PERFORMANCE WORK STATEMENT (PWS)

Title: TAO 205 PSA MRG TransALT Work Package Development

Technical POC: TBD

Enclosures:

(1): TAO-205 0046 MAIN REDUCTION GEAR HEAD TANK REQUIREMENTS

(2): TAO-205 0047 0047 MAIN REDUCTION GEAR SENSOR REDUNDANCY

REQUIREMENT

1. Background: The Military Sealift Command (MSC) requires Contractor support for the development of the TRANSALT work packages outlined in the Enclosures (1) and (2).

This PWS details the standard deliverables that are generated when developing a

TRANSALT. This PWS is used in conjunction with the Enclosures and detailed in the

Enclosures themselves. The Enclosures call out the required deliverables as defined in this

PWS and also identify any non-standard deliverables that are necessary for development of a TRANSALT.

2. Scope: MSC requires Wartsila OEM professional engineering services to design and develop ABS approved TRANSALT work packages required for the execution of several modifications onboard the TAO-205 Class. Each TRANSALT work package consists of a work item, contract guidance drawings, list of materials, shipyard production estimate, design history folder and weight report. Enclosures detail exceptions to or additional deliverables over and above this requirement.

3. Specific Tasks: The Contractor shall perform the tasks in Sections 3.1, 3.2, 3.3, 3.4, 3.5 and 3.6 in support of the development of the Enclosures. The Enclosures may require additional deliverables, which will be detailed in the corresponding Enclosure.

3.1. Kickoff Meeting – The Contractor shall conduct a kick-off meeting with MSC in accordance with Section 0. All Key Technical Personnel shall participate in the kick-off meeting. The Contractor shall arrange the date and time with the Contracting

Officer (KO) and Contracting Officer’s Representative (COR)/Technical Point of

Contact (TPOC) to attend a kickoff meeting via Microsoft Teams including a Microsoft

Teams meeting call in number.

3.2. Progress Meetings – The Contractor shall host regular progress meetings. The purpose of these meetings will be to discuss physical progress of the project and to identify any issues that will impact the design or schedule. A standard agenda shall be developed and customized by the Contractor for each meeting. The agenda shall be distributed to the COR/TPOC a minimum of 48 hours prior to each meeting. The frequency of these meetings shall be held in accordance with Section 0. Deviation from this periodicity or the cancellation of any meetings shall be approved by the TPOC/COR. Meetings shall be held using Microsoft Teams (with call in number).

3.3. Meeting Minutes – The Contractor shall provide minutes from all meetings to be delivered in accordance with Section 0. These minutes shall document the discussion

(including any formal concerns raised by the Government), any decisions made during the meeting, and all action items (including the individual responsible, the deliverable, and the due date).

3.4. Project Plan – The Contractor shall develop a Project Plan consisting of a Gantt chart to account for the development and submission of all deliverables in accordance the milestones identified in Section 0 and the Enclosures. The Contractor shall incorporate the submission of all deliverables outlined in the Enclosures into the Project Plan. The

Project Plan shall show the original Project Plan and a revised schedule updated on a 2-week basis (biweekly) to serve as a metric to gauge the Contractor’s schedule performance. The original and biweekly Project Plan updates shall be submitted to the

TPOC/COR on a biweekly basis to reflect actual progress. The start date of the Project

Plan shall be aligned with the issue date of this task.

3.5 Virtual Shipcheck – Due to DoD COVID-19 travel and access restrictions, T-AO

205 will not be available for a physical ship check. The Contractor shall perform a virtual ship check of the NAVISWORKS 3D Model (GFI 7.18) for each Enclosure.

3.5.1 The Contractor shall obtain all shipboard information (configuration details and measurements) necessary to accomplish each TRANSALT Work

Package. Identify the relevant ship structure, piping, ducting, conduit and cableways, power panels, load centers and ancillary equipment and interferences as it pertains to each TRANSALT.

3.5.1.1 Identify all permanent and temporary interferences in way of structure, piping, Heating Ventilation and Air Conditioning (HVAC) and electrical installations and modifications required to meet this PWS.

3.5.1.2 Pull screen captures from the model and compile spatial requirements to develop Work Package removal and installation drawings.

3.6 Virtual Shipcheck & Conceptual Design Report: The Contractor shall develop and deliver a Virtual Ship Check & Conceptual Design Report (VSCCDR) detailing survey results and conceptual designs for all affected systems for each Enclosure and submit it to the TPOC/COR for review in accordance with Section 0. Each VSCCDR shall be submitted as an individual report to speed up the submission process with included conceptual designs which layout the proposed solution at a conceptual level to inform the development of the P1 Deliverables for each Enclosure. The conceptual design shall be used to validate the functionality of all proposed modifications. For each Enclosure, the contractor shall provide the following information:

3.6.1 Annotate currently installed equipment make, model, and manufacturer for reference. Identify any missing or required information that is not contained in the model or other information provided in GFI 7.18.

3.6.2 Provide multiple screen captures from the model to document all interferences, proposed locations for equipment, and system/structural interface points/areas.

3.6.3 Provide a list of calculations or other engineering efforts that must be accomplished in order to finalize the design.

