This is a Performance Work Statement (PWS) for portable toilets and handwash station services at North Field, Tinian, Commonwealth of the Northern Mariana Islands (CNMI), effective September 2, 2026, with a one-year period of performance.
The contractor must provide eight western-style, portable, chemical flush toilets with seat and hand sanitizer dispensers, and four double-sided-sink handwash stations with hand soap and paper towel dispensers. Service requirements include mobilization and de-mobilization to three designated delivery locations shown in Appendix A maps, daily cleaning and restocking, and facility relocation within 24 hours upon request. Toilets and handwash stations shall be serviced five times per week (Monday through Friday) with restocking of toilet paper, hand sanitizers, deodorizers, water, and soaps, plus complete interior and exterior cleaning. Toilets must be pumped and fluid replaced at minimum twice weekly. The contractor must acknowledge discrepancies, damages, or malfunctions within 24 hours and resolve them within 48 hours, provide proper waste disposal per all applicable regulations with proof of permits prior to award, and implement securing mechanisms to prevent weather-related damage. Weekly written service reports must be submitted to the Contracting Officer detailing contractor name, service date, contract number, units serviced or not serviced with reasons, locations, and technician names. Standard hours of operation are Monday through Friday, 8:00 AM to 5:00 PM local time, with standby personnel required during U.S. Federal and local holidays upon coordination approval. The contractor must maintain current employee listings including names, social security numbers, and driver's license numbers, comply with all traffic and safety procedures, immediately report accidents, and follow OSHA and Department of Defense safety requirements. Performance is measured against six objectives: timely delivery and installation with zero discrepancies, adherence to service schedules with zero discrepancies, acknowledgment and resolution of complaints within specified timeframes with zero discrepancies, proper waste disposal with zero discrepancies, effective weather-related securing with zero discrepancies, and timely and accurate reporting with zero discrepancies, all requiring 100 percent compliance.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT (PWS)
PORTABLE TOILETS & HANDWASH STATIONS
NORTH FIELD, TINIAN, CNMI
02 SEPTEMBER 2026
1.0. GENERAL SCOPE: The Contractor shall provide all personnel, labor, vehicles, supervision, training, tools, equipment, safety equipment and other items necessary to provide portable toilets and handwash stations to include mobilization/de-mobilization, daily cleaning, and restocking, at multiple locations on North Field, Tinian, CNMI.
1.1. DESCRIPTION OF EQUIPMENT AND SERVICE REQUIREMENTS: The Period of Performance (PoP) for this contract shall be a 1 year duration. Each CLIN listed in the Schedule shall be quoted with a price per item and total per CLIN.
CLIN 0001: Portable Toilets – 8 each CLIN 0002: Handwash Station– 4 each
The Contractor shall provide the following service requirements:
1.1.1. Mobilize/de-mobilize portable toilets and handwashing stations to locations shown in Appendix A. The contractor may be required to relocate units to other designated areas within 24 hours upon request by the customer.
1.1.2. Toilets shall be a western style, portable, and chemical flush type with seat and hand sanitizer dispensers. Handwash stations shall be double-sided-sink type with hand soap and paper towel dispensers.
1.1.3. Toilets and handwash stations shall be serviced five times per week (i.e. Monday, Tuesday, Wednesday, Thursday, and Friday), unless more-frequent service is requested and directed by the Contracting Officer. Service shall include restocking of toilet paper, hand sanitizers, deodorizers, water, soaps, and complete cleaning inside and out.
1.1.4. Toilets shall be pumped, and fluid replaced no less than two times per week or as required and requested by the Contracting Officer.
1.1.5. Contractor shall acknowledge discrepancies, damages, malfunctions, and/or valid complaints within 24 hours and achieve resolution within 48 hours.
1.1.6. Contractor shall be responsible for proper waste disposal in accordance with all regulations. Contractor shall provide proof of permits prior to contract award.
1.1.7. Contractor shall provide a securing mechanism that prevents damage to surrounding areas and keeps the toilets and handwash stations in place in the event of inclement weather.
1.1.8. The contractor shall provide a weekly written service report to the Contracting Officer.
Information in the report shall include:
a. Contractor’s name
b. Date of service
c. Contract number
d. Units serviced or not serviced (include reason)
e. Units location
f. Technician’s name
2.0. SERVICE SUMMARY: Monitoring methods include periodic inspections, 100% inspection and customer complaint. Complaints include any form of non-compliance violation notice or warning from any official entity. Re-performance of unacceptable services at no additional cost will be the preferred course of action when appropriate. The absence of any contract requirement from the Service Summary shall not detract from its enforceability nor limit the rights or remedies of the Government under any other provision of the contract. The below Performance Thresholds identify the SATISFACTORY level of performance.
