Bid Tabulation Report Summary
This is a Bid Tabulation Report for federal contract solicitation 693C73-26-B-000006, issued by the Eastern Federal Lands division for repair work on storm and flood damage affecting multiple roads and trails in West Virginia counties (Grant, Pocahontas, Randolph, Tucker, and Webster) within the Monongahela National Forest. The project includes bridge replacement and slide remediation work. Bids were opened on April 28, 2026, in Ashburn, Virginia, and the contract was awarded to Structural Engineering Group, Inc. on June 11, 2026.
The solicitation encompassed three schedules with base and optional pricing. For Schedule A (Base), four contractors submitted bids ranging from $764,406.70 to $4,553,496.50, with an engineer's estimate of $645,000.00. Schedule B (Option) saw bids from $5,652,024.90 to $8,174,100.00 against an estimate of $9,960,000.00. Schedule C (Option) received bids from $5,959,527.50 to $9,068,551.70 against an estimate of $6,105,000.00. The total combined base and option pricing for the awarded contractor, Structural Engineering Group, Inc., was $12,375,959.10. Line-item pricing details are provided across multiple pages for construction activities including mobilization, clearing and grubbing, culvert removal and installation, riprap placement, structural concrete work, bridge construction, retaining walls, geotechnical work, and erosion control measures. The report was generated on April 29, 2026, by Contract Specialist Emily McCleary.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TABULATION REPORT
Project No. : WV ERFO FS MNGAH921 2018-1(1) Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Contractor Responsive? Base Schedule A Central Southern Construction Corp. $4,553,496.50
Kovilic Construction Company Inc $1,180,500.00 ERon Road Construction LLC $946,991.00 Structural Engineering Group, Inc. $764,406.70 Engineer's Estimate $645,000.00
Contractor Responsive? Total Base Schedule A and Option(s): BC Central Southern Construction Corp. $21,683,838.10
Kovilic Construction Company Inc $18,394,175.00 ERon Road Construction LLC $16,688,337.00 Structural Engineering Group, Inc. $12,375,959.10 Engineer's Estimate $16,710,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Emily McCleary
Contractor Responsive? Option: B Central Southern Construction Corp. $8,061,789.90
Kovilic Construction Company Inc $8,174,100.00 ERon Road Construction LLC $7,803,912.00 Structural Engineering Group, Inc. $5,652,024.90 Engineer's Estimate $9,960,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Contractor Responsive? Option: C Central Southern Construction Corp. $9,068,551.70
Kovilic Construction Company Inc $9,039,575.00 ERon Road Construction LLC $7,937,434.00 Structural Engineering Group, Inc. $5,959,527.50 Engineer's Estimate $6,105,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Project No. : WV ERFO FS
MNGAH921 2018-1
(1)
Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Division: Eastern Federal Lands
Schedule: A Schedule Type: Base Lead Designer:
Solicitation No. : 693C73-26-B-000006 Opened at: Ashburn, Virginia Opened by: Emily McCleary State: WV County: Grant, Pocahontas, Randolph, Tucker, Webster
Federal Land: Monongahela National Forest
Bid Open Date and Time: 04/28/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive Central Southern Construction Corp., 119 Sewald Street, Jacksonville, FL, 32204
$4,553,496.50
Kovilic Construction Company Inc, 3721 N Carnation Street, Franklin Park, IL, 60131
$1,180,500.00
ERon Road Construction LLC, 11938 Mayfield Road Building 1, Chardon, OH, 44024
$946,991.00
Structural Engineering Group, Inc., 38997 E. Colonial Highway, Hamilton, VA, 20158
$764,406.70
Engineer's Estimate $645,000.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Emily McCleary
Emily McCleary
Contract Specialist
28 April 2026
Structural Engineering Group, Inc. 11 June 2026
Project No. : WV ERFO FS MNGAH921 2018-1 (1)
Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Schedule: A Schedule Type: Base
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
A1000 15101-0000 MOBILIZATION Central Southern Construction Corp. $2,111,600.00
ERon Road Construction LLC $271,828.00
Structural Engineering Group, Inc.
$151,320.50
Kovilic Construction Company Inc $100,000.00
Engineer's Estimate ALL LPSM LPSM $79,781.50
A1010 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
Central Southern Construction Corp. $743,000.00
Kovilic Construction Company Inc $50,000.00
ERon Road Construction LLC $23,404.00
Structural Engineering Group, Inc.
$19,737.50
Engineer's Estimate ALL LPSM LPSM $14,000.00
A1020 15401-0000 CONTRACTOR
TESTING
Central Southern Construction Corp. $643,000.00
ERon Road Construction LLC $75,192.00
Kovilic Construction Company Inc $50,000.00
Structural Engineering Group, Inc.
$19,737.50
Engineer's Estimate ALL LPSM LPSM $11,000.00
A1030 15702-6000 SOIL EROSION
CONTROL,
TEMPORARY
STREAM
DIVERSION
Kovilic Construction Company Inc $200,000.00
Central Southern Construction Corp. $50,000.00
Structural Engineering Group, Inc.
$39,474.90
ERon Road Construction LLC $34,882.00
Engineer's Estimate ALL LPSM LPSM $8,500.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1040 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM
Kovilic Construction Company Inc 6.000 $2,500.00 $15,000.00
Central Southern Construction Corp. 6.000 $706.50 $4,239.00
Structural Engineering Group, Inc.
6.000 $460.50 $2,763.00
ERon Road Construction LLC 6.000 $270.00 $1,620.00
Engineer's Estimate 6.000 EACH $770.00 $4,620.00
A1050 15720-0000 STORM WATER
POLLUTION
PREVENTION PLAN
Central Southern Construction Corp. $50,000.00
Kovilic Construction Company Inc $22,000.00
ERon Road Construction LLC $12,705.00
Structural Engineering Group, Inc.
$9,161.30
Engineer's Estimate ALL LPSM LPSM $6,400.00
A1060 20103-0000 CLEARING AND
GRUBBING
Central Southern Construction Corp. 2,750.000 $30.00 $82,500.00
ERon Road Construction LLC 2,750.000 $18.50 $50,875.00
Structural Engineering Group, Inc.
2,750.000 $9.20 $25,300.00
Kovilic Construction Company Inc 2,750.000 $9.00 $24,750.00
Engineer's Estimate 2,750.000 SQYD $15.50 $42,625.00
A1070 20301-1900 REMOVAL OF PIPE
CULVERT
Central Southern Construction Corp. 6.000 $5,000.00 $30,000.00
Kovilic Construction Company Inc 6.000 $5,000.00 $30,000.00
ERon Road Construction LLC 6.000 $2,622.00 $15,732.00
Structural Engineering Group, Inc.
6.000 $2,105.30 $12,631.80
Engineer's Estimate 6.000 EACH $3,500.00 $21,000.00
A1080 20401-0000 ROADWAY
EXCAVATION
Kovilic Construction Company Inc 180.000 $200.00 $36,000.00
Central Southern Construction Corp. 180.000 $100.00 $18,000.00
ERon Road Construction LLC 180.000 $86.00 $15,480.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1080 20401-0000 ROADWAY
EXCAVATION
Structural Engineering Group, Inc.
180.000 $32.90 $5,922.00
Engineer's Estimate 180.000 CUYD $80.00 $14,400.00 A1090 20820-0000 DEWATERING Kovilic Construction
Company Inc $50,000.00
Central Southern Construction Corp. $30,000.00
ERon Road Construction LLC $20,009.00
Structural Engineering Group, Inc.
$3,947.50
Engineer's Estimate ALL LPSM LPSM $27,300.00
A1100 25102-0200 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 265.000 $300.00 $79,500.00
Kovilic Construction Company Inc 265.000 $300.00 $79,500.00
Structural Engineering Group, Inc.
