Tabulation of Bids - MS ERFO NP VICK 2020-1(2).pdf

PDF 921 KB Posted

Attached to
Vicksburg National Military Park
Solicitation number
693C73-25-C-000007
Issued by

About this file

This is a bid tabulation report for a construction project at Vicksburg National Military Park for Grant Avenue and Union Avenue slide repairs. The project consists of a base Schedule A and optional Schedule B, with bids opened on December 12, 2024 in Ashburn, Virginia.

The contract was awarded to Central Southern Construction Corp. on January 9, 2025, who submitted the lowest combined bid of $7,438,460 ($3,789,630 for Schedule A and $3,648,830 for Schedule B). Other bidders included Eclipse Companies LLC ($8,468,086 total), Kovilic Construction Company Inc. ($11,233,200 total), and McKenzie Construction & Site Development LLC ($14,413,735.29 total). The Engineer's Estimate was $8,221,500 total. The work includes mobilization, construction survey and staking, erosion control, excavation, asphalt pavement, drilled shafts, drainage systems, concrete work, and traffic control. Eclipse Companies LLC had a bid error in Schedule B where their computed bid amount ($4,859,324) differed from their submitted amount ($4,863,604).

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tabulation of Bids Report Date: 01/09/25

1 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Contractor Responsive?

Engineer's Estimate

Central Southern Construction Corp.

Eclipse Companies, LLC

Kovilic Construction Company, Inc.

McKenzie Construction & Site Development, LLC

Base Schedule A

$3,315,500.00

$3,789,630.00

$3,608,762.00

$3,952,950.00

$6,438,149.28

Option: B

$4,906,000.00

$3,648,830.00

$4,859,324.00

$7,280,250.00

$7,975,586.01

Contractor Responsive?

Engineer's Estimate

Central Southern Construction Corp.

Eclipse Companies, LLC

Kovilic Construction Company, Inc.

McKenzie Construction & Site Development, LLC

Total Base Schedule A and Option(s): B

$8,221,500.00

$7,438,460.00

$8,468,086.00

$11,233,200.00

$14,413,735.29

2 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Solcitation No: 693C73-25-B-000002

Division: Eastern Federal Lands

State: MS County: Warren

Federal Land: Vicksburg National Military Park Opened at: Ashburn, Virginia

Opened by: Emily McCleary

Date: 12/12/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Eclipse Companies, LLC $3,608,762.00 11554 East Washington Street Chagrin Falls Ohio 44023

Central Southern Construction Corp. Low bidder $3,789,630.00 119 Sewald Street Jacksonville Florida 32204

Kovilic Construction Company, Inc. $3,952,950.00 3721 N. Carnation Street Franklin Park Illinois 60131

McKenzie Construction & Site Development, LLC $6,438,149.28 2301 Calvert Street NW Washington District of Columbia 20008

Engineer's Estimate $3,315,500.00

Emily McCleary

Contract Specialist

12 December 2024

Central Southern Construction Corp. 9 January 2025

3 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0100 15101-0000 MOBILIZATION

Eclipse Companies, LLC Lump Sum $985,255.00 Central Southern Construction Corp. Lump Sum $675,000.00 Kovilic Construction Company, Inc. Lump Sum $300,000.00 McKenzie Construction & Site Development, LLC Lump Sum $983,446.00 Engineer's Estimate ALL LPSM Lump Sum $335,780.00

A0110 15201-0000 CONSTRUCTION SURVEY AND STAKING

Eclipse Companies, LLC Lump Sum $57,486.00 Central Southern Construction Corp. Lump Sum $450,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 McKenzie Construction & Site Development, LLC Lump Sum $516,976.26 Engineer's Estimate ALL LPSM Lump Sum $42,000.00

A0120 15401-0000 CONTRACTOR TESTING

Eclipse Companies, LLC Lump Sum $150,820.00 Central Southern Construction Corp. Lump Sum $350,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 McKenzie Construction & Site Development, LLC Lump Sum $182,267.27 Engineer's Estimate ALL LPSM Lump Sum $37,500.00