3.6.4 Provide system diagrams to show conceptual modified system removals and installations

3.6.5 Provide sketches and material & construction requirements

3.6.6 Provide class/regulatory compliance review findings

3.6.7 Provide control system interface requirements, programming performance requirements; and alarm and monitoring requirements.

3.6.8 Provide market research for specialty equipment, a list of major equipment end items including all equipment, specialty end-items (i.e. non-standard commercial off the shelf), and other items that have lead times greater than four (4) weeks. Cut sheets or other vendor provided information for these items that details all salient characteristics shall be provided.

3.6.9 Provide drawing requirements including a list of drawing titles in the

Military Sealift Command (MSC) drawing number request spreadsheet (GFI

7.23)

*Contractor shall not proceed to TRANSALT work package development until the conceptual design reports are approved by the TPOC/COR. Deviations from these conceptual design reports shall be approved by the TPOC/COR.

3.7 TRANSALT Work Packages – The Contractor shall develop TRANSALT work packages for the PWS Enclosures in accordance with Section 0. TRANSALT work packages shall be based off the VSCCDR as required by each Enclosure. Any work items or drawings not expressly identified in this PWS shall not absolve the Contractor from providing complete work packages necessary to meet all design requirements listed in the Enclosures. Work package requirements include:

3.7.1 System Engineering Calculations – The Contractor shall develop all engineering calculations required to ensure the final designs will be fully functional. The source for all calculation methods shall be documented.

All assumptions shall be clearly identified and explained. The calculations shall clearly link the design results and equipment selected to ensure that the system will function to the satisfaction of the government. MSC may require more information if what is provided by the Contractor is unclear, incomplete, or untraceable as determined by the

TPOC. The Contractor shall provide all working files used to develop the calculations. Calculations shall be submitted in a report format for each system that requires calculations as described in this Section and identified in the Enclosures. Additionally, all designs shall comply with all

ABS rules, USCG regulations, international laws and regulations

(SOLAS/IMO), and applicable requirements outlined in Sections 7 and 8.

The Contractor is responsible for any calculations associated with ABS rules and USCG regulations and resolution of any resulting comments to the satisfaction of ABS, USCG and the TPOC. The following shall be developed and submitted as required to validate acceptable system performance for all new and modified systems:

3.7.1.1 Naval Architecture Calculations and Schematics

3.7.1.1.1 Structural Analyses

3.7.1.1.2 Rigging, Cargo Handling and Lifesaving Systems

Analyses

3.7.1.1.3 Weight and Moment Reports and Calculations

3.7.1.1.4 Arrangements (Hull and Deck) and Outfitting

3.7.1.1.5 Material Analyses

3.7.1.1.6 Weld and Connection Analyses

3.7.1.2 Electrical Calculations and Schematics

3.7.1.2.1 Voltage Drop Calculations

3.7.1.2.2 Load Calculations

3.7.1.2.3 Power & Lighting One Line Diagram

3.7.1.2.4 Electrical Plant Load Analysis (EPLA)

3.7.1.2.5 Protective Device Coordination Study

3.7.1.2.6 Fault Current Analysis

3.7.1.2.7 Electric Plant Distribution Impact Data (EPDID)

3.7.1.3 Mechanical System Calculations and Schematics

3.7.1.3.1 System Load Estimates

3.7.1.3.2 Pipe Sizing/Fluid Flow Calculations/Models in accordance with CRANE Technical Paper No. 410 or equivalent;

models shall be compatible with PIPE-FLO

3.7.1.3.3 HVAC Calculations in accordance with SNAME T&R

Bulletin 4-16; Recommended Practices for Merchant Ship

HVAC Design Calculations

3.7.1.3.4 Thermostat & Reheat Design/Selection

3.7.1.3.5 Equipment Selection Methodology

3.7.1.4 All other calculations required by ABS, USCG, & the

Enclosures.

3.7.1.5 All other calculations required to prove proper system functionality to the satisfaction of the government/TPOC.

Calculation sets not expressly identified in Sections

3.7.1.1– 3.9.1.5 do not alleviate the Contractor from providing all information to clearly demonstrate that all aspects of the system designs will operate to the satisfaction of the government and meet the design performance requirements.

3.7.2 Work Item – The Contractor shall develop a work item to cover all modifications for each Enclosure. Work items are the contractual vehicle for tasking a shipyard to perform work. Work items shall be produced to the standards outlined in the MSC Work Item Preparation Guide (GFI 7.4) and the General

Technical Requirements (GFI 7.1). Sample work items are provided in GFI 7.5.

The work items must contain all the necessary working level detail needed for shipyard workforce implementation that meets the quality standards shown in GFI

7.5.

3.7.3 Contract Guidance Drawings – The Contractor shall develop guidance drawings that address all removals (temporary and permanent), renewals, modifications, and installations necessary to ensure all systems are fully functional. These drawings shall be separated by engineering discipline and provide all necessary electrical power, controls, mechanical, and structural/outfitting modifications required to install a fully functional system.

Guidance drawings are developed along with the work item and are provided as guidance for installation and shall comply with the standards outlined in GFI 7.2.