265.000 $151.30 $40,094.50
ERon Road Construction LLC 265.000 $100.00 $26,500.00
Engineer's Estimate 265.000 TON $175.00 $46,375.00
A1110 25102-0300 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 30.000 $350.00 $10,500.00
Kovilic Construction Company Inc 30.000 $350.00 $10,500.00
Structural Engineering Group, Inc.
30.000 $177.60 $5,328.00
ERon Road Construction LLC 30.000 $130.00 $3,900.00
Engineer's Estimate 30.000 TON $324.00 $9,720.00
A1120 30110-0000 AGGREGATE
SURFACE COURSE
Central Southern Construction Corp. 680.000 $204.00 $138,720.00
Structural Engineering Group, Inc.
680.000 $105.30 $71,604.00
Kovilic Construction Company Inc 680.000 $100.00 $68,000.00
ERon Road Construction LLC 680.000 $93.00 $63,240.00
Engineer's Estimate 680.000 TON $130.00 $88,400.00
A1130 30302-1000 DITCH
RECONDITIONING
Structural Engineering Group, Inc.
1,610.000 $35.50 $57,155.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1130 30302-1000 DITCH
RECONDITIONING
Kovilic Construction Company Inc 1,610.000 $25.00 $40,250.00
ERon Road Construction LLC 1,610.000 $21.00 $33,810.00
Central Southern Construction Corp. 1,610.000 $20.00 $32,200.00
Engineer's Estimate 1,610.000 LNFT $14.60 $23,506.00
A1140 30303-2000 AGGREGATE
SURFACE
RECONDITIONING
Kovilic Construction Company Inc 2,045.000 $100.00 $204,500.00
Central Southern Construction Corp. 2,045.000 $37.50 $76,687.50
Structural Engineering Group, Inc.
2,045.000 $14.50 $29,652.50
ERon Road Construction LLC 2,045.000 $5.00 $10,225.00
Engineer's Estimate 2,045.000 SQYD $21.50 $43,967.50
A1150 60103-1920 CONCRETE,
HEADWALL FOR 24
-INCH EQUIVALENT
DIAMETER PIPE
CULVERT
Structural Engineering Group, Inc.
3.000 $5,263.30 $15,789.90
Kovilic Construction Company Inc 3.000 $5,000.00 $15,000.00
ERon Road Construction LLC 3.000 $3,984.00 $11,952.00
Central Southern Construction Corp. 3.000 $2,025.00 $6,075.00
Engineer's Estimate 3.000 EACH $6,040.00 $18,120.00
A1160 60103-1940 CONCRETE,
HEADWALL FOR 30
-INCH EQUIVALENT
DIAMETER PIPE
CULVERT
Structural Engineering Group, Inc.
1.000 $6,579.20 $6,579.20
Kovilic Construction Company Inc 1.000 $6,000.00 $6,000.00
ERon Road Construction LLC 1.000 $4,602.00 $4,602.00
Central Southern Construction Corp. 1.000 $2,475.00 $2,475.00
Engineer's Estimate 1.000 EACH $10,250.00 $10,250.00
A1170 60103-1960 CONCRETE,
HEADWALL FOR 36
-INCH EQUIVALENT
DIAMETER PIPE
CULVERT (33-INCH
EQUIVALENT)
Kovilic Construction Company Inc 2.000 $7,000.00 $14,000.00
Structural Engineering Group, Inc.
2.000 $6,579.20 $13,158.40
ERon Road Construction LLC 2.000 $4,602.00 $9,204.00
Central Southern Construction Corp. 2.000 $3,150.00 $6,300.00
Engineer's Estimate 2.000 EACH $12,400.00 $24,800.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1180 60202-0400 24-INCH
EQUIVALENT
DIAMETER ARCH
OR ELLIPTICAL PIPE
CULVERT
Central Southern Construction Corp. 70.000 $1,000.00 $70,000.00
Structural Engineering Group, Inc.
70.000 $500.00 $35,000.00
ERon Road Construction LLC 70.000 $259.00 $18,130.00
Kovilic Construction Company Inc 70.000 $200.00 $14,000.00
Engineer's Estimate 70.000 LNFT $380.00 $26,600.00
A1190 60202-0500 30-INCH
EQUIVALENT
DIAMETER ARCH
OR ELLIPTICAL PIPE
CULVERT
Central Southern Construction Corp. 33.000 $1,200.00 $39,600.00
Structural Engineering Group, Inc.
33.000 $684.20 $22,578.60
ERon Road Construction LLC 33.000 $417.00 $13,761.00
Kovilic Construction Company Inc 33.000 $250.00 $8,250.00
Engineer's Estimate 33.000 LNFT $560.00 $18,480.00
A1200 60202-0600 36-INCH
EQUIVALENT
DIAMETER ARCH
OR ELLIPTICAL PIPE
CULVERT (33-INCH
EQUIVALENT)
Central Southern Construction Corp. 57.000 $1,400.00 $79,800.00
Structural Engineering Group, Inc.
57.000 $815.80 $46,500.60
ERon Road Construction LLC 57.000 $419.00 $23,883.00
Kovilic Construction Company Inc 57.000 $300.00 $17,100.00
Engineer's Estimate 57.000 LNFT $575.00 $32,775.00
A1210 62502-0000 TURF
ESTABLISHMENT
ERon Road Construction LLC 2,565.000 $33.00 $84,645.00
Central Southern Construction Corp. 2,565.000 $20.00 $51,300.00
Kovilic Construction Company Inc 2,565.000 $10.00 $25,650.00
Structural Engineering Group, Inc.
2,565.000 $1.30 $3,334.50
Engineer's Estimate 2,565.000 SQYD $12.00 $30,780.00
A1220 63501-0000 TEMPORARY
TRAFFIC CONTROL
Central Southern Construction Corp. $100,000.00
Kovilic Construction Company Inc $50,000.00
ERon Road Construction LLC $28,802.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
A1220 63501-0000 TEMPORARY
TRAFFIC CONTROL
Structural Engineering Group, Inc.
$26,316.60
Engineer's Estimate ALL LPSM LPSM $10,600.00 A1230 63701-0000 FIELD OFFICE Structural
Engineering Group, Inc.
1.000 $101,318.90 $101,318.90
Central Southern Construction Corp. 1.000 $98,000.00 $98,000.00
ERon Road Construction LLC 1.000 $92,610.00 $92,610.00
Kovilic Construction Company Inc 1.000 $50,000.00 $50,000.00
Engineer's Estimate 1.000 EACH $31,000.00 $31,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
MNGAH921 2018-1
(1)
Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Division: Eastern Federal Lands
Schedule: B Schedule Type: Option Lead Designer:
Solicitation No. : 693C73-26-B-000006 Opened at: Ashburn, Virginia Opened by: Emily McCleary State: WV County: Grant, Pocahontas, Randolph, Tucker, Webster
Federal Land: Monongahela National Forest
Bid Open Date and Time: 04/28/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive Kovilic Construction Company Inc, 3721 N Carnation Street, Franklin Park, IL, 60131
$8,174,100.00
Central Southern Construction Corp., 119 Sewald Street, Jacksonville, FL, 32204
$8,061,789.90
ERon Road Construction LLC, 11938 Mayfield Road Building 1, Chardon, OH, 44024
$7,803,912.00
Structural Engineering Group, Inc., 38997 E. Colonial Highway, Hamilton, VA, 20158
$5,652,024.90
Engineer's Estimate $9,960,000.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Emily McCleary
Emily McCleary
Contract Specialist
(1)
Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Schedule: B Schedule Type: Option
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
B1000 15101-0000 MOBILIZATION ERon Road Construction LLC $1,262,705.00
Structural Engineering Group, Inc.
$513,817.50
Central Southern Construction Corp. $506,900.00
Kovilic Construction Company Inc $400,000.00
Engineer's Estimate ALL LPSM LPSM $1,210,788.75
B1010 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
Central Southern Construction Corp. $272,000.00
Structural Engineering Group, Inc.