A0130 15705-0100 SOIL EROSION CONTROL, SILT FENCE

Eclipse Companies, LLC $13.00 $13,650.00 Central Southern Construction Corp. $5.00 $5,250.00 Kovilic Construction Company, Inc. $10.00 $10,500.00 McKenzie Construction & Site Development, LLC $17.23 $18,091.50 Engineer's Estimate 1,050 LNFT $15.60 $16,380.00

A0140 15705-0300 SOIL EROSION CONTROL, SLOPE DRAINS

Eclipse Companies, LLC $136.00 $13,600.00 Central Southern Construction Corp. $50.00 $5,000.00 Kovilic Construction Company, Inc. $150.00 $15,000.00 McKenzie Construction & Site Development, LLC $861.62 $86,162.00 Engineer's Estimate 100 LNFT $104.00 $10,400.00

A0150 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Eclipse Companies, LLC $13.00 $2,600.00 Central Southern Construction Corp. $5.00 $1,000.00 Kovilic Construction Company, Inc. $50.00 $10,000.00 McKenzie Construction & Site Development, LLC $172.32 $34,464.00 Engineer's Estimate 200 LNFT $9.50 $1,900.00

4 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0160 15706-0400 SOIL EROSION CONTROL, SEDIMENT TRAP

Eclipse Companies, LLC $30,953.00 $30,953.00 Central Southern Construction Corp. $20,000.00 $20,000.00 Kovilic Construction Company, Inc. $5,000.00 $5,000.00 McKenzie Construction & Site Development, LLC $8,616.27 $8,616.27 Engineer's Estimate 1 EACH $10,400.00 $10,400.00

A0170 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

Eclipse Companies, LLC $17,714.00 $17,714.00 Central Southern Construction Corp. $15,000.00 $15,000.00 Kovilic Construction Company, Inc. $7,500.00 $7,500.00 McKenzie Construction & Site Development, LLC $25,848.81 $25,848.81 Engineer's Estimate 1 EACH $10,400.00 $10,400.00

A0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Eclipse Companies, LLC Lump Sum $6,720.00 Central Southern Construction Corp. Lump Sum $25,000.00 Kovilic Construction Company, Inc. Lump Sum $15,000.00 McKenzie Construction & Site Development, LLC Lump Sum $172,325.42 Engineer's Estimate ALL LPSM Lump Sum $15,000.00

A0190 20103-0000 CLEARING AND GRUBBING

Eclipse Companies, LLC $20.00 $72,000.00 Central Southern Construction Corp. $8.00 $28,800.00 Kovilic Construction Company, Inc. $5.00 $18,000.00 McKenzie Construction & Site Development, LLC $25.84 $93,024.00 Engineer's Estimate 3,600 SQYD $52.00 $187,200.00

A0200 20301-1400 REMOVAL OF INLET

Eclipse Companies, LLC $1,361.00 $1,361.00 Central Southern Construction Corp. $3,000.00 $3,000.00 Kovilic Construction Company, Inc. $1,000.00 $1,000.00 McKenzie Construction & Site Development, LLC $5,169.76 $5,169.76 Engineer's Estimate 1 EACH $1,600.00 $1,600.00

A0210 20302-0500 REMOVAL OF CURB, CONCRETE

Eclipse Companies, LLC $22.00 $4,950.00 Central Southern Construction Corp. $15.00 $3,375.00 Kovilic Construction Company, Inc. $25.00 $5,625.00 McKenzie Construction & Site Development, LLC $34.46 $7,753.50 Engineer's Estimate 225 LNFT $31.20 $7,020.00

5 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0220 20303-1600 REMOVAL OF PAVEMENT, ASPHALT

Eclipse Companies, LLC $26.00 $10,400.00 Central Southern Construction Corp. $10.00 $4,000.00 Kovilic Construction Company, Inc. $27.00 $10,800.00 McKenzie Construction & Site Development, LLC $17.23 $6,892.00 Engineer's Estimate 400 SQYD $26.00 $10,400.00

