This document is a Performance Work Statement (PWS) for the relocation of two United States Coast Guard (USCG) National Security Cutters, the USCGC STONE and USCGC JAMES, to support dredging operations at Pier Papa, USCG Base Charleston, South Carolina. The PWS outlines a five-phase approach, including preparation, logistics and coordination, safety and compliance, communication and reporting, and post-relocation activities. The contractor shall provide tug services and coordination to execute four berthing shifts for the vessels between August 29, 2024 and September 17, 2024. Due to maintenance issues, the STONE will require a minimum of two tugboats, and the JAMES may require a third tug for safe maneuvering during "dead stick" operations. The contractor must adhere to USCG safety regulations and provide a final report detailing the completion of the berthing shifts.
The related federal contract opportunity is a solicitation for Tugboat Services for Dredging at USCGC Base Charleston. The Government intends to award a contract to the responsible offeror submitting the lowest price proposal that is most advantageous. The solicitation closes on August 26, 2024 at 11:00 AM Eastern Standard Time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFQ SF-1449 Tug RFQ.pdf | ||
| Tug Dredging SOW.pdf | ||
| RFQ SF-1449 Tug RFQ.pdf | ||
| Wage_Determination.txt | TXT text file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNITED STATES COAST GUARD CUTTERS PIER SLIP MOVEMENT FOR DREDGING OPERATIONS
PERFORMANCE WORK STATEMENT
1.0 GENERAL.
1.1 SCOPE.
The purpose of this Performance Work Statement (PWS) is for the relocation of two United States Coast
Guard National Security Cutters (WMSLs), specifically the USCGC STONE and USCGC JAMES, to support dredging operations at Pier Papa, Cooper River, USCG Base Charleston (1050 Register St. North
Charleston, SC 29405). The berthing shifts involve multiple movements of these vessels between designated berths and will require two tugboats at minimum, considering STONE’s steering system will be down for maintenance during its scheduled moves and JAMES’ propulsion system will be down for maintenance during its scheduled moves, necessitating potential dead stick operations.
1.2 BACKGROUND.
To facilitate necessary dredging operations at Pier Papa, it is required to relocate the STONE and JAMES to alternate berthing locations within Pier Papa Charleston, SC. STONE will not have steering for either of their berth shifts/moves and JAMES will be unable to utilize its propulsion system for either of their berth shifts, due to maintenance, possibly requiring an additional third tug for safe maneuvering.
1.2.1 The process is comprised of a five-phase approach.
1.2.1.1 Phase 1: Preparation- The result of this phase is to conduct an initial assessment of the current berthing situation and the new berthing location. To develop a detailed relocation plan outlining the steps involved, including timelines, resources required, and safety measures. Obtain all necessary permits and approvals for the relocation process. Address assumptions, operational conditions, complexity, timeline, points of contact, deliverables, and funding issues.
1.2.1.2 Phase 2: Logistics and Coordination- The result of this phase is to organize with the United States
Coast Guard personnel for the scheduling of the relocation. Arrange for the necessary tugboats, pilots, and any other equipment required for the safe transfer of the cutters. Ensure that all logistical arrangements are in place to facilitate a smooth relocation process. This is found using all relevant documentation, site visits, personal interviews, and data analysis and reporting (adjudication).
1.2.1.3 Phase 3: Safety and Compliance- The result of this phase is an implement safety protocols to ensure the protection of personnel and vessels during the relocation. Adhere to all relevant regulations and guidelines set forth by the United States Coast Guard and other governing bodies. Conduct safety briefings for all personnel involved in the relocation process.
1.2.1.4 Phase 4: Communication and Reporting: The result of this phase is to maintain regular communication with all stakeholders throughout the relocation process. Provide progress reports and updates on the status of the relocation to the project sponsors and stakeholders. Document all activities and incidents during the relocation for future reference.
1.2.1.5 Phase 5: Post-Relocation Phase: This result is to conduct a final inspection of the vessels to ensure that they are securely berthed at the new location. Address any outstanding issues or concerns related to the relocation process. Provide a comprehensive report detailing the successful completion of the relocation project.