$157,486.70
Kovilic Construction Company Inc $100,000.00
ERon Road Construction LLC $41,033.00
Engineer's Estimate ALL LPSM LPSM $218,000.00
B1020 15401-0000 CONTRACTOR
TESTING
ERon Road Construction LLC $284,960.00
Central Southern Construction Corp. $272,000.00
Structural Engineering Group, Inc.
$145,821.00
Kovilic Construction Company Inc $100,000.00
Engineer's Estimate ALL LPSM LPSM $162,000.00
B1030 15702-4000 SOIL EROSION
CONTROL, FILTER
BAG
Kovilic Construction Company Inc $200,000.00
Central Southern Construction Corp. $10,000.00
Structural Engineering Group, Inc.
$9,332.50
ERon Road Construction LLC $3,033.00
Engineer's Estimate ALL LPSM LPSM $9,100.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1040 15702-5000 SOIL EROSION
CONTROL,
TEMPORARY
DIVERSION BERM
Kovilic Construction Company Inc $250,000.00
ERon Road Construction LLC $55,266.00
Central Southern Construction Corp. $40,000.00
Structural Engineering Group, Inc.
$17,498.50
Engineer's Estimate ALL LPSM LPSM $10,100.00
B1050 15702-6000 SOIL EROSION
CONTROL,
TEMPORARY
STREAM
DIVERSION
Kovilic Construction Company Inc $350,000.00
Structural Engineering Group, Inc.
$74,660.40
ERon Road Construction LLC $40,233.00
Central Southern Construction Corp. $40,000.00
Engineer's Estimate ALL LPSM LPSM $25,000.00
B1060 15705-0100 SOIL EROSION
CONTROL, SILT
FENCE
Structural Engineering Group, Inc.
1,915.000 $15.20 $29,108.00
Central Southern Construction Corp. 1,915.000 $13.50 $25,852.50
ERon Road Construction LLC 1,915.000 $11.00 $21,065.00
Kovilic Construction Company Inc 1,915.000 $10.00 $19,150.00
Engineer's Estimate 1,915.000 LNFT $17.85 $34,182.75
B1070 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM
Kovilic Construction Company Inc 6.000 $2,500.00 $15,000.00
Central Southern Construction Corp. 6.000 $706.50 $4,239.00
ERon Road Construction LLC 6.000 $688.00 $4,128.00
Structural Engineering Group, Inc.
6.000 $414.10 $2,484.60
Engineer's Estimate 6.000 EACH $770.00 $4,620.00
B1080 15720-0000 STORM WATER
POLLUTION
PREVENTION PLAN
Central Southern Construction Corp. $50,000.00
Kovilic Construction Company Inc $30,000.00
Structural Engineering Group, Inc.
$13,998.80
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1080 15720-0000 STORM WATER
POLLUTION
PREVENTION PLAN
ERon Road Construction LLC $12,705.00
Engineer's Estimate ALL LPSM LPSM $6,400.00
B1090 20103-0000 CLEARING AND
GRUBBING
ERon Road Construction LLC 13,130.000 $18.50 $242,905.00
Central Southern Construction Corp. 13,130.000 $15.00 $196,950.00
Kovilic Construction Company Inc 13,130.000 $9.00 $118,170.00
Structural Engineering Group, Inc.
13,130.000 $8.20 $107,666.00
Engineer's Estimate 13,130.000 SQYD $15.50 $203,515.00
B1100 20301-0300 REMOVAL OF BOX
CULVERT
Central Southern Construction Corp. 1.000 $40,000.00 $40,000.00
Structural Engineering Group, Inc.
1.000 $32,663.90 $32,663.90
Kovilic Construction Company Inc 1.000 $20,000.00 $20,000.00
ERon Road Construction LLC 1.000 $14,741.00 $14,741.00
Engineer's Estimate 1.000 EACH $39,300.00 $39,300.00
B1110 20301-0400 REMOVAL OF
BRIDGE (TIMBER
TRAIL BRIDGE)
Central Southern Construction Corp. 2.000 $45,000.00 $90,000.00
Structural Engineering Group, Inc.
2.000 $41,996.50 $83,993.00
Kovilic Construction Company Inc 2.000 $25,000.00 $50,000.00
ERon Road Construction LLC 2.000 $7,812.00 $15,624.00
Engineer's Estimate 2.000 EACH $20,200.00 $40,400.00
B1120 20301-1900 REMOVAL OF PIPE
CULVERT
Central Southern Construction Corp. 4.000 $5,000.00 $20,000.00
Kovilic Construction Company Inc 4.000 $5,000.00 $20,000.00
Structural Engineering Group, Inc.
4.000 $2,333.10 $9,332.40
ERon Road Construction LLC 4.000 $1,595.00 $6,380.00
Engineer's Estimate 4.000 EACH $3,500.00 $14,000.00
B1130 20303-1600 REMOVAL OF
PAVEMENT,
ASPHALT
ERon Road Construction LLC 1,315.000 $27.00 $35,505.00
Kovilic Construction Company Inc 1,315.000 $27.00 $35,505.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1130 20303-1600 REMOVAL OF
PAVEMENT,
ASPHALT
Structural Engineering Group, Inc.
1,315.000 $23.30 $30,639.50
Central Southern Construction Corp. 1,315.000 $22.50 $29,587.50
Engineer's Estimate 1,315.000 SQYD $21.00 $27,615.00
B1140 20401-0000 ROADWAY
EXCAVATION
Kovilic Construction Company Inc 10,940.000 $150.00 $1,641,000.00
Central Southern Construction Corp. 10,940.000 $80.00 $875,200.00
ERon Road Construction LLC 10,940.000 $76.00 $831,440.00
Structural Engineering Group, Inc.
10,940.000 $60.70 $664,058.00
Engineer's Estimate 10,940.000 CUYD $80.00 $875,200.00 B1150 20410-0000 SELECT BORROW Structural
Engineering Group, Inc.
4,460.000 $168.00 $749,280.00
Kovilic Construction Company Inc 4,460.000 $150.00 $669,000.00
Central Southern Construction Corp. 4,460.000 $120.00 $535,200.00
ERon Road Construction LLC 4,460.000 $116.00 $517,360.00
Engineer's Estimate 4,460.000 CUYD $82.00 $365,720.00
B1160 20420-0000 EMBANKMENT
CONSTRUCTION
Kovilic Construction Company Inc 100.000 $200.00 $20,000.00
ERon Road Construction LLC 100.000 $187.00 $18,700.00
Central Southern Construction Corp. 100.000 $100.00 $10,000.00
Structural Engineering Group, Inc.
100.000 $17.50 $1,750.00
Engineer's Estimate 100.000 CUYD $120.00 $12,000.00
B1170 20703-2000 GEOGRID,
STABILIZATION
Central Southern Construction Corp. 24,500.000 $9.00 $220,500.00
Kovilic Construction Company Inc 24,500.000 $9.00 $220,500.00
ERon Road Construction LLC 24,500.000 $6.00 $147,000.00
Structural Engineering Group, Inc.
24,500.000 $5.20 $127,400.00
Engineer's Estimate 24,500.000 SQYD $5.50 $134,750.00
B1180 20801-0000 STRUCTURE
EXCAVATION
Kovilic Construction Company Inc 165.000 $150.00 $24,750.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1180 20801-0000 STRUCTURE
EXCAVATION
Central Southern Construction Corp. 165.000 $100.00 $16,500.00
ERon Road Construction LLC 165.000 $84.00 $13,860.00
Structural Engineering Group, Inc.
165.000 $40.80 $6,732.00
Engineer's Estimate 165.000 CUYD $140.00 $23,100.00 B1190 20820-0000 DEWATERING Kovilic Construction
Company Inc $300,000.00
Central Southern Construction Corp. $30,000.00
ERon Road Construction LLC $26,845.00
Structural Engineering Group, Inc.
