Tabulation of Bids - PA ST Keystone.pdf

PDF 1 MB Posted

Attached to
PA ST KEYSTONE (Mike Wood BLVD)
Solicitation number
693C73-20-C-000017
Issued by

About this file

This document contains a tabulation of bids report and award notice for a federal highway construction project. The tabulation of bids report details bids received on April 14, 2020 for the PA ST KEYSTONE (Mike Wood BLVD) project to be completed on federal land in Pennsylvania. The apparent low bid of $3,822,864.85 was submitted by Ray Showman Jr. Excavating, Inc. The related award notice indicates contract 693C73-20-C-000017 was awarded to Ray Showman Jr. Excavating, Inc. on June 4, 2020 for a total of $3,983,572.85 including base bid and estimated incentives. The Department of Transportation Federal Highway Administration is the awarding agency.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 05/28/20

1 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Solcitation No: 693C73-20-B-000011

Division: Eastern Federal Lands

State: PA County: Crawford

Federal Land: Army Reserve, Keystone Opened at: Sterling, VA

Opened by: C. Shawn Long

Date: 04/14/20

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Ray Showman Jr. Excavating, Inc. Apparent low bidder. $3,822,864.84 12671 Route 19 South Waterford Pennsylvania 16441

Dean Construction, LLC $4,004,149.90 15884 Route 6 Smithport Pennsylvania 16749

Eclipse Companies, LLC $4,936,395.00 11554 E. Washington Street Chagrin Falls Ohio 44023

Engineer's Estimate $4,175,000.00

C. Shawn Long

Contract Specialist

4/14/2020

Ray Showman Jr. Excavating, Inc. 6/04/2020

2 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0100 15101-0000 MOBILIZATION

Ray Showman Jr. Excavating, Inc. Lump Sum $147,709.85 Dean Construction, LLC Lump Sum $281,000.00 Eclipse Companies, LLC Lump Sum $480,000.00 Engineer's Estimate ALL LPSM Lump Sum $272,415.00

A0120 15201-0000 CONSTRUCTION SURVEY AND STAKING

Ray Showman Jr. Excavating, Inc. Lump Sum $46,204.76 Dean Construction, LLC Lump Sum $27,300.00 Eclipse Companies, LLC Lump Sum $108,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

A0140 15401-0000 CONTRACTOR TESTING

Ray Showman Jr. Excavating, Inc. Lump Sum $15,119.22 Dean Construction, LLC Lump Sum $48,072.00 Eclipse Companies, LLC Lump Sum $311,391.00 Engineer's Estimate ALL LPSM Lump Sum $45,000.00

A0160 15702-1000 SOIL EROSION CONTROL, TEMPORARY DIVERSION CHANNEL

Ray Showman Jr. Excavating, Inc. Lump Sum $4,196.28 Dean Construction, LLC Lump Sum $51,438.00 Eclipse Companies, LLC Lump Sum $40,000.00 Engineer's Estimate ALL LPSM Lump Sum $8,750.00

A0180 15705-0100 SOIL EROSION CONTROL, SILT FENCE

Ray Showman Jr. Excavating, Inc. $6.39 $19,170.00 Dean Construction, LLC $9.00 $27,000.00 Eclipse Companies, LLC $3.25 $9,750.00 Engineer's Estimate 3,000 LNFT $4.50 $13,500.00

A0200 15706-0200 SOIL EROSION CONTROL, CHECK DAM

Ray Showman Jr. Excavating, Inc. $155.45 $8,549.75 Dean Construction, LLC $253.00 $13,915.00 Eclipse Companies, LLC $750.00 $41,250.00 Engineer's Estimate 55 EACH $500.00 $27,500.00

3 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0220 20104-0000 CLEARING

Ray Showman Jr. Excavating, Inc. $20,124.24 $70,434.84 Dean Construction, LLC $7,380.00 $25,830.00 Eclipse Companies, LLC $6,700.00 $23,450.00 Engineer's Estimate 3.5 ACRE $14,500.00 $50,750.00

A0240 20201-0000 SELECTIVE CLEARING

Ray Showman Jr. Excavating, Inc. $20,124.24 $30,186.36 Dean Construction, LLC $8,519.00 $12,778.50 Eclipse Companies, LLC $8,100.00 $12,150.00 Engineer's Estimate 1.5 ACRE $15,000.00 $22,500.00

