Tabulation of Proposals - FW-PATU 13(1).pdf
PDF 761 KB Posted
- Attached to
- Baltimore Washington Parkway Federal contract opportunity
- Solicitation number
- 693C73-22-C-000010
About this file
This document is a tabulation of bids report for the rehabilitation of Powder Mill Road project. Bluegrass Contracting Corporation submitted the lowest bid of $1,994,563.00 and was awarded the contract. The report provides pricing details for line items such as mobilization, construction surveying and staking, soil erosion control fiber rolls, removal of delineators and signs, removal of guardrail, sawcutting pavement, aggregate topsoil course, and asphalt concrete pavement. Quantities, units, unit pricing, and totals are specified for each line item from all bidding contractors as well as the engineer's estimate. The related federal contract opportunity notice indicates Ardent Company, LLC was awarded contract 693C73-22-C-000010 for $2,363,200.00 on March 21, 2022 for work on the Baltimore Washington Parkway through the Department of Transportation Federal Highway Administration.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Tabulation of Bids - NP BAWA 1(9) 2(9).pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 10/19/21
1 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Solcitation No: 693C73-22-R-000003
Division: Eastern Federal Lands
State: MD County: Prince Georges
Federal Land: Patuxent Research Refuge Opened at: Ashburn, Virginia
Opened by: Emily McCleary
Date: 10/19/21
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Bluegrass Contracting Corporation Lowest offeror $1,994,563.00 1075 Red Mile Road Lexington Kentucky 40504
Kovilic Construction Company, Inc. $2,919,270.00 3721 N. Carnation Street Franklin Park Illinois 60131
Aspen Construction Company $2,930,844.00 3798 State Highway 371 NW Hackensack Minnesota 56452
Estes Bros. Const., Inc. $3,709,584.10 126 Sugar Run Road Jonesville Virginia 24263
Engineer's Estimate $1,765,000.00
Emily McCleary Contract Specialist
19 October 2021
Bluegrass Contracting Corporation 7 December 2021
2 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0020 15101-0000 MOBILIZATION
Bluegrass Contracting Corporation Lump Sum $175,000.00 Kovilic Construction Company, Inc. Lump Sum $200,000.00 Aspen Construction Company Lump Sum $44,945.00 Estes Bros. Const., Inc. Lump Sum $679,185.00 Engineer's Estimate ALL LPSM Lump Sum $142,938.00
A0040 15201-0000 CONSTRUCTION SURVEY AND STAKING
Bluegrass Contracting Corporation Lump Sum $30,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Aspen Construction Company Lump Sum $51,175.00 Estes Bros. Const., Inc. Lump Sum $129,428.00 Engineer's Estimate ALL LPSM Lump Sum $23,000.00
A0060 15401-0000 CONTRACTOR TESTING
Bluegrass Contracting Corporation Lump Sum $34,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Aspen Construction Company Lump Sum $41,000.00 Estes Bros. Const., Inc. Lump Sum $358,800.00 Engineer's Estimate ALL LPSM Lump Sum $31,000.00
A0080 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Bluegrass Contracting Corporation $18.50 $72,150.00 Kovilic Construction Company, Inc. $15.00 $58,500.00 Aspen Construction Company $13.25 $51,675.00 Estes Bros. Const., Inc. $21.52 $83,928.00 Engineer's Estimate 3,900 LNFT $11.50 $44,850.00
A0100 20301-0700 REMOVAL OF DELINEATOR
Bluegrass Contracting Corporation $425.00 $2,975.00 Kovilic Construction Company, Inc. $150.00 $1,050.00 Aspen Construction Company $1,025.00 $7,175.00 Estes Bros. Const., Inc. $97.50 $682.50 Engineer's Estimate 7 EACH $42.00 $294.00
A0120 20301-2400 REMOVAL OF SIGN
Bluegrass Contracting Corporation $320.00 $3,200.00 Kovilic Construction Company, Inc. $250.00 $2,500.00 Aspen Construction Company $1,025.00 $10,250.00 Estes Bros. Const., Inc. $325.00 $3,250.00 Engineer's Estimate 10 EACH $150.00 $1,500.00
3 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0140 20302-1200 REMOVAL OF GUARDRAIL
Bluegrass Contracting Corporation $6.60 $46,200.00 Kovilic Construction Company, Inc. $15.00 $105,000.00 Aspen Construction Company $51.17 $358,190.00 Estes Bros. Const., Inc. $10.92 $76,440.00 Engineer's Estimate 7,000 LNFT $8.85 $61,950.00
