with Coast Guard Drawing 87-WPB-593-003. Dispose of removed components in accordance with all federal, state, and local regulations, or as designated by Coast Guard Inspector.

Note

The vanity tops in 87 WPB heads are constructed of honey comb panel with a ¼” granite veneer. The panel is held in place with silicone around the perimeter. During removal of the crew’s head vanity for sewage pipe installation, care must be taken not to flex the panel or the granite will crack or shatter. If the top is damaged during removal, replace all loose pieces with adhesive and wrap top with stainless steel (see sheet 4 of CG Drawing 87-WPB-186-001).

3.3 Installation. The Contractor shall provide all labor and materials to install two Jets Vacuum toilets, vacuum macerator pump, accumulator tank and associated wiring and piping in accordance with Coast Guard Drawings 87-WPB -184-028, 87-WPB -320-016, and 87-WPB -593-006.

Note

Install toilets as far aft as is practical to provide maximum clearance to head door.

3.3.1 System adjustment. After installation of all sewage system components, the Contractor shall test all sewage piping for leaks and perform repairs as needed. Verify correct pump rotation in accordance with markings on pump housing. Adjust system in accordance with Coast Guard TP 9115 prior to system testing.

3.4 Touch-up preservation. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces to match existing adjacent surfaces, in accordance with SFLC Std Spec 6310.

3.5 Operational test – post repairs. After completion of work, the Contractor shall, in the presence of the Coast Guard Inspector, thoroughly test and prove all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

4. NOTES

4.1 Content of GFP kit.

· (1ea) Vacuum accumulator tank PN: 012101207

· (1ea) Jets 15MB-D vacuum/macerator pump PN: 029015001

· (1ea) Vacuum collecting unit controller panel PN: 121801043

· (4ea) Vibration absorbers PN: 030303400

· (1ea) Pressure Switch PN: 032300100

· (2ea) Toilet 610SS PN: 065604500

· (2ea) Elbow, rubber, with stainless steel clamps PN: 034505450

· (1ea) Coupling, rubber, with stainless steel clamps PN: 034505550

· (2ea) Soft close toilet seat and cover PN: 069608830

· (2ea) Valve, vacuum flush and discharge PN: 054100960

· (2ea) Vacuum breaker kit PN: 034507620

· (2ea) Release button, vacuum operated PN: 100100030

S17_003_51401_FJL_0917_87317

WORK ITEM 5: HVAC System, Ducting, Clean

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the shipboard HVAC system ducting.

1.2 Government-furnished property.

None.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 87 WPB 514-001, Rev M, HVAC Duct & Piping System Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2014, Clean Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Other References

None

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not Applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

· Ducting screens.

· Electric preheaters.

· Overhead sheathing and panels.

· Ventilation covers.

3.1.5. Operational test - initial. Prior to commencement of work, the Contractor shall witness an operational pre-test (by Coast Guard personnel) of the ventilation systems included in this work item, to demonstrate existing operational condition. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Cleaning particulars. Using Coast Guard Drawing 87 WPB 514-001 as guidance, the Contractor shall accomplish the following:

3.2.1 Clean all supply and exhaust portions of the HVAC system (all ducting leading to and from the air handler unit) in accordance with SFLC Std Spec 5100.

3.2.2 Mark the positions of all diverting, balance, and splitter dampers prior to disassembly and restore to original configuration at reassembly.

3.3 Operational test – post repairs. In the presence of the Coast Guard Inspector, the Contractor shall thoroughly test and prove the disturbed ventilation systems to be in satisfactory operating condition. Repair all leaks. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs).

4. NOTES

This section is not applicable to this work item.

EC_042_FJL_0917_87WPB

WORK ITEM 6: Fire/Bilge Pump, Port, Install New

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to install a new port fire/bilge pump. This work item accomplishes EC 087-C-042AM1.

CAUTION

The pump OEM has recently changed the design of the pump foundation/adaptor. The Contractor may receive one of these new pump/adaptor sets. If the GFP pump and adaptor received do not mate perfectly with the existing foundation on the cutter, minor modifications to the cutter’s foundation will be required and are allowable. Submit a CFR describing the required changes, they will be authorized/funded by CR.

1.2 Government-furnished property.

MTI
ITEM DESCRIPTION
NSN/PN
QTY
ESTIMATED COST

($/UNIT)

Y
Fire Pump
NSN: 4320-01-477-8625

PN: CRN 32-40

1
6068.31
N
Adaptor Kit
NSN: 4320-01-543-3949

PN: 290843

1
117.46

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center.

2. REFERENCES

Coast Guard Drawings

Coast Guard Drawing 87WPB 185-001, Rev AN, Sheet 1 and 2, Auxiliary Foundation Booklet

Coast Guard Drawing 87 WPB 310-001, Rev H, Ship's Service One-Line Diagram

Coast Guard Publications

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2014, General Requirements

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2014, Requirements for Preservation of Ship Structures

Engineering Change Approval (EC) 087-C-042 AM1, JUN 2009, Fire/Bilge Pump Replacement

Coast Guard Technical Publication (TP) 4583B, MAR 2003, Pump, Fire / Bilge Centrifugal - Series Crn32-4 Other References

None.

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor shall furnish and install all protective coverings to seal off and protect all non-affected vessel's components, equipment, and spaces near the work area against contamination during the performance of work. Upon completion of work, the Contractor shall remove all installed protective measures, inspect for the presence of contamination, and return all contaminated equipment, components, and spaces to original condition of cleanliness.

3.1.4 Interferences. The Contractor shall handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences).

3.2 Fire pump installation particulars. The Contractor shall install one new fire pump assembly in accordance with EC 087-C-042AM1. Refer to Coast Guard Drawing 87WPB 185-001, 87WPB 310-001 and TP-4583.

3.3 Touch-up preservation, general. The Contractor shall prepare and coat all new and disturbed exterior and interior surfaces, as applicable, to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

3.4 Leak test. After completing all authorized mechanical (i.e. threaded, bolted, etc.) joint repairs, the Contractor shall test the firemain system's operation using the system fluid at normal operating pressure. Ensure zero visible leakage from or deformation of mechanical parts by repairing all leaks and discrepancies. Submit a CFR.

3.5 Operational test – post repairs. After completion of work, the Contractor shall thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

4. NOTES

This section not applicable to this work item.