Tabulation of Bids - NP-NATR 3D34 3E15.pdf
PDF 839 KB Posted
- Attached to
- Natchez Trace Parkway Federal contract opportunity
- Solicitation number
- 693C73-21-C-000005
About this file
This document contains a bid tabulation report and related federal contract opportunity award notice. The bid tabulation report details bids received for the Natchez Trace Parkway project to resurface and reconstruct 15 miles of roadway between mile markers 251 to 266.37 in Pontotoc and Lee Counties, Mississippi. Riley Bridge Co., Inc. provided the apparent low bid of $4,246,133.59 for Schedule A work. The contract was awarded to Riley Bridge Co., Inc. on February 4, 2021 for a total of $7,349,436.54 to complete both Schedule A and Schedule B work. The awarding agency was the Department of Transportation Federal Highway Administration. Work is to be completed by the awarded contractor Riley Bridge Co., Inc. based on the line item bids and pricing terms specified in the tabulation report.
View the file
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 02/04/21
1 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Contractor Responsive?
Engineer's Estimate
Ausbeen Contruction Company, Inc.
Central Southern Construction Corporation
Estes Bros. Const., Inc.
Riley Bridge Co., Inc.
WG Construction Company, Inc.
Base Schedule A
$4,030,000.00
$4,531,193.55
$5,276,745.00
$5,539,105.30
$4,246,133.59
$4,522,190.00
Option: B
$2,380,000.00
$2,910,796.70
$2,817,655.00
$3,223,298.35
$2,831,962.75
$2,822,200.00
Contractor Responsive?
Engineer's Estimate
Ausbeen Contruction Company, Inc.
Central Southern Construction Corporation
Estes Bros. Const., Inc.
Riley Bridge Co., Inc.
WG Construction Company, Inc.
Total Base Schedule A and Option(s): B
$6,410,000.00
$7,441,990.25
$8,094,400.00
$8,762,403.65
$7,078,096.34
$7,344,390.00
2 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Solcitation No: 693C7321B000004
Division: Eastern Federal Lands
State: MS County: Pontotoc, Lee
Federal Land: Natchez Trace Parkway Opened at: Ashburn, VA
Opened by: Johnnie Ordonez
Date: 12/09/20
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Riley Bridge Co., Inc. Apparent low bidder $4,246,133.59 1001 East Lawrence Street Russellville, AL 35654
WG Construction Company, Inc. $4,522,190.00 12051 Hwy 4 East Ripley, MS 38663
Ausbeen Contruction Company, Inc. $4,531,193.55 31385 County Line Rd Okolona Mississippi 38860
Central Southern Construction Corporation $5,276,745.00 2410 Harper Street Jacksonville, FL 32204
Estes Bros. Const., Inc. $5,539,105.30 126 Sugar Run Road Jonesville, VA 24263
Engineer's Estimate $4,030,000.00
Contract Specialist Johnnie Ordonez
2/4/2021
Riley Bridge Co., Inc. 2/4/2021
3 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0100 15101-0000 MOBILIZATION
Riley Bridge Co., Inc. Lump Sum $360,090.60 WG Construction Company, Inc. Lump Sum $500,000.00 Ausbeen Contruction Company, Inc. Lump Sum $736,500.00 Central Southern Construction Corporation Lump Sum $850,000.00 Estes Bros. Const., Inc. Lump Sum $940,847.00 Engineer's Estimate ALL LPSM Lump Sum $445,665.00
A0110 15201-0000 CONSTRUCTION SURVEY AND STAKING
Riley Bridge Co., Inc. Lump Sum $22,000.00 WG Construction Company, Inc. Lump Sum $60,000.00 Ausbeen Contruction Company, Inc. Lump Sum $20,000.00 Central Southern Construction Corporation Lump Sum $150,000.00 Estes Bros. Const., Inc. Lump Sum $66,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
A0120 15401-0000 CONTRACTOR TESTING
Riley Bridge Co., Inc. Lump Sum $54,595.75 WG Construction Company, Inc. Lump Sum $48,000.00 Ausbeen Contruction Company, Inc. Lump Sum $50,000.00 Central Southern Construction Corporation Lump Sum $175,000.00 Estes Bros. Const., Inc. Lump Sum $65,000.00 Engineer's Estimate ALL LPSM Lump Sum $32,000.00
A0130 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Riley Bridge Co., Inc. $7.36 $5,152.00 WG Construction Company, Inc. $6.00 $4,200.00 Ausbeen Contruction Company, Inc. $8.00 $5,600.00 Central Southern Construction Corporation $5.00 $3,500.00 Estes Bros. Const., Inc. $6.07 $4,249.00 Engineer's Estimate 700 LNFT $8.00 $5,600.00