Sample drawings are provided in GFI 7.5. The drawings shall contain all the necessary working level detail needed for installing activity implementation that meets the samples shown in GFI 7.5. Any equipment or material identified as

Long Lead Time Material per Section 3.7.4 shall be identified as GFM in the List of Material (LOM). New MSC drawing numbers will be provided by the TPOC using the Contractor’s requested drawing information resulting from Section

3.5.1.11. Types of guidance drawings that may be included for each TRANSALT work package may include, but should not be limited to:

3.7.3.1 Arrangements & Outfitting

3.7.3.2 Structural & Foundations

3.7.3.3 Piping Systems (Multiple)

3.7.3.4 HVAC Systems

3.7.3.5 Electrical Power Systems

3.7.3.6 Lighting Systems

3.7.3.7 Alarm, Monitoring, & Controls Systems

3.7.4 Sortable List of Material – The Contractor shall provide a sortable List of Materials (LOM) spreadsheet (GFI 7.5) that includes all material and equipment for each work package broken out by drawing. Each spreadsheet will be broken out by drawing as well as one sheet showing all material required for each entire work package. This list should mirror the contents of all drawings.

The materials list shall contain the following for each piece of equipment:

3.7.4.1 Equipment name, make, and model

3.7.4.2 Description

3.7.4.3 Distributor (Identify website, POC, and contact info)

3.7.4.4 Distributor Part Number (if different than above)

3.7.4.5 Salient characteristics (size/dimensions, power, capacity, etc.)

3.7.4.6 Quantity

3.7.4.7 Applicable Design and Material Standards for mechanical components

3.7.4.8 Purchase lead-time for all items, and provide the estimated lead time for any items with a lead time greater than four (4) weeks.

These items shall also be designated as long lead-time material

(LLTM).

3.7.4.9 Designate which items shall be Government Furnished Material

(GFM) or Installing Activity Furnished (IAF)

3.7.4.10 Price Quote or Catalog Pricing

3.7.4.11 Reference to work item and drawing where the material is used

3.7.4.12 Additional Comments (as warranted)

3.7.5 Equipment Cut Sheets/Vendor Quotes - Any long lead time material per Section 3.7.4 or equipment/material with special requirements including custom built equipment or furniture shall be identified. Cut sheets, or vendor quotes, shall be provided for all equipment/material identified in the LOM.

3.7.6 Installing Activity Cost Estimate – Provide a detailed installing activity cost estimate spreadsheet (MS Excel) for each work item showing man hours, labor cost, and material cost (both GFM and IAF), and a sheet showing the total cost for each work package. Cost estimates consist of a detailed breakdown of all the labor categories and materials associated with a work package. A detailed breakout of all labor categories that corresponds to the required production steps shall be provided. The spreadsheet shall be created such that changing the labor rate in one cell adjusts the labor cost throughout the

MS Excel workbook. A sample estimate is provided in GFI 7.5 to communicate the level of detail required.

3.7.7 Weight Report – The Contractor shall prepare a detailed weight report for each work package per GFI 7.8. The report shall list all weight additions, removals and relocations on the ship, including the associated centers of gravity, as a result of the work performed in this task. The weight report is to specify the aggregate weight change and impact to lightship. Each drawing shall have a weight and moment impact table that matches the weight reports provided.

3.7.7.1 Account for all weight changes

3.7.7.1.1 Small weights (less than 200 lbs) may be combined and estimated so long as the total combination does not exceed 200lb

3.7.7.1.2 Document weights by actual weighing, using a

manufacturer’s catalog weight, calculating or estimating. If an estimate, the basis of estimate shall be provided.

3.7.7.1.3 Account for items at the component level. For systems normally containing liquids (piping, machinery with sumps, etc.) report the weight of liquid in the system separate from the dry weight of the system

3.7.7.2 Prepare the report in tabular format, per GFI 7.8, with the following information grouped according to work items in the work package

3.7.7.2.1 Item number and description

3.7.7.2.2 Weight (lbs/Tonnes)

3.7.7.2.3 Vertical level (VCG), (ft or m) above baseline

3.7.7.2.4 Vertical Moment (ft-lbs or m-tonne)

3.7.7.2.5 Longitudinal lever (LCG), (ft or m) aft of the

forward perpendicular

3.7.7.2.6 Longitudinal moment (f-lbs or m-tonne)

3.7.7.2.7 Transverse lever (TCG), (ft or m) off centerline

port/starboard

3.7.7.2.8 Transverse moment (ft-lbs or m-tonne)

3.7.7.2.9 Resultant weight (lbs/Tonnes)

3.7.7.2.10 Resultant VCG, (ft or m) above baseline

3.7.7.2.11 Resultant LCG, (ft or m) aft of the forward

perpendicular

3.7.7.2.12 Resultant TCG, (ft or m) off centerline

port/starboard

3.7.7.3 Round-off values as follows:

3.7.7.3.1 Weight and distance to two (2) places to the right

of the decimal point

3.7.7.3.2 Moments to the whole ft-lbs or m-tonne

3.7.7.4 Denote dimensions aft of the forward

perpendicular, above baseline, and to starboard as

“positive” values

3.7.8 Design History Folder - Design history folder for each Enclosure. At a minimum, the design history folder shall include all information used in making design decisions, including but not limited to:

3.7.8.1 Analysis completed (electrical, structural, etc)

3.7.8.2 Vendor cut sheets for each item

3.7.8.3 Excel table which identifies the cost, lead time, vendor, and model number of each item

3.7.8.4 Correspondence related to the Enclosure

3.7.8.5 Calculations

3.7.8.6 In progress drawing revisions

3.7.8.7 Documentation of comment adjudication;

Adjudication shall be in a different color from the governments comments. Adjudication may be hand written and scanned to PDF or electronic.