A0260 20301-1200 REMOVAL OF HEADWALL

Ray Showman Jr. Excavating, Inc. $214.58 $1,716.64 Dean Construction, LLC $346.00 $2,768.00 Eclipse Companies, LLC $1,200.00 $9,600.00 Engineer's Estimate 8 EACH $700.00 $5,600.00

A0280 20301-2400 REMOVAL OF SIGN

Ray Showman Jr. Excavating, Inc. $110.59 $1,105.90 Dean Construction, LLC $109.00 $1,090.00 Eclipse Companies, LLC $190.00 $1,900.00 Engineer's Estimate 10 EACH $200.00 $2,000.00

A0300 20302-0900 REMOVAL OF FENCE, CHAIN LINK

Ray Showman Jr. Excavating, Inc. $3.06 $30,600.00 Dean Construction, LLC $3.40 $34,000.00 Eclipse Companies, LLC $3.15 $31,500.00 Engineer's Estimate 10,000 LNFT $3.00 $30,000.00

A0320 20302-2100 REMOVAL OF PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $11.35 $11,917.50 Dean Construction, LLC $23.50 $24,675.00 Eclipse Companies, LLC $25.00 $26,250.00 Engineer's Estimate 1,050 LNFT $22.00 $23,100.00

4 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0340 20315-0000 SAWCUTTING PAVEMENT

Ray Showman Jr. Excavating, Inc. $7.52 $2,256.00 Dean Construction, LLC $12.00 $3,600.00 Eclipse Companies, LLC $3.15 $945.00 Engineer's Estimate 300 LNFT $5.50 $1,650.00

A0360 20401-0000 ROADWAY EXCAVATION

Ray Showman Jr. Excavating, Inc. $13.00 $234,000.00 Dean Construction, LLC $11.90 $214,200.00 Eclipse Companies, LLC $18.80 $338,400.00 Engineer's Estimate 18,000 CUYD $21.00 $378,000.00

A0380 25102-0300 PLACED RIPRAP, METHOD A, CLASS 3

Ray Showman Jr. Excavating, Inc. $76.28 $8,390.80 Dean Construction, LLC $112.30 $12,353.00 Eclipse Companies, LLC $140.00 $15,400.00 Engineer's Estimate 110 TON $90.00 $9,900.00

A0400 30101-4000 AGGREGATE BASE GRADING C OR D

Ray Showman Jr. Excavating, Inc. $29.80 $536,400.00 Dean Construction, LLC $34.40 $619,200.00 Eclipse Companies, LLC $42.00 $756,000.00 Engineer's Estimate 18,000 TON $30.00 $540,000.00

A0440 31303-0000 AGGREGATE-TOPSOIL COURSE

Ray Showman Jr. Excavating, Inc. $44.45 $43,561.00 Dean Construction, LLC $97.80 $95,844.00 Eclipse Companies, LLC $93.50 $91,630.00 Engineer's Estimate 980 CUYD $85.00 $83,300.00

A0460 40101-0600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3

MILLION ESAL (PG 76-22, TYPE III-B PAVEMENT ROUGHNESS)

Ray Showman Jr. Excavating, Inc. $118.48 $497,616.00 Dean Construction, LLC $105.30 $442,260.00 Eclipse Companies, LLC $98.00 $411,600.00 Engineer's Estimate 4,200 TON $105.00 $441,000.00

5 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0500 40101-1300 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1-INCH NOMINAL MAXIMUM SIZE AGGREGATE, <0.3

MILLION ESAL (PG 58-28)

Ray Showman Jr. Excavating, Inc. $88.28 $865,144.00 Dean Construction, LLC $85.80 $840,840.00 Eclipse Companies, LLC $81.00 $793,800.00 Engineer's Estimate 9,800 TON $90.00 $882,000.00

A0560 41201-0000 TACK COAT

Ray Showman Jr. Excavating, Inc. $844.20 $21,105.00 Dean Construction, LLC $574.00 $14,350.00 Eclipse Companies, LLC $555.00 $13,875.00 Engineer's Estimate 25 TON $1,700.00 $42,500.00

A0580 41301-0000 ASPHALT PAVEMENT MILLING

Ray Showman Jr. Excavating, Inc. $56.16 $8,424.00 Dean Construction, LLC $22.90 $3,435.00 Eclipse Companies, LLC $17.70 $2,655.00 Engineer's Estimate 150 SQYD $30.00 $4,500.00

A0600 60103-0180 CONCRETE, HEADWALL FOR 36-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $5,932.01 $11,864.02 Dean Construction, LLC $6,111.00 $12,222.00 Eclipse Companies, LLC $5,700.00 $11,400.00 Engineer's Estimate 2 EACH $5,500.00 $11,000.00

