UAS Information.pdf
PDF 158 KB Posted
- Solicitation number
- PE-66098-NONST-2024-000000011
- Issued by
- Fulton County, Georgia
About this file
This document appears to be an email containing information related to a state and local contract opportunity for Utility Relocation Services. The email is from Wesley Hertz, the TSPLOST Utility Field Coordinator for the City of Sandy Springs, Georgia, and provides estimated start dates and timelines for various telecommunication providers to complete their utility relocations.
The email indicates that the project involves relocations for several telecommunication providers, including GA Power, AGL, AT&T, Comcast, Crown Castle, Fiberlight, Verizon, Lumen, and Zayo. The estimated timelines for these providers to complete their work range from 30 days to 10 months, with most providers anticipated to start in mid-January. The email also notes that some providers' work is dependent on the completion of GA Power's relocation efforts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Tabulation 24_026.pdf | ||
| 24_026 TS192 Mount Vernon Highway Multi_Use P.pdf | ||
| Offerors List.pdf | ||
| Addendum 1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Stallings, Katelyn
From: Hertz, Wesley
Sent: Tuesday, November 21, 2023 8:28 AM
To: Stallings, Katelyn
Cc: Johnson, Allen; Campbell, Toni
Subject: Answer to UAS question TS 192
GA Power – unavailable – est start date is Mid January
AGL – 175 days for construc�on – est start mid January
AT&T -T – 10 months – est start date mid January
AT&T – D – unavailable
Comcast – 60 days – dependent on GA Power comple�on
Crown Castle – 120 days – dependent on GA power comple�on
Fiberlight – claims to be complete with reloca�ons
Verizon – claims no conflict
Lumen – Design not finalized. Shared conduit system with AT&T-T. Must wait un�l they are done to pull new fiber. Also must wait on GA Power to be complete. Est schedule is 60 days.
Zayo – 30 days and needs to coordinate with other joint trench telecoms- est start date is Mid January
Wesley Hertz TSPLOST Utility Field Coordinator M 4043870277 WHertz@SandySpringsGA.gov 1 Galambos Way, Sandy Springs, GA 30328, USA