TO 008 SOW.docx

DOCX document 42 KB Posted

Attached to
EDG Fuel System Upgrades
Solicitation number
N6449823R4036
Issued by

About this file

This statement of work outlines requirements for upgrading the fuel injection systems on six submarine emergency diesel generators at the Trident Refit Facility in Bangor, Washington. The Naval Surface Warfare Center Philadelphia Division will award a firm-fixed price contract to remove existing fuel injection components, convert pumps to a gasketless configuration and calibrate them, install new components, and conduct operational retesting for each generator. The contractor must develop a project plan and technical work document, conduct a condition found analysis if needed, and submit status and technical reports. Upgrades are to occur during specified maintenance periods from October 2023 through July 2024. The contractor shall provide all labor, materials, and equipment to complete the upgrades at the Trident Refit Facility and their own facilities.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) Trident Refit Facility Bangor Diesel Engine Fuel System Upgrade

INTRODUCTION

1.0.1 The Naval Surface Warfare Center - Philadelphia Division (NSWCPD) is the Department of Defense entity responsible for research and development, test and evaluation, engineering and fleet support organization for the Navy’s ships, submarines, military watercraft and unmanned vehicles. This requirement is for NSWCPD Code 422 Diesel Engine Branch, which is responsible for diesel engines within the U.S. Navy Fleet, including the SSBN/GN 726 and SSN 688 ship classes.

1.0.2 This contract is for non-personal services. It does not create employment rights with the U.S. Government whether actual, inherent, or implied. By agreeing to perform the services described in these specifications, the Contractor acknowledges that he/she is not, and shall not become, an employee of the U.S. Government. The Contractor further agrees that he/she shall not bring any cause of action in any forum claiming that he/she has become an employee of the U.S. Government.

1.0.3 The Contractor shall, pursuant to the Government’s right and obligation to inspect, accept, or reject the work, comply with such general direction of the Contracting Officer, or the duly authorized representative of the Contracting Officer as is necessary to ensure accomplishment of the contract objectives.

1.0.4 Government / Contractor Relationship

The services to be delivered under this Task Order are non-personal services and the parties recognize and agree that no employer-employee relationship exists or will exist under the Task Order between the Government and the Contractor's personnel. Therefore, it is in the best interest of the Government to provide both parties a full understanding of their respective obligations.

The Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishable badges or other visible identification for meetings with Government personnel. In addition, Contractor personnel shall appropriately identify themselves as Contractor employees in telephone conversations and in formal and informal written correspondence

Contractor personnel under this Task Order shall not engage in any of the inherently Governmental functions listed at FAR Subpart 7.5 or DFARS Subpart 207.5.

Employee Relationship:

The services to be performed under this Task Order do not require the Contractor or its personnel to exercise personal judgment and discretion on behalf of the Government. Rather the Contractor's personnel will act and exercise personal judgment and discretion on behalf of the Contractor.

Rules, regulations, directives, and requirements that are issued by the U. S. Navy and NSWCPD under its responsibility for good order, administration, and security are applicable to all personnel who enter a Government installation or who travel on Government transportation. This is not to be construed or interpreted to establish any degree of Government control that is inconsistent with a non-personal services contract.

Inapplicability of Employee Benefits: This Task Order does not create an employer-employee relationship. Accordingly, entitlements and benefits applicable to such relationships do not apply.

Notice: It is the Contractor's, as well as the Government's, responsibility to monitor Task Order activities and notify the Contracting Officer if the Contractor believes that the intent of this Section has been or may be violated.

The Contractor shall notify the Contracting Officer in writing via letter or email within three (3) calendar days from the date of any incident that the Contractor considers to constitute a violation of this Section. The notice should include the date, nature, and circumstances of the conduct; the name, function, and activity of each Government employee or Contractor official or employee involved or knowledgeable about such conduct; identify any documents or substance of any oral communication involved in the conduct; and the Contractor's estimated date when, absent a response, cost, schedule or performance will be impacted.

