About this file
The document is a Quote Solicitation for a camera system upgrade issued by South Shore Charter Public School (SSCPS) for their 700 Longwater Drive building, with Project 2026-003 seeking bids to enhance their security camera infrastructure. SSCPS is requesting two bidding options: a Supplement Option that maintains existing systems and adds new cameras, and a Consolidation Option that combines existing systems into one comprehensive solution. The project involves relocating 13 cameras and adding 19 new cameras on the first floor, plus 27 new cameras on the second floor, with installation contingent on construction phases expected to complete in October 2025 and January 2026. The written quote is due on 7/16/2025 at 10:00am, with the backend system required to be operational by 8/22/2025.
The current security environment includes three existing camera systems: 21 Axis cameras on a ZoneMinder server, 3 Verkada cameras, and 12 Speco Technologies cameras, all using the same PoE switches on a separate network and maintaining approximately 14 days of footage. Bidders are required to include all cameras, PoE switches, materials, labor, licensing, installation, setup, and configuration costs. The school prefers to keep as many existing cameras as possible to manage costs and has specified that contractors must pay prevailing wages, remove project debris, and perform work during standard hours of Monday-Friday, 6:30 am to 3:00 pm. Network cabling will be run separately during construction, and bidders should not include cabling costs in their proposals.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
South Shore Charter Public School 100 Longwater Circle Norwell, MA 02061 781-982-4202 www.sscps.org
Quote Solicitation Project 2026-003: Camera System Date 7/2/2025
Scope of Work South Shore Charter Public School (SSCPS) requests bids to enhance our security camera solution at our 700 Longwater Drive building (700L). The enhancements can be bid under two options:
● Supplement Option: This option involves any bid that maintains our existing systems and adds the necessary cameras, storage, and related installation and configuration costs.
● Consolidation Option: This option involves any bid that combines our existing systems into one system. This option would include switching all existing cameras to one system we already use or replacing it with a new system.
Each bidder may submit one bid for each option. SSCPS prefers to have one camera system throughout the building, the Consolidation Option.
SSCPS also prefers to keep as many existing cameras as possible since all new cameras could be cost-prohibitive. Doing this could be under either or both options.
Our existing 3 systems are outlined below. Attached are also floor plans detailing the locations & directions of existing cameras and new cameras that will be part of both options. Some existing cameras will be moved, as detailed below and on the floor plans.
An additional circumstance is that our 700L building will be under construction in multiple phases.
● Phase 1: Rooms circled in purple on the floor plan; expected completion in October 2025.
● Phase 2: Rooms circled in green on the floor plan; expected completion in January 2026.
These areas are noted on the floor plans. The exact completion dates for each phase are not finalized. The backend system needs to be operational by 8/22/2025. Camera installation can only happen once the phase of construction is completed.
During construction, network cabling will be run to the locations detailed on the floor plans. Bids should not include any costs related to network cabling.
http://www.sscps.org
Current Solutions Our primary system consists of 21 Axis cameras connected to a ZoneMinder server (https://zoneminder.com/).
We also have 3 Verkada cameras internally. These are not among the moved or new cameras.
Both Axis and Verkada cameras use the same PoE switches on a separate network.
We also have 12 cameras on a Speco Technologies system. The current system supports 16 cameras. Ten (10) of these cameras are external. The 2 internal cameras overlap with Axis camera moves on the first floor. These cameras can be reused under either bid option; please specify if this is part of either bid.
All systems keep approximately 14 days of footage.
Solution Requirements Under each of the bid options, the following would need to be addressed:
● 1st floor has 13 camera relocations, circled in yellow on the floor plan.
● 1st floor has 19 new cameras, circled in green on the first floor.
● 2nd floor has 27 new cameras.
● 2nd floor does not have any camera relocations.
Please review the floor plans for additional clarification.
Submitted bids should include any cameras, PoE switches (if required), materials, labor, etc. It should also cover all licensing, installation, setup, configuration, etc. For bids under Consolidation Option, costs should include the proposed new camera system or specify which system is being used. All licensing, installation, setup, configuration, etc. for that system should also be included.
Other Requirements Contractors must pay prevailing wages. Contractors must remove any debris resulting from the project. All work by contractors and/or subcontractors must be done in a workmanlike manner.
General hours of operation are Monday-Friday, 6:30 am to 3:00 pm. Working outside those hours must be specifically scheduled in advance.
Dates of installation are to be determined.
Questions about this project should be directed to Ralph deGennaro, Director of Technology at rdegennaro@sscps.org or 781-982-4202 x111
Written Quote Due: 7/16/2025 10:00am Kerri Doble, Procurement Manager South Shore Charter Public School Business Office 141 Longwater Drive, Unit 100, Silver Entrance, Norwell MA 02061 kdoble@sscps.org mailto:kdoble@sscps.org
700 Longwater Drive - 1st Floor
700 Longwater Drive - 2nd Floor
| Quote Solicitation |
| Project 2026-003: Camera System |
| Scope of Work |
File details come from the government source that posted it. Updated .