Traffic Signal Modifications - Clark Avenue and Cedar Street.pdf
PDF 94 KB Posted
- Attached to
- Subcontractor Opportunities* Traffic Signal Modifications - Clark Avenue and Cedar Street
- Solicitation number
- 51610
- Issued by
- Los Angeles County, California
About this file
This is a Notice Inviting Sealed Bids issued by the City of Bellflower, California for a public works capital improvement project involving traffic signal modifications at the intersection of Clark Avenue and Cedar Street. The project requires all necessary equipment, materials, transportation, and labor as detailed in the plans maintained by the City's Public Works Department. Sealed bids must be submitted to the City Clerk's office at 16600 Civic Center Drive, Bellflower, CA 90706, by 11:00 a.m. on Wednesday, September 23, 2026, at which time bids will be publicly opened. A mandatory jobsite walk is scheduled for Tuesday, September 8, 2026, at 10:00 a.m. at 9944 Flora Vista Street, Bellflower, CA 90706, and attendance is required for prime contractors wishing to submit bids. Following issuance of the Notice to Proceed, the contractor shall have sixty (60) working days to complete the work in strict conformity with Specification No. 52604. Prospective bidders may obtain specification copies at no cost from the Public Works Department by contacting Kimberly Gonzalez at (562) 804-1424, ext. 2285 or kgonzalez@bellflower.ca.gov.
The Engineer's Estimate of cost is $57,000. Bidders must submit a certified or cashier's check, bidder's bond, or cash deposit equal to ten percent (10%) of the bid price, with the successful bidder's deposit subject to forfeiture if the contract is not executed within ten days of award notification. Contractors must hold a valid Class A or C-10 Contractor's License in accordance with California Business and Professions Code Chapter 9, Division III. The project is subject to California prevailing wage requirements for Los Angeles County, with the contractor required to post wage schedules at the jobsite. Five percent (5%) of each progress payment will be retained by the City, with contractors able to substitute securities or request escrow placement of retention monies at their own expense. The project is subject to compliance monitoring and enforcement by the California Department of Industrial Relations, and all bids must comply with applicable Labor Code requirements including sections 1725.5 and 1771.4.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTICE INVITING SEALED BIDS
FOR THE TRAFFIC SIGNAL MODIFICATIONS - CLARK AVENUE AND CEDAR
STREET
IN THE CITY OF BELLFLOWER
CAPITAL IMPROVEMENT PROJECT NO. 51610
The City of Bellflower is accepting sealed bids in the City Clerk’s office, 16600 Civic Center Drive, Bellflower, CA 90706, until 11:00 a.m. on:
WEDNESDAY, SEPTEMBER 23, 2026
at which time they will be publicly opened. Bids will not be accepted after that time. Each bid must be accompanied by a certified or cashier’s check or bidder’s bond payable to the order of the City of Bellflower or cash for an amount not less than ten percent (10%) of the bid price submitted, and the check, bond, or cash deposit of the successful bidder shall be forfeited to the City if such bidder fails to enter into the contract to perform the work within ten (10) days after written notice of award.
As described in the Bidding Documents, the bids are for a public works project (“Project”) which consists of Traffic Signal Modification – Clark Avenue and Cedar Street and related work, including providing all necessary equipment, materials, transportation and labor for the project as shown on the plans on file with the City’s Public Works Department. The Engineer’s Estimate of cost is $57,000. Bids will be publicly opened on Wednesday, September 23, 2026 at 11:00 AM.
The contractor shall possess a Class A or C-10 Contractor’s License. No bid will be accepted from a contractor who has not been licensed in accordance with the Provisions of Chapter 9, Division III, of the Business and Professions Code of the State of California at the time the bid is submitted.
Following the issuance of the Notice to Proceed, the contractor shall have sixty (60) working days to complete the work.
Work on the Project must be performed in strict conformity with Specification No. 52604, which is filed with the City’s Public Works Department. Copies of these specifications may be obtained by prospective bidders from the Public Works Department at no cost by contacting Kimberly Gonzalez at (562) 804-1424, ext. 2285 or via email at kgonzalez@bellflower.ca.gov
A mandatory jobsite walk will be held on Tuesday, September 8, 2026, at 10:00 AM, at 9944 Flora Vista St., Bellflower, CA 90706. Prospective bidders will have opportunity to examine the project site and are encouraged to raise any questions associated with the project and site. Attendance of the jobsite walk is mandatory for parties wishing to submit a bid as the Prime Contractor.
The terms and conditions for bidding on the Project are described in the attached Bidding Instructions.
N-2
This project requires payment of State prevailing rates of wages for Los Angeles County.
The contractor must post copies of the prevailing schedule at each job site. Copies of these rates of wages are available from the State of California Department of Industrial Relations Prevailing Wage Unit, Telephone No. (415) 703-4774. The website for this agency is currently located at www.dir.ca.gov.
Note that the Project is subject to compliance monitoring and enforcement by the California Department of Industrial Relations. Pursuant to California law, the City must find bids failing to comply with all applicable Labor Code requirements including, without limitation, Labor Code §§ 1725.5 and 1771.4, to be nonresponsive.
Five percent (5%) will be deducted from each progress payment and retained by the City.
The remainder less the amount of all previous payments will be paid to the Contractor.
Pursuant to Public Contracts Code (“PCC”) § 22300, the Contractor may substitute securities for retention monies held by the City or request that the City place such monies into an escrow account. The Contractor is notified, pursuant to PCC § 22300, any such election will be at the Contractor own expense and will include costs incurred by the City to accommodate the Contractor’s request.
DATED this 28th day of August 2026.
CITY OF BELLFLOWER, CALIFORNIA
http://www.dir.ca.gov/
File details come from the government source that posted it. Updated .