Tabulation of Bids - PR ER DOT PRMNT RPR(17).pdf
PDF 501 KB Posted
- Attached to
- Landslide Repairs in Morovis, Puerto Rico
- Solicitation number
- 693C73-25-C-000005
About this file
This is a bid tabulation document for a landslide repair project in Morovis, Puerto Rico (Project No. PR ER DOT PRMNT RPR(17)) administered by the Eastern Federal Lands Highway Division of the Federal Highway Administration. The project consists of three schedules: Schedule A (ER-HWY-483, 258, 262, 263, 264, 265) at PR-155 KM 0.35-56.7, Schedule B (ER-HWY-259) at PR-155 KM 38.65, and Schedule C (ER-HWY-257, 260, 261) at PR-155 KM 36.15-40.30.
The bids were opened on September 5, 2024 in Ashburn, Virginia, with five responsive bidders participating: Design Build LLC, LPC Contractors Inc, Maglez Engineering & Contractors Corp, and Novel Construction LLC. Novel Construction LLC was awarded the contract (693C73-25-C-000005) on December 12, 2024, with the lowest combined bid for Schedule A ($8,061,826.00) and Schedule C ($3,733,410.00), totaling $11,795,236.00. The Engineer's Estimate for these schedules was $10,410,000.00. The detailed bid tabulation includes extensive line items for construction activities including excavation, paving, drainage structures, guardrails, traffic control, and utility work.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
T A B U L A T I O N O F B I D S Schedule A Eastern Federal Lands Highway Division
Project No : PR ER DOT PRMNT RPR(17) FLMA No:
Project Name : AC-857579, AC-893579, AC-905579: ER-HWY-483, 258, 262, 263, 264, 265 Solcitation No:
State : PUERTO RICO County : MOROVIS Federal Location : PR-155 (KM 0.35, 0.37, 40.3, 43.25, 45.5, & 56.7)
Opened at: Ashburn, Virginia Opened by: Emily McCleary Date: 9/5/2024
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed:
Title:
Date: 9/9/2024
Contract Awarded to: Award Date:
Contract Number: Data is Public
Contractor Comment Bid Amount Responsive
Engineer's Estimate 6,925,000.00$
Design Build, LLC 9,163,477.00$
LPC Contractors, Inc 10,799,490.00$
Maglez Engineering & Contractors Corp. 8,351,159.75$
Novel Construction, LLC 8,061,826.00$
P.O. Box 1787 Sabana Seca, PR 00951
YES
PR-140 Km. 59.0 Bo. Puerto Blanco Florida, PR 00650
1738 Calle Amarillo Suite 205, Box 15 San Juan, Puerto Rico 00926
YES
YES
YES
Bo. Boquerón PR-937 Km. 3.0 Las Piedras, PR 00771
693C73-24-B-000015
Emily McCleary
Contract Specialist
9/10/2024 FHWA Confidential Page 1 of 5
693C73-25-C-000005
Novel Construction, LLC 12 December 2024
Schedule Total of Bid Items: 6,925,000.00$ 32.3% 9,163,477.00$ 55.9% 10,799,490.00$ 20.6% 8,351,159.75$ 16.4% 8,061,826.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-857579, AC-893579, AC-905579: ER-HWY-483, 258, 262, 263, 264, 265
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
15000-1000
Line 0010 ALL LPSM 140,000.00$ 140,000.00$ 200,000.00$ 800,000.00$ 20,000.00$ 40,000.00$
15100-1000
Line 0020 ALL LPSM 357,922.50$ 357,922.50$ 900,000.00$ 960,000.00$ 748,181.00$ 847,086.00$
15102-0000
Line 0030 1 CTSM 630,000.00$ 630,000.00$ 630,000.00$ 630,000.00$ 630,000.00$ 630,000.00$
15401-0000
Line 0040 ALL LPSM 170,000.00$ 170,000.00$ 50,000.00$ 800,000.00$ 25,000.00$ 100,000.00$
15401-1000
Line 0050 ALL LPSM 240,000.00$ 240,000.00$ 247,104.00$ 400,000.00$ 35,000.00$ 20,000.00$
15401-2000
Line 0060 ALL LPSM 39,000.00$ 39,000.00$ 76,328.00$ 700,000.00$ 40,000.00$ 30,000.00$
15501-0000
Line 0070 ALL LPSM 91,000.00$ 91,000.00$ 42,000.00$ 596,940.00$ 15,000.00$ 20,000.00$
20100-1000
Line 0080 0.80 Cuerda 21,500.00$ 17,200.00$ 9,600.00$ 4,000.00$ 11,296.00$ 42,500.00$
20100-2000
Line 0090 51 Each 1,200.00$ 61,200.00$ 142,800.00$ 10,200.00$ 153,000.00$ 76,500.00$
20100-3000
Line 0100 6 Each 1,800.00$ 10,800.00$ 33,000.00$ 18,000.00$ 60,000.00$ 24,000.00$
20200-1000
Line 0110 ALL LPSM 18,000.00$ 18,000.00$ 30,000.00$ 20,000.00$ 39,600.00$ 40,000.00$
20201-6000
Line 0120 140 M 325.00$ 45,500.00$ 9,100.00$ 28,000.00$ 9,800.00$ 28,000.00$
20300-1000
Line 0130 5,720 m3 35.00$ 200,200.00$ 286,000.00$ 97,240.00$ 348,920.00$ 228,800.00$
20300-4000
Line 0140 1,895 m3 45.00$ 85,275.00$ 113,700.00$ 37,900.00$ 123,175.00$ 75,800.00$
20300-5000
Line 0150 2,950 m3 55.00$ 162,250.00$ 177,000.00$ 59,000.00$ 191,750.00$ 103,250.00$
20600-1000
Line 0160 7,005 m3 45.00$ 315,225.00$ 350,250.00$ 175,125.00$ 455,325.00$ 245,175.00$
20600-5000
Line 0170 ALL LPSM 70,000.00$ 70,000.00$ 30,000.00$ 60,000.00$ 100,000.00$ 15,000.00$
20600-6000
Line 0180 ALL LPSM 65,000.00$ 65,000.00$ 130,000.00$ 60,000.00$ 100,000.00$ 30,000.00$
20600-7000
Line 0190 ALL LPSM 180,000.00$ 180,000.00$ 150,000.00$ 100,000.00$ 100,000.00$ 15,000.00$
20700-1000
Line 0200 500 m3 28.00$ 14,000.00$ 50,000.00$ 35,000.00$ 50,000.00$ 20,000.00$
21000-1000
Line 0210 740 M 10.00$ 7,400.00$ 7,400.00$ 7,400.00$ 7,400.00$ 7,400.00$
21000-2000
Line 0220 774 Each 15.00$ 11,610.00$ 11,610.00$ 11,610.00$ 11,610.00$ 11,610.00$
21000-8000
Line 0230 20 M 105.00$ 2,100.00$ 2,100.00$ 2,100.00$ 2,100.00$ 2,100.00$
21000-9000
Line 0240 490 m2 25.00$ 12,250.00$ 19,600.00$ 14,700.00$ 9,800.00$ 7,350.00$
21001-1000
Line 0250 7 Each 8,500.00$ 59,500.00$ 70,000.00$ 35,000.00$ 45,500.00$ 35,000.00$
21200-1000
Line 0260 145 m2 60.00$ 8,700.00$ 7,250.00$ 5,800.00$ 14,500.00$ 7,250.00$
30400-1000
Contractor Testing
50,000.00$ 800,000.00$ 25,000.00$ 100,000.00$
Construction Survey and Staking
Mobilization
Reimbursement for Municipal Tax Payments
Unclassified Excavation for Structures
Temporary Shoring and Bracing (HWY-263)
Temporary Shoring and Bracing (HWY-265)
Construction Schedule
Clearing and Grubbing
Cutting and Removing Trees, Small
Cutting and Removing Trees, Large
Removal of Structures and Obstructions
Removal of Concrete Barrier
Stabilized Construction Exit
Reconditioning of Shoulders and Ditches
Aggregate Base Course, Grading A
Temporary Shoring and Bracing (HWY-483)
Foundation Fill
Silt Fence
Straw Bales
Floating Turbidity Barrier
Turf Reinforcement Mat
Contractor Testing (Biological Species Monitoring)