3.7.8.8 Salient characteristic data for each piece of

equipment with sufficient detail to purchase of “or equal” equipment.

Design history folders shall be organized into separate sections for drawing updates/comments adjudication, analysis completed, correspondence in date sequential order, and the Excel Table followed by vendor cut sheets in order of the material list part numbers. Design history folder shall be provided in hard copy and electronic Portable Document Format (PDF) format. Drawing updates shall include one-for-one comment adjudication directly on a pdf of the drawing. Adjudication shall be in a different color from the government’s comments. Adjudication may be hand written and scanned to PDF or electronic.

3.7.9 Shipboard Test Procedures – The Contractor shall develop separate detailed test procedures for each modified system in order to ensure the proper operation of all modified and installed equipment.

3.7.10 Technical Manuals – Technical Manuals shall be provided for all new and modified equipment and systems. Technical Manuals shall be developed in accordance with GFI 7.19. Any modified Technical Manuals shall be updated and not just redlined or inserted. Technical manuals not currently in MS Word shall be converted into MS Word 2016.

3.7.11 Spare Parts - The Contractor shall provide a list of recommended spare parts and maintenance equipment and associated costs. The spare parts list shall include both recommended shipboard spares and shore based spares for thirty

(30) day, one (1) year, and five (5) year time periods. The list shall give a full description of each part with component manufacturer's part number, ordering data, including source for the part, and National Stock Number (NSN) if available. Parts shall be priced individually.

4 Deliverable Format: It is the responsibility of the Contractor to plan for submission of all deliverables in order to ensure that the final deliverables are accepted by MSC prior to the end of the Period of Performance (POP).

4.1 The Contractor shall deliver all drawings using AutoCAD LT 2017 compatible versions. The drawing details shall be located in model space. The drawing sheet zones and title shall be located in layout/paper space. The drawing details shall be placed on the pages using viewports with hidden

(invisible) lines. The native sheet size shall be 11 x 17 inches. The Contractor shall follow the guidelines identified in GFI 7.1 thru 7.5. Electronic copies shall be in both AutoCAD Lt 2017 and Adobe PDF (Version 6 or newer). Final approved drawings shall be delivered with approval letters from ABS and

USCG.

4.2 The Contractor shall deliver Work Items, Technical Manuals, Test

Procedures, and Reports in MS Word 2016 compatible format using MSC

Standard Work Item format found in Section 7. The Contractor shall provide electronic copy in MS WORD and PDF (Version 6 or newer).

4.3 The Contractor shall provide Cost Estimates and Engineering

Calculations using MS Excel 2016 compatible spreadsheets. Alternate formats for Engineering Calculations will be considered for requests submitted with the

Contractor’s proposal or as part of the VSCCDR; however, determination as to technical acceptability is to be made by TPOC prior to the Contractor utilizing alternate methods.

4.4 The Contractor shall submit all electronic files (AutoCAD 2017 [.dwg], MS Word 2016 [.doc], MS Excel 2016 [.xls], and Adobe Portable Data Files

[.pdf]) via SAFE or by other means deemed acceptable by the TPOC/COR.

5 Review Process: All deliverables described in Section 3 and called out in the

Enclosures shall be submitted in accordance with the following process:

5.1 The Contractor shall submit P1 Deliverables for MSC review and comment in accordance with Section 6.1. The P1 deliverables shall be technically complete and properly formatted with no reservations, errors or omissions and reviewed by the Contractor’s Quality Assurance personnel as identified in the Section 11 prior to submission to the MSC TPOC/COR.

MSC review is not to be used as the Contractor’s Quality Assurance (QA) review. The Contractor shall incorporate all comments from the TPOC/COR to create the P2 Deliverables. If a Preliminary Copy is submitted with reservations, omissions or is, unacceptable per the Quality Assurance

Surveillance Plan (QASP) the deliverable will be returned to the contractor as unacceptable and an updated Preliminary Copy (P1) shall be submitted to

MSC within two (2) business days for review. All comments from the

TPOC/COR shall be adjudicated to the satisfaction of the

Government/TPOC.

5.2 The Contractor shall submit the P2 deliverables for TPOC/COR review and approval. The P2 deliverables shall be technically complete and properly formatted with no reservations, errors or omissions and reviewed by the

Contractor’s Quality Assurance personnel prior to submission to the MSC COR.

