This is an addendum to a tree removal and stumping services request for proposals issued by the Town of Killingly, Connecticut for work at 226 Putnam Pike. The addendum addresses three critical questions submitted by prospective bidders regarding prevailing wage requirements, environmental protections for northern long-eared bats, and protected plants or vegetation in the project area. The project encompasses approximately 1.70 acres along an emergency access road requiring tree and brush clearing and removal services. A mandatory site walk was scheduled for June 17, 2026 at 9:00 a.m., with questions due by June 25, 2026 at 2:00 p.m. and proposals due July 14, 2026 at 2:00 p.m. Contractors must submit bids on three line items: a base bid for tree and brush clearing and disposal, Alternate #1 for stump removal and disposal, and Alternate #2 for stump removal and stockpiling. Work must commence within 15 days of contract execution and complete within 45 calendar days of notice to proceed, with liquidated damages of $100 per calendar day assessed for completion beyond 60 calendar days.

The Town clarified that the project is expected to fall below the prevailing wage threshold; however, if the bid exceeds $100,000, prevailing wage rates will apply and contractors should include that amount in their bids. The project area falls outside the mapped Natural Diversity Data Base area, indicating no concerns regarding northern long-eared bat habitat or protected plants requiring additional environmental permits. The Town of Killingly is obtaining the required wetland permits for the project. Contractors must demonstrate a minimum of five years of experience completing similar projects and must provide a 5 percent surety bid bond and 100 percent labor, materials, and performance bonds. Required insurance includes commercial general liability of $1 million per occurrence, automobile liability of $1 million, workers' compensation with $500,000 employer's liability, excess liability of $5 million, and pollution liability of $2 million. The Town waives permit fees and reserves the right to reject any or all bids.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Enginnering1/Projects/High School/Emergency Access/Addendum/Addendum 04

June 25, 2026

TOWN OF KILLINGLY

Tree Removal and Stumping Services

226 Putnam Pike

ADDENDUM NO. 3

Questions:

1. Is this project going to be bid under CT prevail wage rates and will Pre Vailing wage rates for this district be supplied?

2. Does this area fall into the northern long-eared bat habitat area and has a study been conducted to confirm we are clear to remove the trees and bats are not present?

3. Are there any protected plants or vegatation in this area to be concerned about that may need additional permitting by Enviromental?

Answers:

1. The project is expected to fall below the amount for prevailing wage rates. In the event the Bid is over $100,000 prevailing wage rates will apply, and the contractor should carry that amount in his bid.

2. The project area falls outside of the mapped Natural Diversity Data Base area.

3. The project area falls outside of the mapped Natural Diversity Data Base area.

AddiƟonally, the Town of Killingly is obtaining the required wetland permits for the project.

Addendum No.3 is available on the Town of Killingly Website https://www.killingly.org/finance/pages/bids-and-rfps and the CTSource Website https://portal.ct.gov/DAS/CTSource/Login