Contractor Testing (Cultural Resource Protection and Monitoring)
Unclassified Excavation
Borrow Class A-1
Borrow Class B-1
800,000.00$ 20,000.00$ 40,000.00$
Design Build, LLC LPC Contractors, Inc Maglez Engineering & Contractors Corp Novel Construction, LLC
900,000.00$
200,000.00$
247,104.00$ 400,000.00$ 35,000.00$ 20,000.00$
960,000.00$ 748,181.00$ 847,086.00$
630,000.00$ 630,000.00$ 630,000.00$ 630,000.00$
12,000.00$ 5,000.00$ 14,120.00$ 53,125.00$
42,000.00$ 596,940.00$ 15,000.00$ 20,000.00$
76,328.00$ 700,000.00$ 40,000.00$ 30,000.00$
5,500.00$ 3,000.00$ 10,000.00$ 4,000.00$
2,800.00$ 200.00$ 3,000.00$ 1,500.00$
65.00$ 200.00$ 70.00$ 200.00$
30,000.00$ 20,000.00$ 39,600.00$ 40,000.00$
60.00$ 20.00$ 65.00$ 40.00$
50.00$ 17.00$ 61.00$ 40.00$
50.00$ 25.00$ 65.00$ 35.00$
60.00$ 20.00$ 65.00$ 35.00$
130,000.00$ 60,000.00$ 100,000.00$ 30,000.00$
30,000.00$ 60,000.00$ 100,000.00$ 15,000.00$
100.00$ 70.00$ 100.00$ 40.00$
150,000.00$ 100,000.00$ 100,000.00$ 15,000.00$
15.00$ 15.00$ 15.00$ 15.00$
10.00$ 10.00$ 10.00$ 10.00$
40.00$ 30.00$ 20.00$ 15.00$
105.00$ 105.00$ 105.00$ 105.00$
50.00$ 40.00$ 100.00$ 50.00$
10,000.00$ 5,000.00$ 6,500.00$ 5,000.00$
Engineer's Estimate
9/10/2024 Page 2 of 5
Schedule Total of Bid Items: 6,925,000.00$ 32.3% 9,163,477.00$ 55.9% 10,799,490.00$ 20.6% 8,351,159.75$ 16.4% 8,061,826.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-857579, AC-893579, AC-905579: ER-HWY-483, 258, 262, 263, 264, 265
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Design Build, LLC LPC Contractors, Inc Maglez Engineering & Contractors Corp Novel Construction, LLC
Line 0270 180 m3 35.00$ 6,300.00$ 30,600.00$ 16,200.00$ 15,480.00$ 10,800.00$
30500-1000
Line 0280 1,050 m2 95.00$ 99,750.00$ 315,000.00$ 84,000.00$ 126,000.00$ 147,000.00$
40200-1000
Line 0290 95 m3 110.00$ 10,450.00$ 5,700.00$ 9,500.00$ 5,700.00$ 3,800.00$
40300-1000
Line 0300 6,430 m2 60.00$ 385,800.00$ 38,580.00$ 64,300.00$ 260,736.50$ 32,150.00$
42100-3000
Line 0310 790 TON 350.00$ 276,500.00$ 237,000.00$ 248,850.00$ 355,500.00$ 158,000.00$
42100-5000
Line 0320 445 TON 350.00$ 155,750.00$ 133,500.00$ 140,175.00$ 200,250.00$ 111,250.00$
42100-6000
Line 0330 20 TON 350.00$ 7,000.00$ 6,000.00$ 6,300.00$ 16,000.00$ 6,000.00$
60200-1000
Line 0340 17,295 lb 3.00$ 51,885.00$ 51,885.00$ 34,590.00$ 102,905.25$ 51,885.00$
60300-2000
Line 0350 28 M 155.00$ 4,340.00$ 16,800.00$ 4,200.00$ 14,000.00$ 8,400.00$
60302-2000
Line 0360 1 Each 3,500.00$ 3,500.00$ 4,000.00$ 2,000.00$ 2,500.00$ 3,100.00$
60302-5000
Line 0370 1 Each 3,500.00$ 3,500.00$ 6,000.00$ 6,000.00$ 6,000.00$ 5,000.00$
60500-2000
Line 0380 85 M 120.00$ 10,200.00$ 34,000.00$ 2,550.00$ 9,137.50$ 2,975.00$
60600-1000
Line 0390 335 M 275.00$ 92,125.00$ 100,500.00$ 67,000.00$ 105,525.00$ 100,500.00$
60600-4000
Line 0400 110 M 18.00$ 1,980.00$ 3,850.00$ 3,300.00$ 7,700.00$ 5,280.00$
60600-9000
Line 0410 12 Each 8,500.00$ 102,000.00$ 120,000.00$ 60,000.00$ 100,800.00$ 60,000.00$
60700-1000
Line 0420 650 M 115.00$ 74,750.00$ 65,000.00$ 65,000.00$ 73,125.00$ 81,250.00$
60900-2000
Line 0430 85 M 65.00$ 5,525.00$ 17,000.00$ 6,800.00$ 14,875.00$ 12,750.00$
60900-6000
Line 0440 80 M 75.00$ 6,000.00$ 28,000.00$ 16,000.00$ 14,000.00$ 12,000.00$
61000-3000
Line 0450 115 M 515.00$ 59,225.00$ 345,000.00$ 40,250.00$ 64,400.00$ 46,000.00$
61000-4000
Line 0460 25 M 675.00$ 16,875.00$ 137,500.00$ 17,500.00$ 17,500.00$ 18,750.00$
61000-5000
Line 0470 40 M 400.00$ 16,000.00$ 48,000.00$ 10,000.00$ 18,000.00$ 16,000.00$
61101-1000
Line 0480 26 mo 4,850.00$ 126,100.00$ 171,600.00$ 104,000.00$ 169,000.00$ 78,000.00$
61200-2000
Line 0490 8 Each 1,800.00$ 14,400.00$ 160,000.00$ 48,000.00$ 72,000.00$ 32,000.00$
61310-1000
Line 0500 1 Each 350.00$ 350.00$ 550.00$ 530.00$ 681.75$ 600.00$
61310-2000
Line 0510 1 Each 350.00$ 350.00$ 550.00$ 530.00$ 757.50$ 600.00$
61310-3000
Line 0520 1 Each 380.00$ 380.00$ 1,000.00$ 860.00$ 1,325.00$ 1,000.00$
61310-4000
Line 0530 1 Each 380.00$ 380.00$ 1,000.00$ 860.00$ 1,802.00$ 1,000.00$
Cold Milling Bituminous Concrete Pavement, Variable Depth (0.025m to 0.075m)
Inlet, Type V
6 inch Pipe Underdrain, Type Non-Perforated PVC Schedule 40
W-Beam Guardrail, Single Face
Removal, Storage and Delivery of Existing Guardrail
ThrieBeam Transition Section, Type II
Barbed Wire Fence, Type A
Hot Plant Mix Asphalt Concrete, Type S (75)(12)
Hot Plant Mix Asphalt Concrete, Type B (75)(34)
Hot Plant Mix Asphalt Concrete, Type B (75)(1)
Reinforcing Steel
24" Reinforced Concrete Pipe Class-III
24" Reinforced Concrete Pipe, End Section
Lean Concrete Base
Full Depth Removal of Bituminous Concrete Pavement
Temporary Lighting Standard
Traffic Sign Assembly, Code 1
Traffic Sign Assembly, Code 2
Traffic Sign Assembly, Code 3
Traffic Sign Assembly, Code 4
Combination Concrete Curb and Gutter, Type-F
Concrete Gutter
Concrete Barrier, Type C
Concrete Barrier, Type C (Modified)
Concrete Barrier, Bridge Parapet
Field Office
300.00$ 80.00$ 120.00$ 140.00$
170.00$ 90.00$ 86.00$ 60.00$
6.00$ 10.00$ 40.55$ 5.00$
60.00$ 100.00$ 60.00$ 40.00$
300.00$ 315.00$ 450.00$ 250.00$
300.00$ 315.00$ 450.00$ 200.00$
3.00$ 2.00$ 5.95$ 3.00$
300.00$ 315.00$ 800.00$ 300.00$
4,000.00$ 2,000.00$ 2,500.00$ 3,100.00$
600.00$ 150.00$ 500.00$ 300.00$
400.00$ 30.00$ 107.50$ 35.00$
6,000.00$ 6,000.00$ 6,000.00$ 5,000.00$
35.00$ 30.00$ 70.00$ 48.00$
300.00$ 200.00$ 315.00$ 300.00$
100.00$ 100.00$ 112.50$ 125.00$
10,000.00$ 5,000.00$ 8,400.00$ 5,000.00$
350.00$ 200.00$ 175.00$ 150.00$
200.00$ 80.00$ 175.00$ 150.00$
5,500.00$ 700.00$ 700.00$ 750.00$
3,000.00$ 350.00$ 560.00$ 400.00$
6,600.00$ 4,000.00$ 6,500.00$ 3,000.00$
1,200.00$ 250.00$ 450.00$ 400.00$
550.00$ 530.00$ 681.75$ 600.00$
20,000.00$ 6,000.00$ 9,000.00$ 4,000.00$
1,000.00$ 860.00$ 1,325.00$ 1,000.00$
550.00$ 530.00$ 757.50$ 600.00$
1,000.00$ 860.00$ 1,802.00$ 1,000.00$
9/10/2024 Page 3 of 5
Schedule Total of Bid Items: 6,925,000.00$ 32.3% 9,163,477.00$ 55.9% 10,799,490.00$ 20.6% 8,351,159.75$ 16.4% 8,061,826.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-857579, AC-893579, AC-905579: ER-HWY-483, 258, 262, 263, 264, 265