The Contracting Officer will, within five (5) calendar days after receipt of notice, respond to the notice in writing. In responding, the Contracting Officer will either:

Confirm the conduct is in violation and when necessary direct the mode of further performance, Countermand any communication regarded as a violation, Deny that the conduct constitutes a violation and when necessary direct the mode of further performance, or In the event the notice is inadequate to make a decision, advise the Contractor what additional information is required, and establish the date by which it should be furnished by the Contractor.

1.1 BACKGROUND

1.1.1 Multiple Submarines Emergency Diesel Generators (EDG) at Trident Refit Facility (TRF) Bangor require upgrade to the fuel injection system. The old style fuel injection pumps, injection nozzles and cylinder adapters are no longer supported and need to be upgraded to the modern style. The submarine hulls to receive this upgrade are:

· USS Nevada (SSBN 733)

· USS Nebraska (SSBN 739)

· USS Alabama (SSBN 731)

· USS Kentucky (SSBN 737)

· USS Henry M. Jackson (SSBN 730)

· USS Maine (SSBN 741)

1.2 SCOPE OF WORK

1.2.1 For each of the submarine EDGs, the scope of work for this Task Order is:

· Remove fuel injection nozzles, injection pumps, and nozzle cylinder liner adapters

· Convert removed injection pumps to gasketless configuration and calibrate

· Install calibrated gasketless injection pumps and new pintle injection nozzles and adapters

· Install gasketless-applicable leak off assemblies

· Analyze operational retest of the engine with the use of an engine analyzer

REFERENCE DOCUMENTS

EDG Renewal Process Control Procedure for 38ND8-1/8 OP Engine

S9312-AH-MMA-020; Emergency Diesel Submarine Technical Manual

OEM Fuel Injection Pump Calibration Manual

PMS MRC 6FNZ, Test Fuel Injection Nozzles

PMS MRC 7EES, Conduct Engine Performance Test

REQUIREMENTS

3.1 The contractor shall develop, maintain, and submit a project plan CDRL (A004) that demonstrates the contractor’s understanding of the task order requirements and establishes critical and measurable task milestones. The project plan will span all six submarine EDG fuel oil system upgrades. The project plan shall also include the requisite tasks and sub-tasks that connect the project milestones, and the predecessor/successor relationship of each task and sub-task, such that a clear path to task completion is represented. The contractor shall attach a completion percentage to each task and sub-task, and the percentage complete for each task shall roll up to the milestone and overall project levels, such that a clear and supportable completion percentage is reflected at the task order, milestone and task/sub-task levels. First submission of the project plan shall be no later than one week after task order award, and subsequent submittals shall be on a weekly basis when onsite at TRF Bangor, and monthly in conjunction with the monthly status report when not onsite at TRF Bangor.

3.2 Using the applicable sections of Reference documents in Section 2.0 and any supplemental proprietary documentation deemed relevant, the Contractor shall develop and submit a Technical Work Document (TWD, CDRL A005) that details and sequences the steps necessary to execute the requirements of this SOW on the applicable EDGs. The TWD shall include all checkpoints and OQE necessary to document satisfactory completion of all process steps through the operational retest phase of the task on each identified EDG. The initial TWD shall be completed and accepted no later than one week prior to the start of the first EDG upgrade or one month after task order award, whichever occurs first. The TWD must be updated and completed as steps are accomplished and be available for TPOC review upon request. The TWD will be the record of Objective Quality Evidence (OQE) of satisfactory material condition and procedural compliance. The TWD must be present at the work site when performing each and all phases of work and testing, and shall be available for review upon request by Government representatives.

3.3 At the completion of each EDG fuel system upgrade, the contractor shall update the TWD to incorporate lessons learned from the completed upgrade event. Revision control of the base TWD shall be maintained via the use of a Revision table within the base TWD. For each successive EDG fuel system upgrade, the contractor shall begin shipboard work using the most current revision of the TWD.

3.4 Throughout execution of this task order, the Contractor shall develop and submit periodic status reports (CDRL A001):

3.4.1 Monthly: A status report shall be submitted monthly. The first submission is due one month after Task Order Award and subsequent submissions are due monthly throughout the period of performance of the Task Order.