$23,331.40
Engineer's Estimate ALL LPSM LPSM $13,650.00
B1200 25102-0200 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 130.000 $300.00 $39,000.00
Kovilic Construction Company Inc 130.000 $300.00 $39,000.00
Structural Engineering Group, Inc.
130.000 $140.00 $18,200.00
ERon Road Construction LLC 130.000 $119.00 $15,470.00
Engineer's Estimate 130.000 TON $175.00 $22,750.00
B1210 25102-0300 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 35.000 $350.00 $12,250.00
Kovilic Construction Company Inc 35.000 $350.00 $12,250.00
Structural Engineering Group, Inc.
35.000 $198.30 $6,940.50
ERon Road Construction LLC 35.000 $168.00 $5,880.00
Engineer's Estimate 35.000 TON $324.00 $11,340.00
B1220 25102-0400 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 585.000 $400.00 $234,000.00
Kovilic Construction Company Inc 585.000 $400.00 $234,000.00
Structural Engineering Group, Inc.
585.000 $175.00 $102,375.00
ERon Road Construction LLC 585.000 $115.00 $67,275.00
Engineer's Estimate 585.000 TON $155.00 $90,675.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1230 25102-0500 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 65.000 $500.00 $32,500.00
Kovilic Construction Company Inc 65.000 $450.00 $29,250.00
Structural Engineering Group, Inc.
65.000 $192.50 $12,512.50
ERon Road Construction LLC 65.000 $128.00 $8,320.00
Engineer's Estimate 65.000 TON $130.00 $8,450.00
B1240 25701-0600 CONTRACTOR
FURNISHED
REINFORCED SOIL
SLOPE DESIGN
ERon Road Construction LLC $280,412.00
Structural Engineering Group, Inc.
$93,325.50
Central Southern Construction Corp. $50,000.00
Kovilic Construction Company Inc $50,000.00
Engineer's Estimate ALL LPSM LPSM $80,600.00
B1250 26303-0000 CONCRETE
LAGGING
Kovilic Construction Company Inc 5,955.000 $100.00 $595,500.00
Central Southern Construction Corp. 5,955.000 $90.48 $538,808.40
ERon Road Construction LLC 5,955.000 $61.00 $363,255.00
Structural Engineering Group, Inc.
5,955.000 $33.80 $201,279.00
Engineer's Estimate 5,955.000 SQFT $155.00 $923,025.00
B1260 30101-4000 AGGREGATE BASE
GRADING C OR D
Central Southern Construction Corp. 700.000 $204.00 $142,800.00
ERon Road Construction LLC 700.000 $187.00 $130,900.00
Kovilic Construction Company Inc 700.000 $100.00 $70,000.00
Structural Engineering Group, Inc.
700.000 $93.30 $65,310.00
Engineer's Estimate 700.000 TON $115.00 $80,500.00
B1270 30110-0000 AGGREGATE
SURFACE COURSE
ERon Road Construction LLC 270.000 $207.00 $55,890.00
Central Southern Construction Corp. 270.000 $204.00 $55,080.00
Kovilic Construction Company Inc 270.000 $100.00 $27,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1270 30110-0000 AGGREGATE
SURFACE COURSE
Structural Engineering Group, Inc.
270.000 $93.30 $25,191.00
Engineer's Estimate 270.000 TON $130.00 $35,100.00
B1280 30302-1000 DITCH
RECONDITIONING
Structural Engineering Group, Inc.
1,535.000 $31.50 $48,352.50
Kovilic Construction Company Inc 1,535.000 $25.00 $38,375.00
Central Southern Construction Corp. 1,535.000 $20.00 $30,700.00
ERon Road Construction LLC 1,535.000 $19.00 $29,165.00
Engineer's Estimate 1,535.000 LNFT $14.60 $22,411.00
B1290 30303-2000 AGGREGATE
SURFACE
RECONDITIONING
Central Southern Construction Corp. 475.000 $37.50 $17,812.50
Kovilic Construction Company Inc 475.000 $27.00 $12,825.00
Structural Engineering Group, Inc.
475.000 $15.10 $7,172.50
ERon Road Construction LLC 475.000 $5.00 $2,375.00
Engineer's Estimate 475.000 SQYD $21.50 $10,212.50
B1300 40301-0100 ASPHALT
CONCRETE
PAVEMENT, TYPE 1
Central Southern Construction Corp. 230.000 $500.00 $115,000.00
ERon Road Construction LLC 230.000 $356.00 $81,880.00
Kovilic Construction Company Inc 230.000 $350.00 $80,500.00
Structural Engineering Group, Inc.
230.000 $347.60 $79,948.00
Engineer's Estimate 230.000 TON $353.00 $81,190.00
B1310 55201-0200 STRUCTURAL
CONCRETE, CLASS
A (AE)
ERon Road Construction LLC 20.000 $6,674.00 $133,480.00
Kovilic Construction Company Inc 20.000 $5,000.00 $100,000.00
Structural Engineering Group, Inc.
20.000 $3,499.70 $69,994.00
Central Southern Construction Corp. 20.000 $3,000.00 $60,000.00
Engineer's Estimate 20.000 CUYD $2,200.00 $44,000.00
B1320 55401-2000 REINFORCING
STEEL, EPOXY
COATED
ERon Road Construction LLC 1,600.000 $23.00 $36,800.00
Central Southern Construction Corp. 1,600.000 $20.00 $32,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1320 55401-2000 REINFORCING
STEEL, EPOXY
COATED
Kovilic Construction Company Inc 1,600.000 $5.00 $8,000.00
Structural Engineering Group, Inc.
1,600.000 $2.60 $4,160.00
Engineer's Estimate 1,600.000 LB $5.00 $8,000.00
B1330 55505-0000 STRUCTURAL STEEL
SOLDIER PILE
Central Southern Construction Corp. 2,970.000 $370.50 $1,100,385.00
Structural Engineering Group, Inc.
2,970.000 $350.00 $1,039,500.00
ERon Road Construction LLC 2,970.000 $333.00 $989,010.00
Kovilic Construction Company Inc 2,970.000 $200.00 $594,000.00
Engineer's Estimate 2,970.000 LNFT $280.00 $831,600.00
B1340 55601-1300 BRIDGE RAILING,
TIMBER
ERon Road Construction LLC 170.000 $738.00 $125,460.00
Central Southern Construction Corp. 170.000 $350.00 $59,500.00
Kovilic Construction Company Inc 170.000 $300.00 $51,000.00
Structural Engineering Group, Inc.
170.000 $145.80 $24,786.00
Engineer's Estimate 170.000 LNFT $155.00 $26,350.00
B1350 55701-2000 STRUCTURAL
TIMBER AND
LUMBER, TREATED
Kovilic Construction Company Inc 6.000 $60,000.00 $360,000.00
Structural Engineering Group, Inc.
6.000 $28,137.60 $168,825.60
ERon Road Construction LLC 6.000 $24,379.00 $146,274.00
Central Southern Construction Corp. 6.000 $20,000.00 $120,000.00
Engineer's Estimate 6.000 MFBM $16,300.00 $97,800.00 B1360 56401-0000 BEARING DEVICE Central Southern
Construction Corp. 10.000 $5,000.00 $50,000.00
Structural Engineering Group, Inc.
10.000 $2,449.80 $24,498.00
ERon Road Construction LLC 10.000 $2,033.00 $20,330.00
Kovilic Construction Company Inc 10.000 $1,000.00 $10,000.00
Engineer's Estimate 10.000 EACH $1,950.00 $19,500.00
B1370 56501-0300 DRILLED SHAFT, 30-
INCH DIAMETER
Central Southern Construction Corp. 2,150.000 $656.50 $1,411,475.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1370 56501-0300 DRILLED SHAFT, 30-
INCH DIAMETER
ERon Road Construction LLC 2,150.000 $394.00 $847,100.00
Kovilic Construction Company Inc 2,150.000 $350.00 $752,500.00
Structural Engineering Group, Inc.