A0140 20301-2400 REMOVAL OF SIGN
Riley Bridge Co., Inc. $113.17 $226.34 WG Construction Company, Inc. $300.00 $600.00 Ausbeen Contruction Company, Inc. $200.00 $400.00 Central Southern Construction Corporation $150.00 $300.00 Estes Bros. Const., Inc. $220.00 $440.00 Engineer's Estimate 2 EACH $150.00 $300.00
4 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0150 20301-3400 REMOVAL OF WHEELSTOP
Riley Bridge Co., Inc. $45.32 $135.96 WG Construction Company, Inc. $300.00 $900.00 Ausbeen Contruction Company, Inc. $200.00 $600.00 Central Southern Construction Corporation $100.00 $300.00 Estes Bros. Const., Inc. $605.00 $1,815.00 Engineer's Estimate 3 EACH $55.00 $165.00
A0160 20302-0500 REMOVAL OF CURB, CONCRETE
Riley Bridge Co., Inc. $28.30 $566.00 WG Construction Company, Inc. $25.00 $500.00 Ausbeen Contruction Company, Inc. $100.00 $2,000.00 Central Southern Construction Corporation $45.00 $900.00 Estes Bros. Const., Inc. $22.00 $440.00 Engineer's Estimate 20 LNFT $35.00 $700.00
A0170 20303-3200 REMOVAL OF SIDEWALK, CONCRETE
Riley Bridge Co., Inc. $16.98 $254.70 WG Construction Company, Inc. $35.00 $525.00 Ausbeen Contruction Company, Inc. $120.00 $1,800.00 Central Southern Construction Corporation $50.00 $750.00 Estes Bros. Const., Inc. $55.00 $825.00 Engineer's Estimate 15 SQYD $50.00 $750.00
A0180 20315-0000 SAWCUTTING PAVEMENT
Riley Bridge Co., Inc. $31.13 $778.25 WG Construction Company, Inc. $13.00 $325.00 Ausbeen Contruction Company, Inc. $25.00 $625.00 Central Southern Construction Corporation $25.00 $625.00 Estes Bros. Const., Inc. $27.50 $687.50 Engineer's Estimate 25 LNFT $15.00 $375.00
A0190 20401-0000 ROADWAY EXCAVATION
Riley Bridge Co., Inc. $46.86 $74,976.00 WG Construction Company, Inc. $30.00 $48,000.00 Ausbeen Contruction Company, Inc. $50.00 $80,000.00 Central Southern Construction Corporation $80.00 $128,000.00 Estes Bros. Const., Inc. $82.50 $132,000.00 Engineer's Estimate 1,600 CUYD $35.00 $56,000.00
5 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0200 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2
Riley Bridge Co., Inc. $124.49 $2,489.80 WG Construction Company, Inc. $120.00 $2,400.00 Ausbeen Contruction Company, Inc. $180.00 $3,600.00 Central Southern Construction Corporation $200.00 $4,000.00 Estes Bros. Const., Inc. $333.85 $6,677.00 Engineer's Estimate 20 TON $70.00 $1,400.00
A0210 31302-0000 AGGREGATE-TOPSOIL COURSE
Riley Bridge Co., Inc. $11.53 $383,949.00 WG Construction Company, Inc. $8.50 $283,050.00 Ausbeen Contruction Company, Inc. $9.00 $299,700.00 Central Southern Construction Corporation $7.00 $233,100.00 Estes Bros. Const., Inc. $8.80 $293,040.00 Engineer's Estimate 33,300 SQYD $7.00 $233,100.00
A0230 40101-0200 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3
MILLION ESAL (TYPE 1-A OR TYPE IV PAVEMENT ROUGHNESS, PG 67-22)
Riley Bridge Co., Inc. $119.60 $1,939,314.00 WG Construction Company, Inc. $126.00 $2,043,090.00 Ausbeen Contruction Company, Inc. $110.17 $1,786,406.55 Central Southern Construction Corporation $125.00 $2,026,875.00 Estes Bros. Const., Inc. $135.30 $2,193,889.50 Engineer's Estimate 16,215 TON $121.00 $1,962,015.00
A0240 40102-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL MAXIMUM SIZE AGGREGATE, WEDGE
AND LEVELING COURSE
Riley Bridge Co., Inc. $123.22 $135,542.00 WG Construction Company, Inc. $130.00 $143,000.00 Ausbeen Contruction Company, Inc. $113.48 $124,828.00 Central Southern Construction Corporation $165.00 $181,500.00 Estes Bros. Const., Inc. $176.00 $193,600.00 Engineer's Estimate 1,100 TON $155.00 $170,500.00
A0260 40301-0200 ASPHALT CONCRETE PAVEMENT, TYPE 2
Riley Bridge Co., Inc. $139.68 $433,008.00 WG Construction Company, Inc. $175.00 $542,500.00 Ausbeen Contruction Company, Inc. $123.39 $382,509.00 Central Southern Construction Corporation $155.00 $480,500.00 Estes Bros. Const., Inc. $165.00 $511,500.00 Engineer's Estimate 3,100 TON $135.00 $418,500.00
6 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0270 41201-0000 TACK COAT