3.4.2 Daily: In addition to a monthly status report, a status report shall be submitted daily when Contractor personnel are working on-site at TRF Bangor. It should include tasks performed that day, problems encountered, and tasks expected to be performed the next day, to include checkpoints and support service requirements.

3.5 Immediately after task order award, the contractor shall place on order all of the contractor-furnished material (CFM) necessary to execute the EDG fuel system upgrades for four SSBN EDGs. CFM orders for the two optional EDG fuel system upgrades shall be placed upon execution of each option.

3.6 The Contractor shall provide all labor, materials, equipment, special tools and technical expertise necessary to complete the fuel system upgrades for each of the EDGs listed in paragraph 1.1.1. The Contractor shall perform the fuel system upgrade on each unit’s EDG as detailed in paragraphs 3.7 through 3.9.

3.7 For each separate EDG fuel system upgrade, the Contractor shall tag components upon removal and maintain a corresponding log of components removed from the engine. The tag and log must include the name of the component, date of removal, name of remover, and any special disposition requirements. Any material that would have been within the scope of work found to be removed by another activity prior to arrival must be noted in the log. The log must be present and up to date whenever the Contractor is on-site, and shall be available for review upon request by Government representatives.

3.8 For each separate EDG fuel system upgrade, the Contractor shall maintain a log of Foreign Material Exclusion (FME) covers and plugs used throughout the project that includes the type of cover or plug, location of the cover or plug, date of install, name of installer, date of removal, and name of remover. The log must be present and up to date whenever the Contractor is on-site, and shall be available for review upon request by Government Representatives.

3.9 For each of the EDGs, the Contractor shall perform removal, conversion & calibration, installation and operational retest efforts described below. The Condition Found Report (CDRL A008) shall be utilized when it is necessary to identify needed repairs and corrective action for work discovered during the performance period which are not covered by this SOW.

3.9.1 Removal

3.9.1.1 Remove existing fuel injection pumps, nozzles, adapters, high pressure (HP) fuel line and leak off hardware from engine in accordance with (IAW) Reference 2.1.

3.9.1.2 Turn nozzles, leak off hardware and liner adapter hardware over to government for disposition. Retain fuel injection pumps for conversion.

3.9.2 Pump Conversion and Calibration

3.9.2.1 Convert removed injection pumps to gasketless style configuration IAW Reference 2.2.

3.9.2.2 Calibrate converted injection pumps for flow rate IAW Reference 2.3.

3.9.3 Installation

3.9.3.1 Install injection pumps IAW Reference 2.1.

3.9.3.2 Install nozzle liner adapter hardware into cylinder liners IAW Reference 2.1.

3.9.3.3 Prior to installing new fuel injection nozzles, the contractor shall test each nozzle IAW Reference 2.4. OQE indicating that all nozzles are in compliance with popping pressure, leak-by, and spray pattern requirements from Reference 2.4 shall be submitted via Technical Report (CDRL A005). The report shall discuss any out of specification readings with OEM recommendations.

3.9.3.4 Install new injection nozzles into liner adapters IAW Reference 2.1. Tighten collar nuts hand tight to allow for alignment of HP fuel lines and leak off hardware.

3.9.3.5 Install HP fuel line and leak off hardware, ensure all fittings are properly aligned (including banjo fitting) before conducting final tightening/torque of all fasteners.

3.9.3.6 Once all threaded connections are properly aligned and threads run up by hand, conduct final tightening/torque of all fasteners and threaded connections.

3.9.3.7 Verify correct injection pump height, injection pump control rack freedom of movement and setting, and injection timing IAW Reference 2.1.

3.9.4 Operational retest

3.9.4.1 Oversee engine operational retest using Reference 2.5 for guidance. Retest & engine balancing shall be accomplished using the Windrock portable engine analyzer (contractor-furnished) to ensure engine is balanced and all cylinder firing pressures, cylinder exhaust temperatures, and fuel rack settings are within specification.