A0620 60201-0500 15-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $57.05 $10,839.50 Dean Construction, LLC $69.00 $13,110.00 Eclipse Companies, LLC $65.00 $12,350.00 Engineer's Estimate 190 LNFT $75.00 $14,250.00

A0640 60201-0600 18-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $101.62 $10,670.10 Dean Construction, LLC $84.70 $8,893.50 Eclipse Companies, LLC $80.50 $8,452.50 Engineer's Estimate 105 LNFT $85.00 $8,925.00

6 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0660 60201-0800 24-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $89.28 $54,460.80 Dean Construction, LLC $123.00 $75,030.00 Eclipse Companies, LLC $91.00 $55,510.00 Engineer's Estimate 610 LNFT $100.00 $61,000.00

A0680 60201-1000 36-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $276.14 $13,807.00 Dean Construction, LLC $303.00 $15,150.00 Eclipse Companies, LLC $147.00 $7,350.00 Engineer's Estimate 50 LNFT $150.00 $7,500.00

A0700 60210-0500 END SECTION FOR 15-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $1,228.76 $12,287.60 Dean Construction, LLC $364.00 $3,640.00 Eclipse Companies, LLC $800.00 $8,000.00 Engineer's Estimate 10 EACH $725.00 $7,250.00

A0720 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $1,281.35 $7,688.10 Dean Construction, LLC $390.00 $2,340.00 Eclipse Companies, LLC $810.00 $4,860.00 Engineer's Estimate 6 EACH $850.00 $5,100.00

A0740 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT

Ray Showman Jr. Excavating, Inc. $1,309.55 $31,429.20 Dean Construction, LLC $459.00 $11,016.00 Eclipse Companies, LLC $890.00 $21,360.00 Engineer's Estimate 24 EACH $1,500.00 $36,000.00

A0760 60220-1800 8 FEET SPAN, 4 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT

Ray Showman Jr. Excavating, Inc. $1,569.18 $70,613.10 Dean Construction, LLC $2,993.00 $134,685.00 Eclipse Companies, LLC $2,800.00 $126,000.00 Engineer's Estimate 45 LNFT $2,800.00 $126,000.00

7 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0780 60220-3000 10 FEET SPAN, 5 FEET RISE PRECAST REINFORCED CONCRETE BOX CULVERT

Ray Showman Jr. Excavating, Inc. $2,405.68 $101,038.56 Dean Construction, LLC $3,405.00 $143,010.00 Eclipse Companies, LLC $3,750.00 $157,500.00 Engineer's Estimate 42 LNFT $3,800.00 $159,600.00

A0800 60226-0000 END SECTION FOR REINFORCED CONCRETE BOX CULVERT (FOR 8 FEET SPAN x 4 FEET RISE BOX CULVERT)

Ray Showman Jr. Excavating, Inc. $15,540.21 $31,080.42 Dean Construction, LLC $11,407.00 $22,814.00 Eclipse Companies, LLC $25,000.00 $50,000.00 Engineer's Estimate 2 EACH $20,000.00 $40,000.00

A0820 60226-0000 END SECTION FOR REINFORCED CONCRETE BOX CULVERT (FOR 10 FEET SPAN x 5 FEET RISE BOX CULVERT

Ray Showman Jr. Excavating, Inc. $22,133.62 $44,267.24 Dean Construction, LLC $13,739.00 $27,478.00 Eclipse Companies, LLC $34,000.00 $68,000.00 Engineer's Estimate 2 EACH $25,000.00 $50,000.00

A0840 61701-4650 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS B STEEL POSTS

Ray Showman Jr. Excavating, Inc. $29.11 $5,822.00 Dean Construction, LLC $71.00 $14,200.00 Eclipse Companies, LLC $30.00 $6,000.00 Engineer's Estimate 200 LNFT $35.00 $7,000.00

A0860 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Ray Showman Jr. Excavating, Inc. $3,370.68 $20,224.08 Dean Construction, LLC $132.00 $792.00 Eclipse Companies, LLC $2,061.00 $12,366.00 Engineer's Estimate 6 EACH $2,600.00 $15,600.00

A0880 61901-2000 FENCE, CHAIN LINK, 72-INCH HEIGHT

Ray Showman Jr. Excavating, Inc. $30.51 $6,102.00 Dean Construction, LLC $63.00 $12,600.00 Eclipse Companies, LLC $21.50 $4,300.00 Engineer's Estimate 200 LNFT $25.00 $5,000.00