Riley Bridge Co., Inc. $1,075.15 $47,306.60 WG Construction Company, Inc. $1,400.00 $61,600.00 Ausbeen Contruction Company, Inc. $950.00 $41,800.00 Central Southern Construction Corporation $850.00 $37,400.00 Estes Bros. Const., Inc. $880.00 $38,720.00 Engineer's Estimate 44 TON $800.00 $35,200.00
A0280 41301-0000 ASPHALT PAVEMENT MILLING (MICROMILLING)
Riley Bridge Co., Inc. $5.59 $90,558.00 WG Construction Company, Inc. $4.00 $64,800.00 Ausbeen Contruction Company, Inc. $11.00 $178,200.00 Central Southern Construction Corporation $14.00 $226,800.00 Estes Bros. Const., Inc. $12.10 $196,020.00 Engineer's Estimate 16,200 SQYD $7.50 $121,500.00
A0290 41301-0800 ASPHALT PAVEMENT MILLING, 3-INCH DEPTH
Riley Bridge Co., Inc. $7.29 $47,385.00 WG Construction Company, Inc. $5.00 $32,500.00 Ausbeen Contruction Company, Inc. $15.00 $97,500.00 Central Southern Construction Corporation $16.00 $104,000.00 Estes Bros. Const., Inc. $15.40 $100,100.00 Engineer's Estimate 6,500 SQYD $17.00 $110,500.00
A0300 41401-2000 CRACKS, CLEANING AND SEALING
Riley Bridge Co., Inc. $5.66 $68,486.00 WG Construction Company, Inc. $5.50 $66,550.00 Ausbeen Contruction Company, Inc. $5.00 $60,500.00 Central Southern Construction Corporation $4.00 $48,400.00 Estes Bros. Const., Inc. $5.50 $66,550.00 Engineer's Estimate 12,100 LNFT $2.40 $29,040.00
A0310 55225-0000 CLEAN AND RESEAL JOINTS
Riley Bridge Co., Inc. $11.32 $13,018.00 WG Construction Company, Inc. $5.50 $6,325.00 Ausbeen Contruction Company, Inc. $10.00 $11,500.00 Central Southern Construction Corporation $14.00 $16,100.00 Estes Bros. Const., Inc. $11.00 $12,650.00 Engineer's Estimate 1,150 LNFT $10.00 $11,500.00
7 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0320 55235-0000 EXPANSION JOINTS (ASPHALTIC PLUG)
Riley Bridge Co., Inc. $565.96 $56,596.00 WG Construction Company, Inc. $200.00 $20,000.00 Ausbeen Contruction Company, Inc. $500.00 $50,000.00 Central Southern Construction Corporation $300.00 $30,000.00 Estes Bros. Const., Inc. $550.00 $55,000.00 Engineer's Estimate 100 LNFT $250.00 $25,000.00
A0330 55235-0000 EXPANSION JOINTS (PRECOMPRESSED HYBRID)
Riley Bridge Co., Inc. $339.53 $33,953.00 WG Construction Company, Inc. $200.00 $20,000.00 Ausbeen Contruction Company, Inc. $300.00 $30,000.00 Central Southern Construction Corporation $200.00 $20,000.00 Estes Bros. Const., Inc. $330.00 $33,000.00 Engineer's Estimate 100 LNFT $100.00 $10,000.00
A0340 60411-0000 INLET MODIFICATION
Riley Bridge Co., Inc. $735.62 $3,678.10 WG Construction Company, Inc. $2,200.00 $11,000.00 Ausbeen Contruction Company, Inc. $5,000.00 $25,000.00 Central Southern Construction Corporation $3,000.00 $15,000.00 Estes Bros. Const., Inc. $4,400.00 $22,000.00 Engineer's Estimate 5 EACH $1,500.00 $7,500.00
A0350 60515-0000 UNDERDRAIN CLEANOUT (INSTALLATION OF BRIDGE WEEP HOLE FILTER)
Riley Bridge Co., Inc. $372.34 $27,925.50 WG Construction Company, Inc. $950.00 $71,250.00 Ausbeen Contruction Company, Inc. $550.00 $41,250.00 Central Southern Construction Corporation $300.00 $22,500.00 Estes Bros. Const., Inc. $577.50 $43,312.50 Engineer's Estimate 75 EACH $350.00 $26,250.00
A0360 60901-1700 CURB, CONCRETE, 18-INCH DEPTH
Riley Bridge Co., Inc. $45.27 $1,810.80 WG Construction Company, Inc. $90.00 $3,600.00 Ausbeen Contruction Company, Inc. $100.00 $4,000.00 Central Southern Construction Corporation $50.00 $2,000.00 Estes Bros. Const., Inc. $68.75 $2,750.00 Engineer's Estimate 40 LNFT $55.00 $2,200.00
8 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0370 61401-0000 LEAN CONCRETE BACKFILL (FLOWABLE FILL)
Riley Bridge Co., Inc. $254.64 $6,366.00 WG Construction Company, Inc. $1,600.00 $40,000.00 Ausbeen Contruction Company, Inc. $500.00 $12,500.00 Central Southern Construction Corporation $700.00 $17,500.00 Estes Bros. Const., Inc. $110.00 $2,750.00 Engineer's Estimate 25 CUYD $400.00 $10,000.00
A0380 61504-1000 ACCESSIBILITY RAMP, CONCRETE
Riley Bridge Co., Inc. $339.53 $5,092.95 WG Construction Company, Inc. $150.00 $2,250.00 Ausbeen Contruction Company, Inc. $350.00 $5,250.00 Central Southern Construction Corporation $250.00 $3,750.00 Estes Bros. Const., Inc. $550.00 $8,250.00 Engineer's Estimate 15 SQYD $170.00 $2,550.00