3.9.4.2 Upon completion of engine operational retest conducted in step 3.9.4.1, submit data sheets via Technical Report (CDRL A005). The report shall discuss any out of specification readings with OEM recommendations.

4.0 DELIVERABLES

4.1 General

4.1.1 All deliverables submitted during the execution of this Task Order shall comply with the applicable Data Item Descriptions (DIDs) referenced in the individual CDRLs (DD 1423s) included in Exhibit A of the base contract.

4.2 Deliverable Acceptance Criteria

4.2.1 Final inspection and acceptance of all work, reports, and other deliverables will be performed by the Government Subject Matter Expert (SME) at the place of delivery. General quality measures, as set forth below, will be applied to each work product delivered under this statement of work:

· Accuracy - Deliverables shall be accurate in presentation, technical content, and adherence to accepted elements of style.

· Clarity – Deliverables shall be clear and concise. Any/all diagrams/text shall be easy to understand and be relevant to the supporting narrative.

· Consistency to Requirements - All deliverables must satisfy the general requirements of this statement of work as well as the specific requirements of each Task Order.

· File Editing - All electronic text and diagrammatic files shall be editable by the Government unless otherwise agreed.

· Timeliness - Deliverables shall be submitted on or before the due date specified by the Government.

4.3 The contractor shall provide the following deliverables during the execution of this Task Order. The specific requirements for each deliverable are provided in applicable Contract Data Requirements Lists (CDRLs) and associated Data Item Descriptions (DIDs).

4.3.1 Contract Status Report (CDRL A001)

4.3.2 Travel Report (CDRL A002)

4.3.3 Contractor’s Personnel Roster (CDRL A003)

4.3.4 Project Planning Chart (CDRL A004)

4.3.5 Technical Reports (CDRL A005)

4.3.6 Condition Found Report (CDRL A008)

5.0 SECURITY REQUIREMENTS

5.1 The Contractor shall comply with the security requirements of the Basic Ordering Agreement.

5.2 Operations Security (OPSEC)

5.2.1 The Contractor shall protect critical information associated with this order to prevent unauthorized disclosure. The NSWC Philadelphia Division's (NSWCPD) Critical Information List (CIL)/ CIIL (Critical Indicators and information list) will be provided on site, if warranted. Performance under this order requires the Contractor to adhere to OPSEC requirements. The Contractor may not impose OPSEC requirements on its sub-contractors unless NSWCPD approves the OPSEC requirements. During the period of performance of this order, the Contractor may be exposed to, use, or produce, NSWCPD Critical Information (CI) and/or observables and indicators which may lead to discovery of CI. NSWCPD’s CI will not be distributed to unauthorized third parties, including foreign governments, or companies under Foreign Ownership, Control, or Influence (FOCI).

5.2.2 Controlled Unclassified Information (CUI) correspondence transmitted internally on the Contractor's unclassified networks or information systems, and externally, shall be protected per NIST SP-800-171, Protecting CUI in Non-federal Systems and Organizations. Assembled large components/systems being transported to and from testing areas, other production or government facilities (whether or not on public roadways) shall be in an enclosed van trailer or covered flatbed trailer. Component/System outside storage, staging, and test areas shall be shielded/obscured from public view wherever physically possible.

5.2.3 NSWCPD’s CI shall not be publicized in corporate wide newsletters, trade magazines, displays, intranet pages or public facing websites. Media requests related to this project shall be directed to the PCO, and the COR who will forward the required to the NSWCPD Public Release Authority for review.

5.2.4 Any attempt by unauthorized third parties to solicit, obtain, photograph, or record, or; incidents of loss/compromise of government Classified or CI, Business Sensitive, Company Proprietary information related to this or other program must be immediately reported to the Contractor's Facility Security Officer and Cognizant Security Office and/or the Naval Criminal Investigative Service, and the NSWC PD Security Division (Code 105.1). Questions concerning these requirements shall be directed to the PCO, and the COR who will forward the request to the NSWC PD Security Division (Code 105.1).