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
61310-5000
Line 0540 2 Each 355.00$ 710.00$ 1,500.00$ 1,670.00$ 2,670.00$ 1,600.00$
61310-6000
Line 0550 6 Each 400.00$ 2,400.00$ 4,500.00$ 5,010.00$ 8,544.00$ 4,800.00$
61310-7000
Line 0560 1 Each 350.00$ 350.00$ 550.00$ 530.00$ 757.50$ 600.00$
61310-8000
Line 0570 1 Each 350.00$ 350.00$ 550.00$ 530.00$ 883.75$ 600.00$
61314-1000
Line 0580 3 Each 350.00$ 1,050.00$ 1,650.00$ 1,590.00$ 2,424.00$ 1,800.00$
61314-2000
Line 0590 10 Each 250.00$ 2,500.00$ 3,000.00$ 4,200.00$ 6,106.00$ 5,300.00$
61314-3000
Line 0600 10 Each 250.00$ 2,500.00$ 3,000.00$ 4,200.00$ 6,450.00$ 5,300.00$
61400-1000
Line 0610 580 m3 585.00$ 339,300.00$ 348,000.00$ 580,000.00$ 406,000.00$ 348,000.00$
61600-1000
Line 0620 ALL LPSM 30,000.00$ 30,000.00$ 25,000.00$ 51,000.00$ 88,000.00$ 30,000.00$
61700-1000
Line 0630 120 m2 150.00$ 18,000.00$ 30,000.00$ 10,800.00$ 30,000.00$ 24,000.00$
61701-1000
Line 0640 195 m2 175.00$ 34,125.00$ 41,925.00$ 17,550.00$ 48,750.00$ 39,000.00$
61701-2000
Line 0650 70 m3 125.00$ 8,750.00$ 7,000.00$ 6,300.00$ 8,400.00$ 3,500.00$
61701-3000
Line 0660 40 m2 225.00$ 9,000.00$ 12,000.00$ 3,600.00$ 10,000.00$ 12,000.00$
61701-4000
Line 0670 100 m2 275.00$ 27,500.00$ 20,000.00$ 9,000.00$ 25,000.00$ 30,000.00$
61800-2000
Line 0680 1,845 M 18.00$ 33,210.00$ 18,450.00$ 22,140.00$ 36,900.00$ 27,675.00$
61800-3000
Line 0690 1,005 M 18.00$ 18,090.00$ 10,050.00$ 12,060.00$ 20,100.00$ 15,075.00$
62100-2000
Line 0700 2 Each 170.00$ 340.00$ 1,300.00$ 900.00$ 1,400.00$ 1,200.00$
62101-2000
Line 0710 51 Each 175.00$ 8,925.00$ 33,150.00$ 5,100.00$ 2,550.00$ 25,500.00$
62200-1000
Line 0720 5 m3 275.00$ 1,375.00$ 1,750.00$ 600.00$ 2,500.00$ 1,250.00$
62200-7000
Line 0730 15 m3 350.00$ 5,250.00$ 9,000.00$ 3,000.00$ 8,250.00$ 9,300.00$
62201-1000
Line 0740 5 m3 175.00$ 875.00$ 1,750.00$ 600.00$ 2,500.00$ 700.00$
62201-2000
Line 0750 5 m3 235.00$ 1,175.00$ 1,750.00$ 600.00$ 2,500.00$ 700.00$
62300-1000
Line 0760 270 m3 52.00$ 14,040.00$ 47,250.00$ 54,000.00$ 94,500.00$ 108,000.00$
62300-2000
Line 0770 90 m3 36.00$ 3,240.00$ 9,900.00$ 13,500.00$ 10,557.00$ 18,000.00$
62400-1000
Line 0780 660 M 5.00$ 3,300.00$ 19,800.00$ 13,200.00$ 3,960.00$ 27,060.00$
62500-1000
Line 0790 270 m3 85.00$ 22,950.00$ 110,700.00$ 21,600.00$ 26,460.00$ 27,000.00$
62600-6000
410.00$ 80.00$ 98.00$ 100.00$
30.00$ 20.00$ 6.00$ 41.00$
110.00$ 150.00$ 117.30$ 200.00$
175.00$ 200.00$ 350.00$ 400.00$
350.00$ 120.00$ 500.00$ 140.00$
350.00$ 120.00$ 500.00$ 140.00$
600.00$ 200.00$ 550.00$ 620.00$
350.00$ 120.00$ 500.00$ 250.00$
650.00$ 100.00$ 50.00$ 500.00$
650.00$ 450.00$ 700.00$ 600.00$
10.00$ 12.00$ 20.00$ 15.00$
10.00$ 12.00$ 20.00$ 15.00$
200.00$ 90.00$ 250.00$ 300.00$
300.00$ 90.00$ 250.00$ 300.00$
100.00$ 90.00$ 120.00$ 50.00$
215.00$ 90.00$ 250.00$ 200.00$
250.00$ 90.00$ 250.00$ 200.00$
25,000.00$ 51,000.00$ 88,000.00$ 30,000.00$
Traffic Sign Assembly, Code 5
Gabions
Structural Steel, Furnished, Fabricated and Erected
Concrete Paved Waterway, Type I
Concrete Paved Waterway, Type II
Bed Course Material
Concrete Paved Waterway, Type III
Traffic Sign Assembly, Code 6
Traffic Sign Assembly, Code 7
Traffic Sign Assembly, Code 8
Traffic Sign Assembly, Code 11
Traffic Sign Assembly, Code 14
Traffic Sign Assembly, Code 15
Grouted Riprap, Class II
Filter Blanket, Type A
Filter Blanket, Type B
Stone Revetment, Type V
Filter Stone, Type D
Vertical Wick Drains
Concrete Paved Waterway, Type IV
Thermoplastic Pavement Marking Stripes, White
Thermoplastic Pavement Marking Stripes, Yellow
Hectometer Marker
Right-of-Way Marker
Dumped Riprap, Class I
Furnishing and Placing Loamy Topsoil
Protection to Existing Trees
750.00$ 835.00$ 1,335.00$ 800.00$
550.00$ 530.00$ 757.50$ 600.00$
750.00$ 835.00$ 1,424.00$ 800.00$
550.00$ 530.00$ 808.00$ 600.00$
550.00$ 530.00$ 883.75$ 600.00$
600.00$ 1,000.00$ 700.00$ 600.00$
300.00$ 420.00$ 645.00$ 530.00$
300.00$ 420.00$ 610.60$ 530.00$
9/10/2024 Page 4 of 5
Schedule Total of Bid Items: 6,925,000.00$ 32.3% 9,163,477.00$ 55.9% 10,799,490.00$ 20.6% 8,351,159.75$ 16.4% 8,061,826.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-857579, AC-893579, AC-905579: ER-HWY-483, 258, 262, 263, 264, 265
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Line 0800 11 Each 500.00$ 5,500.00$ 7,920.00$ 440.00$ 825.00$ 3,300.00$
62700-1000
Line 0810 810 m2 5.50$ 4,455.00$ 32,400.00$ 4,050.00$ 137,700.00$ 5,670.00$
62700-3000
Line 0820 515 m2 8.50$ 4,377.50$ 2,575.00$ 5,150.00$ 10,300.00$ 7,725.00$
62700-4000
Line 0830 600 m2 12.00$ 7,200.00$ 1,800.00$ 9,000.00$ 15,000.00$ 4,200.00$
62800-1000
Line 0840 340 m2 15.00$ 5,100.00$ 15,300.00$ 3,400.00$ 6,800.00$ 8,500.00$
63100-1000
Line 0850 1,660 m2 130.00$ 215,800.00$ 531,200.00$ 149,400.00$ 456,500.00$ 581,000.00$
63200-2000
Line 0860 20 M 175.00$ 3,500.00$ 10,000.00$ 6,000.00$ 5,200.00$ 6,000.00$
63200-3000
Line 0870 4 Each 625.00$ 2,500.00$ 28,000.00$ 4,000.00$ 10,000.00$ 8,000.00$
63802-1000
Line 0880 ALL LPSM 345,000.00$ 345,000.00$ 622,000.00$ 500,000.00$ 42,000.00$ 905,165.00$
64000-3000
Line 0890 15 Each 7.00$ 105.00$ 300.00$ 120.00$ 750.00$ 225.00$
64000-6000
Line 0900 130 Each 8.00$ 1,040.00$ 2,600.00$ 1,040.00$ 2,600.00$ 1,950.00$
64000-7000
Line 0910 100 Each 8.00$ 800.00$ 2,000.00$ 800.00$ 2,000.00$ 1,500.00$
66100-1000
Line 0920 2 Each 2,000.00$ 4,000.00$ 7,000.00$ 6,000.00$ 13,000.00$ 10,000.00$
91001-4000
Line 0930 4 Each 6,300.00$ 25,200.00$ 40,000.00$ 20,000.00$ 28,800.00$ 24,000.00$
91001-5000
Line 0940 8 Each 4,900.00$ 39,200.00$ 80,000.00$ 40,000.00$ 57,600.00$ 48,000.00$
91200-1000
Line 0950 770 m2 22.00$ 16,940.00$ 30,800.00$ 15,400.00$ 23,100.00$ 10,780.00$
91300-4000
Line 0960 1 Each 330.00$ 330.00$ 100.00$ 100.00$ 1,800.00$ 440.00$
92600-1000
Line 0970 65 m2 1,600.00$ 104,000.00$ 130,000.00$ 65,000.00$ 118,495.00$ 195,000.00$
93101-1000
Line 0980 60 M 110.00$ 6,600.00$ 30,000.00$ 30,000.00$ 17,160.00$ 18,000.00$
93101-4000