A0230 20420-0000 EMBANKMENT CONSTRUCTION

Eclipse Companies, LLC $66.00 $514,800.00 Central Southern Construction Corp. $45.00 $351,000.00 Kovilic Construction Company, Inc. $100.00 $780,000.00 McKenzie Construction & Site Development, LLC $51.69 $403,182.00 Engineer's Estimate 7,800 CUYD $22.35 $174,330.00

A0240 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E

Eclipse Companies, LLC $8.00 $17,600.00 Central Southern Construction Corp. $5.00 $11,000.00 Kovilic Construction Company, Inc. $10.00 $22,000.00 McKenzie Construction & Site Development, LLC $25.84 $56,848.00 Engineer's Estimate 2,200 SQYD $8.35 $18,370.00

A0250 20703-0000 GEOGRID (TYPE VI)

Eclipse Companies, LLC $5.00 $60,000.00 Central Southern Construction Corp. $6.00 $72,000.00 Kovilic Construction Company, Inc. $10.00 $120,000.00 McKenzie Construction & Site Development, LLC $25.84 $310,080.00 Engineer's Estimate 12,000 SQYD $13.00 $156,000.00

A0260 20803-0000 STRUCTURAL BACKFILL

Eclipse Companies, LLC $106.00 $10,600.00 Central Southern Construction Corp. $100.00 $10,000.00 Kovilic Construction Company, Inc. $250.00 $25,000.00 McKenzie Construction & Site Development, LLC $86.16 $8,616.00 Engineer's Estimate 100 CUYD $125.00 $12,500.00

A0270 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2

Eclipse Companies, LLC $152.00 $60,800.00 Central Southern Construction Corp. $200.00 $80,000.00 Kovilic Construction Company, Inc. $150.00 $60,000.00 McKenzie Construction & Site Development, LLC $430.81 $172,324.00 Engineer's Estimate 400 TON $208.00 $83,200.00

6 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0280 25302-1000 GABIONS, GALVANIZED OR ALUMINIZED COATED

Eclipse Companies, LLC $382.00 $171,900.00 Central Southern Construction Corp. $465.00 $209,250.00 Kovilic Construction Company, Inc. $500.00 $225,000.00 McKenzie Construction & Site Development, LLC $2,067.90 $930,555.00 Engineer's Estimate 450 CUYD $286.00 $128,700.00

A0290 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE (FULL DEPTH PATCH)

Eclipse Companies, LLC $76.00 $26,600.00 Central Southern Construction Corp. $40.00 $14,000.00 Kovilic Construction Company, Inc. $20.00 $7,000.00 McKenzie Construction & Site Development, LLC $258.48 $90,468.00 Engineer's Estimate 350 SQFT $52.00 $18,200.00

A0300 30101-4000 AGGREGATE BASE GRADING C OR D

Eclipse Companies, LLC $96.00 $14,400.00 Central Southern Construction Corp. $75.00 $11,250.00 Kovilic Construction Company, Inc. $100.00 $15,000.00 McKenzie Construction & Site Development, LLC $430.81 $64,621.50 Engineer's Estimate 150 TON $109.20 $16,380.00

A0310 30201-1000 ROADWAY AGGREGATE, METHOD 1 (#3 STONE)

Eclipse Companies, LLC $184.00 $78,200.00 Central Southern Construction Corp. $175.00 $74,375.00 Kovilic Construction Company, Inc. $175.00 $74,375.00 McKenzie Construction & Site Development, LLC $387.73 $164,785.25 Engineer's Estimate 425 CUYD $130.00 $55,250.00

A0320 30302-1000 DITCH RECONDITIONING

Eclipse Companies, LLC $37.00 $3,700.00 Central Southern Construction Corp. $50.00 $5,000.00 Kovilic Construction Company, Inc. $50.00 $5,000.00 McKenzie Construction & Site Development, LLC $258.48 $25,848.00 Engineer's Estimate 100 LNFT $22.00 $2,200.00

A0330 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA)

Eclipse Companies, LLC $258.00 $79,980.00 Central Southern Construction Corp. $218.00 $67,580.00 Kovilic Construction Company, Inc. $300.00 $93,000.00 McKenzie Construction & Site Development, LLC $430.81 $133,551.10 Engineer's Estimate 310 TON $286.00 $88,660.00