1.3 PERSONNEL
1.3.1 Project Manager
USCG shall provide a Team Leader who shall be responsible for all work performed under this PWS.
During any absence of the Team Leader, one team member shall have full authority to act on all matters relating to work performed under this PWS.
Project Manager: Anthony Boyd, Logistics Branch Chief
1.3.2 Qualified Personnel
Contractor shall provide qualified personnel to perform all requirements specified in this POW.
1.3.3 Logistics Team:
Contracting Officer: Shannon Bistline, GS12
Contracting Specialist: Julia Kline, GS9
1.3.4 Port Operation Manager
Base Operations / Port Services Officer: Duane “Doug” Wood, LCDR
1.4 SECURITY.
Prior to performance and if access to USCG Base Charleston is required all contracting personnel must give
24-hour notice and have proper personal identification.
2.0 PERFORMANCE
The contractor shall provide all necessary tug services and coordination to execute the following berthing shifts:
• STONE shifting from berth S2 to berth N3 on August 29th, 2024. (Propulsion available; no steering)
• JAMES shifting from berth N2 to berth S1 on September 9th, 2024. (No propulsion; dead stick operation likely, third tug possibly required)
• STONE shifting from berth N3 to berth S2 on September 9th, 2024. (Propulsion available; no steering)
• JAMES shifting from berth S1 to berth N3 on September 17th, 2024. (No propulsion; dead stick operation likely, third tug possibly required)
These shifts will require precise coordination and execution, particularly for the JAMES, which will need to be maneuvered from a port side to a starboard side position at both S1 and N3 (see figure 1 for Pier Slips).
Figure 1:
2.1 PLACE OF PERFORMANCE
The movements will be performed at Pier Papa, Cooper River, USCG Base Charleston (1050 Register ST.
North Charleston, SC 29401) or as specified in the travel section.
2.2 PERIOD OF PERFORMANCE.
Contractor must be available with 48-hour notice between August 29th, 2024 - September 17th, 2024
2.3 TECHNICAL REQUIREMENTS
2.3.1 Vessel Characteristics
Length: 418 ft
Beam: 54 ft
Height: 147 ft
Draft: 22.5 ft
Displacement: 4500 long tons
2.3.2 Tug Requirements
All tugs shall be properly reinforced and fendered to support the berthing shift of a National Security
Cutter/WMSL. Due to the STONE’s steering system will be down for maintenance during its scheduled moves and JAMES’ propulsion system will be down for maintenance during its scheduled moves, a third tug may be required to ensure safe maneuvering during dead stick operations.
3.0 SCHEDULE AND COORDINATION
The contractor shall adhere to the tentative berthing shift schedule outlined in Section 2.0. This schedule is for planning purposes only and may be subject to change. 24 hours prior to each scheduled berthing shift, Base Charleston Port Operations will contact the tug service to confirm the schedule and relay any changes or additional information relevant to the shift.
3.1 Site Visit:
Site visit is optional and can be conducted Monday – Friday between the hours of 8:00 AM to 3:00 PM.
Request must be coordinated 24 hours before desired time due to Base access authorization. Proper vehicle registration and driver identification is required to access facilities. Contact point of contact to schedule site visit.
POC:
Anthony Boyd anthony.e.boyd@uscg.mil
(843) 740-3052
4.0 SAFETY REQUIREMENTS
All operations must be conducted in strict compliance with USCG safety regulations and protocols. Safety briefings shall be conducted for all personnel involved in the berthing shifts to ensure full awareness of procedures and potential hazards.
5.0 DELIVERABLES
The contractor shall provide a final report detailing the completion of each berthing shift outlined in Section
2.0, including any incidents or deviations.
6.0 ACCEPTANCE CRITERIA.
Full compliance with all safety and technical requirements as detailed in this SOW. Successful relocation of
USCGC STONE and USCGC JAMES to their designated berths without incident.
mailto:anthony.e.boyd@uscg.mil