A0160 20315-0000 SAWCUTTING PAVEMENT
Bluegrass Contracting Corporation $6.50 $910.00 Kovilic Construction Company, Inc. $10.00 $1,400.00 Aspen Construction Company $41.00 $5,740.00 Estes Bros. Const., Inc. $19.50 $2,730.00 Engineer's Estimate 140 LNFT $10.50 $1,470.00
A0180 31302-0000 AGGREGATE-TOPSOIL COURSE
Bluegrass Contracting Corporation $135.00 $35,100.00 Kovilic Construction Company, Inc. $10.00 $2,600.00 Aspen Construction Company $102.35 $26,611.00 Estes Bros. Const., Inc. $135.53 $35,237.80 Engineer's Estimate 260 SQYD $8.00 $2,080.00
A0200 40101-0200 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3
MILLION ESAL PG 64-22 (TYPE IV ROUGHNESS)
Bluegrass Contracting Corporation $168.00 $327,600.00 Kovilic Construction Company, Inc. $225.00 $438,750.00 Aspen Construction Company $184.25 $359,287.50 Estes Bros. Const., Inc. $211.25 $411,937.50 Engineer's Estimate 1,950 TON $120.00 $234,000.00
A0240 40101-1000 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/4-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3
MILLION ESAL PG 64-22
Bluegrass Contracting Corporation $117.00 $355,680.00 Kovilic Construction Company, Inc. $210.00 $638,400.00 Aspen Construction Company $184.25 $560,120.00 Estes Bros. Const., Inc. $203.13 $617,515.20 Engineer's Estimate 3,040 TON $110.00 $334,400.00
4 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0260 41201-0000 TACK COAT
Bluegrass Contracting Corporation $2,750.00 $27,500.00 Kovilic Construction Company, Inc. $1,000.00 $10,000.00 Aspen Construction Company $1,024.00 $10,240.00 Estes Bros. Const., Inc. $715.00 $7,150.00 Engineer's Estimate 10 TON $600.00 $6,000.00
A0280 41301-1000 ASPHALT PAVEMENT MILLING, 4-INCH DEPTH
Bluegrass Contracting Corporation $8.60 $168,560.00 Kovilic Construction Company, Inc. $27.00 $529,200.00 Aspen Construction Company $10.23 $200,508.00 Estes Bros. Const., Inc. $4.23 $82,908.00 Engineer's Estimate 19,600 SQYD $10.25 $200,900.00
A0300 60703-0000 CLEANING CULVERTS IN PLACE
Bluegrass Contracting Corporation $30.00 $6,600.00 Kovilic Construction Company, Inc. $50.00 $11,000.00 Aspen Construction Company $102.35 $22,517.00 Estes Bros. Const., Inc. $37.44 $8,236.80 Engineer's Estimate 220 LNFT $24.00 $5,280.00
A0320 60706-0000 CLEANING DRAINAGE STRUCTURE (INLETS)
Bluegrass Contracting Corporation $3,400.00 $6,800.00 Kovilic Construction Company, Inc. $250.00 $500.00 Aspen Construction Company $5,117.00 $10,234.00 Estes Bros. Const., Inc. $975.00 $1,950.00 Engineer's Estimate 2 EACH $450.00 $900.00
A0340 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
Bluegrass Contracting Corporation $54.25 $379,750.00 Kovilic Construction Company, Inc. $75.00 $525,000.00 Aspen Construction Company $102.35 $716,450.00 Estes Bros. Const., Inc. $64.35 $450,450.00 Engineer's Estimate 7,000 LNFT $68.00 $476,000.00
A0360 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Bluegrass Contracting Corporation $5,600.00 $16,800.00 Kovilic Construction Company, Inc. $4,500.00 $13,500.00 Aspen Construction Company $10,235.50 $30,706.50 Estes Bros. Const., Inc. $5,720.00 $17,160.00 Engineer's Estimate 3 EACH $5,100.00 $15,300.00
5 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0380 62030-0000 REPOINT STONE MASONRY (HEADWALLS)
Bluegrass Contracting Corporation $185.00 $38,850.00 Kovilic Construction Company, Inc. $25.00 $5,250.00 Aspen Construction Company $41.00 $8,610.00 Estes Bros. Const., Inc. $170.30 $35,763.00 Engineer's Estimate 210 LNFT $36.00 $7,560.00
A0400 62501-0000 TURF ESTABLISHMENT
Bluegrass Contracting Corporation $12,280.00 $614.00 Kovilic Construction Company, Inc. $50,000.00 $2,500.00 Aspen Construction Company $164,000.00 $8,200.00 Estes Bros. Const., Inc. $188,500.00 $9,425.00 Engineer's Estimate 0.05 ACRE $5,200.00 $260.00
A0420 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING (WOOD POST)
Bluegrass Contracting Corporation $115.00 $16,675.00 Kovilic Construction Company, Inc. $50.00 $7,250.00 Aspen Construction Company $154.00 $22,330.00 Estes Bros. Const., Inc. $497.58 $72,149.10 Engineer's Estimate 145 SQFT $55.00 $7,975.00
