Type_II_Slurry_Seal_Package_Bid_Analisys_Comparison.xlsx

XLSX spreadsheet 27 KB Posted

Attached to
BID# 2023-42 Type II Slurry Seal Package
Solicitation number
S-C01010-00006686
Issued by
Clackamas County, Oregon

About this file

This document appears to be a bid analysis and comparison for a Type II Slurry Seal Package contract opportunity issued by Clackamas County and Oregon City in Oregon. The contract includes three separate worksites - Happy Valley, Damascus, and Overland Park - with a total of approximately 236,000 square yards of slurry seal work. The bid items include mobilization, pollution control, removal of pavement markings, and the slurry seal work itself. Bids were received from four contractors, with the low bid totaling $667,104.51 and the average of all bids coming in at $705,700.39.

The bid tabulations provide detailed pricing for each bid item at each worksite, allowing for comparison between the engineer's estimate and the submitted bids. Key details include unit prices ranging from $2.40 to $2.65 per square yard for the slurry seal work, with mobilization costs ranging from $10,000 to $25,874. There does not appear to be any mention of set-asides, incumbents, or specific funding sources, but the contract opportunity is identified as BID# 2023-42 for the Type II Slurry Seal Package.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Compare to Estimate Type II Slurry Seal Package Estimate Verse Low Bid

Engineer's EstimateBlackline Inc.Comparison (total price)Average of the Bids
West Clackamas Paving Project
Bid ItemUnitQuantityUnit PriceTotal PriceUnit PriceTotal PriceMaximumMinimumAverage Unit PriceAverage Total
1EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
2MOBILIZATIONLS1$ 16,000.00$ 16,000.00$ 10,000.00$ 10,000.00$ 16,000.00$ 10,000.00$ 17,435.52$ 17,435.52
3POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,450.00$ 1,450.00
4REMOVAL OF PAVEMENT MARKINGSLS1$ 5,000.00$ 5,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 5,000.00$ 11,134.50$ 11,134.50
5TYPE II SLURRY SEALSY65,433$ 2.50$ 163,582.50$ 2.43$ 159,002.19$ 163,582.50$ 159,002.19$ 2.52$ 164,891.16
WORKSITE #1 - HAPPY VALLEY PROJECT TOTAL$ 190,582.50$ 190,002.19$ 190,582.50$ 190,002.19$ - 0$ 199,911.18
1EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
2MOBILIZATIONLS1$ 21,000.00$ 21,000.00$ 10,000.00$ 10,000.00$ 21,000.00$ 10,000.00$ 18,902.32$ 18,902.32
3POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,450.00$ 1,450.00
4REMOVAL OF PAVEMENT MARKINGSLS1$ 7,000.00$ 7,000.00$ 15,000.00$ 15,000.00$ 15,000.00$ 7,000.00$ 9,645.25$ 9,645.25
5TYPE II SLURRY SEALSY84,973$ 2.50$ 212,432.50$ 2.43$ 206,484.39$ 212,432.50$ 206,484.39$ 2.52$ 214,131.96
WORKSITE #2 - DAMASCUS PROJECT TOTAL$ 246,432.50$ 237,484.39$ 246,432.50$ 237,484.39$ - 0$ 249,129.53
1EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
2MOBILIZATIONLS1$ 19,000.00$ 19,000.00$ 10,000.00$ 10,000.00$ 19,000.00$ 10,000.00$ 19,371.41$ 19,371.41
3POLLUTION CONTROL PLANLS1$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,000.00$ 1,450.00$ 1,450.00
4REMOVAL OF PAVEMENT MARKINGSLS1$ 5,500.00$ 5,500.00$ 15,000.00$ 15,000.00$ 15,000.00$ 5,500.00$ 14,493.75$ 14,493.75
5TYPE II SLURRY SEALSY85,851$ 2.50$ 214,627.50$ 2.43$ 208,617.93$ 214,627.50$ 208,617.93$ 2.52$ 216,344.52
WORKSITE #3 - OVERLAND PARK PROJECT TOTAL$ 245,127.50$ 239,617.93$ 245,127.50$ 239,617.93$ - 0$ - 0
WORKSITE #1 - HAPPY VALLEY PROJECT TOTAL$ 190,582.50$ 190,002.19$ 190,582.50$ 190,002.19$ - 0
WORKSITE #2 - DAMASCUS PROJECT TOTAL$ 246,432.50$ 237,484.39$ 246,432.50$ 237,484.39$ 199,911.18
WORKSITE #3 - OVERLAND PARK PROJECT TOTAL$ 245,127.50$ 239,617.93$ 245,127.50$ 239,617.93$ 249,129.53
TYPE II SLURRY SEAL PACKAGE TOTAL$ 682,142.50Total$ 667,104.51Average Total$ 705,700.39