7 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0340 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (3/4-INCH NMSA)

Eclipse Companies, LLC $377.00 $28,275.00 Central Southern Construction Corp. $205.00 $15,375.00 Kovilic Construction Company, Inc. $300.00 $22,500.00 McKenzie Construction & Site Development, LLC $430.81 $32,310.75 Engineer's Estimate 75 TON $286.00 $21,450.00

A0350 41102-0000 PRIME COAT

Eclipse Companies, LLC $9.00 $4,050.00 Central Southern Construction Corp. $10.00 $4,500.00 Kovilic Construction Company, Inc. $5.00 $2,250.00 McKenzie Construction & Site Development, LLC $17.23 $7,753.50 Engineer's Estimate 450 SQYD $2.10 $945.00

A0360 41202-0000 TACK COAT

Eclipse Companies, LLC $8.00 $3,200.00 Central Southern Construction Corp. $5.00 $2,000.00 Kovilic Construction Company, Inc. $10.00 $4,000.00 McKenzie Construction & Site Development, LLC $17.23 $6,892.00 Engineer's Estimate 400 GAL $6.50 $2,600.00

A0370 41301-0600 ASPHALT PAVEMENT MILLING, 2-INCH DEPTH

Eclipse Companies, LLC $14.00 $32,900.00 Central Southern Construction Corp. $10.00 $23,500.00 Kovilic Construction Company, Inc. $27.00 $63,450.00 McKenzie Construction & Site Development, LLC $34.46 $80,981.00 Engineer's Estimate 2,350 SQYD $21.00 $49,350.00

A0380 56501-0200 DRILLED SHAFT, 24-INCH DIAMETER

Eclipse Companies, LLC $515.00 $412,000.00 Central Southern Construction Corp. $500.00 $400,000.00 Kovilic Construction Company, Inc. $1,065.00 $852,000.00 McKenzie Construction & Site Development, LLC $569.99 $455,992.00 Engineer's Estimate 800 LNFT $1,405.00 $1,124,000.00

A0390 60501-0000 STANDARD UNDERDRAIN SYSTEM

Eclipse Companies, LLC $75.00 $7,500.00 Central Southern Construction Corp. $100.00 $10,000.00 Kovilic Construction Company, Inc. $50.00 $5,000.00 McKenzie Construction & Site Development, LLC $258.48 $25,848.00 Engineer's Estimate 100 LNFT $94.00 $9,400.00

8 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0400 60521-0000 GRANULAR BACKFILL (#57 STONE)

Eclipse Companies, LLC $79.00 $592,500.00 Central Southern Construction Corp. $80.00 $600,000.00 Kovilic Construction Company, Inc. $125.00 $937,500.00 McKenzie Construction & Site Development, LLC $137.86 $1,033,950.00 Engineer's Estimate 7,500 TON $72.75 $545,625.00

A0410 60811-0000 DRAINAGE CHUTE

Eclipse Companies, LLC $4,584.00 $13,752.00 Central Southern Construction Corp. $5,000.00 $15,000.00 Kovilic Construction Company, Inc. $5,000.00 $15,000.00 McKenzie Construction & Site Development, LLC $25,848.81 $77,546.43 Engineer's Estimate 3 EACH $3,650.00 $10,950.00

A0420 60901-1700 CURB, CONCRETE, 18-INCH DEPTH (NON-MOUNTABLE)

Eclipse Companies, LLC $122.00 $27,450.00 Central Southern Construction Corp. $80.00 $18,000.00 Kovilic Construction Company, Inc. $100.00 $22,500.00 McKenzie Construction & Site Development, LLC $86.16 $19,386.00 Engineer's Estimate 225 LNFT $75.00 $16,875.00

A0430 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH

Eclipse Companies, LLC $22.00 $11,550.00 Central Southern Construction Corp. $25.00 $13,125.00 Kovilic Construction Company, Inc. $10.00 $5,250.00 McKenzie Construction & Site Development, LLC $17.36 $9,114.00 Engineer's Estimate 525 SQYD $21.00 $11,025.00