A0390 62403-0000 FURNISHING AND PLACING TOPSOIL
Riley Bridge Co., Inc. $56.59 $848.85 WG Construction Company, Inc. $120.00 $1,800.00 Ausbeen Contruction Company, Inc. $250.00 $3,750.00 Central Southern Construction Corporation $75.00 $1,125.00 Estes Bros. Const., Inc. $55.00 $825.00 Engineer's Estimate 15 CUYD $90.00 $1,350.00
A0400 62501-0000 TURF ESTABLISHMENT
Riley Bridge Co., Inc. $3,621.56 $23,540.14 WG Construction Company, Inc. $3,200.00 $20,800.00 Ausbeen Contruction Company, Inc. $4,500.00 $29,250.00 Central Southern Construction Corporation $5,000.00 $32,500.00 Estes Bros. Const., Inc. $11,000.00 $71,500.00 Engineer's Estimate 6.5 ACRE $4,000.00 $26,000.00
A0410 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
Riley Bridge Co., Inc. $69.15 $8,643.75 WG Construction Company, Inc. $65.00 $8,125.00 Ausbeen Contruction Company, Inc. $65.00 $8,125.00 Central Southern Construction Corporation $100.00 $12,500.00 Estes Bros. Const., Inc. $71.50 $8,937.50 Engineer's Estimate 125 SQFT $60.00 $7,500.00
9 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0420 63401-1700 PAVEMENT MARKINGS, TYPE I, SOLID
Riley Bridge Co., Inc. $0.54 $94,500.00 WG Construction Company, Inc. $0.50 $87,500.00 Ausbeen Contruction Company, Inc. $0.50 $87,500.00 Central Southern Construction Corporation $0.52 $91,000.00 Estes Bros. Const., Inc. $0.55 $96,250.00 Engineer's Estimate 175,000 LNFT $0.40 $70,000.00
A0430 63401-1700 PAVEMENT MARKINGS, TYPE I, SOLID (PROFILED)
Riley Bridge Co., Inc. $4.79 $108,254.00 WG Construction Company, Inc. $4.50 $101,700.00 Ausbeen Contruction Company, Inc. $4.50 $101,700.00 Central Southern Construction Corporation $6.50 $146,900.00 Estes Bros. Const., Inc. $4.95 $111,870.00 Engineer's Estimate 22,600 LNFT $2.90 $65,540.00
A0440 63401-1800 PAVEMENT MARKINGS, TYPE I, BROKEN
Riley Bridge Co., Inc. $0.22 $12,320.00 WG Construction Company, Inc. $0.20 $11,200.00 Ausbeen Contruction Company, Inc. $0.20 $11,200.00 Central Southern Construction Corporation $0.32 $17,920.00 Estes Bros. Const., Inc. $0.22 $12,320.00 Engineer's Estimate 56,000 LNFT $0.30 $16,800.00
A0450 63405-3300 PAVEMENT MARKINGS, TYPE I, TURN ARROW
Riley Bridge Co., Inc. $425.54 $1,702.16 WG Construction Company, Inc. $400.00 $1,600.00 Ausbeen Contruction Company, Inc. $400.00 $1,600.00 Central Southern Construction Corporation $550.00 $2,200.00 Estes Bros. Const., Inc. $440.00 $1,760.00 Engineer's Estimate 4 EACH $300.00 $1,200.00
A0460 63405-3650 PAVEMENT MARKINGS, TYPE I, ACCESSIBILITY SYMBOL
Riley Bridge Co., Inc. $851.07 $1,702.14 WG Construction Company, Inc. $800.00 $1,600.00 Ausbeen Contruction Company, Inc. $800.00 $1,600.00 Central Southern Construction Corporation $1,000.00 $2,000.00 Estes Bros. Const., Inc. $880.00 $1,760.00 Engineer's Estimate 2 EACH $450.00 $900.00
10 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0470 63406-0200 RAISED PAVEMENT MARKER, NON-PLOWABLE, BI-DIRECTIONAL REFLECTIVE
Riley Bridge Co., Inc. $15.96 $957.60 WG Construction Company, Inc. $15.00 $900.00 Ausbeen Contruction Company, Inc. $15.00 $900.00 Central Southern Construction Corporation $30.00 $1,800.00 Estes Bros. Const., Inc. $16.50 $990.00 Engineer's Estimate 60 EACH $40.00 $2,400.00
A0480 63501-0000 TEMPORARY TRAFFIC CONTROL
Riley Bridge Co., Inc. Lump Sum $118,410.60 WG Construction Company, Inc. Lump Sum $160,000.00 Ausbeen Contruction Company, Inc. Lump Sum $203,500.00 Central Southern Construction Corporation Lump Sum $150,000.00 Estes Bros. Const., Inc. Lump Sum $210,780.30 Engineer's Estimate ALL LPSM Lump Sum $60,000.00
A0490 63701-0000 FIELD OFFICE
Riley Bridge Co., Inc. $60,000.00 $60,000.00 WG Construction Company, Inc. $50,000.00 $50,000.00 Ausbeen Contruction Company, Inc. $30,000.00 $30,000.00 Central Southern Construction Corporation $40,000.00 $40,000.00 Estes Bros. Const., Inc. $30,000.00 $30,000.00 Engineer's Estimate 1 EACH $35,000.00 $35,000.00
Total Schedule - All Items