Bid Tabs

Type II Slurry Seal Package Bid Tabulations
Doolittle Construction, LLCBlackline, Inc.One Way Trigger, LLCVSS, International, Inc.Low/High AnalysisAverage of the Bids
Bid ItemUnitQuantityUnit PriceTotalUnit PriceTotalUnit PriceTotalUnit PriceTotalLow UPHigh UPAverage Unit PriceAverage Total
1EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
2MOBILIZATIONLS1$ 18,000.00$ 18,000.00$ 10,000.00$ 10,000.00$ 18,750.00$ 18,750.00$ 22,992.08$ 22,992.08$ 10,000.00$ 22,992.08$ 17,435.52$ 17,435.52
3POLLUTION CONTROL PLANLS1$ 1,200.00$ 1,200.00$ 1,000.00$ 1,000.00$ 600.00$ 600.00$ 3,000.00$ 3,000.00$ 600.00$ 3,000.00$ 1,450.00$ 1,450.00
4REMOVAL OF PAVEMENT MARKINGSLS1$ 10,000.00$ 10,000.00$ 15,000.00$ 15,000.00$ 10,250.00$ 10,250.00$ 9,288.00$ 9,288.00$ 9,288.00$ 15,000.00$ 11,134.50$ 11,134.50
5TYPE II SLURRY SEALSY65433$ 2.40$ 157,039.20$ 2.43$ 159,002.19$ 2.65$ 173,397.45$ 2.60$ 170,125.80$ 2.40$ 2.65$ 2.52$ 164,891.16
WORKSITE #1 - HAPPY VALLEY PROJECT TOTAL$ 191,239.20$ 190,002.19$ 207,997.45$ 210,405.88$ 199,911.18
1EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
2MOBILIZATIONLS1$ 24,000.00$ 24,000.00$ 10,000.00$ 10,000.00$ 18,750.00$ 18,750.00$ 22,859.28$ 22,859.28$ 10,000.00$ 24,000.00$ 18,902.32$ 18,902.32
3POLLUTION CONTROL PLANLS1$ 1,200.00$ 1,200.00$ 1,000.00$ 1,000.00$ 600.00$ 600.00$ 3,000.00$ 3,000.00$ 600.00$ 3,000.00$ 1,450.00$ 1,450.00
4REMOVAL OF PAVEMENT MARKINGSLS1$ 8,000.00$ 8,000.00$ 15,000.00$ 15,000.00$ 8,075.00$ 8,075.00$ 7,506.00$ 7,506.00$ 7,506.00$ 15,000.00$ 9,645.25$ 9,645.25
5TYPE II SLURRY SEALSY84973$ 2.40$ 203,935.20$ 2.43$ 206,484.39$ 2.65$ 225,178.45$ 2.60$ 220,929.80$ 2.40$ 2.65$ 2.52$ 214,131.96
WORKSITE #2 - DAMASCUS PROJECT TOTAL$ 242,135.20$ 237,484.39$ 257,603.45$ 259,295.08$ 249,129.53
1EXTRA WORK DONE ON FORCE ACCOUNT BASISFA1$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00$ 5,000.00
2MOBILIZATIONLS1$ 25,874.20$ 25,874.20$ 10,000.00$ 10,000.00$ 18,750.00$ 18,750.00$ 22,861.44$ 22,861.44$ 10,000.00$ 25,874.20$ 19,371.41$ 19,371.41
3POLLUTION CONTROL PLANLS1$ 1,200.00$ 1,200.00$ 1,000.00$ 1,000.00$ 600.00$ 600.00$ 3,000.00$ 3,000.00$ 600.00$ 3,000.00$ 1,450.00$ 1,450.00
4REMOVAL OF PAVEMENT MARKINGSLS1$ 13,000.00$ 13,000.00$ 15,000.00$ 15,000.00$ 12,425.00$ 12,425.00$ 17,550.00$ 17,550.00$ 12,425.00$ 17,550.00$ 14,493.75$ 14,493.75
5TYPE II SLURRY SEALSY85851$ 2.40$ 206,042.40$ 2.43$ 208,617.93$ 2.65$ 227,505.15$ 2.60$ 223,212.60$ 2.40$ 2.65$ 2.52$ 216,344.52
WORKSITE #3 - OVERLAND PARK PROJECT TOTAL$ 251,116.60$ 239,617.93$ 264,280.15$ 271,624.04$ 256,659.68
WORKSITE #1 - HAPPY VALLEY PROJECT TOTAL$ 191,239.20$ 190,002.19$ 207,997.45$ 210,405.88$ 199,911.18
WORKSITE #2 - DAMASCUS PROJECT TOTAL$ 242,135.20$ 237,484.39$ 257,603.45$ 259,295.08$ 249,129.53
WORKSITE #3 - OVERLAND PARK PROJECT TOTAL$ 251,116.60$ 239,617.93$ 264,280.15$ 271,624.04$ 256,659.68
TYPE II SLURRY SEAL PACKAGE TOTAL$ 684,491.00Total$ 667,104.51Total$ 729,881.05Total$ 741,325.00Average$ 705,700.39

Reported as $691,691.00 in bid Reported as $729,889.00 in bid.

File details come from the government source that posted it. Updated .