2,150.000 $93.30 $200,595.00
Engineer's Estimate 2,150.000 LNFT $1,660.00 $3,569,000.00
B1380 60103-0140 CONCRETE,
HEADWALL FOR 24
-INCH PIPE
CULVERT
Kovilic Construction Company Inc 2.000 $5,000.00 $10,000.00
Structural Engineering Group, Inc.
2.000 $4,666.30 $9,332.60
ERon Road Construction LLC 2.000 $3,984.00 $7,968.00
Central Southern Construction Corp. 2.000 $2,025.00 $4,050.00
Engineer's Estimate 2.000 EACH $6,350.00 $12,700.00
B1390 60103-0260 CONCRETE,
HEADWALL FOR 60
-INCH PIPE
CULVERT
Central Southern Construction Corp. 2.000 $21,150.00 $42,300.00
Structural Engineering Group, Inc.
2.000 $18,665.10 $37,330.20
Kovilic Construction Company Inc 2.000 $15,000.00 $30,000.00
ERon Road Construction LLC 2.000 $10,834.00 $21,668.00
Engineer's Estimate 2.000 EACH $17,300.00 $34,600.00
B1400 60201-0400 12-INCH PIPE
CULVERT
Central Southern Construction Corp. 11.000 $700.00 $7,700.00
Structural Engineering Group, Inc.
11.000 $233.30 $2,566.30
ERon Road Construction LLC 11.000 $170.00 $1,870.00
Kovilic Construction Company Inc 11.000 $150.00 $1,650.00
Engineer's Estimate 11.000 LNFT $310.00 $3,410.00
B1410 60201-0800 24-INCH PIPE
CULVERT
Central Southern Construction Corp. 48.000 $1,000.00 $48,000.00
Structural Engineering Group, Inc.
48.000 $280.00 $13,440.00
Kovilic Construction Company Inc 48.000 $250.00 $12,000.00
ERon Road Construction LLC 48.000 $141.00 $6,768.00
Engineer's Estimate 48.000 LNFT $280.00 $13,440.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1420 60201-1400 60-INCH PIPE
CULVERT
Central Southern Construction Corp. 97.000 $1,900.00 $184,300.00
Structural Engineering Group, Inc.
97.000 $1,283.20 $124,470.40
Kovilic Construction Company Inc 97.000 $1,000.00 $97,000.00
ERon Road Construction LLC 97.000 $802.00 $77,794.00
Engineer's Estimate 97.000 LNFT $555.00 $53,835.00
B1430 60202-0600 36-INCH
EQUIVALENT
DIAMETER ARCH
OR ELLIPTICAL PIPE
CULVERT
Central Southern Construction Corp. 35.000 $1,700.00 $59,500.00
Structural Engineering Group, Inc.
35.000 $699.90 $24,496.50
Kovilic Construction Company Inc 35.000 $500.00 $17,500.00
ERon Road Construction LLC 35.000 $415.00 $14,525.00
Engineer's Estimate 35.000 LNFT $575.00 $20,125.00
B1440 60502-0000 GEOCOMPOSITE
UNDERDRAIN
SYSTEM
Structural Engineering Group, Inc.
545.000 $93.30 $50,848.50
Central Southern Construction Corp. 545.000 $60.00 $32,700.00
ERon Road Construction LLC 545.000 $47.00 $25,615.00
Kovilic Construction Company Inc 545.000 $45.00 $24,525.00
Engineer's Estimate 545.000 LNFT $130.00 $70,850.00
B1450 60704-0000 CLEANING
CULVERT IN PLACE
Central Southern Construction Corp. 1.000 $6,000.00 $6,000.00
ERon Road Construction LLC 1.000 $3,192.00 $3,192.00
Structural Engineering Group, Inc.
1.000 $2,333.10 $2,333.10
Kovilic Construction Company Inc 1.000 $2,000.00 $2,000.00
Engineer's Estimate 1.000 EACH $3,170.00 $3,170.00
B1460 61010-0000 DRAINAGE WEEP
HOLE
Central Southern Construction Corp. 11.000 $1,000.00 $11,000.00
ERon Road Construction LLC 11.000 $908.00 $9,988.00
Kovilic Construction Company Inc 11.000 $500.00 $5,500.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
B1460 61010-0000 DRAINAGE WEEP
HOLE
Structural Engineering Group, Inc.
11.000 $70.00 $770.00
Engineer's Estimate 11.000 EACH $2,215.00 $24,365.00
B1470 62502-0000 TURF
ESTABLISHMENT
ERon Road Construction LLC 11,580.000 $35.00 $405,300.00
Central Southern Construction Corp. 11,580.000 $15.00 $173,700.00
Kovilic Construction Company Inc 11,580.000 $5.00 $57,900.00
Structural Engineering Group, Inc.
11,580.000 $1.20 $13,896.00
Engineer's Estimate 11,580.000 SQYD $12.00 $138,960.00
B1480 62901-0000 ROLLED EROSION
CONTROL
PRODUCT
Structural Engineering Group, Inc.
2,750.000 $122.50 $336,875.00
ERon Road Construction LLC 2,750.000 $81.00 $222,750.00
Central Southern Construction Corp. 2,750.000 $13.20 $36,300.00
Kovilic Construction Company Inc 2,750.000 $5.00 $13,750.00
Engineer's Estimate 2,750.000 SQYD $10.00 $27,500.00
B1490 62903-0000 CELLULAR
CONFINEMENT
SYSTEM
Central Southern Construction Corp. 20.000 $1,000.00 $20,000.00
ERon Road Construction LLC 20.000 $525.00 $10,500.00
Structural Engineering Group, Inc.
20.000 $332.50 $6,650.00
Kovilic Construction Company Inc 20.000 $250.00 $5,000.00
Engineer's Estimate 20.000 SQYD $55.00 $1,100.00
B1500 63501-0000 TEMPORARY
TRAFFIC CONTROL
Kovilic Construction Company Inc $250,000.00
ERon Road Construction LLC $61,210.00
Central Southern Construction Corp. $50,000.00
Structural Engineering Group, Inc.
$34,997.00
Engineer's Estimate ALL LPSM LPSM $164,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
MNGAH921 2018-1
(1)
Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Division: Eastern Federal Lands
Schedule: C Schedule Type: Option Lead Designer:
Solicitation No. : 693C73-26-B-000006 Opened at: Ashburn, Virginia Opened by: Emily McCleary State: WV County: Grant, Pocahontas, Randolph, Tucker, Webster
Federal Land: Monongahela National Forest
Bid Open Date and Time: 04/28/2026
Contract Awarded to: Award Date:
Contractor Comment Bid Amount Responsive Central Southern Construction Corp., 119 Sewald Street, Jacksonville, FL, 32204
$9,068,551.70
Kovilic Construction Company Inc, 3721 N Carnation Street, Franklin Park, IL, 60131
$9,039,575.00
ERon Road Construction LLC, 11938 Mayfield Road Building 1, Chardon, OH, 44024
$7,937,434.00
Structural Engineering Group, Inc., 38997 E. Colonial Highway, Hamilton, VA, 20158
$5,959,527.50
Engineer's Estimate $6,105,000.00
I certify that this Bid Tabulation reflects the offers received for this solicitation
Signed:
Title:
Date:
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
Generated by : Emily McCleary
Emily McCleary
Contract Specialist
(1)
Project Name: Repair storm & flood damage on multiple roads & trails, including bridge replacement and slides
Schedule: C Schedule Type: Option
Line Item Number
Pay Item Number Description Contractor Quantity Unit Unit Price Amount
C1000 15101-0000 MOBILIZATION ERon Road Construction LLC $1,599,331.00
Structural Engineering Group, Inc.