Performance Objective PWS Paragraph Performance Threshold Method of
Surveillance
PO – 01: Deliver and install appropriate type & quantity portable toilets and double-sided handwash stations in designated locations within specified timeframe.
1.1.1.
1.1.2.
Zero Discrepancies 100%
Compliance
PO – 02: Service all toilets and handwash stations according to designated service schedule.
1.1.3.
1.1.4.
Zero Discrepancies 100% Compliance
PO – 03: Acknowledge and resolve discrepancies, damages, malfunctions, and/or valid complaints within specified timeframe.
1.1.5. Zero Discrepancies 100%
Compliance
PO – 04: Properly dispose of all waste material. 1.1.6. Zero Discrepancies 100%
Compliance
Performance Objective PWS Paragraph Performance Threshold Method of
Surveillance
PO – 05: Effectively secure all toilets and handwash stations during inclement weather and restore serviceability within specified timeframe in the event of damage and/or loss.
1.1.7. Zero Discrepancies 100%
Compliance
PO – 06: Submit timely and accurate reports to Contracting Officer as specified.
1.1.8. Zero Discrepancies 100%
Compliance
3.0. GOVERNMENT PROPERTY, GOVERNMENT FURNISHED MATERIAL (GFM),
GOVERNMENT FURNISHED SERVICES (GFS):
3.1. Government Property (GP): This contract contains no Government Furnished Property
(GFP).
3.2. Government Furnished Material (GFM): This contract contains no Government Furnished Material (GFM).
3.3. Government Furnished Services (GFS): This contract contains no Government Furnished Services (GFS).
4.0. GENERAL INFORMATION:
4.1. The Contractor shall follow existing traffic and safety procedures applicable to the installation at all times. In the event of necessary traffic pattern coordination, the Contractor shall contact the onsite 513th Expeditionary RED HORSE Squadron (ERHS) Officer-in- Charge and/or Project Manager. Contact info is posted at the site entrance.
4.2. The contractor shall maintain a current listing of employees. The list will include employee names, social security numbers and driver’s license numbers. This list shall be provided to the contracting officer and an updated listing shall be provided upon change of employees.
The Contractor must provide all names, social security numbers and duty hours of all personnel who will be on site at start or anytime during this project.
4.3. The Contractor shall immediately report accidents to the unit representative, ACO, and PCO.
Contractor personnel shall support and comply with all safety/accident investigations.
Contractor shall initiate Contractor corporate internal investigations as required. The Contractor shall follow prevailing Department of Defense regulations and procedures for contacting U.S. Government personnel in conjunction with obtaining investigation statements or any documents.
4.4. Hazardous Material (HAZMAT): The Contractor shall fully comply with installation HAZMAT requirements. The Contractor shall maintain Safety Data Sheets and the mandatory authorization (Form AF 3952) for hazardous chemicals used or stored on the installation.
4.5. Voluntary Protection Program: The contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements. Provide a verbal report to the CO as soon as possible of each occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of required Accident Investigation Reports to the CO within five calendar days of each occurrence. Detailed information on Voluntary Protection Plan
4.6. Hours Of Operation: Services shall typically be performed Monday through Friday from 8:00 am to 5:00pm local time in coordination with the Government, unless otherwise specified.
4.7. Holidays: Due to mission requirements, work performance may be required during U.S.
Federal holidays or during local holidays. During American and local holidays, the Contractor shall provide stand-by personnel when coordination with the COR and ACO indicates performance of service will not be required. One week prior to the holiday, the Contractor shall provide written notification to both the COR and ACO for approval. The notification shall identify by name which personnel will be on stand-by and a contact number. Stand-by personnel shall be available at all times and shall arrive at the installation within one (1) hour after being contacted.
5.0. APPENDICES:
Appendix A – Maps and/or Site Plans
Appendix A – Maps and/or Site Plans
Delivery Location 1
Delivery Location 2
Delivery Location 3
| Tinian Portable Toilet PWS 20260711.pdf |
| Tinian Portable Toilet PWS 20260902.pdf |
File details come from the government source that posted it. Updated .