Line 0990 45 SQM 750.00$ 33,750.00$ 45,000.00$ 22,500.00$ 21,600.00$ 9,000.00$
93400-1000
Line 1000 5 m3 1,350.00$ 6,750.00$ 45,000.00$ 5,000.00$ 7,500.00$ 15,000.00$
93400-3000
Line 1010 85 m3 1,500.00$ 127,500.00$ 127,500.00$ 76,500.00$ 93,500.00$ 212,500.00$
99100-1000
Line 1020 755 m2 1,100.00$ 830,500.00$ 755,000.00$ 2,265,000.00$ 1,300,110.00$ 1,510,000.00$ 1,000.00$ 3,000.00$ 1,722.00$ 2,000.00$
1,500.00$ 900.00$ 1,100.00$ 2,500.00$
9,000.00$ 1,000.00$ 1,500.00$ 3,000.00$
1,000.00$ 500.00$ 480.00$ 200.00$
500.00$ 500.00$ 286.00$ 300.00$
2,000.00$ 1,000.00$ 1,823.00$ 3,000.00$
100.00$ 100.00$ 1,800.00$ 440.00$
40.00$ 20.00$ 30.00$ 14.00$
10,000.00$ 5,000.00$ 7,200.00$ 6,000.00$
10,000.00$ 5,000.00$ 7,200.00$ 6,000.00$
3,500.00$ 3,000.00$ 6,500.00$ 5,000.00$
20.00$ 8.00$ 20.00$ 15.00$
20.00$ 8.00$ 20.00$ 15.00$
20.00$ 8.00$ 50.00$ 15.00$
622,000.00$ 500,000.00$ 42,000.00$ 905,165.00$
7,000.00$ 1,000.00$ 2,500.00$ 2,000.00$
500.00$ 300.00$ 260.00$ 300.00$
320.00$ 90.00$ 275.00$ 350.00$
45.00$ 10.00$ 20.00$ 25.00$
3.00$ 15.00$ 25.00$ 7.00$
5.00$ 10.00$ 20.00$ 15.00$
40.00$ 5.00$ 170.00$ 7.00$
720.00$ 40.00$ 75.00$ 300.00$
Pneumatically Applied Mortar
Cleaning and Repair of Storm Sewer
Cleaning and Repair of Manholes, Inlets and Catch Basins
Maintenance of Traffic (MOT)
Reflective Raised Pavement Markers, One way, Clear
Reflective Raised Pavement Markers, Two way, Clear-Red
Seeding, (without mulch)
Jute Mesh
Erosion Control Blanket
Sodding
Mechanically Stabilized Earth (MSE) Retaining Wall
Removal and Disposal of Lead Based Paint (Guardrail)
Removal and Disposal of Lead Based Paint (Concrete Barrier, Parapet)
Structural Concrete, Class III (General Use)
Structural Concrete, Class V (General Use)
Mechanically Stabilized Earth (MSE) Slopes
Reflective Raised Pavement Markers, Two way, Yellow-Yellow
Project Funding Sign
New Transition Module (Cast-In-Place)
New Transition Module, < 45mph
Pre-fabricated Drainage Composite
Removal of Existing Traffic Signs
9/10/2024 Page 5 of 5
Schedule B Eastern Federal Lands Highway Division
Project No : PR ER DOT PRMNT RPR(17) FLMA No:
Project Name : AC-919579: ER-HWY-259 Solcitation No:
State : PUERTO RICO County : MOROVIS Federal Location : PR-155 (KM 38.65)
Opened at: Ashburn, Virginia Opened by: Emily McCleary Date: 9/5/2024
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed:
Title:
Date: 9/9/2024
Contract Awarded to: Award Date:
Contract Number: Data is Public
Contractor Comment Bid Amount Responsive
Engineer's Estimate 615,000.00$
Design Build, LLC 1,372,560.00$
LPC Contractors, Inc. 700,000.00$
Maglez Engineering & Contractors Corp. 941,690.00$
Novel Construction, LLC 661,964.00$
693C73-24-B-000015
Emily McCleary
Contract Specialist
YES
YES
YES
Bo. Boquerón PR-937 Km. 3.0 Las Piedras, PR 00771
P.O. Box 1787 Sabana Seca, PR 00951
YES
PR-140 Km. 59.0 Bo. Puerto Blanco Florida, PR 00650
1738 Calle Amarillo Suite 205, Box 15 San Juan, Puerto Rico 00926
9/10/2024 FHWA Confidential Page 1 of 3
Novel Construction, LLC
12 December 2024
Schedule Total of Bid Items: 615,000.00$ 123.2% 1,372,560.00$ 13.8% 700,000.00$ 53.1% 941,690.00$ 7.6% 661,964.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-919579: ER-HWY-259
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
15000-1000
Line 0010 ALL LPSM 12,000.00$ 12,000.00$ 50,000.00$ 100,000.00$ 10,000.00$ 20,000.00$
15100-1000
Line 0020 ALL LPSM 46,035.00$ 46,035.00$ 120,000.00$ 60,000.00$ 85,748.00$ 66,196.00$
15102-0000
Line 0030 1 CTSM 55,000.00$ 55,000.00$ 55,000.00$ 55,000.00$ 55,000.00$ 55,000.00$
15401-0000
Line 0040 ALL LPSM 15,000.00$ 15,000.00$ 50,000.00$ 50,000.00$ 22,500.00$ 15,000.00$
15401-1000
Line 0050 ALL LPSM 28,000.00$ 28,000.00$ 37,000.00$ 42,650.00$ 35,000.00$ 3,100.00$
15501-0000
Line 0060 ALL LPSM 14,000.00$ 14,000.00$ 6,600.00$ 4,000.00$ 13,500.00$ 6,000.00$
20100-1000
Line 0070 0.15 Cuerda 21,500.00$ 3,225.00$ 3,000.00$ 750.00$ 3,000.00$ 6,000.00$
20100-2000
Line 0080 4 Each 1,200.00$ 4,800.00$ 11,200.00$ 800.00$ 12,400.00$ 6,000.00$
20100-3000
Line 0090 1 Each 1,800.00$ 1,800.00$ 5,500.00$ 3,000.00$ 6,800.00$ 2,500.00$
20200-1000
Line 0100 ALL LPSM 9,200.00$ 9,200.00$ 25,500.00$ 10,000.00$ 29,000.00$ 10,000.00$
20201-6000
Line 0110 15 M 325.00$ 4,875.00$ 2,400.00$ 3,000.00$ 1,275.00$ 1,500.00$
20300-1000
Line 0120 50 m3 35.00$ 1,750.00$ 3,500.00$ 850.00$ 3,000.00$ 1,750.00$
20300-7000
Line 0130 10 m3 65.00$ 650.00$ 2,400.00$ 200.00$ 1,000.00$ 800.00$
20600-1000
Line 0140 235 m3 45.00$ 10,575.00$ 14,100.00$ 5,875.00$ 19,975.00$ 9,400.00$
20600-5000
Line 0150 ALL LPSM 50,000.00$ 50,000.00$ 50,000.00$ 60,000.00$ 100,000.00$ 15,000.00$
21000-1000
Line 0160 65 M 10.00$ 650.00$ 650.00$ 650.00$ 650.00$ 650.00$
21000-2000
Line 0170 200 Each 15.00$ 3,000.00$ 3,000.00$ 3,000.00$ 3,000.00$ 3,000.00$
21001-1000
Line 0180 1 Each 8,500.00$ 8,500.00$ 10,000.00$ 5,000.00$ 8,500.00$ 4,000.00$
21200-1000
Line 0190 95 m2 60.00$ 5,700.00$ 4,750.00$ 4,750.00$ 7,125.00$ 4,750.00$
30400-1000
Line 0200 30 m3 35.00$ 1,050.00$ 6,450.00$ 2,700.00$ 2,700.00$ 1,800.00$
30500-1000
Line 0210 155 m2 95.00$ 14,725.00$ 46,500.00$ 12,400.00$ 23,250.00$ 18,600.00$
40200-1000
Line 0220 5 m3 110.00$ 550.00$ 300.00$ 500.00$ 2,500.00$ 250.00$
40300-1000
Line 0230 530 m2 60.00$ 31,800.00$ 2,650.00$ 5,300.00$ 20,140.00$ 4,240.00$
42100-3000
Line 0240 105 TON 350.00$ 36,750.00$ 31,500.00$ 33,075.00$ 47,250.00$ 23,100.00$
42100-5000
Line 0250 70 TON 350.00$ 24,500.00$ 21,000.00$ 22,050.00$ 35,000.00$ 28,000.00$
60200-1000
Line 0260 235 lb 3.00$ 705.00$ 940.00$ 470.00$ 1,410.00$ 1,175.00$
4.00$ 2.00$ 6.00$ 5.00$
300.00$ 315.00$ 500.00$ 400.00$
300.00$ 315.00$ 450.00$ 220.00$
5.00$ 10.00$ 38.00$ 8.00$
60.00$ 100.00$ 500.00$ 50.00$
300.00$ 80.00$ 150.00$ 120.00$
215.00$ 90.00$ 90.00$ 60.00$
50.00$ 50.00$ 75.00$ 50.00$
10,000.00$ 5,000.00$ 8,500.00$ 4,000.00$
15.00$ 15.00$ 15.00$ 15.00$
10.00$ 10.00$ 10.00$ 10.00$
50,000.00$ 60,000.00$ 100,000.00$ 15,000.00$
60.00$ 25.00$ 85.00$ 40.00$
240.00$ 20.00$ 100.00$ 80.00$
