About this file

This document is an "Understanding and Expectations" document for the Birchland Park Refrigeration Project Contractor related to a state and local contract opportunity in Massachusetts. The document outlines the general requirements for the contractor, including the need to furnish all labor and materials, provide submittals such as schematic designs, obtain applicable permits after the contract is awarded, and perform the work in accordance with the contract documents and any municipal requirements. The project scope includes removing and disposing of the existing walk-in refrigerator and freezer enclosure, as well as all existing refrigeration/freezer equipment, and installing new equipment to specification and approved drawings. Permit fees will be waived by the town, and all bidders must attend a pre-bid onsite walk-through. The contractor will be solely responsible for all materials stored on the site.

The related state and local contract opportunity is for the "GRO40 Replacement Walk In Refrigerator & Freezer" project in Massachusetts. The document does not provide specific pricing terms, set-asides, incumbent information, funding requirements, or other salient details about the contract opportunity.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Understanding and Expectations Document for Birchland Park Refrigeration Project

Contractor

● General

○ The contractor to furnish all labor and materials required in accordance with the specifications.

Submittals

● General

○ A schematic design of the proposed work will also be required by manufacturer and/or contractor.

Permits

● General

○ General Requirements

■ The contractor shall perform the work in accordance with the Contract Documents, and any applicable municipal requirements.

○ Permits by Contractor

■ The contractor shall prepare permit applications and obtain applicable permits after the contract is awarded. Permit fees will be waived by the town. All required permits shall be obtained, including but not limited to the following: Building Permit, Electrical Permit

General

● Work Included

○ Remove and Dispose

■ Existing walk-in refrigerator and freezer enclosure

■ All existing refrigeration/freezer equipment including, but not limited to: evaporator coils, compressors, refrigeration piping and associated wiring back to disconnect

○ Install to specification and approved drawings

○ Miscellaneous

■ All installations to meet factory specifications and final walk through approval

■ Permit fees by East Longmeadow

■ All bidders must attend a pre-bid onsite walk through

■ All trash and debris must be removed and site left in workable condition

■ Electric service to disconnect by East Longmeadow

■ All refrigeration to be calibrated per specifications

Execution

● Examination

○ Field Conditions

■ Prior to commencing installation, examine parts of building structure, which will be included in construction

■ Report, in writing, conditions which would prevent proper execution or endanger permanency of the work to the owner

○ Corrective measures, when necessary, shall be determined and approved prior to commencing fabrication.

● Installation

○ Install work in accordance with Contract Documents and reviewed shop drawings

● Product delivery, Storage and Handling

○ Deliver materials in manufacturer’s original unopened and undamaged packages with label legible and intact.

○ Store materials in unopened packages in a manner to prevent damage from the environment and construction operations.

○ Handle in accordance with manufacturer’s instructions.

○ The contractor shall be solely responsible for all the materials stored on the site once delivered. Any materials left unsecured at the job site shall be solely at the contractors own risk.