All TPOC/COR questions and comments from MSC shall documented in the P1

Deliverable shall be addressed in full. Submission of successive rounds of

Preliminary deliverables will continue until all deliverables have been adjudicated to the satisfaction of the Government/TPOC. It is imperative that the

Contractor perform an acceptable QA review to ensure that updates and changes are fully integrated and that any cascading effects of those changes are properly accounted for.

5.3 After Preliminary deliverables have been approved by the

TPOC/COR, all preliminary revision marks and revision notes shall be removed from the drawings and they shall be labeled as “Rev –” or revision as identified by the TPOC. The “Rev –” deliverables shall be reviewed by the Contractor’s Quality Assurance personnel prior to submission to the

TPOC/COR. This process will continue until MSC accepts the final version of the design package. For any deliverables that do not require regulatory body approval, this deliverable will become the Final Copy after MSC’s comments are incorporated/adjudicated to the satisfaction of the

Government/TPOC.

5.4 After the “Rev –” deliverables are approved by MSC; the Contractor shall submit the approved “Rev –” final deliverables to ABS for review via ABS

O2E website (www.eagle.org). When submitting to ABS O2E (see GFI 7.9-

7.12), the Contractor shall include the TPOC/COR in the Notification List with both Submission and Approval rights. The Contractor is responsible for addressing any technical comments from ABS and USCG, including all required calculations to obtain ABS/USCG approvals. Prior to uploading any technical comment responses to O2E and the USCG, the Contractor shall first submit the responses to the TPOC/COR. Upon approval from the TPOC/COR, technical comment responses shall be officially uploaded to the ABS O2E website. MSC shall be copied on all information submitted to ABS/USCG and all ABS/USCG responses. The Contractor is responsible for following up with ABS/USCG to ensure Final Deliverables are received on time from ABS/USCG to meet MSC

Final Delivery dates. The Contractor shall be responsible for delivering all

ABS/USCG stamped plans and corresponding approval letters to the

TPOC/COR. ABS/USCG stamped plans and corresponding approval letters must be submitted directly to the TPOC/COR from the Contractor; the

TPOC/COR downloading plans and letters from the ABS O2E website does not meet this requirement. All items shall be returned stamped ABS “APPROVED” and with a letter of approval from USCG or ABS Stamped “APPROVED BY

ABS ON BEHALF OF USCG” in accordance with the ACP Program review procedures as outlined in Reference 8.12.

6 Delivery Schedule:

6.1 The delivery schedule for all deliverables shall be in accordance with the approved Project Plan described in Section 3.4, the Enclosure Delivery

Schedules, and the milestones listed below:

No. Deliverable/Activity Due Date

3.1 Kickoff Meeting Within 5 Business Days of Award

3.2 Progress Meetings Weekly

3.3 Meeting Minutes COB the Business Day after the Meeting

3.4 Project Plan Within 4 Business Days of Award

3.6 Virtual Shipcheck & Conceptual Design Report

(VSCCDR)

See Enclosures

E_-5 Enclosure Deliverables See Enclosures

5 Final Deliverables (ABS and USCG Approved) 15 June 2021

7. Government Furnished Information (GFI): The following is general GFI to be used for all tasks. Task specific GFI will be provided in each task Enclosure. Electronic copies of these documents are available from the TPOC/COR upon request; however, due to applicable distribution statements and need to know, MSC will not be distributing all GFI prior to award of the contract/delivery order.

7.1 MSC Standard Drawing # 7081122 – MSC General Technical

Requirements

7.2 MSC Standard Drawing # 7080803 – Preparation of CAD Drawings for

USNS Ships

7.3 MSC Standard Drawing # 7079667 – Preparation of Selected Record

Drawings

7.4 MSC Standard Drawing # 7081124 – Work Item Preparation Guide

7.5 Sample WI, Drawings, and Shipyard Cost Estimate

7.6 MSC COMSCINST 4750.2 Preservation Instructions for MSC Ships

7.7 MSC EPI N721-9096-001 Weight and Stability Control

7.8 Weight and Moment Calculation Sheet and User Guide

7.9 ABS Services

7.10 Engineering Manager Help

7.11 O2E

7.12 ABS Service Request Form

7.13 USNS John Lewis New Construction Contract J2 for Ship Drawing Index

(with each specific drawings potentially being available upon request based on request date and new construction contract progress)

7.14 USNS John Lewis New Construction Contract J2 for Tech Manual Index with each specific technical manual potentially being available upon request based on request date and new construction contract progress)

7.15 MSC Electrical Drawing Template

7.16 MSC Naval Architect Drawing Template

7.17 MSC Mechanical Drawing Template

7.18 TAO-205 NAVISWORKS 3D Model

7.19 ODP Form Blank

7.20 MSC Tech Library Guidance - Tech Manual Creation/Modification

7.21 MSC Quality Management Standards Index for N7 Standards (with each specific standard available upon request)

7.22 MSC Safety Management Standards Index for TAO 187 Class (which will be similar to the TAO 205 Class when the ship is delivered) (with each specific standard available upon request)

7.23 MSC Drawing Number Request Form

8 Applicable Documents: Design and review shall be in accordance with the following specifications, standards and all requirements incorporated within these documents. Where requirements of these documents conflict the most stringent requirement shall take precedent. It is the Contractor’s responsibility to furnish these documents. The MSC

Contracting Officer shall approve any deviation from the requirements of these documents in writing.