5.3 Receipt, Storage and Generation of Controlled Unclassified Information (CUI)

5.3.1 All Controlled Unclassified Information (CUI) associated with this order must follow the minimum marking requirements of DoDI 5200.48, Section 3, paragraph 3.4.a, and include the acronym "CUI" in the banner and footer of the document. In accordance with DoDI 5200.48, CUI must be safeguarded to prevent Unauthorized Disclosure (UD). CUI export controlled technical information or other scientific, technical, and engineering information must be marked with an export control warning as directed in DoDI 5230.24, DoDD 5230.25, and Part 250 of Title 32, CFR. Nonfederal information systems storing and processing CUI shall be protected per NIST SP-800-171, or subsequent revisions. All transmissions to personal email accounts (AOL, Yahoo, Hotmail, Comcast, etc.) and posting on social media websites (Facebook, Instagram, Twitter, LinkedIn, etc.) are prohibited. Destroy CUI associated with this contract by any of the following approved methods: A cross-cut shredder; a certified commercial destruction vendor; a central destruction facility; incineration; chemical decomposition; pulverizing, disintegration; or methods approved for classified destruction.

6.0 PLACE OF PERFORMANCE

6.1 The primary places of performance for this Task Order shall be at TRF Bangor and Contractor’s facilities.

7.0 TRAVEL

7.1 This task order is being awarded on a firm-fixed price basis to support the fuel system upgrade for six submarine EDGs at TRF Bangor. The contractor shall include in their proposal all costs associated with travel necessary to complete all elements of this task order within the established period of performance.

7.2 A travel report (CDRL A002) is required after each hull fuel system upgrade occurrence.

8.0 GOVERNMENT FURNISHED SERVICES

8.1 Government furnished services include but are not limited to rigging, staging, electrical power, low pressure air, ventilation, gas free certification, and personnel escorts as required.

9.0 TYPE OF CONTRACT

9.1 This task order is being awarded on a firm-fixed price basis to support the upgrade of the fuel system of six 12-cylinder OP EDGs. As a result, the contractor shall include in their proposal the appropriate labor mix and level of effort necessary to complete all elements of this task order within the established period of performance and specific hull repair availability timeframes indicated in Section 10.2. On-site work shall be accomplished during normal business hours, defined as 8 hours per day Monday through Friday.

10.0 TASK ORDER PERIOD OF PERFORMANCE

10.1 The overall period of performance for this task order is from award through 31 July 2024.

10.2 Fuel oil system upgrades will be scheduled to be within diesel inspection periods for each submarine EDG. Below are the planned work periods for each hull:

Table 1

Boat
Hull
Timeframe
Nevada
SSBN 733
Oct-Dec 2023
Nebraska
SSBN 739
Oct-Nov 2023
Alabama
SSBN 731
Nov-Dec 2023
Kentucky
SSBN 737
Dec 2023 - Jan 2024
Henry M. Jackson
SSBN 730
Dec 2023 - Feb 2024
Maine
SSBN 741
Jun-Jul 2024

11.0 TECHNICAL POINTS OF CONTACT (TPOC)

11.1 The TPOCs for this delivery order are:

· Greg Crompton, NSWCPD Code 422, Philadelphia PA. Mr. Crompton can be contacted at gregory.j.crompton.civ@us.navy.mil or (267) 449-1488

· Kurt Weaver, NSWCPD Code 422, Philadelphia PA. Mr. Weaver can be contacted at kurt.r.weaver.civ@us.navy.mil or (215) 834-4677

12.0 SUBJECT MATTER EXPERT (SME)

12.1 The SME for this delivery order is Stephen Kovacs, NSWCPD Code 421, Philadelphia PA. Mr. Kovacs can be contacted at stephen.n.kovacs.civ@us.navy.mil or (856) 904-2587.

13.0 CONTRACTING OFFICER’S REPRESENTATIVE (COR)

13.1 The COR for this task order will be Lauren Markey, NSWCPD Code 4021, Philadelphia, PA. Ms. Markey can be contacted at lauren.v.markey.civ@us.navy.mil or (215) 704-8801.