70.00$ 17.00$ 60.00$ 35.00$
160.00$ 200.00$ 85.00$ 100.00$
25,500.00$ 10,000.00$ 29,000.00$ 10,000.00$
5,500.00$ 3,000.00$ 6,800.00$ 2,500.00$
2,800.00$ 200.00$ 3,100.00$ 1,500.00$
20,000.00$ 5,000.00$ 20,000.00$ 40,000.00$
6,600.00$ 4,000.00$ 13,500.00$ 6,000.00$
37,000.00$ 42,650.00$ 35,000.00$ 3,100.00$
60,000.00$ 85,748.00$ 66,196.00$
55,000.00$ 55,000.00$ 55,000.00$ 55,000.00$
Design Build, LLC LPC Contractors, Inc. Maglez Engineering & Contractors Corp Novel Construction, LLC
120,000.00$
50,000.00$ 100,000.00$ 10,000.00$ 20,000.00$
Construction Survey and Staking
Mobilization
Reimbursement for Municipal Tax Payments
Silt Fence
Straw Bales
Stabilized Construction Exit
Clearing and Grubbing
Cutting and Removing Trees, Small
Cutting and Removing Trees, Large
Removal of Structures and Obstructions
Removal of Concrete Barrier
Unclassified Excavation
Hot Plant Mix Asphalt Concrete, Type B (75)(34)
Reinforcing Steel
Reconditioning of Shoulders and Ditches
Aggregate Base Course, Grading A
Lean Concrete Base
Full Depth Removal of Bituminous Concrete Pavement
Cold Milling Bituminous Concrete Pavement, Variable Depth (0.025m to 0.075m)
Hot Plant Mix Asphalt Concrete, Type S (75)(12)
Contractor Testing (Biological Species Monitoring)
Construction Schedule
Borrow Class D-1
Unclassified Excavation for Structures
Temporary Shoring and Bracing (HWY-259)
Contractor Testing
50,000.00$ 50,000.00$ 22,500.00$ 15,000.00$
9/10/2024 Page 2 of 3
Schedule Total of Bid Items: 615,000.00$ 123.2% 1,372,560.00$ 13.8% 700,000.00$ 53.1% 941,690.00$ 7.6% 661,964.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-919579: ER-HWY-259
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Engineer's Estimate Design Build, LLC LPC Contractors, Inc. Maglez Engineering & Contractors Corp Novel Construction, LLC
60600-1000
Line 0270 40 M 275.00$ 11,000.00$ 14,000.00$ 8,000.00$ 15,000.00$ 12,000.00$
60600-9000
Line 0280 2 Each 8,500.00$ 17,000.00$ 20,000.00$ 10,000.00$ 17,000.00$ 12,000.00$
60700-1000
Line 0290 40 M 115.00$ 4,600.00$ 4,000.00$ 4,000.00$ 4,400.00$ 4,800.00$
61000-4000
Line 0300 20 M 675.00$ 13,500.00$ 70,000.00$ 14,000.00$ 14,500.00$ 12,000.00$
61101-1000
Line 0310 4 mo 4,850.00$ 19,400.00$ 26,400.00$ 20,000.00$ 20,000.00$ 12,000.00$
61200-2000
Line 0320 2 Each 1,800.00$ 3,600.00$ 50,000.00$ 12,000.00$ 21,000.00$ 8,000.00$
61400-1000
Line 0330 5 m3 585.00$ 2,925.00$ 8,000.00$ 5,000.00$ 4,500.00$ 5,000.00$
61800-2000
Line 0340 220 M 18.00$ 3,960.00$ 7,700.00$ 2,640.00$ 4,400.00$ 2,200.00$
61800-3000
Line 0350 30 M 18.00$ 540.00$ 1,050.00$ 360.00$ 900.00$ 300.00$
62101-2000
Line 0360 10 Each 175.00$ 1,750.00$ 6,300.00$ 1,000.00$ 500.00$ 5,000.00$
62200-1000
Line 0370 3 m3 275.00$ 825.00$ 1,500.00$ 360.00$ 1,950.00$ 2,400.00$
62201-1000
Line 0380 1 m3 175.00$ 175.00$ 1,300.00$ 120.00$ 500.00$ 800.00$
62500-1000
Line 0390 10 m3 85.00$ 850.00$ 4,000.00$ 800.00$ 1,100.00$ 1,000.00$
62800-1000
Line 0400 75 m2 15.00$ 1,125.00$ 3,375.00$ 750.00$ 2,625.00$ 3,000.00$
63200-2000
Line 0410 25 M 175.00$ 4,375.00$ 9,375.00$ 7,500.00$ 5,000.00$ 7,500.00$
63200-3000
Line 0420 1 Each 625.00$ 625.00$ 4,400.00$ 1,000.00$ 3,700.00$ 3,000.00$
63802-1000
Line 0430 ALL LPSM 35,000.00$ 35,000.00$ 240,200.00$ 50,000.00$ 163,242.00$ 80,753.00$
64000-6000
Line 0440 30 Each 8.00$ 240.00$ 480.00$ 300.00$ 1,500.00$ 600.00$
64000-7000
Line 0450 15 Each 8.00$ 120.00$ 240.00$ 150.00$ 750.00$ 300.00$
66100-1000
Line 0460 2 Each 2,000.00$ 4,000.00$ 7,400.00$ 6,000.00$ 16,000.00$ 12,000.00$
91001-5000
Line 0470 2 Each 4,900.00$ 9,800.00$ 18,400.00$ 10,000.00$ 14,400.00$ 12,000.00$
92600-1000
Line 0480 55 m2 1,600.00$ 88,000.00$ 275,000.00$ 55,000.00$ 71,500.00$ 137,500.00$
93400-1000
Line 0490 5 m3 1,350.00$ 6,750.00$ 35,500.00$ 5,000.00$ 7,500.00$ 20,000.00$ 7,100.00$ 1,000.00$ 1,500.00$ 4,000.00$
5,000.00$ 1,000.00$ 1,300.00$ 2,500.00$
9,200.00$ 5,000.00$ 7,200.00$ 6,000.00$
3,700.00$ 3,000.00$ 8,000.00$ 6,000.00$
16.00$ 10.00$ 50.00$ 20.00$
16.00$ 10.00$ 50.00$ 20.00$
240,200.00$ 50,000.00$ 163,242.00$ 80,753.00$
4,400.00$ 1,000.00$ 3,700.00$ 3,000.00$
375.00$ 300.00$ 200.00$ 300.00$
45.00$ 10.00$ 35.00$ 40.00$
400.00$ 80.00$ 110.00$ 100.00$
1,300.00$ 120.00$ 500.00$ 800.00$
500.00$ 120.00$ 650.00$ 800.00$
630.00$ 100.00$ 50.00$ 500.00$
35.00$ 12.00$ 30.00$ 10.00$
35.00$ 12.00$ 20.00$ 10.00$
1,600.00$ 1,000.00$ 900.00$ 1,000.00$
25,000.00$ 6,000.00$ 10,500.00$ 4,000.00$
6,600.00$ 5,000.00$ 5,000.00$ 3,000.00$
3,500.00$ 700.00$ 725.00$ 600.00$
100.00$ 100.00$ 110.00$ 120.00$
10,000.00$ 5,000.00$ 8,500.00$ 6,000.00$
350.00$ 200.00$ 375.00$ 300.00$
Structural Concrete, Class III (General Use)
Maintenance of Traffic (MOT)
Reflective Raised Pavement Markers, Two way, Clear-Red
Reflective Raised Pavement Markers, Two way, Yellow-Yellow
Project Funding Sign
New Transition Module, < 45mph
Mechanically Stabilized Earth (MSE) Retaining Wall
W-Beam Guardrail, Single Face
ThrieBeam Transition Section, Type II
Barbed Wire Fence, Type A
Concrete Barrier, Type C (Modified)
Dumped Riprap, Class I
Filter Blanket, Type A
Furnishing and Placing Loamy Topsoil
Sodding
Cleaning and Repair of Storm Sewer
Cleaning and Repair of Manholes, Inlets and Catch Basins
Field Office
Temporary Lighting Standard
Gabions
Thermoplastic Pavement Marking Stripes, White
Thermoplastic Pavement Marking Stripes, Yellow
Right-of-Way Marker
9/10/2024 Page 3 of 3
Schedule C Eastern Federal Lands Highway Division
Project No : PR ER DOT PRMNT RPR(17) FLMA No:
Project Name : AC-908579, ER-HWY-257; AC-857579, ER-HWY-260 & 261 Solcitation No:
State : PUERTO RICO County : MOROVIS Federal Location : PR-155 (KM 36.15, 39.1, & 40.30)
Opened at: Ashburn, Virginia Opened by: Emily McCleary Date: 9/5/2024
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Title:
Date: 9/9/2024
Contract Awarded to: Award Date:
Contract Number: Data is Public
Contractor Comment Bid Amount Responsive
Engineer's Estimate 3,485,000.00$
Design Build, LLC 5,716,162.50$
LPC Contractors, Inc. 5,700,000.00$
