This document is an order of procedures for the replacement of two concrete pontoons (floats) at the Massachusetts Maritime Academy (MMA) pier located in Buzzards Bay, Massachusetts. The scope of work includes disconnecting and removing the existing floats, relocating an existing float, installing two new floats, and reconnecting the electrical and water utilities. The work must be performed in accordance with MGL c.149 and 801 CMR 21.00. The contract opportunity is for the installation of the two replacement concrete pontoons. The jurisdiction is Barnstable County in the state of Massachusetts.
The document provides detailed steps for completing the float replacement project, including the order of activities such as withdrawing electrical and water cables, disconnecting and removing the existing floats, relocating an existing float, installing the two new floats, and reconnecting the utilities. Specific installation requirements for the new floats are outlined, including the use of existing pile guides and the installation of new pile guides. MMA representatives will determine the location of the piles for the new floats.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFR 2021-14 Addenda 1 Questions and Responses~1.pdf | ||
| Prevailing Wage Sheet 20210318-066.pdf | ||
| Signature authorization Form.pdf | ||
| FAMMACD0002P4 20210218.pdf | ||
| TAX COMPLIANCE CERTIFICATION.pdf | ||
| attachment A - Prevailing Wage Rates 012621~2.pdf | ||
| 2021_14_Two Float Replacement SOW 031721.docx | DOCX document | |
| FORM OF GENERAL BID~1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
March 1, 2021Title
Note:
1. Withdraw electrical and water cable from MM3 and MM4 back to MM8‐1
MASSACHUSETTS MARITIME ACADEMY FLOATS (2) REPLACEMENTMASSACHUSETTS MARITIME ACADEMY FLOATS (2) REPLACEMENT
Note:
1. Disconnect chains and remove the two existing floats: F‐1 and F‐2 Floats.
‐ floats are to be hauled off campus for demolition or to recycler
MASSACHUSETTS MARITIME ACADEMY FLOATS (2) REPLACEMENT
Notes:
Note:
1. Disconnect and remove gangway, including gangway guide
2. Remove two (2) pile guides from F‐3 Float
3. Remove extra buoyancy foam cubes from under the float (or alternate add weights to the other end to counter and trim the float)
5. Relocate F‐3 Float as shown
6. Install new two (2) pile guides to F‐3 Float. Installation requires drilling into the side wall and deck of the float with deep core drill.
7. Secure to pile guides to the piles. Location of the two piles shall determine by MMA representative.
Note:
1. Install new MM‐5 and MM‐6 Floats as shown
2. Use the two (2) unbolted F‐3's pile guides and bolted to MM‐5
3. Secure the two pile guides to the two pilings
4. Install the gangway guide to MM‐5 Float
5. Reconnect gangway from dolphin to MM‐5 Float
6. Install new MM‐6 Float as shown
7. Install the two (2) supplied pile guides to MM‐6 Float
8. Secure the two bolted pile guides to the two piles (TBD by MMA).
Note:
1. Rerun power and potable water service from MM8‐1 to MM‐6 utilities pedestal
(MMA).