2024.02.15_GTP_GOPAX Industry QA.docx

DOCX document 14 KB Posted

Attached to
Global Transportation Planning (GTP) and Groups Operational Passenger (GOPAX) Systems Operations and Sustainment
Solicitation number
TRANSCOM23D017
Issued by

About this file

This document provides details for the Global Transportation Planning (GTP) and Groups Operational Passenger (GOPAX) Systems Operations and Sustainment federal contract opportunity. The anticipated acquisition strategy is currently being developed for a contract with a period of performance from 1 October 2024 through 30 September 2029 and a one-month transition beginning 1 September 2024. The solicitation is anticipated to be released in January 2024 with quotations/proposals due in February 2024. Source selection activities including evaluations and exchanges will take place from February through June 2024, with contract award on 25 July 2024 and contract start on 1 October 2024. Functional, engineering, and technical support is required for the design, development, modification, and integration of capabilities to support the reengineering and sustainment of business process management development activities for discrete and capacity-based deployment and distribution processes.

View the file

Other files

File Type Posted
2024.06.04_GTP_GOPAX Industry QA.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Industry Q&A

Special Notice: TRANSCOM23D017

Q: Will government provide PEO-T Agile Scrum Framework Guide?

A: Yes; however, more useful resources would be the Scrum.org Scrum guide in the resources section and what has been identified in the PWS.

Q: What COTS products are currently in use for GTP/GOPAX?

A: COTS products anticipated to be used and some currently being used, were listed in the PWS (page 13) and sent out with the RFI. These will be updated and sent out again with the PWS in the RFP. The COTS in and for the Cloud support seem to be evolving as we go forward.

Q: How many latent defects were found during last period of performance?

A: Four (4) latent defects were found during the last period of performance.

Q: Will the government provide historical workload data for each task area?

A: Historical workload data is not guaranteed, but if any data pertaining to the current acquisition is found relavent, it will be posted along with the solicitation.

Please direct any questions to Darrah Hill, darrah.m.hill.civ@mail.mil and Jonathan Severin, jonathan.a.severin.civ@mail.mil.

File details come from the government source that posted it. Updated .