Maglez Engineering & Contractors Corp. 4,391,781.00$
Novel Construction, LLC 3,733,410.00$
P.O. Box 1787 Sabana Seca, PR 00951
YES
PR-140 Km. 59.0 Bo. Puerto Blanco Florida, PR 00650
1738 Calle Amarillo Suite 205, Box 15 San Juan, Puerto Rico 00926
YES
YES
YES
Bo. Boquerón PR-937 Km. 3.0 Las Piedras, PR 00771
693C73-24-B-000015
Signed: Emily McCleary
Contract Specialist
9/10/2024 FHWA Confidential Page 1 of 5
Novel Construction, LLC 12 December 2024
Schedule Total of Bid Items: 3,485,000.00$ 64.0% 5,716,162.50$ 63.6% 5,700,000.00$ 26.0% 4,391,781.00$ 7.1% 3,733,410.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-908579, ER-HWY-257; AC-857579, ER-HWY-260 & 261
CQ = "Contract Quantity"
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
15000-1000
Line 0010 ALL LPSM 70,000.00$ 70,000.00$ 124,000.00$ 500,000.00$ 9,000.00$ 30,000.00$
15100-1000
Line 0020 ALL LPSM 171,541.50$ 171,541.50$ 550,000.00$ 55,000.00$ 399,284.00$ 280,000.00$
15102-0000
Line 0030 1 CTSM 315,000.00$ 315,000.00$ 315,000.00$ 315,000.00$ 315,000.00$ 315,000.00$
15401-0000
Line 0040 ALL LPSM 85,000.00$ 85,000.00$ 50,000.00$ 500,000.00$ 32,000.00$ 30,000.00$
15401-1000
Line 0050 ALL LPSM 100,000.00$ 100,000.00$ 108,000.00$ 500,000.00$ 60,000.00$ 10,000.00$
15501-0000
Line 0060 ALL LPSM 42,000.00$ 42,000.00$ 20,000.00$ 189,656.00$ 15,000.00$ 10,000.00$
20100-1000
Line 0070 0.30 Cuerda 21,500.00$ 6,450.00$ 1,800.00$ 1,500.00$ 3,600.00$ 12,000.00$
20100-2000
Line 0080 19 Each 1,200.00$ 22,800.00$ 51,300.00$ 3,800.00$ 55,081.00$ 20,900.00$
20200-1000
Line 0090 ALL LPSM 5,300.00$ 5,300.00$ 15,000.00$ 50,000.00$ 37,500.00$ 20,000.00$
20200-9000
Line 0100 1 Each 250.00$ 250.00$ 150.00$ 100.00$ 1,500.00$ 5,000.00$
20201-6000
Line 0110 115 M 325.00$ 37,375.00$ 8,050.00$ 17,250.00$ 7,475.00$ 11,500.00$
20300-1000
Line 0120 1,020 m3 35.00$ 35,700.00$ 69,360.00$ 16,728.00$ 61,200.00$ 35,700.00$
20300-2000
Line 0130 30 m3 370.00$ 11,100.00$ 19,050.00$ 6,000.00$ 3,750.00$ 7,500.00$
20300-5000
Line 0140 2,760 m3 55.00$ 151,800.00$ 165,600.00$ 55,200.00$ 110,400.00$ 82,800.00$
20500-1000
Line 0150 145 m3 40.00$ 5,800.00$ 10,150.00$ 2,900.00$ 10,440.00$ 5,800.00$
20600-1000
Line 0160 1,780 m3 45.00$ 80,100.00$ 80,100.00$ 44,500.00$ 106,800.00$ 71,200.00$
20600-5000
Line 0170 ALL LPSM 90,000.00$ 90,000.00$ 30,000.00$ 100,000.00$ 100,000.00$ 30,000.00$
20600-6000
Line 0180 ALL LPSM 35,000.00$ 35,000.00$ 30,000.00$ 100,000.00$ 85,000.00$ 10,000.00$
20600-7000
Line 0190 ALL LPSM 105,000.00$ 105,000.00$ 120,000.00$ 300,000.00$ 100,000.00$ 30,000.00$
21000-1000
Line 0200 620 M 10.00$ 6,200.00$ 6,200.00$ 6,200.00$ 6,200.00$ 6,200.00$
21000-2000
Line 0210 550 Each 15.00$ 8,250.00$ 8,250.00$ 8,250.00$ 8,250.00$ 8,250.00$
21000-6000
Line 0220 1 Each 5,800.00$ 5,800.00$ 35,000.00$ 10,000.00$ 7,500.00$ 10,000.00$
21001-1000
Line 0230 3 Each 8,500.00$ 25,500.00$ 45,000.00$ 15,000.00$ 22,500.00$ 18,000.00$
30400-1000
Line 0240 145 m3 35.00$ 5,075.00$ 24,650.00$ 13,050.00$ 14,500.00$ 8,700.00$
30500-1000
Line 0250 875 m2 95.00$ 83,125.00$ 262,500.00$ 70,000.00$ 105,000.00$ 105,000.00$
40200-1000
Line 0260 90 m3 110.00$ 9,900.00$ 5,400.00$ 9,000.00$ 5,400.00$ 3,600.00$
Contractor Testing
50,000.00$ 500,000.00$ 32,000.00$ 30,000.00$
Construction Survey and Staking
Mobilization
Reimbursement for Municipal Tax Payments
Unclassified Excavation for Structures
Temporary Shoring and Bracing (HWY-257)
Temporary Shoring and Bracing (HWY-260)
Clearing and Grubbing
Cutting and Removing Trees, Small
Removal of Structures and Obstructions
Removal of Traffic Sign
Removal of Concrete Barrier
Unclassified Excavation
Lean Concrete Base
Full Depth Removal of Bituminous Concrete Pavement
Temporary Shoring and Bracing (HWY-261)
Silt Fence
Straw Bales
Temporary Rock Barrier Sediment Trap
Stabilized Construction Exit
Aggregate Base Course, Grading A
Contractor Testing (Biological Species Monitoring)
Construction Schedule
Rock Excavation
Borrow Class B-1
Trench Excavation, Unclassified
500,000.00$ 9,000.00$ 30,000.00$
Design Build, LLC LPC Contractors, Inc. Maglez Engineering & Contractors Corp Novel Construction, LLC
550,000.00$
124,000.00$
108,000.00$ 500,000.00$ 60,000.00$ 10,000.00$
55,000.00$ 399,284.00$ 280,000.00$
315,000.00$ 315,000.00$ 315,000.00$ 315,000.00$
2,700.00$ 200.00$ 2,899.00$ 1,100.00$
6,000.00$ 5,000.00$ 12,000.00$ 40,000.00$
20,000.00$ 189,656.00$ 15,000.00$ 10,000.00$
150.00$ 100.00$ 1,500.00$ 5,000.00$
15,000.00$ 50,000.00$ 37,500.00$ 20,000.00$
68.00$ 16.40$ 60.00$ 35.00$
70.00$ 150.00$ 65.00$ 100.00$
60.00$ 20.00$ 40.00$ 30.00$
635.00$ 200.00$ 125.00$ 250.00$
45.00$ 25.00$ 60.00$ 40.00$
70.00$ 20.00$ 72.00$ 40.00$
30,000.00$ 100,000.00$ 85,000.00$ 10,000.00$
30,000.00$ 100,000.00$ 100,000.00$ 30,000.00$
10.00$ 10.00$ 10.00$ 10.00$
120,000.00$ 300,000.00$ 100,000.00$ 30,000.00$
35,000.00$ 10,000.00$ 7,500.00$ 10,000.00$
15.00$ 15.00$ 15.00$ 15.00$
170.00$ 90.00$ 100.00$ 60.00$
15,000.00$ 5,000.00$ 7,500.00$ 6,000.00$
60.00$ 100.00$ 60.00$ 40.00$
300.00$ 80.00$ 120.00$ 120.00$
9/10/2024 Page 2 of 5
Schedule Total of Bid Items: 3,485,000.00$ 64.0% 5,716,162.50$ 63.6% 5,700,000.00$ 26.0% 4,391,781.00$ 7.1% 3,733,410.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-908579, ER-HWY-257; AC-857579, ER-HWY-260 & 261
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Design Build, LLC LPC Contractors, Inc. Maglez Engineering & Contractors Corp Novel Construction, LLC
40300-1000
Line 0270 2,010 m2 60.00$ 120,600.00$ 30,150.00$ 20,100.00$ 76,380.00$ 20,100.00$
42100-1000
Line 0280 30 TON 350.00$ 10,500.00$ 7,500.00$ 9,450.00$ 15,300.00$ 9,000.00$
42100-2000
Line 0290 15 TON 350.00$ 5,250.00$ 3,750.00$ 4,725.00$ 10,500.00$ 4,500.00$
42100-3000
Line 0300 300 TON 350.00$ 105,000.00$ 75,000.00$ 94,500.00$ 135,000.00$ 90,000.00$
42100-5000
Line 0310 395 TON 350.00$ 138,250.00$ 98,750.00$ 98,750.00$ 187,625.00$ 118,500.00$
60200-1000
Line 0320 700 lb 3.00$ 2,100.00$ 3,500.00$ 1,400.00$ 4,200.00$ 3,500.00$
60300-3000
Line 0330 20 M 875.00$ 17,500.00$ 10,000.00$ 5,000.00$ 14,500.00$ 8,000.00$
