This document is a product specification sheet outlining requirements for a mobile boat hoist system to be located at the US Coast Guard Industrial Production Facility in New Orleans, Louisiana. The specification calls for a 35-ton capacity hoist with a minimum 35-metric ton working load limit and independent strap control capable of synchronization. The hoist must have a minimum 22-foot inside clear height and 20-foot, 4-inch inside clear width to accommodate specific vessels. Additional requirements include all-wheel drive, LED lighting, overload alarms, corrosion resistant coatings, weighted sling pads, and a 2-year parts and labor warranty. The manufacturer must be based in the United States and arrange for a third-party inspection including load testing prior to acceptance. The related pre-solicitation opportunity is identified as solicitation number 70Z04024SSBPL0003 for the mobile boat hoist with bids due within 120 days of award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 45-RB-M-084-002 -Docking plan.pdf | ||
| ASME B30.2-2011.pdf | ||
| TS_583-4_Shore_Based_Boat_Hoisting_Systems.pdf | ||
| 47B-MLB-801-002 Docking Plan.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MOBLIE BOAT HOIST PRODUCT SPECIFICATION SHEET
The Government’s Requirement is for a Mobile Boat Hoist system, located at USCG Industrial Production Facility (IPF) New Orleans, LA.
USCG IPF New Orleans Specifications 35T Mobile Boast Hoist:
Hoist System: Each end of the hoisting strap (control) must be capable on moving independently.
Hoist System Travel speed: 2-speed (dual range) hoists
Wire rope: Must have a minimum rating of 110% of the Working Load Limit.
Must have a standard 5’ drop below grade.
Slings: Sling Spacing must be adjustable. Slings must provide Spacing and configuration for the 45-RBM- 084-002 and 47B-MLB-801-002.
(2) additional complete sling assemblies
Drive System: All Wheel Drive System (4 WD)
22’ Inside Clear Height (4’ over standard for pilot house/antenna clearance, 24’ OA height to clear 30’ doorway)
20’-4” Inside Clear Width (to suit 20’-1” pier width; Vendor to confirm on-site prior to production)
Shall have a maximum Hoist Length of 35’. No minimum length as long as it meets the sling spacing measurements identified above.
Hoist Weight: Not to exceed 600 lbs per sqft based on pier rating.
Working Load Limit: Minimum of 35 Metric Tons
Standard equipment: Vendor shall provide product sheet for hoist system they may choose to propose that can meet (or exceed) the standard equipment requirements identified here:
Wireless Remote control
Greaseable pivot trunnion with Zerk fittings
All greaseable sheaves/pins
Bolting flange in top beam
No sheet metal
O-ring face hydraulic fittings.
Minimum 2205 stainless steel Stainless steel hydraulic tubing
Inline hoist block sheaves
Powered sling adjustment
Independent hoisting strap control (capable of synchronization)
Load indicators
Use Corrosion resistant Coating System based on Federal, State, and Local environmental requirements.
Weighted Chine pads for each sling
Shall have a minimum (8) DC-LED both drive lights and work lights designed to provide safe nighttime operating capabilities.
Manufacturer shall provide USCG data plates and documents.
Overload alarm system installed in accordance with SFLC Technical Standard (TS) 583-4, which is included.
Manufacturer shall provide maintenance manual and (2) operating manuals, drawings, and a consumable parts list.
Manufacturer shall provide a minimum of a 2-year parts and labor warranty, from the date of final inspection and acceptance.
(1) year maintenance consumable filters
Manufacturer shall provide onsite maintenance training – Government expectation is for 2-3 days of training.
Manufacturer: Hoist must be manufactured in the United States
Manufacturer shall provide 3rd party inspection of final assembly prior to acceptance, which includes 3 Static and 3 Dynamic Weight Tests - Resistance load fixture that tests full machine is acceptable. Due to environmental restrictions, water MAY NOT be allowed to be drained on-site. A USCG representative must be present to witness the 3rd party inspection.
Hoist shall be built to comply with all federal, state, and local standards.
Manufacture shall provide technical data sheet with proposal.
Hoist must be delivered and installed within 120 days after award.
Manufacturer may request a pre-award site survey prior to proposal submission.
Manufacturer shall perform a site visit/evaluation following award to confirm on-site measurements prior to production.
Contractor is responsible for removing the old hoist and disposing of it properly in accordance with Federal, State and Local regulations. Current MBH Manufacturer: ACME, Model: H-50/4T
Coast Guard Facilities to provide a staging area sufficient for delivery and installation of the hoist.