$745,116.80
Kovilic Construction Company Inc $500,000.00
Central Southern Construction Corp. $436,700.00
Engineer's Estimate ALL LPSM LPSM $738,687.00
C1010 15201-0000 CONSTRUCTION
SURVEY AND
STAKING
Central Southern Construction Corp. $272,000.00
Structural Engineering Group, Inc.
$160,531.70
Kovilic Construction Company Inc $150,000.00
ERon Road Construction LLC $59,954.00
Engineer's Estimate ALL LPSM LPSM $133,000.00
C1020 15401-0000 CONTRACTOR
TESTING
ERon Road Construction LLC $309,521.00
Central Southern Construction Corp. $272,000.00
Structural Engineering Group, Inc.
$172,422.90
Kovilic Construction Company Inc $150,000.00
Engineer's Estimate ALL LPSM LPSM $99,000.00
C1030 15702-4000 SOIL EROSION
CONTROL, FILTER
BAG
Kovilic Construction Company Inc $200,000.00
Central Southern Construction Corp. $15,000.00
Structural Engineering Group, Inc.
$9,513.00
ERon Road Construction LLC $4,840.00
Engineer's Estimate ALL LPSM LPSM $9,100.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1040 15702-5000 SOIL EROSION
CONTROL,
TEMPORARY
DIVERSION BERM
Kovilic Construction Company Inc $400,000.00
ERon Road Construction LLC $105,988.00
Structural Engineering Group, Inc.
$45,186.70
Central Southern Construction Corp. $40,000.00
Engineer's Estimate ALL LPSM LPSM $10,100.00
C1050 15702-6000 SOIL EROSION
CONTROL,
TEMPORARY
STREAM
DIVERSION
Kovilic Construction Company Inc $400,000.00
Structural Engineering Group, Inc.
$136,749.20
ERon Road Construction LLC $52,511.00
Central Southern Construction Corp. $40,000.00
Engineer's Estimate ALL LPSM LPSM $50,000.00
C1060 15705-0100 SOIL EROSION
CONTROL, SILT
FENCE
Structural Engineering Group, Inc.
1,190.000 $15.50 $18,445.00
ERon Road Construction LLC 1,190.000 $14.00 $16,660.00
Central Southern Construction Corp. 1,190.000 $13.50 $16,065.00
Kovilic Construction Company Inc 1,190.000 $10.00 $11,900.00
Engineer's Estimate 1,190.000 LNFT $17.85 $21,241.50
C1070 15706-0200 SOIL EROSION
CONTROL, CHECK
DAM
Kovilic Construction Company Inc 14.000 $2,500.00 $35,000.00
Central Southern Construction Corp. 14.000 $706.50 $9,891.00
Structural Engineering Group, Inc.
14.000 $422.10 $5,909.40
ERon Road Construction LLC 14.000 $337.00 $4,718.00
Engineer's Estimate 14.000 EACH $770.00 $10,780.00
C1080 15720-0000 STORM WATER
POLLUTION
PREVENTION PLAN
Central Southern Construction Corp. $50,000.00
Kovilic Construction Company Inc $50,000.00
Structural Engineering Group, Inc.
$47,565.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1080 15720-0000 STORM WATER
POLLUTION
PREVENTION PLAN
ERon Road Construction LLC $12,705.00
Engineer's Estimate ALL LPSM LPSM $12,800.00
C1090 20103-0000 CLEARING AND
GRUBBING
ERon Road Construction LLC 14,720.000 $18.00 $264,960.00
Central Southern Construction Corp. 14,720.000 $15.00 $220,800.00
Kovilic Construction Company Inc 14,720.000 $9.00 $132,480.00
Structural Engineering Group, Inc.
14,720.000 $8.30 $122,176.00
Engineer's Estimate 14,720.000 SQYD $15.50 $228,160.00
C1100 20301-0400 REMOVAL OF
BRIDGE (STEEL
TRAIL BRIDGE)
Kovilic Construction Company Inc 2.000 $100,000.00 $200,000.00
Structural Engineering Group, Inc.
2.000 $89,184.30 $178,368.60
Central Southern Construction Corp. 2.000 $40,000.00 $80,000.00
ERon Road Construction LLC 2.000 $9,146.00 $18,292.00
Engineer's Estimate 2.000 EACH $97,500.00 $195,000.00
C1110 20301-0400 REMOVAL OF
BRIDGE (TIMBER
TRAIL BRIDGE)
Kovilic Construction Company Inc 1.000 $100,000.00 $100,000.00
Structural Engineering Group, Inc.
1.000 $49,943.20 $49,943.20
Central Southern Construction Corp. 1.000 $30,000.00 $30,000.00
ERon Road Construction LLC 1.000 $9,146.00 $9,146.00
Engineer's Estimate 1.000 EACH $20,200.00 $20,200.00
C1120 20301-1900 REMOVAL OF PIPE
CULVERT
Kovilic Construction Company Inc 10.000 $5,000.00 $50,000.00
Central Southern Construction Corp. 10.000 $3,500.00 $35,000.00
ERon Road Construction LLC 10.000 $2,661.00 $26,610.00
Structural Engineering Group, Inc.
10.000 $2,378.20 $23,782.00
Engineer's Estimate 10.000 EACH $3,500.00 $35,000.00
C1130 20304-8000 REMOVAL OF
WINGWALL
CONCRETE
Kovilic Construction Company Inc $85,000.00
ERon Road Construction LLC $43,091.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1130 20304-8000 REMOVAL OF
WINGWALL
CONCRETE
Central Southern Construction Corp. $10,000.00
Structural Engineering Group, Inc.
$8,918.40
Engineer's Estimate ALL LPSM LPSM $8,500.00
C1140 20401-0000 ROADWAY
EXCAVATION
Kovilic Construction Company Inc 3,665.000 $200.00 $733,000.00
Central Southern Construction Corp. 3,665.000 $100.00 $366,500.00
ERon Road Construction LLC 3,665.000 $85.00 $311,525.00
Structural Engineering Group, Inc.
3,665.000 $65.40 $239,691.00
Engineer's Estimate 3,665.000 CUYD $80.00 $293,200.00 C1150 20402-0000 SUBEXCAVATION Kovilic Construction
Company Inc 720.000 $200.00 $144,000.00
Central Southern Construction Corp. 720.000 $150.00 $108,000.00
ERon Road Construction LLC 720.000 $98.00 $70,560.00
Structural Engineering Group, Inc.
720.000 $65.40 $47,088.00
Engineer's Estimate 720.000 CUYD $75.00 $54,000.00 C1160 20410-0000 SELECT BORROW Structural
Engineering Group, Inc.
1,090.000 $211.70 $230,753.00
Kovilic Construction Company Inc 1,090.000 $200.00 $218,000.00
ERon Road Construction LLC 1,090.000 $167.00 $182,030.00
Central Southern Construction Corp. 1,090.000 $125.00 $136,250.00
Engineer's Estimate 1,090.000 CUYD $82.00 $89,380.00
C1170 20420-0000 EMBANKMENT
CONSTRUCTION
Kovilic Construction Company Inc 665.000 $350.00 $232,750.00
ERon Road Construction LLC 665.000 $175.00 $116,375.00
Central Southern Construction Corp. 665.000 $80.00 $53,200.00
Structural Engineering Group, Inc.
665.000 $20.20 $13,433.00
Engineer's Estimate 665.000 CUYD $120.00 $79,800.00 C1180 20421-0000 ROCK EXCAVATION Central Southern
Construction Corp. 17.000 $1,200.00 $20,400.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1180 20421-0000 ROCK EXCAVATION Kovilic Construction Company Inc 17.000 $1,000.00 $17,000.00
ERon Road Construction LLC 17.000 $165.00 $2,805.00
Structural Engineering Group, Inc.
17.000 $101.10 $1,718.70
Engineer's Estimate 17.000 CUYD $650.00 $11,050.00
C1190 20703-2000 GEOGRID,
STABILIZATION
Kovilic Construction Company Inc 425.000 $27.00 $11,475.00
Central Southern Construction Corp. 425.000 $20.00 $8,500.00
ERon Road Construction LLC 425.000 $15.00 $6,375.00
Structural Engineering Group, Inc.
