About this file
This document is a Request for Information issued by the United States Agency for International Development Ukraine seeking information about potential suppliers of autotransformers to meet urgent needs in Ukraine. USAID requires single-phase autotransformers rated at 333 MVA and 750/400/330/220/15.75 kV, as well as three-phase autotransformers rated between 125-250 MVA and 330/220/150/110/35/20/10/6 kV. Interested parties must submit responses by August 15, 2023 detailing whether autotransformers are currently in stock and available for shipment, lead times for obtaining or manufacturing, and earliest potential delivery dates to Ukraine. USAID also requests technical specifications for available or manufacturable transformers. This RFI is open to all qualified firms within USAID's Geographic Code 935 and is not a solicitation, but aims to gather market research to potentially inform future procurements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| Issuance Date: | August 10, 2023 | |
| RFI Reponse Deadline: | August 15, 2023 at 17:00 EST |
SUBJECT: Urgent Request for Information (RFI): Need for Autotransformers in Ukraine.
Dear Interested Parties:
The United States Agency for International Development (USAID) urgently seeks information about potential suppliers of autotransformers per the below specifications (or technically equivalent and compatible with Ukraine’s energy infrastructure) that can be delivered to Ukraine earlier than February 28, 2024.
Frequency: 50 Hz Single-phase autotransformers Rated power, MVA: 333 Voltage, kV
HV: 750, 400
MV: 330, 220
LV: 15.75
Three-phase autotransformers Rated power, MVA: 125-250 Voltage, kV
HV: 330
MV: 220, 150, 110
LV: 35, 20, 10, 6
Interested parties should submit their responses electronically to Mr. Michael Capobianco at mcapobianco@usaid.gov and kyivrcoeg@usaid.gov no later than the date above using the attached ATTACHMENT A
As per Attachment A, USAID is especially interested in 1) whether the autotransformers are currently in stock and available for shipment 2) if not in stock, the lead time in days to obtain and/or manufacture 3) the date by which autotransformers could be delivered to Ukraine 4) any technical specification available for potentially available or manufacturable autotransformers. USAID/Ukraine requires potential partners' responses to this RFI to be written in English.
You may receive an electronic confirmation acknowledging receipt of your response but will not receive individualized feedback. We may reach out to individual respondents for further clarifications.
This RFI is open to all qualified firms within USAID’s Geographic Code 935.
Per FAR 52.215-3, this is not a solicitation and should not be construed as a commitment by the U.S. Government to issue any solicitation or ultimately award based on this RFI or to pay for any cost incurred in the preparation and submission in responses to this RFI. Responding to this RFI will not give any advantage in a subsequent procurement. USAID is prohibited from procuring goods from prohibited sources in accordance with Agency policy.
Regards, /S/
Michael Capobianco Director Regional Contracting Office USAID/Ukraine
Attachment A - RFI RESPONSE FORM
| Description: |
| Response: |
Name of Organization
Nationality of the Organization
Address
Website
Point of Contact, including phone and email address
Relevant Skills, Resources, and Abilities
Number of autotransformers on stock and their technical specifications.
Earliest possible date for delivery of in-stock, technically compatible autotransformers
If manufacturing is necessary, timeline for production. Delineate by batch/number if necessary to permit fastest possible production
Earliest possible date for delivery of manufacturable, technically compatible autotransformers
How is your supply chain structured?