USCGC TERRAPIN - Statement of Work - Fuel Tank Cleaning and Inspection.docx
DOCX document 27 KB Posted
- Attached to
- USCGC TERRAPIN Fuel Tank Cleaning
- Solicitation number
- 52000QR250002047
About this file
This is a Statement of Work (SOW) and related solicitation for fuel tank cleaning and inspection services for the USCGC TERRAPIN, located in Bellingham, WA. The work involves cleaning and inspecting two diesel fuel service tanks, each with 1,450-gallon capacity, including removal of up to 2,000 gallons of contaminated diesel fuel and 600 gallons of wash water. The contractor must provide a certified Marine Chemist, handle all protective measures and interferences, maintain plug logs, and perform thorough cleaning and inspection of tank interiors.
The opportunity is a total small business set-aside under NAICS code 336611, issued by the US Coast Guard Surface Force Logistics Center. Work must be completed between January 27 and February 7, 2025, with quotes due by January 27, 2025, at 9:00 AM EST. The contract will be awarded as a firm-fixed price using simplified acquisition procedures, with award based on best value considering specification, price, past performance, and quality. Contractors must be registered in SAM.gov and submit quotes via email to the specified contracting officers.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| January 2025 52000PR250001974 FAR CLAUSE 52.212-5 (2).docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
USCGC TERRAPIN – FUEL TANK CLEANING AND INSPECTIONS USCGC TERRAPIN
365 Harris Ave. Bellingham, WA 98225
CONTENTS
1. Introduction
2. References
3. Scope of Work
4. Period of Performance
5. Deliverables
6. Acceptance Criteria
7. Notes
1.0 INTRODUCTION
The U.S. Coast Guard Cutter TERRAPIN (WPB-87366) requires commercial providers to perform cleanings on the following: Fuel Service Tanks.
| TYPE OF TANK |
| LOCATION |
| CAPACITY - 95% |
(GALLONS)
LOW SUCTION
(GALLONS)
| Diesel Fuel |
| 3-9-1-F |
| 1450 |
| 40 |
| Diesel Fuel |
| 3-9-2-F |
| 1450 |
| 40 |
2.0 REFERENCES
COAST GUARD DRAWINGS
Coast Guard Drawing 87 WPB 111-001, Rev H, Shell Expansion Coast Guard Drawing 87 WPB 113-001, Rev G, Platform Plating & Framing Coast Guard Drawing 87 WPB 116-001, Rev -, Longitudinal Girders & BHD’s Coast Guard Drawing 87 WPB 122-001, Rev C, Watertight Bulkheads Coast Guard Drawing 87 WPB 601-001, Rev R, Outboard Profile & General Arrangements
COAST GUARD PUBLICATIONS
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2022, General Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2022, Welding and Allied Processes
OTHER REFERENCES
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets Maintenance Procedure Card (MPC) B24101.D
3.0 SCOPE OF WORK- The work is to be accomplished through the following tasks:
3.1. Work to be completed at the following location: USCG Fairhaven – cutter moorings; 365 Harris Ave., Bellingham, WA 98225. POC: MKC Aaron Wills; Mobile: 619-962-1617, Office: 360-477-2380
3.2. The Contractor shall provide a certified Marine Chemist to gas-free the ship’s fuel service tanks, Vestibule space, and any other spaces as deemed necessary by the Contractor.
3.3. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).
3.4. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:
3.4.1. Fuel
3.4.2. Piping
3.4.3. Tank access cover
3.5. The Contractor must remove up to a total of 2000 gallons of contaminated diesel fuel. Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit document to the COR or Coast Guard Inspector upon completion of work. Dispose of removed fluids in accordance with all applicable Federal, State, and Local regulations.
3.6. Plug Log: The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.
3.6.1. Ensure that all plugs are removed from each tank upon completion of work in the tank.
3.6.2. Ensure the Plug Log is available to the Coast Guard Inspector when the inspector is performing their close-out inspection on each tank.
3.7. Cleaning requirements: The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process, and dispose of approximately 600 gallons of wash water. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths. The Contractor must refer to Coast Guard Drawings 87 WPB 111-001, 87 WPB 113-001, 87 WPB 116-001, 87 WPB 122-001, and 87 WPB 601-001 for guidance.
3.8. Inspection: The Contractor, in the presence of a Coast Guard Inspector, must accomplish the following tasks:
3.8.1. Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.
3.8.2. • Tank structural condition.
3.8.3. • Inaccessible areas.
3.8.4. • Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (if tank interior surfaces are coated).
3.8.5. • Tank level indicator (TLI) and/or float switch condition, as applicable.
3.8.6. • Sounding/vent tube and striker plate condition.
3.8.7. • Suction and discharge piping condition.
3.8.8. • Fastener material and condition (correct fastener material is stainless steel).
3.9. Tank closing. The Contractor must accomplish the following after completion of all authorized repairs and/or preservation procedures:
3.9.1. For unpainted fuel tank(s) that are not ballasted, apply a heavy coat of lube oil to the entire tank interior(s).
3.9.2. Ensure that the tank(s) remain open for at least 24 hours. Notify the COR at least 24 hours prior to closing the tank(s) and ensure tank closure is accomplished in the presence of the Coast Guard Inspector. After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183. Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing fasteners. Existing undamaged fasteners may be reused.
4.0 PERIOD OF PERFORMANCE
4.1. The Contractor shall coordinate the work schedule with Coast Guard Cutter TERRAPIN. Once the Contractor is in receipt of final authorization and prepared to conduct services, the period of performance shall not exceed 07 days after contract award date. The requested work period is between 27 JAN to 07 FEB, 2025, or as soon as service provider availability will allow, with the requested date of completion no later than 07 FEB 2025.
DELIVERABLES
4.2. The Contractor shall provide all required equipment and labor costs.
4.3. The Unit shall schedule a service date and be available to receive contracted services.
5.0 ACCEPTANCE CRITERIA
5.1. The government reserves the right to witness the contract repairs. The service provider shall keep the Engineer Petty Officer, MKC Aaron S. Wills, fully informed of servicing plans so that he or his authorized representative may arrange to be present when work is being performed.
5.2. When the work is complete, the Contractor shall notify the unit’s EPO for final inspections.
6.0 QUALITY ASSURANCE
6.1. The Contractor shall develop and maintain an effective Quality Control Program (QCP) to ensure that services are performed in accordance with the terms of this Statement of Work (SOW), and in accordance with manufacturer’s guidance and procedures. The QCP is the means which the vendor assures all work complies with the terms of awarded contract. It identifies, prevents, and ensures non-occurrence of defective services.
7.0 NOTES
7.1. Tank Conent Restoration: The Coast Guard shall procure and refill all tanks at the conclusion of all work.
File details come from the government source that posted it. Updated .