8.1 USCG Code of Federal Regulations

8.2 American Bureau of Shipping, Rules for Building and Classing Marine

Vessels

8.3 IEEE –STD-45, Recommended Practice for Electrical Installations on

Shipboard

8.4 MARPOL

8.5 SOLAS

8.6 SNAME T&R Bulletin 4-7; Thermal Insulation Report

8.7 SNAME T&R Bulletin 4-16; Recommended Practices for Merchant Ship

HVAC Design Calculations

8.8 CRANE Technical Paper No. 410; Flow of Fluids

8.9 MSC Standard Drawing # 7081122 – MSC General Technical

Requirements

8.10 MSC Quality Management Standards

8.11 MSC Safety Management Standards

8.12 ACP Program

9 Place and Period of Performance. The overall Period of Performance will begin upon

Order issuance and end 15 June 2021. Each individual task outlined in Section 3 and detailed in the Enclosures will further define the Period of Performance for this PWS. All work shall be performed at the Contractor’s facility.

10 Invoice Schedule: The Contractor shall submit an invoice upon acceptance of the final deliverables by the Government unless an alternate invoice schedule is proposed by the

Contractor and accepted with the initial proposal.

11 Key Personnel: Key personnel shall be responsible for the development of all deliverables. Resumes for all key personnel shall be provided. No personnel may be “dual hatted”.

12 Markings: All drawings shall include DoD Distribution Statement C to read:

“DISTRIBUTION C. DISTRIBUTION AUTHORIZED TO U.S. GOVERNMENT

AGENCIES AND THEIR CONTRACTORS ONLY; ADMINISTRATIVE OR

OPERATIONAL USE; 1 OCTOBER 2020. OTHER REQUESTS FOR THIS

DOCUMENT SHALL BE REFERRED TO MILITARY SEALIFT COMMAND, 471

EAST C STREET, NORFOLK VA 23511.” and shall replace the distribution statement in the MSC Drawing templates.

Enclosure (1): TAO-205 0046 MAIN REDUCTION GEAR HEAD TANK

REQUIREMENTS

T-ALT NUMBER: TAO-205 0046

SHIP NAME/CLASS: TAO-205 CLASS

Abstract: The Main Reduction Gears (MRG) on the T-AO 205 Class do not utilize a head tank arrangement for lube oil supply as has been installed on other classes of vessels, including the

187 Class Oiler that the 205 Class will replace. The addition of a head tank on the 205 Class

MRG Lube oil system would provide several benefits:

1) Allow for robust monitoring of MRG lube oil levels

2) Allow for passive flow of Low Pressure lube oil to the mesh and bearing lubrication system in the event of loss to the LP lube oil Supply system over a designed amount of time

3) Allow for robust system of safety system sensors to prevent inadvertent activation of

MRG Low-Low lube oil pressure safety shaft lock automated sequence (non-over rideable)

4) Allows for designed amount of additional lube oil supply once a critical low level alarm set point is reached

On the 187 class, this combination of design factors was used to provide a level of built in lube oil margin for the in conjunction with the vessel’s automated safety system to protect the MRGs in critical maneuvering scenarios. When a “Low-Low Level” switch is activated in the head tank, the vessel has 6 minutes of lube oil supply volume below that level. In combination with a feature called the “UNREP Switch” which, when activated, delays the MRG auto-brake sequence for low lube oil. The goal of the UNREP switch in combination with the physical supply of lube oil below the sensor is to allow for 5 minutes of continued operations to perform an emergency breakaway. The 6 minute of lube oil is sized for 5 minutes of operations and then

1 minute for the automation sequence to declutch and brake the shaft.

E1-1. Applicable References: The References listed below shall be used by the

Contractor in addition to those identified in Sections 0 and 8 of the PWS.

E1-1.1. Wartsila Reduction Gear Technical Manual

E1-1.2. Shafting System Report, Rev. X

E1-1.3. Propulsion System Design Report, Rev. X

E1-1.4. Propulsion Control System Description of Operations, Rev. I

E1-1.5. MCCS Description of Operations, Rev. G

E1-1.6. MCCS System Architecture Diagram, Rev. C

E1-1.7. Electrical One-Line Diagram, Rev. F

E1-1.8. Machinery Arrangement, Rev. J

E1-1.9. Vessel 3D Model

E1-1.10. MCCS Network Architecture Diagram

E1-1.11. Input/output Diagram

E1-2. Scope of Work: The Contractor shall provide and Install a head tank solution for the Main Reduction Gears’ lube oil systems. Each of the two (2) MRGs shall have a dedicated head tank. The head tank shall be located at a height to provide sufficient head pressure to match the current systems design pressure for the “Low Pressure” lube oil system, which supplies lubricating oil to the gear meshes and bearings. The head tank shall be provided with a tank level monitoring system as well as level switches that can be used for the propulsion control automated safety system. The Switches shall indicate a “Low Level” and a “Low-Low Level”. The “Low-Low Level” switch shall be placed such that the quantity of oil between the level switch and the gravity line to the MRG provides 5 minutes of lube oil supply at rated Low Pressure lube oil when the clutch system is engaged to the prime movers. Additionally, the head tank margin below the

“Low-Low” switch shall include sufficient lube oil needed for the amount of time necessary for automations to disengage the shaft line, slow and stop the shaft.