60300-8000
Line 0340 5 M 1,800.00$ 9,000.00$ 147,500.00$ 2,000.00$ 10,500.00$ 100,000.00$
60301-1000
Line 0350 1 Each 8,000.00$ 8,000.00$ 5,000.00$ 4,000.00$ 7,500.00$ 6,000.00$
60301-2000
Line 0360 1 Each 13,000.00$ 13,000.00$ 21,500.00$ 20,000.00$ 9,000.00$ 30,000.00$
60400-1000
Line 0370 1 Each 5,500.00$ 5,500.00$ 18,000.00$ 15,000.00$ 12,300.00$ 25,000.00$
60401-1000
Line 0380 1 Each 4,000.00$ 4,000.00$ 17,000.00$ 15,000.00$ 7,850.00$ 25,000.00$
60401-2000
Line 0390 1 Each 7,500.00$ 7,500.00$ 13,000.00$ 10,000.00$ 10,000.00$ 15,000.00$
60500-1000
Line 0400 40 M 100.00$ 4,000.00$ 10,000.00$ 1,600.00$ 2,880.00$ 1,200.00$
60600-1000
Line 0410 185 M 275.00$ 50,875.00$ 55,500.00$ 37,000.00$ 60,125.00$ 40,700.00$
60600-4000
Line 0420 30 M 18.00$ 540.00$ 990.00$ 900.00$ 2,160.00$ 1,500.00$
60600-5000
Line 0430 2 Each 10,000.00$ 20,000.00$ 12,600.00$ 20,000.00$ 16,800.00$ 12,000.00$
60600-9000
Line 0440 4 Each 8,500.00$ 34,000.00$ 39,600.00$ 20,000.00$ 34,500.00$ 24,000.00$
60601-1000
Line 0450 60 M 350.00$ 21,000.00$ 24,000.00$ 18,000.00$ 19,200.00$ 18,000.00$
60700-1000
Line 0460 235 M 115.00$ 27,025.00$ 23,265.00$ 23,500.00$ 23,500.00$ 23,500.00$
60700-3000
Line 0470 22 M 175.00$ 3,850.00$ 5,500.00$ 4,400.00$ 7,150.00$ 4,620.00$
61000-3000
Line 0480 70 M 515.00$ 36,050.00$ 196,000.00$ 35,000.00$ 42,000.00$ 28,000.00$
61000-4000
Line 0490 22 M 675.00$ 14,850.00$ 121,000.00$ 15,400.00$ 19,800.00$ 17,600.00$
61101-1000
Line 0500 12 mo 4,850.00$ 58,200.00$ 79,200.00$ 60,000.00$ 86,400.00$ 36,000.00$
61200-2000
Line 0510 4 Each 1,800.00$ 7,200.00$ 44,000.00$ 24,000.00$ 36,000.00$ 16,000.00$
61400-1000
Line 0520 1,520 m3 585.00$ 889,200.00$ 760,000.00$ 1,520,000.00$ 1,086,800.00$ 912,000.00$
Hot Plant Mix Asphalt Concrete, Type S (75)(12)
Manhole, No. 1: Model B (Depth 3.50 m)
Inlet, No. 1: Model B (Depth 2.33 m)
Inlet, No. 2: Model A (Depth 3.39 m)
4 inch Pipe Underdrain, Type Non-Perforated PVC Schedule 40
W-Beam Guardrail, Single Face
Removal, Storage and Delivery of Existing Guardrail
Hot Plant Mix Asphalt Concrete, Type B (75)(34)
Reinforcing Steel
30" Reinforced Concrete Pipe Class-III
60" Reinforced Concrete Pipe Class III
30-inch Headwall, Type B
60-inch (Double) Headwall, Type B
Cold Milling Bituminous Concrete Pavement, Variable Depth (0.025m to 0.075m)
Hot Plant Mix Asphalt Concrete, Type S (50)(38)
Hot Plant Mix Asphalt Concrete, Type B (50)(12)
Concrete Barrier, Type C (Modified)
Field Office
Temporary Lighting Standard
Gabions
Crashworthy End Terminal Type II, TL-2
ThrieBeam Transition Section, Type II
W-Beam Guardrail, Single Face (Strong Post)
Barbed Wire Fence, Type A
Chain-Link Fence, Type A
Concrete Barrier, Type C
250.00$ 315.00$ 510.00$ 300.00$
15.00$ 10.00$ 38.00$ 10.00$
250.00$ 315.00$ 450.00$ 300.00$
250.00$ 315.00$ 700.00$ 300.00$
5.00$ 2.00$ 6.00$ 5.00$
250.00$ 250.00$ 475.00$ 300.00$
29,500.00$ 400.00$ 2,100.00$ 20,000.00$
500.00$ 250.00$ 725.00$ 400.00$
21,500.00$ 20,000.00$ 9,000.00$ 30,000.00$
5,000.00$ 4,000.00$ 7,500.00$ 6,000.00$
17,000.00$ 15,000.00$ 7,850.00$ 25,000.00$
18,000.00$ 15,000.00$ 12,300.00$ 25,000.00$
250.00$ 40.00$ 72.00$ 30.00$
13,000.00$ 10,000.00$ 10,000.00$ 15,000.00$
33.00$ 30.00$ 72.00$ 50.00$
300.00$ 200.00$ 325.00$ 220.00$
9,900.00$ 5,000.00$ 8,625.00$ 6,000.00$
6,300.00$ 10,000.00$ 8,400.00$ 6,000.00$
99.00$ 100.00$ 100.00$ 100.00$
400.00$ 300.00$ 320.00$ 300.00$
2,800.00$ 500.00$ 600.00$ 400.00$
250.00$ 200.00$ 325.00$ 210.00$
6,600.00$ 5,000.00$ 7,200.00$ 3,000.00$
5,500.00$ 700.00$ 900.00$ 800.00$
500.00$ 1,000.00$ 715.00$ 600.00$
11,000.00$ 6,000.00$ 9,000.00$ 4,000.00$
9/10/2024 Page 3 of 5
Schedule Total of Bid Items: 3,485,000.00$ 64.0% 5,716,162.50$ 63.6% 5,700,000.00$ 26.0% 4,391,781.00$ 7.1% 3,733,410.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-908579, ER-HWY-257; AC-857579, ER-HWY-260 & 261
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Design Build, LLC LPC Contractors, Inc. Maglez Engineering & Contractors Corp Novel Construction, LLC
61700-1000
Line 0530 60 m2 150.00$ 9,000.00$ 37,800.00$ 5,400.00$ 15,000.00$ 9,000.00$
61701-1000
Line 0540 95 m2 175.00$ 16,625.00$ 60,800.00$ 8,550.00$ 23,750.00$ 14,250.00$
61701-2000
Line 0550 20 m3 125.00$ 2,500.00$ 2,900.00$ 1,800.00$ 2,200.00$ 1,000.00$
61800-2000
Line 0560 775 M 18.00$ 13,950.00$ 10,075.00$ 9,300.00$ 16,275.00$ 7,750.00$
61800-3000
Line 0570 105 M 18.00$ 1,890.00$ 1,365.00$ 1,260.00$ 2,205.00$ 1,050.00$
62101-2000
Line 0580 25 Each 175.00$ 4,375.00$ 15,750.00$ 2,500.00$ 1,000.00$ 15,000.00$
62200-1000
Line 0590 10 m3 275.00$ 2,750.00$ 3,200.00$ 1,200.00$ 5,000.00$ 2,500.00$
62200-3000
Line 0600 5 m3 350.00$ 1,750.00$ 1,765.00$ 600.00$ 2,500.00$ 1,500.00$
62201-1000
Line 0610 10 m3 175.00$ 1,750.00$ 5,550.00$ 1,200.00$ 5,000.00$ 1,500.00$
62500-1000
Line 0620 70 m3 85.00$ 5,950.00$ 18,200.00$ 5,600.00$ 7,000.00$ 7,000.00$
62700-1000
Line 0630 110 m2 5.50$ 605.00$ 3,960.00$ 550.00$ 29,700.00$ 3,850.00$
62700-3000
Line 0640 375 m2 8.50$ 3,187.50$ 1,687.50$ 3,750.00$ 8,250.00$ 37,500.00$
62800-1000
Line 0650 270 m2 15.00$ 4,050.00$ 10,800.00$ 2,700.00$ 6,750.00$ 6,750.00$
63200-2000
Line 0660 20 M 175.00$ 3,500.00$ 9,200.00$ 6,000.00$ 4,500.00$ 4,000.00$
63200-3000
Line 0670 2 Each 625.00$ 1,250.00$ 8,400.00$ 2,000.00$ 5,120.00$ 4,000.00$
63500-6000
Line 0680 2 Each 4,800.00$ 9,600.00$ 11,200.00$ 6,000.00$ 28,800.00$ 28,000.00$
63500-7000
Line 0690 130 M 5.25$ 682.50$ 3,120.00$ 260.00$ 10,400.00$ 5,200.00$
63500-8000
Line 0700 175 M 12.50$ 2,187.50$ 4,725.00$ 875.00$ 6,314.00$ 2,625.00$
63504-1000
Line 0710 ALL LPSM 2,800.00$ 2,800.00$ 20,600.00$ 50,000.00$ 37,200.00$ 30,000.00$
63504-2000
Line 0720 1 CTSM 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$
63505-1000
Line 0730 3 Each 760.00$ 2,280.00$ 6,600.00$ 3,000.00$ 2,544.00$ 10,500.00$
63505-2000
Line 0740 1 Each 300.00$ 300.00$ 480.00$ 1,000.00$ 580.00$ 800.00$
63505-3000
Line 0750 1 Each 225.00$ 225.00$ 480.00$ 1,000.00$ 600.00$ 1,500.00$
63505-4000