Riley Bridge Co., Inc. $4,246,133.59 WG Construction Company, Inc. $4,522,190.00 Ausbeen Contruction Company, Inc. $4,531,193.55 Central Southern Construction Corporation $5,276,745.00 Estes Bros. Const., Inc. $5,539,105.30 Engineer's Estimate $4,030,000.00
11 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Solcitation No: 693C7321B000004
Division: Eastern Federal Lands
State: MS County: Pontotoc, Lee
Federal Land: Natchez Trace Parkway Opened at: Ashburn, VA
Opened by: Johnnie Ordonez
Date: 12/09/20
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Central Southern Construction Corporation $2,817,655.00 2410 Harper Street Jacksonville, FL 32204
WG Construction Company, Inc. $2,822,200.00 12051 Hwy 4 East Ripley, MS 38663
Riley Bridge Co., Inc. Apparent low bidder $2,831,962.75 1001 East Lawrence Street Russellville, AL 35654
Ausbeen Contruction Company, Inc. $2,910,796.70 31385 County Line Rd Okolona Mississippi 38860
Estes Bros. Const., Inc. $3,223,298.35 126 Sugar Run Road Jonesville, VA 24263
Engineer's Estimate $2,380,000.00
Johnnie Ordonez Contract Specialist 2/4/2021
Riley Bridge Co., Inc. 2/4/2021
12 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0500 15101-0000 MOBILIZATION
Central Southern Construction Corporation Lump Sum $250,000.00 WG Construction Company, Inc. Lump Sum $315,000.00 Riley Bridge Co., Inc. Lump Sum $241,664.30 Ausbeen Contruction Company, Inc. Lump Sum $389,783.70 Estes Bros. Const., Inc. Lump Sum $419,536.00 Engineer's Estimate ALL LPSM Lump Sum $198,095.00
B0510 15201-0000 CONSTRUCTION SURVEY AND STAKING
Central Southern Construction Corporation Lump Sum $20,000.00 WG Construction Company, Inc. Lump Sum $50,000.00 Riley Bridge Co., Inc. Lump Sum $9,000.00 Ausbeen Contruction Company, Inc. Lump Sum $10,000.00 Estes Bros. Const., Inc. Lump Sum $24,000.00 Engineer's Estimate ALL LPSM Lump Sum $20,000.00
B0520 15401-0000 CONTRACTOR TESTING
Central Southern Construction Corporation Lump Sum $50,000.00 WG Construction Company, Inc. Lump Sum $50,000.00 Riley Bridge Co., Inc. Lump Sum $21,276.60 Ausbeen Contruction Company, Inc. Lump Sum $40,000.00 Estes Bros. Const., Inc. Lump Sum $46,000.00 Engineer's Estimate ALL LPSM Lump Sum $25,000.00
B0530 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Central Southern Construction Corporation $5.00 $1,500.00 WG Construction Company, Inc. $6.00 $1,800.00 Riley Bridge Co., Inc. $7.37 $2,211.00 Ausbeen Contruction Company, Inc. $8.00 $2,400.00 Estes Bros. Const., Inc. $6.07 $1,821.00 Engineer's Estimate 300 LNFT $8.00 $2,400.00
B0540 20301-2400 REMOVAL OF SIGN
Central Southern Construction Corporation $150.00 $600.00 WG Construction Company, Inc. $200.00 $800.00 Riley Bridge Co., Inc. $113.17 $452.68 Ausbeen Contruction Company, Inc. $200.00 $800.00 Estes Bros. Const., Inc. $220.00 $880.00 Engineer's Estimate 4 EACH $150.00 $600.00
13 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0550 20302-0500 REMOVAL OF CURB, CONCRETE
Central Southern Construction Corporation $45.00 $1,800.00 WG Construction Company, Inc. $25.00 $1,000.00 Riley Bridge Co., Inc. $28.30 $1,132.00 Ausbeen Contruction Company, Inc. $100.00 $4,000.00 Estes Bros. Const., Inc. $22.00 $880.00 Engineer's Estimate 40 LNFT $35.00 $1,400.00
B0560 20302-2600 REMOVAL OF PAVEMENT MARKINGS
Central Southern Construction Corporation $5.00 $14,000.00 WG Construction Company, Inc. $2.00 $5,600.00 Riley Bridge Co., Inc. $2.13 $5,964.00 Ausbeen Contruction Company, Inc. $2.00 $5,600.00 Estes Bros. Const., Inc. $2.20 $6,160.00 Engineer's Estimate 2,800 LNFT $6.00 $16,800.00
B0570 20303-0300 REMOVAL OF CONCRETE
Central Southern Construction Corporation $50.00 $1,750.00 WG Construction Company, Inc. $40.00 $1,400.00 Riley Bridge Co., Inc. $16.98 $594.30 Ausbeen Contruction Company, Inc. $120.00 $4,200.00 Estes Bros. Const., Inc. $55.00 $1,925.00 Engineer's Estimate 35 SQYD $50.00 $1,750.00
B0580 20303-1400 REMOVAL OF PAVED WATERWAY, CONCRETE
Central Southern Construction Corporation $50.00 $16,250.00 WG Construction Company, Inc. $40.00 $13,000.00 Riley Bridge Co., Inc. $22.64 $7,358.00 Ausbeen Contruction Company, Inc. $70.00 $22,750.00 Estes Bros. Const., Inc. $44.00 $14,300.00 Engineer's Estimate 325 SQYD $25.00 $8,125.00