The Wartsila MRGs used on 205 also have High Pressure Lube Oil system pumps that are used to operate the attached clutches. These pumps also take suction from the common MRG sump and need to be accounted for in the consumption rate of the overall lube oil system and the sizing of the lube oil head tank. The sizing of the head tank needs to be a balance to ensure the head tank does not flood the sump of the

MRG when the system is not in operation or the pumps are not running.

The design of the head tank should be accomplished in close coordination with the OEM of the gearbox (Wartsila) to ensure the OEM will support the design implementation or if they have an existing design for a head thank solution. The OEM should also be consulted to determine if a COTS solution is available

E1-2.1. Discipline Specific Considerations:

E1-2.1.1. Arrangements and Outfitting: Location of the head tank and associated pipe routing to the MRGs.

E1-2.1.2. Structural: Provide sufficient support for pipes to prevent vibration but allow for any necessary flexibility of the system from MEG vibration and ship’s motion. If necessary, provide sufficient foundation structure for the head tank.

E1-2.1.3. Mechanical: Suitability of the current MRG lube oil pumps needs to be investigated to determine if the current pumps can be used to feed the lube oil to the necessary head tank height. If lube oil pumps are not sufficient then a recommendation on replacement pumps should be included.

E1-2.1.4. Electrical: Provide necessary power, control and signal cables for monitoring devices associated with the new head tank. If mechanical determines that new pumps are needed, an assessment of the current electric motors, motor controllers and feed power should be looked at. The each MRG has a PLC that controls the logic for the duty/standby pumps; the design of the head tank monitoring should include any necessary changes to the PLC logic to ensure satisfactory operation.

E1-2.1.5. Automation Modifications: None additional.

E1-3. Deliverables Requirements: The Contractor shall provide the following

Deliverables in the development of this Enclosure.

E1-3.1. Deliverables Described in Section 3 of the PWS:

E1-3.1.1. The contractor shall provide deliverables in accordance 3.1, 3.2, 3.3, 3.4,

3.6 and 3.7 as described in Section 3 of the PWS.

E1-3.1.2. Additional Deliverables: None additional.

E1-4. Delivery Schedule:

No. Activity Due Date

3.6 Virtual Ship Check & Conceptual Design Report 15 Business Days after Kick-off Meeting

5.6 P1 TRANSALT Work Package 15 Business Days after Approved Conceptual

Design

5.7 P2 TRANSALT Work Package 12 Business Days after Submission of P1

5.8 Rev – TRANSALT Work Package 2 Business Days after Submission of P2

5.9 Submittal to USCG/ABS Within 1 Business Day of COR Approval

5.9 Draft Response to ABS Comments 5 Business Days from Posting of ABS Comments on Eagle.org

5 Submittal to ABS for Comment Adjudication Within 1 Business Day of COR Approval

5 Final Deliverables (ABS Approved) 14 June 2021

Enclosure (2): TAO-205 00047 MAIN REDUCTION GEAR SENSOR REDUNDANCY

REQUIREMENTS

T-ALT NUMBER: TAO-205 0047 MAIN REDUCTION GEAR SENSOR REDUNDANCY

SHIP NAME/CLASS: TAO-205 CLASS

Abstract: The Main Reduction Gears (MRG) on the T-AO 205 Class utilize a skid mounted

PLC system to collect sensor data, which is used as part of the lube oil pump start logic, clutch engagement and MRG’s safety monitoring, alarm and shutdown system. Loss of Lube Oil pressure is considered a critical, non-over ridable, safety alarm per ABS SVR 4-9-2. To monitor

Low Pressure System (gear mesh and bearing lubrication) lube oil pressure the MRG utilizes two (2) separate types of sensors. A pressure transducer (“L01”) is used for monitoring and outputs a 4-20 mA signal to the PLC system (which is relayed to the Machinery Centralized

Control System (MCCS)) to provide an analog reading of the dynamic system pressure. MCCS has alarm set points set for assigned to critical pressure values from the analog signal. Two (2) additional calibrated pressure switches are used to the safety shutdown system. Pressure switch

“L04”is calibrated for a low-low pressure shutdown at 0.6 bar and the signal is routed directly to the Main Diesel Engine’s (MDE) safety and control system (SaCoSone). Activation of “L04” will cause SaCoSone to initiate and emergency shutdown of the MDE and an alarm will output from SaCoSone via a serial interface to MCCS indicating a shutdown on low MRG lube oil pressure. Pressure switch “L012” performs a similar function, but it provides an output to the

Shaft Generator Motor’s (SGM) Drive Control Unit to shut down the SGM.