8 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0900 62402-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH

Ray Showman Jr. Excavating, Inc. $8,310.69 $54,019.49 Dean Construction, LLC $41,300.00 $268,450.00 Eclipse Companies, LLC $21,736.00 $141,284.00 Engineer's Estimate 6.5 ACRE $20,000.00 $130,000.00

A0920 62501-0000 TURF ESTABLISHMENT

Ray Showman Jr. Excavating, Inc. $6,990.96 $67,113.22 Dean Construction, LLC $5,894.00 $56,582.40 Eclipse Companies, LLC $2,600.00 $24,960.00 Engineer's Estimate 9.6 ACRE $4,100.00 $39,360.00

A0940 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING

Ray Showman Jr. Excavating, Inc. $100.46 $7,534.50 Dean Construction, LLC $86.90 $6,517.50 Eclipse Companies, LLC $35.00 $2,625.00 Engineer's Estimate 75 SQFT $90.00 $6,750.00

A0960 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID

Ray Showman Jr. Excavating, Inc. $1.28 $65,792.00 Dean Construction, LLC $1.32 $67,848.00 Eclipse Companies, LLC $1.50 $77,100.00 Engineer's Estimate 51,400 LNFT $1.35 $69,390.00

A0980 63401-1600 PAVEMENT MARKINGS, TYPE H, BROKEN

Ray Showman Jr. Excavating, Inc. $1.28 $4,128.00 Dean Construction, LLC $1.32 $4,257.00 Eclipse Companies, LLC $1.50 $4,837.50 Engineer's Estimate 3,225 LNFT $0.80 $2,580.00

A1000 63405-3200 PAVEMENT MARKINGS, TYPE H, RAILROAD SYMBOL

Ray Showman Jr. Excavating, Inc. $1,123.56 $2,247.12 Dean Construction, LLC $1,298.00 $2,596.00 Eclipse Companies, LLC $1,182.00 $2,364.00 Engineer's Estimate 2 EACH $1,750.00 $3,500.00

9 out of 9

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A1020 63501-0000 TEMPORARY TRAFFIC CONTROL

Ray Showman Jr. Excavating, Inc. Lump Sum $365,397.31 Dean Construction, LLC Lump Sum $73,775.00 Eclipse Companies, LLC Lump Sum $365,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00

A1040 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION

Ray Showman Jr. Excavating, Inc. Lump Sum $95,230.00 Dean Construction, LLC Lump Sum $95,230.00 Eclipse Companies, LLC Lump Sum $95,230.00 Engineer's Estimate ALL CTSM Lump Sum $95,230.00

A1060 63701-0000 FIELD OFFICE

Ray Showman Jr. Excavating, Inc. $15,401.59 $15,401.59 Dean Construction, LLC $25,965.00 $25,965.00 Eclipse Companies, LLC $40,000.00 $40,000.00 Engineer's Estimate 1 EACH $30,000.00 $30,000.00

A1080 64803-0100 SYSTEM INSTALLATION, NATURAL GAS UTILITY COMPANY COMPENSATION

Ray Showman Jr. Excavating, Inc. Lump Sum $110,000.00 Dean Construction, LLC Lump Sum $110,000.00 Eclipse Companies, LLC Lump Sum $110,000.00 Engineer's Estimate ALL CTSM Lump Sum $110,000.00

Total Schedule - All Items

Ray Showman Jr. Excavating, Inc. $3,822,864.84 Dean Construction, LLC $4,004,149.90 Eclipse Companies, LLC $4,936,395.00 Engineer's Estimate $4,175,000.00

Bid Error Report

1 out of 2

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Bid Item Check Pass

Bidder Line Item Number Bidder's Extension Computed Extension

No Line Item Errors Found

Bid Error Report

2 out of 2

Project No: PA ST KEYSTONE

Project Name: Mike Wood Boulevard

Schedule: A

Schedule Type: Base

Bid Total Check Pass

Bidder Bidder's Bid Amount Computed Bid Amount Error

Eclipse Companies, LLC $4,940,595.00 $4,936,395.00 X

Dean Construction, LLC $4,004,194.90 $4,004,149.90 X

Ray Showman Jr. Excavating, Inc. $3,822,864.85 $3,822,864.85

The apparent low bidder is 8.43% below the engineer's estimate.

File details come from the government source that posted it. Updated .