B0590 20303-3200 REMOVAL OF SIDEWALK, CONCRETE
Central Southern Construction Corporation $50.00 $1,500.00 WG Construction Company, Inc. $35.00 $1,050.00 Riley Bridge Co., Inc. $16.98 $509.40 Ausbeen Contruction Company, Inc. $120.00 $3,600.00 Estes Bros. Const., Inc. $55.00 $1,650.00 Engineer's Estimate 30 SQYD $50.00 $1,500.00
14 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0600 20315-0000 SAWCUTTING PAVEMENT
Central Southern Construction Corporation $25.00 $625.00 WG Construction Company, Inc. $13.00 $325.00 Riley Bridge Co., Inc. $31.13 $778.25 Ausbeen Contruction Company, Inc. $25.00 $625.00 Estes Bros. Const., Inc. $27.50 $687.50 Engineer's Estimate 25 LNFT $15.00 $375.00
B0610 20401-0000 ROADWAY EXCAVATION
Central Southern Construction Corporation $80.00 $68,000.00 WG Construction Company, Inc. $30.00 $25,500.00 Riley Bridge Co., Inc. $56.25 $47,812.50 Ausbeen Contruction Company, Inc. $75.00 $63,750.00 Estes Bros. Const., Inc. $82.50 $70,125.00 Engineer's Estimate 850 CUYD $35.00 $29,750.00
B0620 31302-0000 AGGREGATE-TOPSOIL COURSE
Central Southern Construction Corporation $7.00 $137,900.00 WG Construction Company, Inc. $8.50 $167,450.00 Riley Bridge Co., Inc. $14.44 $284,468.00 Ausbeen Contruction Company, Inc. $10.25 $201,925.00 Estes Bros. Const., Inc. $8.80 $173,360.00 Engineer's Estimate 19,700 SQYD $7.00 $137,900.00
B0630 40101-0200 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3
MILLION ESAL (TYPE 1-A OR TYPE IV PAVEMENT ROUGHNESS, PG 67-22)
Central Southern Construction Corporation $125.00 $1,256,250.00 WG Construction Company, Inc. $126.00 $1,266,300.00 Riley Bridge Co., Inc. $125.57 $1,261,978.50 Ausbeen Contruction Company, Inc. $115.63 $1,162,081.50 Estes Bros. Const., Inc. $135.30 $1,359,765.00 Engineer's Estimate 10,050 TON $121.00 $1,216,050.00
B0650 40102-0100 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 3/8-INCH NOMINAL MAXIMUM SIZE AGGREGATE, WEDGE
AND LEVELING COURSE
Central Southern Construction Corporation $165.00 $90,750.00 WG Construction Company, Inc. $130.00 $71,500.00 Riley Bridge Co., Inc. $126.33 $69,481.50 Ausbeen Contruction Company, Inc. $116.37 $64,003.50 Estes Bros. Const., Inc. $176.00 $96,800.00 Engineer's Estimate 550 TON $155.00 $85,250.00
15 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0670 40301-0200 ASPHALT CONCRETE PAVEMENT, TYPE 2
Central Southern Construction Corporation $150.00 $232,500.00 WG Construction Company, Inc. $175.00 $271,250.00 Riley Bridge Co., Inc. $133.73 $207,281.50 Ausbeen Contruction Company, Inc. $118.16 $183,148.00 Estes Bros. Const., Inc. $165.00 $255,750.00 Engineer's Estimate 1,550 TON $135.00 $209,250.00
B0680 41201-0000 TACK COAT
Central Southern Construction Corporation $850.00 $20,400.00 WG Construction Company, Inc. $1,400.00 $33,600.00 Riley Bridge Co., Inc. $1,075.16 $25,803.84 Ausbeen Contruction Company, Inc. $950.00 $22,800.00 Estes Bros. Const., Inc. $880.00 $21,120.00 Engineer's Estimate 24 TON $800.00 $19,200.00
B0690 41301-0000 ASPHALT PAVEMENT MILLING (MICROMILLING)
Central Southern Construction Corporation $14.00 $110,600.00 WG Construction Company, Inc. $4.00 $31,600.00 Riley Bridge Co., Inc. $11.45 $90,455.00 Ausbeen Contruction Company, Inc. $14.50 $114,550.00 Estes Bros. Const., Inc. $15.40 $121,660.00 Engineer's Estimate 7,900 SQYD $7.50 $59,250.00
B0700 41301-0800 ASPHALT PAVEMENT MILLING, 3-INCH DEPTH
Central Southern Construction Corporation $16.00 $8,000.00 WG Construction Company, Inc. $5.00 $2,500.00 Riley Bridge Co., Inc. $27.13 $13,565.00 Ausbeen Contruction Company, Inc. $24.00 $12,000.00 Estes Bros. Const., Inc. $27.50 $13,750.00 Engineer's Estimate 500 SQYD $17.00 $8,500.00
B0710 41401-2000 CRACKS, CLEANING AND SEALING
Central Southern Construction Corporation $4.00 $19,600.00 WG Construction Company, Inc. $5.50 $26,950.00 Riley Bridge Co., Inc. $5.66 $27,734.00 Ausbeen Contruction Company, Inc. $5.00 $24,500.00 Estes Bros. Const., Inc. $5.50 $26,950.00 Engineer's Estimate 4,900 LNFT $2.40 $11,760.00