A0440 62502-0000 TURF ESTABLISHMENT

Eclipse Companies, LLC $23.00 $12,075.00 Central Southern Construction Corp. $10.00 $5,250.00 Kovilic Construction Company, Inc. $5.00 $2,625.00 McKenzie Construction & Site Development, LLC $24.93 $13,088.25 Engineer's Estimate 525 SQYD $26.00 $13,650.00

A0450 62901-0300 ROLLED EROSION CONTROL PRODUCT, TYPE 1.C

Eclipse Companies, LLC $28.00 $2,100.00 Central Southern Construction Corp. $8.00 $600.00 Kovilic Construction Company, Inc. $25.00 $1,875.00 McKenzie Construction & Site Development, LLC $86.16 $6,462.00 Engineer's Estimate 75 SQYD $10.40 $780.00

9 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0460 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID

Eclipse Companies, LLC $4.00 $11,200.00 Central Southern Construction Corp. $4.00 $11,200.00 Kovilic Construction Company, Inc. $5.00 $14,000.00 McKenzie Construction & Site Development, LLC $3.31 $9,268.00 Engineer's Estimate 2,800 LNFT $2.10 $5,880.00

A0470 63501-0000 TEMPORARY TRAFFIC CONTROL

Eclipse Companies, LLC Lump Sum $15,522.00 Central Southern Construction Corp. Lump Sum $150,000.00 Kovilic Construction Company, Inc. Lump Sum $25,000.00 McKenzie Construction & Site Development, LLC Lump Sum $86,162.71 Engineer's Estimate ALL LPSM Lump Sum $16,000.00

A0480 63701-0000 FIELD OFFICE

Eclipse Companies, LLC $23,399.00 $23,399.00 Central Southern Construction Corp. $25,000.00 $25,000.00 Kovilic Construction Company, Inc. $50,000.00 $50,000.00 McKenzie Construction & Site Development, LLC $66,279.00 $66,279.00 Engineer's Estimate 1 EACH $42,000.00 $42,000.00

A0490 66702-0000 NEGOTIATED PAY ITEM (WILDLIFE BIOLOGIST)

Eclipse Companies, LLC Lump Sum $5,200.00 Central Southern Construction Corp. Lump Sum $5,200.00 Kovilic Construction Company, Inc. Lump Sum $5,200.00 McKenzie Construction & Site Development, LLC Lump Sum $5,200.00 Engineer's Estimate ALL CTSM Lump Sum $5,200.00

Total Schedule - All Items

Eclipse Companies, LLC $3,608,762.00 Central Southern Construction Corp. $3,789,630.00 Kovilic Construction Company, Inc. $3,952,950.00 McKenzie Construction & Site Development, LLC $6,438,149.28 Engineer's Estimate $3,315,500.00

10 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Solcitation No: 693C73-25-B-000002

Division: Eastern Federal Lands

State: MS County: Warren

Federal Land: Vicksburg National Military Park Opened at: Ashburn, Virginia

Opened by: Emily McCleary

Date: 12/12/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Central Southern Construction Corp. Low bidder $3,648,830.00 119 Sewald Street Jacksonville Florida 32204

Eclipse Companies, LLC $4,859,324.00 11554 East Washington Street Chagrin Falls Ohio 44023

Kovilic Construction Company, Inc. $7,280,250.00 3721 N. Carnation Street Franklin Park Illinois 60131

McKenzie Construction & Site Development, LLC $7,975,586.01 2301 Calvert Street NW Washington District of Columbia 20008

Engineer's Estimate $4,906,000.00

Emily McCleary

Contract Specialist

12 December 2024

Central Southern Construction Corp. 9 January 2025

11 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0200 15101-0000 MOBILIZATION

Central Southern Construction Corp. Lump Sum $250,000.00 Eclipse Companies, LLC Lump Sum $923,000.00 Kovilic Construction Company, Inc. Lump Sum $300,000.00 McKenzie Construction & Site Development, LLC Lump Sum $718,392.79 Engineer's Estimate ALL LPSM Lump Sum $460,625.00