425.000 $8.30 $3,527.50
Engineer's Estimate 425.000 SQYD $5.50 $2,337.50
C1200 20801-0000 STRUCTURE
EXCAVATION
Kovilic Construction Company Inc 550.000 $150.00 $82,500.00
ERon Road Construction LLC 550.000 $104.00 $57,200.00
Central Southern Construction Corp. 550.000 $100.00 $55,000.00
Structural Engineering Group, Inc.
550.000 $53.50 $29,425.00
Engineer's Estimate 550.000 CUYD $140.00 $77,000.00 C1210 20802-0000 FOUNDATION FILL Central Southern
Construction Corp. 100.000 $360.00 $36,000.00
Structural Engineering Group, Inc.
100.000 $154.60 $15,460.00
Kovilic Construction Company Inc 100.000 $150.00 $15,000.00
ERon Road Construction LLC 100.000 $66.00 $6,600.00
Engineer's Estimate 100.000 CUYD $160.00 $16,000.00
C1220 20803-0000 STRUCTURAL
BACKFILL
Central Southern Construction Corp. 220.000 $360.00 $79,200.00
Structural Engineering Group, Inc.
220.000 $237.80 $52,316.00
ERon Road Construction LLC 220.000 $216.00 $47,520.00
Kovilic Construction Company Inc 220.000 $150.00 $33,000.00
Engineer's Estimate 220.000 CUYD $110.00 $24,200.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1230 20820-0000 DEWATERING Kovilic Construction Company Inc $300,000.00
Structural Engineering Group, Inc.
$65,401.80
ERon Road Construction LLC $36,900.00
Central Southern Construction Corp. $35,000.00
Engineer's Estimate ALL LPSM LPSM $31,850.00
C1240 25102-0200 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 1,295.000 $300.00 $388,500.00
Kovilic Construction Company Inc 1,295.000 $300.00 $388,500.00
Structural Engineering Group, Inc.
1,295.000 $160.50 $207,847.50
ERon Road Construction LLC 1,295.000 $113.00 $146,335.00
Engineer's Estimate 1,295.000 TON $175.00 $226,625.00
C1250 25102-0300 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 122.000 $350.00 $42,700.00
Kovilic Construction Company Inc 122.000 $350.00 $42,700.00
Structural Engineering Group, Inc.
122.000 $196.20 $23,936.40
ERon Road Construction LLC 122.000 $132.00 $16,104.00
Engineer's Estimate 122.000 TON $324.00 $39,528.00
C1260 25102-0400 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 970.000 $400.00 $388,000.00
Kovilic Construction Company Inc 970.000 $400.00 $388,000.00
Structural Engineering Group, Inc.
970.000 $172.40 $167,228.00
ERon Road Construction LLC 970.000 $120.00 $116,400.00
Engineer's Estimate 970.000 TON $155.00 $150,350.00
C1270 25102-0500 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 210.000 $500.00 $105,000.00
Kovilic Construction Company Inc 210.000 $450.00 $94,500.00
Structural Engineering Group, Inc.
210.000 $208.10 $43,701.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1270 25102-0500 PLACED RIPRAP,
METHOD A, CLASS
ERon Road Construction LLC 210.000 $121.00 $25,410.00
Engineer's Estimate 210.000 TON $130.00 $27,300.00
C1280 25102-0600 PLACED RIPRAP,
METHOD A, CLASS
Central Southern Construction Corp. 300.000 $550.00 $165,000.00
Kovilic Construction Company Inc 300.000 $500.00 $150,000.00
Structural Engineering Group, Inc.
300.000 $208.10 $62,430.00
ERon Road Construction LLC 300.000 $123.00 $36,900.00
Engineer's Estimate 300.000 TON $186.00 $55,800.00
C1290 25302-1000 GABIONS,
GALVANIZED OR
ALUMINIZED
COATED
Kovilic Construction Company Inc 30.000 $1,000.00 $30,000.00
Central Southern Construction Corp. 30.000 $800.00 $24,000.00
Structural Engineering Group, Inc.
30.000 $755.10 $22,653.00
ERon Road Construction LLC 30.000 $742.00 $22,260.00
Engineer's Estimate 30.000 CUYD $493.00 $14,790.00
C1300 25302-2000 GABIONS,
POLYVINYL
CHLORIDE COATED
Kovilic Construction Company Inc 172.000 $1,000.00 $172,000.00
ERon Road Construction LLC 172.000 $974.00 $167,528.00
Central Southern Construction Corp. 172.000 $850.00 $146,200.00
Structural Engineering Group, Inc.
172.000 $755.10 $129,877.20
Engineer's Estimate 172.000 CUYD $700.00 $120,400.00
C1310 25305-1000 REVET MATTRESS,
GALVANIZED OR
ALUMINIZED
COATED
Kovilic Construction Company Inc 380.000 $500.00 $190,000.00
Central Southern Construction Corp. 380.000 $450.00 $171,000.00
Structural Engineering Group, Inc.
380.000 $410.20 $155,876.00
ERon Road Construction LLC 380.000 $385.00 $146,300.00
Engineer's Estimate 380.000 SQYD $420.00 $159,600.00
C1320 25501-2000 MECHANICALLY
STABILIZED EARTH
WALL, GABION
FACE
Central Southern Construction Corp. 2,125.000 $575.00 $1,221,875.00
ERon Road Construction LLC 2,125.000 $301.00 $639,625.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1320 25501-2000 MECHANICALLY
STABILIZED EARTH
WALL, GABION
FACE
Structural Engineering Group, Inc.
2,125.000 $166.50 $353,812.50
Kovilic Construction Company Inc 2,125.000 $110.00 $233,750.00
Engineer's Estimate 2,125.000 SQFT $116.00 $246,500.00
C1330 25801-0000 REINFORCED
CONCRETE
RETAINING WALL
Central Southern Construction Corp. 580.000 $1,200.00 $696,000.00
ERon Road Construction LLC 580.000 $279.00 $161,820.00
Structural Engineering Group, Inc.
580.000 $249.70 $144,826.00
Kovilic Construction Company Inc 580.000 $150.00 $87,000.00
Engineer's Estimate 580.000 SQFT $177.00 $102,660.00
C1340 25902-0000 SOIL NAIL
RETAINING WALL
Central Southern Construction Corp. 745.000 $412.50 $307,312.50
ERon Road Construction LLC 745.000 $377.00 $280,865.00
Structural Engineering Group, Inc.
745.000 $321.10 $239,219.50
Kovilic Construction Company Inc 745.000 $200.00 $149,000.00
Engineer's Estimate 745.000 SQFT $165.00 $122,925.00
C1350 25903-0000 VERIFICATION TEST
NAIL
Central Southern Construction Corp. 8.000 $9,734.40 $77,875.20
Kovilic Construction Company Inc 8.000 $5,000.00 $40,000.00
Structural Engineering Group, Inc.
8.000 $2,140.40 $17,123.20
ERon Road Construction LLC 8.000 $2,024.00 $16,192.00
Engineer's Estimate 8.000 EACH $13,000.00 $104,000.00
C1360 26303-0000 CONCRETE
LAGGING
Central Southern Construction Corp. 1,250.000 $118.30 $147,875.00
Kovilic Construction Company Inc 1,250.000 $100.00 $125,000.00
ERon Road Construction LLC 1,250.000 $85.00 $106,250.00
Structural Engineering Group, Inc.
1,250.000 $35.70 $44,625.00
Engineer's Estimate 1,250.000 SQFT $155.00 $193,750.00
C1370 30101-4000 AGGREGATE BASE
GRADING C OR D
Central Southern Construction Corp. 685.000 $204.00 $139,740.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1370 30101-4000 AGGREGATE BASE
GRADING C OR D
ERon Road Construction LLC 685.000 $109.00 $74,665.00
Kovilic Construction Company Inc 685.000 $100.00 $68,500.00
Structural Engineering Group, Inc.