Neither the analog pressure transducer or the safety shutdown pressure switches (“L04” and

“L012”) are routed directly to the Propulsion Control System Data Acquisition Units

(Port/STBD Propulsions DAUs). The PCS can monitor the serial alarms and analog pressure signal over the MCCS network backbone, but PCS (the dedicated PCS PLC’s) will take action based on these signals to provide subsequent automation to meet ABS requirements for AMS and ACCU. PCS will initiate automatic load reductions and automatic shaft brake sequences based on values given by the pressure transducer (“L01”). The MDE shutdown is handled solely by SaCoSone and is based on the single input from sensor “L04” (similarly for the SGM shutdown). PCS processes a combination of “L01” and MDE serial output alarms to initiate an automated sequence to declutch, slow and lock the affected shaft to protect the MRG from operating without sufficient lube oil pressure. The automatic shaft break sequence on Low-Low lube oil pressure is a non-over ridable sequence to meet the requirements of ABS. The shutdown of the MDE (and SGM) are non-over ridable as well in accordance with ABS.

It is determined to be an operational risk that a single sensor failure or faulty activation could result in a non-over ridable loss of propulsion. In high risk, critical maneuvering scenarios (such as an UNREP), the sudden loss of propulsion could result in the vessel losing course keeping and result in a collision. Additional redundancy of sensors driving a non-over ridable safety automation sequence would prevent a single point of failure.

E2-1. Applicable References: The References listed below shall be used by the

Contractor in addition to those identified in Sections 0 and 8 of the PWS.

E1-4.1. Wartsila Reduction Gear Technical Manual

E1-4.2. Shafting System Report, Rev. X

E1-4.3. Propulsion System Design Report, Rev. X

E1-4.4. Propulsion Control System Description of Operations, Rev. I

E1-4.5. MCCS Description of Operations, Rev. G

E1-4.6. MCCS System Architecture Diagram, Rev. C

E1-4.7. Electrical One-Line Diagram, Rev. F

E1-4.8. Machinery Arrangement, Rev. J

E1-4.9. Lube Oil Service System Diagram, Rev. B

E1-4.10. Vessel 3D Model

E1-4.11. MCCS Network Architecture Diagram

E1-4.12. Input/output Diagram

E2-2. Scope of Work: The Contractor shall investigate and provide a scope of work to add redundancy to the safety sensor system on the MRGs to remove single point of failure concerns. The MRG OEM (Wartsila) shall be contacted to determine if there is a

COTS solution for additional sensor redundancy. If a non-OEM solution is required, investigation should look at the potential of using the currently installed transducers and switches in combination to the greatest extent possible to limit the amount of physical modification to the lube oil piping. If the existing sensors can be used, provide a work package of wiring changes (such as the addition of relays if needed) and/or necessary software modification specification for modifications to the Propulsion Control System in order to achieve redundancy.

If utilizing the current sensors is not feasible, provide a work package for installation of necessary sensors, wiring and software change specifications to update the current design to meet the needed redundancy.

The MRG safety system should utilize at least two (2) positive signals (configured in a fail-safe arrangement with the physical sensors) to initiate any safety shutdown of the

MRG. This includes automatic declutching (loss of High Pressure Lube Oil pressure);

Low Pressure System shutdowns (MDE shutdown output signal (“L04”); and signals processed by PCS for shaft locking sequence.

The work item will require coordination between the MRG OEM; the engine controls manufacturer (Fairbanks Morse Engines) and the control and automation system OEM

(Trident Marine Systems). Modifications must meet the design requirements of ABS

AMS and ACCU notation and applicable SVRs. If a design constraint requires a deviation from the rules, a specific “UNREP Mode” should be created to allow the system to go between maximum redundancy and full ACCU/AMS compliance. This deviation needs to be presented to MSC for potential to route through USCG in a

Memorandum of Understanding.

E2-2.1. Discipline Specific Considerations:

E2-2.1.1. Arrangements and Outfitting: Provide sufficient support for any additional cabling to sensors.

E2-2.1.2. Structural: None additional.

E2-2.1.3. Mechanical: None additional.

E2-2.1.4. Electrical: Provide necessary power, control and signal cables for monitoring devices associated with the new sensor redundancy.

E2-2.1.5. Automation: None additional.

E2-3. Deliverables Requirements: The Contractor shall provide the following

Deliverables in the development of this Enclosure.

E2-3.1. Deliverables Described in Section 3 of the PWS: The contractor shall provide deliverables in accordance 3.1, 3.2, 3.3, 3.4, 3.6 and 3.7 as described in

Section 3 of the PWS.

E2-3.2. Additional Deliverables: None additional.

E2-4. Delivery Schedule:

No. Activity Due Date

3.6 Virtual Ship Check & Conceptual Design Report 15 Business Days after Kick-off Meeting

5.6 P1 TRANSALT Work Package 15 Business Days after Approved Conceptual

Design

5.7 P2 TRANSALT Work Package 12 Business Days after Submission of P1

5.8 Rev – TRANSALT Work Package 2 Business Days after Submission of P2

5.9 Submittal to USCG/ABS Within 1 Business Day of COR Approval

5.9 Draft Response to ABS Comments 5 Business Days from Posting of ABS Comments on Eagle.org

5 Submittal to ABS for Comment Adjudication Within 1 Business Day of COR Approval

5 Final Deliverables (ABS Approved) 14 June 2021