16 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0720 55225-0000 CLEAN AND RESEAL JOINTS
Central Southern Construction Corporation $14.00 $7,700.00 WG Construction Company, Inc. $5.50 $3,025.00 Riley Bridge Co., Inc. $11.32 $6,226.00 Ausbeen Contruction Company, Inc. $10.00 $5,500.00 Estes Bros. Const., Inc. $11.00 $6,050.00 Engineer's Estimate 550 LNFT $10.00 $5,500.00
B0730 55235-0000 EXPANSION JOINTS (ASPHALTIC PLUG)
Central Southern Construction Corporation $300.00 $45,000.00 WG Construction Company, Inc. $200.00 $30,000.00 Riley Bridge Co., Inc. $565.96 $84,894.00 Ausbeen Contruction Company, Inc. $500.00 $75,000.00 Estes Bros. Const., Inc. $550.00 $82,500.00 Engineer's Estimate 150 LNFT $250.00 $37,500.00
B0740 55235-0000 EXPANSION JOINTS (PRECOMPRESSED HYBRID)
Central Southern Construction Corporation $200.00 $20,000.00 WG Construction Company, Inc. $200.00 $20,000.00 Riley Bridge Co., Inc. $339.53 $33,953.00 Ausbeen Contruction Company, Inc. $300.00 $30,000.00 Estes Bros. Const., Inc. $330.00 $33,000.00 Engineer's Estimate 100 LNFT $100.00 $10,000.00
B0750 60411-0000 INLET MODIFICATION
Central Southern Construction Corporation $3,000.00 $12,000.00 WG Construction Company, Inc. $2,200.00 $8,800.00 Riley Bridge Co., Inc. $814.86 $3,259.44 Ausbeen Contruction Company, Inc. $4,500.00 $18,000.00 Estes Bros. Const., Inc. $4,400.00 $17,600.00 Engineer's Estimate 4 EACH $1,500.00 $6,000.00
B0760 60515-0000 UNDERDRAIN CLEANOUT (INSTALLATION OF BRIDGE WEEP HOLE FILTER)
Central Southern Construction Corporation $300.00 $7,500.00 WG Construction Company, Inc. $950.00 $23,750.00 Riley Bridge Co., Inc. $478.73 $11,968.25 Ausbeen Contruction Company, Inc. $550.00 $13,750.00 Estes Bros. Const., Inc. $577.50 $14,437.50 Engineer's Estimate 25 EACH $350.00 $8,750.00
17 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0770 60801-0400 PAVED WATERWAY, TYPE 4
Central Southern Construction Corporation $300.00 $97,500.00 WG Construction Company, Inc. $100.00 $32,500.00 Riley Bridge Co., Inc. $135.81 $44,138.25 Ausbeen Contruction Company, Inc. $90.00 $29,250.00 Estes Bros. Const., Inc. $132.00 $42,900.00 Engineer's Estimate 325 SQYD $105.00 $34,125.00
B0780 60901-1700 CURB, CONCRETE, 18-INCH DEPTH
Central Southern Construction Corporation $50.00 $2,000.00 WG Construction Company, Inc. $90.00 $3,600.00 Riley Bridge Co., Inc. $45.27 $1,810.80 Ausbeen Contruction Company, Inc. $100.00 $4,000.00 Estes Bros. Const., Inc. $68.75 $2,750.00 Engineer's Estimate 40 LNFT $55.00 $2,200.00
B0790 61401-0000 LEAN CONCRETE BACKFILL (FLOWABLE FILL)
Central Southern Construction Corporation $700.00 $14,000.00 WG Construction Company, Inc. $1,600.00 $32,000.00 Riley Bridge Co., Inc. $254.64 $5,092.80 Ausbeen Contruction Company, Inc. $400.00 $8,000.00 Estes Bros. Const., Inc. $110.00 $2,200.00 Engineer's Estimate 20 CUYD $400.00 $8,000.00
B0800 61504-1000 ACCESSIBILITY RAMP, CONCRETE
Central Southern Construction Corporation $250.00 $7,500.00 WG Construction Company, Inc. $150.00 $4,500.00 Riley Bridge Co., Inc. $339.53 $10,185.90 Ausbeen Contruction Company, Inc. $250.00 $7,500.00 Estes Bros. Const., Inc. $550.00 $16,500.00 Engineer's Estimate 30 SQYD $170.00 $5,100.00
B0810 61601-1000 SLOPE PAVING, CONCRETE
Central Southern Construction Corporation $350.00 $12,250.00 WG Construction Company, Inc. $200.00 $7,000.00 Riley Bridge Co., Inc. $80.36 $2,812.60 Ausbeen Contruction Company, Inc. $140.00 $4,900.00 Estes Bros. Const., Inc. $572.00 $20,020.00 Engineer's Estimate 35 SQYD $190.00 $6,650.00
18 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0820 62403-0000 FURNISHING AND PLACING TOPSOIL
Central Southern Construction Corporation $75.00 $750.00 WG Construction Company, Inc. $120.00 $1,200.00 Riley Bridge Co., Inc. $56.69 $566.90 Ausbeen Contruction Company, Inc. $350.00 $3,500.00 Estes Bros. Const., Inc. $55.00 $550.00 Engineer's Estimate 10 CUYD $90.00 $900.00
B0830 62501-0000 TURF ESTABLISHMENT
Central Southern Construction Corporation $5,000.00 $17,500.00 WG Construction Company, Inc. $3,200.00 $11,200.00 Riley Bridge Co., Inc. $3,621.55 $12,675.43 Ausbeen Contruction Company, Inc. $4,500.00 $15,750.00 Estes Bros. Const., Inc. $11,000.00 $38,500.00 Engineer's Estimate 3.5 ACRE $4,000.00 $14,000.00