A0440 63309-0200 DELINEATOR, TYPE 2
Bluegrass Contracting Corporation $90.00 $720.00 Kovilic Construction Company, Inc. $250.00 $2,000.00 Aspen Construction Company $3,100.00 $24,800.00 Estes Bros. Const., Inc. $422.50 $3,380.00 Engineer's Estimate 8 EACH $120.00 $960.00
A0460 63313-1000 RUMBLE STRIP, SHOULDER (MUMBLE STRIP, SHOULDER)
Bluegrass Contracting Corporation $3.00 $26,100.00 Kovilic Construction Company, Inc. $6.00 $52,200.00 Aspen Construction Company $10.50 $91,350.00 Estes Bros. Const., Inc. $3.64 $31,668.00 Engineer's Estimate 8,700 LNFT $1.30 $11,310.00
A0480 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
Bluegrass Contracting Corporation $1.45 $37,265.00 Kovilic Construction Company, Inc. $2.00 $51,400.00 Aspen Construction Company $4.00 $102,800.00 Estes Bros. Const., Inc. $2.02 $51,914.00 Engineer's Estimate 25,700 LNFT $1.15 $29,555.00
6 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0500 63401-1600 PAVEMENT MARKINGS, TYPE H, BROKEN
Bluegrass Contracting Corporation $0.70 $364.00 Kovilic Construction Company, Inc. $1.00 $520.00 Aspen Construction Company $4.00 $2,080.00 Estes Bros. Const., Inc. $4.36 $2,267.20 Engineer's Estimate 520 LNFT $1.40 $728.00
A0520 63405-0050 PAVEMENT MARKINGS, SYMBOLS (BIKE SYMBOL AND THROUGH BIKE LANE-USE ARROW)
Bluegrass Contracting Corporation $675.00 $6,750.00 Kovilic Construction Company, Inc. $700.00 $7,000.00 Aspen Construction Company $1,025.00 $10,250.00 Estes Bros. Const., Inc. $715.00 $7,150.00 Engineer's Estimate 10 EACH $300.00 $3,000.00
A0540 63405-2900 PAVEMENT MARKINGS, TYPE H, TURN ARROW
Bluegrass Contracting Corporation $425.00 $1,275.00 Kovilic Construction Company, Inc. $500.00 $1,500.00 Aspen Construction Company $1,550.00 $4,650.00 Estes Bros. Const., Inc. $975.00 $2,925.00 Engineer's Estimate 3 EACH $210.00 $630.00
A0560 63405-3000 PAVEMENT MARKINGS, TYPE H, STRAIGHT/TURN ARROW COMBINATION
Bluegrass Contracting Corporation $625.00 $625.00 Kovilic Construction Company, Inc. $650.00 $650.00 Aspen Construction Company $1,550.00 $1,550.00 Estes Bros. Const., Inc. $2,002.00 $2,002.00 Engineer's Estimate 1 EACH $280.00 $280.00
A0580 63405-3050 PAVEMENT MARKINGS, TYPE H, "ONLY" WORD MESSAGE
Bluegrass Contracting Corporation $750.00 $1,500.00 Kovilic Construction Company, Inc. $800.00 $1,600.00 Aspen Construction Company $2,050.00 $4,100.00 Estes Bros. Const., Inc. $1,475.50 $2,951.00 Engineer's Estimate 2 EACH $440.00 $880.00
A0600 63501-0000 TEMPORARY TRAFFIC CONTROL
Bluegrass Contracting Corporation Lump Sum $125,000.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 Aspen Construction Company Lump Sum $102,350.00 Estes Bros. Const., Inc. Lump Sum $336,401.00 Engineer's Estimate ALL LPSM Lump Sum $85,000.00
7 out of 7Source Selection Information - See FAR 2.101 & 3.104
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0620 63701-0000 FIELD OFFICE
Bluegrass Contracting Corporation $50,000.00 $50,000.00 Kovilic Construction Company, Inc. $50,000.00 $50,000.00 Aspen Construction Company $40,950.00 $40,950.00 Estes Bros. Const., Inc. $184,600.00 $184,600.00 Engineer's Estimate 1 EACH $35,000.00 $35,000.00
Total Schedule - All Items
Bluegrass Contracting Corporation $1,994,563.00 Kovilic Construction Company, Inc. $2,919,270.00 Aspen Construction Company $2,930,844.00 Estes Bros. Const., Inc. $3,709,584.10 Engineer's Estimate $1,765,000.00
Bid Error Report
1 out of 2
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
No Line Item Errors Found
Source Selection Information - See FAR 2.101 & 3.104
Bid Error Report
2 out of 2
Project No: FW-PATU 13(1)
Project Name: Rehabilitation of Powder Mill Road
Schedule: A
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Estes Bros. Const., Inc. $3,709,584.10 $3,709,584.10
Bluegrass Contracting Corporation $1,994,563.00 $1,994,563.00
Aspen Construction Company $2,930,844.00 $2,930,844.00
Kovilic Construction Company, Inc. $2,919,270.00 $2,919,270.00
The apparent low bidder is 13.01% above the engineer's estimate.
Source Selection Information - See FAR 2.101 & 3.104