TANQUE VERDE RECREATION ENHANCEMENT PROJECT PHASE II_SOW.pdf
PDF 202 KB Posted
- Attached to
- Tanque Verde Recreation Enhancement Federal contract opportunity
- Solicitation number
- 127EAX24R0028
- Issued by
- Department of Agriculture Forest Service
About this file
This document is a Statement of Work (SOW) for the Tanque Verde Recreation Enhancement Project Phase II. It outlines the scope of work, location, performance period, submittal requirements, and security needs for this government contract opportunity.
The SOW requires the contractor to furnish all labor, supervision, equipment, and materials necessary to complete work at the Tanque Verde Recreation Site in the Santa Catalina Ranger District of the Coronado National Forest near Tucson, Arizona. The work includes installing a new double vault toilet, sidewalk, pavilion, ramadas, picnic tables, and placing decomposed granite on existing pads and pathways. The performance period is 35 calendar days from the Notice to Proceed. Contractor submittals are required for various materials and components. The contractor is responsible for securing all equipment and materials on-site. This project is part of the broader Tanque Verde Recreation Enhancement opportunity, Solicitation Number 127EAX24R0028, administered by the US Department of Agriculture Forest Service.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Department of Agriculture (USDA)
Statement of Work
Contents Project General Information
1.0 Scope of Work
2.0 Location
Contractor Requirements
3.0 Performance Period
4.0 Government Furnished
5.0 Submittal Log
6.0 Security Requirements
Project
TANQUE VERDE RECREATION ENHANCEMENT PROJECT - PHASE II
General Information
1.0 Scope of Work
This Contract shall furnish all labor, supervision, equipment, and materials necessary to complete work as shown on the plans for the Tanque Verde Recreation Site as shown on the Drawings and outlined in the specifications. This work includes the install of a new double vault toilet, sidewalk, pavilion, ramadas, picnic tables, and placing decomposed granite on existing pads and existing pathways.
2.0 Location
This project is located in the Santa Catalin Ranger District of the Coronado National Forest approximately 23 miles East of Downtown Tucson, AZ. Coordinates to the project location are N 32°15'20.98" W 110°39'44.01".
Contractor Requirements
3.0 Performance Period
The performance period is 35 calendar days from Notice to Proceed.
4.0 Government Furnished
N/A
5.0 Submittal Log
1. 01030 – Noxious Weed Control
Fill material and surfacing source weed free documentation
2. 02213 – Trails & Graded Pads Decomposed Granite Product Data, color
3. 02232 – Aggregate Base Course Product Data
4. 02270 – Rip-Rap Product Data, color
5. 03200 – Concrete Reinforcement
Material Certification
6. 05120 – Structural Steel
Shop Drawings, material Certification
7. 03301 – Cast-in-Place Concrete
Mix Design
8. 13100 – Precast Concrete Toilet Building
Toilet plans, specifications, and warranty information
9. 13600 – Picnic Table
Picnic plans, specifications, and warranty information
6.0 Security Requirements
Contractor shall be responsible for securing all equipment and materials at project site.
| Project |
| General Information |
| 1.0 Scope of Work |
| 2.0 Location |
| Contractor Requirements |
| 3.0 Performance Period |
| 4.0 Government Furnished |
| 5.0 Submittal Log |
| 6.0 Security Requirements |
File details come from the government source that posted it. Updated .