B0840 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
Central Southern Construction Corporation $100.00 $15,000.00 WG Construction Company, Inc. $90.00 $13,500.00 Riley Bridge Co., Inc. $95.75 $14,362.50 Ausbeen Contruction Company, Inc. $90.00 $13,500.00 Estes Bros. Const., Inc. $99.00 $14,850.00 Engineer's Estimate 150 SQFT $60.00 $9,000.00
B0850 63313-0000 RUMBLE STRIP
Central Southern Construction Corporation $20.00 $20,000.00 WG Construction Company, Inc. $2.00 $2,000.00 Riley Bridge Co., Inc. $0.12 $120.00 Ausbeen Contruction Company, Inc. $5.00 $5,000.00 Estes Bros. Const., Inc. $1.21 $1,210.00 Engineer's Estimate 1,000 LNFT $30.00 $30,000.00
B0860 63401-1700 PAVEMENT MARKINGS, TYPE I, SOLID (PROFILED)
Central Southern Construction Corporation $6.50 $96,200.00 WG Construction Company, Inc. $4.50 $66,600.00 Riley Bridge Co., Inc. $4.79 $70,892.00 Ausbeen Contruction Company, Inc. $4.50 $66,600.00 Estes Bros. Const., Inc. $4.95 $73,260.00 Engineer's Estimate 14,800 LNFT $2.90 $42,920.00
19 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0870 63401-1700 PAVEMENT MARKINGS, TYPE I, SOLID
Central Southern Construction Corporation $0.52 $65,000.00 WG Construction Company, Inc. $0.50 $62,500.00 Riley Bridge Co., Inc. $0.54 $67,500.00 Ausbeen Contruction Company, Inc. $0.50 $62,500.00 Estes Bros. Const., Inc. $0.55 $68,750.00 Engineer's Estimate 125,000 LNFT $0.40 $50,000.00
B0880 63401-1800 PAVEMENT MARKINGS, TYPE I, BROKEN
Central Southern Construction Corporation $0.32 $6,080.00 WG Construction Company, Inc. $0.20 $3,800.00 Riley Bridge Co., Inc. $0.22 $4,180.00 Ausbeen Contruction Company, Inc. $0.20 $3,800.00 Estes Bros. Const., Inc. $0.22 $4,180.00 Engineer's Estimate 19,000 LNFT $0.30 $5,700.00
B0890 63405-3300 PAVEMENT MARKINGS, TYPE I, TURN ARROW
Central Southern Construction Corporation $550.00 $6,050.00 WG Construction Company, Inc. $400.00 $4,400.00 Riley Bridge Co., Inc. $425.54 $4,680.94 Ausbeen Contruction Company, Inc. $400.00 $4,400.00 Estes Bros. Const., Inc. $440.00 $4,840.00 Engineer's Estimate 11 EACH $300.00 $3,300.00
B0900 63405-3450 PAVEMENT MARKINGS, TYPE I, "ONLY" WORD MESSAGE
Central Southern Construction Corporation $550.00 $4,400.00 WG Construction Company, Inc. $400.00 $3,200.00 Riley Bridge Co., Inc. $425.54 $3,404.32 Ausbeen Contruction Company, Inc. $400.00 $3,200.00 Estes Bros. Const., Inc. $440.00 $3,520.00 Engineer's Estimate 8 EACH $275.00 $2,200.00
B0910 63405-3650 PAVEMENT MARKINGS, TYPE I, ACCESSIBILITY SYMBOL
Central Southern Construction Corporation $1,000.00 $8,000.00 WG Construction Company, Inc. $800.00 $6,400.00 Riley Bridge Co., Inc. $851.07 $6,808.56 Ausbeen Contruction Company, Inc. $800.00 $6,400.00 Estes Bros. Const., Inc. $880.00 $7,040.00 Engineer's Estimate 8 EACH $450.00 $3,600.00
20 out of 20
Project No: NP-NATR 3D34, 3E15
Project Name: Natchez Trace Parkway (MP 251 to MP 266.37)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0920 63406-0200 RAISED PAVEMENT MARKER, NON-PLOWABLE, BI-DIRECTIONAL REFLECTIVE
Central Southern Construction Corporation $30.00 $1,200.00 WG Construction Company, Inc. $15.00 $600.00 Riley Bridge Co., Inc. $15.96 $638.40 Ausbeen Contruction Company, Inc. $15.00 $600.00 Estes Bros. Const., Inc. $16.50 $660.00 Engineer's Estimate 40 EACH $40.00 $1,600.00
B0930 63501-0000 TEMPORARY TRAFFIC CONTROL
Central Southern Construction Corporation Lump Sum $50,000.00 WG Construction Company, Inc. Lump Sum $145,000.00 Riley Bridge Co., Inc. Lump Sum $122,272.29 Ausbeen Contruction Company, Inc. Lump Sum $197,130.00 Estes Bros. Const., Inc. Lump Sum $110,861.35 Engineer's Estimate ALL LPSM Lump Sum $40,000.00
Total Schedule - All Items
Central Southern Construction Corporation $2,817,655.00 WG Construction Company, Inc. $2,822,200.00 Riley Bridge Co., Inc. $2,831,962.75 Ausbeen Contruction Company, Inc. $2,910,796.70 Estes Bros. Const., Inc. $3,223,298.35 Engineer's Estimate $2,380,000.00