UAS Information.pdf

PDF 158 KB Posted

Attached to
24-026 TS192 Mount Vernon Highway Multi-Use Path Intersection Project
Solicitation number
PE-66098-NONST-2024-000000011
Issued by
Fulton County, Georgia

About this file

This document appears to be an email containing information related to a state and local contract opportunity for Utility Relocation Services. The email is from Wesley Hertz, the TSPLOST Utility Field Coordinator for the City of Sandy Springs, Georgia, and provides estimated start dates and timelines for various telecommunication providers to complete their utility relocations.

The email indicates that the project involves relocations for several telecommunication providers, including GA Power, AGL, AT&T, Comcast, Crown Castle, Fiberlight, Verizon, Lumen, and Zayo. The estimated timelines for these providers to complete their work range from 30 days to 10 months, with most providers anticipated to start in mid-January. The email also notes that some providers' work is dependent on the completion of GA Power's relocation efforts.

View the file

Other files

File Type Posted
Bid Tabulation 24_026.pdf PDF
24_026 TS192 Mount Vernon Highway Multi_Use P.pdf PDF
Offerors List.pdf PDF
Addendum 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Stallings, Katelyn

From: Hertz, Wesley

Sent: Tuesday, November 21, 2023 8:28 AM

To: Stallings, Katelyn

Cc: Johnson, Allen; Campbell, Toni

Subject: Answer to UAS question TS 192

GA Power – unavailable – est start date is Mid January

AGL – 175 days for construc�on – est start mid January

AT&T -T – 10 months – est start date mid January

AT&T – D – unavailable

Comcast – 60 days – dependent on GA Power comple�on

Crown Castle – 120 days – dependent on GA power comple�on

Fiberlight – claims to be complete with reloca�ons

Verizon – claims no conflict

Lumen – Design not finalized. Shared conduit system with AT&T-T. Must wait un�l they are done to pull new fiber. Also must wait on GA Power to be complete. Est schedule is 60 days.

Zayo – 30 days and needs to coordinate with other joint trench telecoms- est start date is Mid January

Wesley Hertz TSPLOST Utility Field Coordinator M 4043870277 WHertz@SandySpringsGA.gov 1 Galambos Way, Sandy Springs, GA 30328, USA