B0210 15201-0000 CONSTRUCTION SURVEY AND STAKING

Central Southern Construction Corp. Lump Sum $200,000.00 Eclipse Companies, LLC Lump Sum $69,929.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 McKenzie Construction & Site Development, LLC Lump Sum $338,270.09 Engineer's Estimate ALL LPSM Lump Sum $42,000.00

B0220 15401-0000 CONTRACTOR TESTING

Central Southern Construction Corp. Lump Sum $75,000.00 Eclipse Companies, LLC Lump Sum $199,820.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 McKenzie Construction & Site Development, LLC Lump Sum $129,146.11 Engineer's Estimate ALL LPSM Lump Sum $37,500.00

B0230 15705-0100 SOIL EROSION CONTROL, SILT FENCE

Central Southern Construction Corp. $5.00 $5,500.00 Eclipse Companies, LLC $17.00 $18,700.00 Kovilic Construction Company, Inc. $10.00 $11,000.00 McKenzie Construction & Site Development, LLC $17.21 $18,931.00 Engineer's Estimate 1,100 LNFT $15.60 $17,160.00

B0240 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Central Southern Construction Corp. $5.00 $4,500.00 Eclipse Companies, LLC $18.00 $16,200.00 Kovilic Construction Company, Inc. $25.00 $22,500.00 McKenzie Construction & Site Development, LLC $154.97 $139,473.00 Engineer's Estimate 900 LNFT $9.50 $8,550.00

B0250 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

Central Southern Construction Corp. $15,000.00 $15,000.00 Eclipse Companies, LLC $17,714.00 $17,714.00 Kovilic Construction Company, Inc. $7,500.00 $7,500.00 McKenzie Construction & Site Development, LLC $25,829.22 $25,829.22 Engineer's Estimate 1 EACH $5,200.00 $5,200.00

12 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN

Central Southern Construction Corp. Lump Sum $25,000.00 Eclipse Companies, LLC Lump Sum $6,720.00 Kovilic Construction Company, Inc. Lump Sum $15,000.00 McKenzie Construction & Site Development, LLC Lump Sum $172,194.81 Engineer's Estimate ALL LPSM Lump Sum $13,600.00

B0270 20103-0000 CLEARING AND GRUBBING

Central Southern Construction Corp. $8.00 $62,400.00 Eclipse Companies, LLC $4.00 $31,200.00 Kovilic Construction Company, Inc. $5.00 $39,000.00 McKenzie Construction & Site Development, LLC $30.99 $241,722.00 Engineer's Estimate 7,800 SQYD $26.00 $202,800.00

B0280 20301-1400 REMOVAL OF INLET

Central Southern Construction Corp. $3,000.00 $6,000.00 Eclipse Companies, LLC $3,473.00 $6,946.00 Kovilic Construction Company, Inc. $1,000.00 $2,000.00 McKenzie Construction & Site Development, LLC $5,165.84 $10,331.68 Engineer's Estimate 2 EACH $1,600.00 $3,200.00

B0290 20302-0500 REMOVAL OF CURB, CONCRETE

Central Southern Construction Corp. $15.00 $15,000.00 Eclipse Companies, LLC $16.00 $16,000.00 Kovilic Construction Company, Inc. $25.00 $25,000.00 McKenzie Construction & Site Development, LLC $43.04 $43,040.00 Engineer's Estimate 1,000 LNFT $31.20 $31,200.00

B0300 20303-1600 REMOVAL OF PAVEMENT, ASPHALT

Central Southern Construction Corp. $10.00 $29,000.00 Eclipse Companies, LLC $23.00 $66,700.00 Kovilic Construction Company, Inc. $27.00 $78,300.00 McKenzie Construction & Site Development, LLC $17.21 $49,909.00 Engineer's Estimate 2,900 SQYD $26.00 $75,400.00