Line 0760 2 Each 375.00$ 750.00$ 810.00$ 2,000.00$ 3,000.00$ 3,000.00$
63505-5000
Line 0770 2 Each 150.00$ 300.00$ 690.00$ 2,000.00$ 1,380.00$ 3,000.00$
63505-6000
Line 0780 2 Each 230.00$ 460.00$ 824.00$ 2,000.00$ 1,620.00$ 4,000.00$ 412.00$ 1,000.00$ 810.00$ 2,000.00$
345.00$ 1,000.00$ 690.00$ 1,500.00$
405.00$ 1,000.00$ 1,500.00$ 1,500.00$
480.00$ 1,000.00$ 600.00$ 1,500.00$
480.00$ 1,000.00$ 580.00$ 800.00$
2,200.00$ 1,000.00$ 848.00$ 3,500.00$
10,000.00$ 10,000.00$ 10,000.00$ 10,000.00$
20,600.00$ 50,000.00$ 37,200.00$ 30,000.00$
27.00$ 5.00$ 36.08$ 15.00$
24.00$ 2.00$ 80.00$ 40.00$
5,600.00$ 3,000.00$ 14,400.00$ 14,000.00$
4,200.00$ 1,000.00$ 2,560.00$ 2,000.00$
460.00$ 300.00$ 225.00$ 200.00$
40.00$ 10.00$ 25.00$ 25.00$
4.50$ 10.00$ 22.00$ 100.00$
36.00$ 5.00$ 270.00$ 35.00$
260.00$ 80.00$ 100.00$ 100.00$
Concrete Paved Waterway, Type I
Concrete Paved Waterway, Type II
Filter Blanket, Type A
Furnishing and Placing Loamy Topsoil
Seeding, (without mulch)
Jute Mesh
Sodding
Cleaning and Repair of Storm Sewer
Bed Course Material
Thermoplastic Pavement Marking Stripes, White
Thermoplastic Pavement Marking Stripes, Yellow
Right-of-Way Marker
Dumped Riprap, Class I
Dumped Riprap, Class III
PREPA Distribution, Standard AC-A6
PREPA Distribution, Standard E1-2-3
PREPA Distribution, Standard E1-2
PREPA Distribution, Standard F1-1
PREPA Distribution, Standard K-5
PREPA Distribution, Standard K-6
Cleaning and Repair of Manholes, Inlets and Catch Basins
Utility Concrete Pole, Class H-6, 45' Size
Conductor Wire, ACSR, 1/0 AWG
Conductor Wire, ACSR Triplex 600V, No. 2 AWG
Removal of Existing PREPA Facilities
Utility Company Compensation (PREPA)
640.00$ 90.00$ 250.00$ 150.00$
630.00$ 90.00$ 250.00$ 150.00$
13.00$ 12.00$ 21.00$ 10.00$
145.00$ 90.00$ 110.00$ 50.00$
630.00$ 100.00$ 40.00$ 600.00$
13.00$ 12.00$ 21.00$ 10.00$
555.00$ 120.00$ 500.00$ 150.00$
353.00$ 120.00$ 500.00$ 300.00$
320.00$ 120.00$ 500.00$ 250.00$
9/10/2024 Page 4 of 5
Schedule Total of Bid Items: 3,485,000.00$ 64.0% 5,716,162.50$ 63.6% 5,700,000.00$ 26.0% 4,391,781.00$ 7.1% 3,733,410.00$ Project No: PR ER DOT PRMNT RPR(17)
Project Name: AC-908579, ER-HWY-257; AC-857579, ER-HWY-260 & 261
Item No. Quantity Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Design Build, LLC LPC Contractors, Inc. Maglez Engineering & Contractors Corp Novel Construction, LLC
63505-7000
Line 0790 2 Each 490.00$ 980.00$ 280.00$ 2,000.00$ 600.00$ 1,000.00$
63505-8000
Line 0800 2 Each 1,100.00$ 2,200.00$ 2,400.00$ 2,000.00$ 1,300.00$ 3,000.00$
63505-9000
Line 0810 2 Each 1,200.00$ 2,400.00$ 23,200.00$ 2,000.00$ 21,800.00$ 12,000.00$
63506-1000
Line 0820 2 Each 1,980.00$ 3,960.00$ 344.00$ 2,000.00$ 900.00$ 6,000.00$
63600-2000
Line 0830 140 M 120.00$ 16,800.00$ 57,400.00$ 11,200.00$ 22,400.00$ 14,000.00$
63600-5000
Line 0840 4 Each 1,500.00$ 6,000.00$ 19,200.00$ 4,000.00$ 4,000.00$ 12,000.00$
63602-1000
Line 0850 40 M 80.00$ 3,200.00$ 40,000.00$ 6,000.00$ 9,000.00$ 12,000.00$
63602-5000
Line 0860 2 Each 550.00$ 1,100.00$ 4,800.00$ 4,000.00$ 2,400.00$ 8,000.00$
63603-9000
Line 0870 4 Each 1,400.00$ 5,600.00$ 30,400.00$ 2,000.00$ 16,000.00$ 16,000.00$
63604-1000
Line 0880 ALL LPSM 5,400.00$ 5,400.00$ 153,000.00$ 50,000.00$ 30,000.00$ 8,000.00$
63604-4000
Line 0890 1 Each 1,800.00$ 1,800.00$ 2,500.00$ 1,000.00$ 2,000.00$ 5,000.00$
63604-8000
Line 0900 1 CTSM 30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$
63802-1000
Line 0910 ALL LPSM 100,000.00$ 100,000.00$ 440,000.00$ 50,000.00$ 37,000.00$ 220,860.00$
64000-6000
Line 0920 108 Each 8.00$ 864.00$ 1,728.00$ 864.00$ 2,322.00$ 1,620.00$
64000-7000
Line 0930 54 Each 8.00$ 432.00$ 864.00$ 432.00$ 1,296.00$ 810.00$
66100-1000
Line 0940 2 Each 2,000.00$ 4,000.00$ 5,600.00$ 6,000.00$ 12,000.00$ 12,000.00$
91001-5000
Line 0950 4 Each 4,900.00$ 19,600.00$ 41,200.00$ 20,000.00$ 30,000.00$ 24,000.00$
91200-1000
Line 0960 135 m2 22.00$ 2,970.00$ 5,400.00$ 2,700.00$ 3,645.00$ 3,375.00$
93400-1000
Line 0970 12 m3 1,350.00$ 16,200.00$ 102,000.00$ 12,000.00$ 18,000.00$ 36,000.00$
93501-0000
Line 0980 8 Each 1,300.00$ 10,400.00$ 8,000.00$ 2,400.00$ 28,000.00$ 24,000.00$
96300-1000
Line 0990 130 m2 164.00$ 21,320.00$ 520,000.00$ 390,000.00$ 262,080.00$ 301,600.00$ 4,000.00$ 3,000.00$ 2,016.00$ 2,320.00$
1,000.00$ 300.00$ 3,500.00$ 3,000.00$
8,500.00$ 1,000.00$ 1,500.00$ 3,000.00$
40.00$ 20.00$ 27.00$ 25.00$
10,300.00$ 5,000.00$ 7,500.00$ 6,000.00$
2,800.00$ 3,000.00$ 6,000.00$ 6,000.00$
16.00$ 8.00$ 24.00$ 15.00$
16.00$ 8.00$ 21.50$ 15.00$
440,000.00$ 50,000.00$ 37,000.00$ 220,860.00$
30,000.00$ 30,000.00$ 30,000.00$ 30,000.00$
2,500.00$ 1,000.00$ 2,000.00$ 5,000.00$
153,000.00$ 50,000.00$ 30,000.00$ 8,000.00$
7,600.00$ 500.00$ 4,000.00$ 4,000.00$
2,400.00$ 2,000.00$ 1,200.00$ 4,000.00$
1,000.00$ 150.00$ 225.00$ 300.00$
4,800.00$ 1,000.00$ 1,000.00$ 3,000.00$
410.00$ 80.00$ 160.00$ 100.00$
172.00$ 1,000.00$ 450.00$ 3,000.00$
11,600.00$ 1,000.00$ 10,900.00$ 6,000.00$
1,200.00$ 1,000.00$ 650.00$ 1,500.00$
140.00$ 1,000.00$ 300.00$ 500.00$
4" Ductile Iron Pipe, Class 350
4" Ductile Iron Pipe, Gate Valve
4 inch Tapping Valve and Sleeve
Removal of Existing PRASA Facilities
4 inch Drain Valve
Utility Company Compensation (PRASA)
PREPA Distribution, Standard M16-2
PREPA Distribution, Standard M16-3
PREPA Distribution, Standard M16-4
PREPA Distribution, Standard M2-1
4" PVC Pipe, DR 14, Class 200
4" Gate Valve
Structural Concrete, Class III (General Use)
Locate Utility, Test Pit
Soil Nail Wall System
Maintenance of Traffic (MOT)
Reflective Raised Pavement Markers, Two way, Clear-Red
Reflective Raised Pavement Markers, Two way, Yellow-Yellow
Project Funding Sign
New Transition Module, < 45mph
Pre-fabricated Drainage Composite
9/10/2024 Page 5 of 5
| Bid Tabs Summary |
| Bid Tabs |
| Schedule B Tabulation of Bids - PR ER DOT PRMNT RPR(17).pdf |
| Bid Tabs Summary |
| Bid Tabs |
| Schedule C Tabulation of Bids - PR ER DOT PRMNT RPR(17).pdf |
| Bid Tabs Summary |
| Bid Tabs |
File details come from the government source that posted it. Updated .