685.000 $92.80 $63,568.00
Engineer's Estimate 685.000 TON $115.00 $78,775.00
C1380 30110-0000 AGGREGATE
SURFACE COURSE
Central Southern Construction Corp. 835.000 $204.00 $170,340.00
Structural Engineering Group, Inc.
835.000 $113.00 $94,355.00
Kovilic Construction Company Inc 835.000 $100.00 $83,500.00
ERon Road Construction LLC 835.000 $97.00 $80,995.00
Engineer's Estimate 835.000 TON $130.00 $108,550.00
C1390 30302-1000 DITCH
RECONDITIONING
Structural Engineering Group, Inc.
2,135.000 $32.10 $68,533.50
Kovilic Construction Company Inc 2,135.000 $25.00 $53,375.00
ERon Road Construction LLC 2,135.000 $22.00 $46,970.00
Central Southern Construction Corp. 2,135.000 $9.00 $19,215.00
Engineer's Estimate 2,135.000 LNFT $14.60 $31,171.00
C1400 30303-2000 AGGREGATE
SURFACE
RECONDITIONING
Central Southern Construction Corp. 1,510.000 $37.50 $56,625.00
Kovilic Construction Company Inc 1,510.000 $27.00 $40,770.00
Structural Engineering Group, Inc.
1,510.000 $15.50 $23,405.00
ERon Road Construction LLC 1,510.000 $5.00 $7,550.00
Engineer's Estimate 1,510.000 SQYD $21.50 $32,465.00 C1410 55115-1000 PREBORING Central Southern
Construction Corp. 42.000 $1,430.00 $60,060.00
ERon Road Construction LLC 42.000 $700.00 $29,400.00
Kovilic Construction Company Inc 42.000 $500.00 $21,000.00
Structural Engineering Group, Inc.
42.000 $107.00 $4,494.00
Engineer's Estimate 42.000 LNFT $140.00 $5,880.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1420 55201-0200 STRUCTURAL
CONCRETE, CLASS
A (AE)
Kovilic Construction Company Inc 100.000 $5,000.00 $500,000.00
ERon Road Construction LLC 100.000 $4,416.00 $441,600.00
Structural Engineering Group, Inc.
100.000 $4,280.80 $428,080.00
Central Southern Construction Corp. 100.000 $3,200.00 $320,000.00
Engineer's Estimate 100.000 CUYD $2,200.00 $220,000.00
C1430 55401-2000 REINFORCING
STEEL, EPOXY
COATED
ERon Road Construction LLC 17,900.000 $16.00 $286,400.00
Central Southern Construction Corp. 17,900.000 $10.00 $179,000.00
Kovilic Construction Company Inc 17,900.000 $5.00 $89,500.00
Structural Engineering Group, Inc.
17,900.000 $3.40 $60,860.00
Engineer's Estimate 17,900.000 LB $5.00 $89,500.00
C1440 55504-0000 PRE-FABRICATED
STEEL BRIDGE
Kovilic Construction Company Inc $600,000.00
Structural Engineering Group, Inc.
$493,486.40
ERon Road Construction LLC $434,172.00
Central Southern Construction Corp. $300,000.00
Engineer's Estimate ALL LPSM LPSM $444,000.00
C1450 55505-0000 STRUCTURAL STEEL
SOLDIER PILE
Central Southern Construction Corp. 495.000 $520.00 $257,400.00
Structural Engineering Group, Inc.
495.000 $475.60 $235,422.00
ERon Road Construction LLC 495.000 $391.00 $193,545.00
Kovilic Construction Company Inc 495.000 $200.00 $99,000.00
Engineer's Estimate 495.000 LNFT $280.00 $138,600.00
C1460 55601-1300 BRIDGE RAILING,
TIMBER
Central Southern Construction Corp. 160.000 $350.00 $56,000.00
ERon Road Construction LLC 160.000 $300.00 $48,000.00
Kovilic Construction Company Inc 160.000 $300.00 $48,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1460 55601-1300 BRIDGE RAILING,
TIMBER
Structural Engineering Group, Inc.
160.000 $95.10 $15,216.00
Engineer's Estimate 160.000 LNFT $155.00 $24,800.00
C1470 55701-2000 STRUCTURAL
TIMBER AND
LUMBER, TREATED
Kovilic Construction Company Inc 5.000 $45,000.00 $225,000.00
Structural Engineering Group, Inc.
5.000 $25,601.80 $128,009.00
Central Southern Construction Corp. 5.000 $20,000.00 $100,000.00
ERon Road Construction LLC 5.000 $10,454.00 $52,270.00
Engineer's Estimate 5.000 MFBM $16,300.00 $81,500.00 C1480 56401-0000 BEARING DEVICE Central Southern
Construction Corp. 6.000 $5,000.00 $30,000.00
Structural Engineering Group, Inc.
6.000 $2,497.20 $14,983.20
ERon Road Construction LLC 6.000 $2,054.00 $12,324.00
Kovilic Construction Company Inc 6.000 $1,000.00 $6,000.00
Engineer's Estimate 6.000 EACH $1,950.00 $11,700.00
C1490 56501-0300 DRILLED SHAFT, 30-
INCH DIAMETER
Central Southern Construction Corp. 355.000 $1,339.00 $475,345.00
ERon Road Construction LLC 355.000 $906.00 $321,630.00
Kovilic Construction Company Inc 355.000 $350.00 $124,250.00
Structural Engineering Group, Inc.
355.000 $101.10 $35,890.50
Engineer's Estimate 355.000 LNFT $1,660.00 $589,300.00
C1500 60103-0100 CONCRETE,
HEADWALL FOR 18
-INCH PIPE
CULVERT
Kovilic Construction Company Inc 1.000 $5,000.00 $5,000.00
Structural Engineering Group, Inc.
1.000 $4,756.50 $4,756.50
ERon Road Construction LLC 1.000 $4,003.00 $4,003.00
Central Southern Construction Corp. 1.000 $3,150.00 $3,150.00
Engineer's Estimate 1.000 EACH $5,000.00 $5,000.00
C1510 60103-0140 CONCRETE,
HEADWALL FOR 24
-INCH PIPE
CULVERT
Kovilic Construction Company Inc 2.000 $6,000.00 $12,000.00
Report Generated on 04/29/2026 12:34 PM [Timezone: (UTC-05:00) Eastern Time (US & Canada)]
C1510 60103-0140 CONCRETE,
HEADWALL FOR 24
-INCH PIPE
CULVERT
Structural Engineering Group, Inc.
2.000 $4,756.50 $9,513.00
Central Southern Construction Corp. 2.000 $4,275.00 $8,550.00
ERon Road Construction LLC 2.000 $4,003.00 $8,006.00
Engineer's Estimate 2.000 EACH $6,350.00 $12,700.00
C1520 60103-0160 CONCRETE,
HEADWALL FOR 30
-INCH PIPE
CULVERT
Kovilic Construction Company Inc 3.000 $7,500.00 $22,500.00
Central Southern Construction Corp. 3.000 $6,525.00 $19,575.00
Structural Engineering Group, Inc.
3.000 $5,945.60 $17,836.80
ERon Road Construction LLC 3.000 $4,621.00 $13,863.00
Engineer's Estimate 3.000 EACH $7,130.00 $21,390.00
C1530 60103-1940 CONCRETE,
HEADWALL FOR 30
-INCH EQUIVALENT
DIAMETER PIPE
CULVERT (27-INCH
EQUIVALENT)
Kovilic Construction Company Inc 2.000 $10,000.00 $20,000.00
Central Southern Construction Corp. 2.000 $6,525.00 $13,050.00
Structural Engineering Group, Inc.
2.000 $5,945.60 $11,891.20