B0310 20401-0000 ROADWAY EXCAVATION

Central Southern Construction Corp. $30.00 $204,000.00 Eclipse Companies, LLC $42.80 $291,040.00 Kovilic Construction Company, Inc. $100.00 $680,000.00 McKenzie Construction & Site Development, LLC $43.04 $292,672.00 Engineer's Estimate 6,800 CUYD $52.00 $353,600.00

13 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0320 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E

Central Southern Construction Corp. $5.00 $50,000.00 Eclipse Companies, LLC $5.00 $50,000.00 Kovilic Construction Company, Inc. $10.00 $100,000.00 McKenzie Construction & Site Development, LLC $25.82 $258,200.00 Engineer's Estimate 10,000 SQYD $8.35 $83,500.00

B0330 20703-0000 GEOGRID (TYPE VI)

Central Southern Construction Corp. $6.00 $81,000.00 Eclipse Companies, LLC $6.00 $81,000.00 Kovilic Construction Company, Inc. $10.00 $135,000.00 McKenzie Construction & Site Development, LLC $25.82 $348,570.00 Engineer's Estimate 13,500 SQYD $13.00 $175,500.00

B0340 20704-0000 GEOMEMBRANE

Central Southern Construction Corp. $12.00 $42,000.00 Eclipse Companies, LLC $7.00 $24,500.00 Kovilic Construction Company, Inc. $25.00 $87,500.00 McKenzie Construction & Site Development, LLC $60.26 $210,910.00 Engineer's Estimate 3,500 SQYD $16.65 $58,275.00

B0350 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2

Central Southern Construction Corp. $200.00 $20,000.00 Eclipse Companies, LLC $152.00 $15,200.00 Kovilic Construction Company, Inc. $250.00 $25,000.00 McKenzie Construction & Site Development, LLC $430.48 $43,048.00 Engineer's Estimate 100 TON $208.00 $20,800.00

B0360 30101-4000 AGGREGATE BASE GRADING C OR D

Central Southern Construction Corp. $75.00 $75,000.00 Eclipse Companies, LLC $83.00 $83,000.00 Kovilic Construction Company, Inc. $100.00 $100,000.00 McKenzie Construction & Site Development, LLC $301.34 $301,340.00 Engineer's Estimate 1,000 TON $109.20 $109,200.00

B0370 30211-0000 MECHANICALLY COMPACTED AGGREGATE COLUMN (IMPACT (DISPLACEMENT) RAMMED AGGREGATE

PIER)

Central Southern Construction Corp. $35.00 $875,000.00 Eclipse Companies, LLC $54.00 $1,350,000.00 Kovilic Construction Company, Inc. $133.00 $3,325,000.00 McKenzie Construction & Site Development, LLC $67.59 $1,689,750.00 Engineer's Estimate 25,000 LNFT $62.40 $1,560,000.00

14 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0380 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (3/4-INCH NMSA)

Central Southern Construction Corp. $205.00 $102,500.00 Eclipse Companies, LLC $213.00 $106,500.00 Kovilic Construction Company, Inc. $300.00 $150,000.00 McKenzie Construction & Site Development, LLC $430.48 $215,240.00 Engineer's Estimate 500 TON $286.00 $143,000.00

B0390 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA)

Central Southern Construction Corp. $218.00 $78,480.00 Eclipse Companies, LLC $227.00 $81,720.00 Kovilic Construction Company, Inc. $300.00 $108,000.00 McKenzie Construction & Site Development, LLC $430.48 $154,972.80 Engineer's Estimate 360 TON $286.00 $102,960.00

B0400 41102-0000 PRIME COAT

Central Southern Construction Corp. $10.00 $29,000.00 Eclipse Companies, LLC $3.00 $8,700.00 Kovilic Construction Company, Inc. $5.00 $14,500.00 McKenzie Construction & Site Development, LLC $17.21 $49,909.00 Engineer's Estimate 2,900 SQYD $2.10 $6,090.00

B0410 41202-0000 TACK COAT

Central Southern Construction Corp. $5.00 $2,250.00 Eclipse Companies, LLC $10.00 $4,500.00 Kovilic Construction Company, Inc. $10.00 $4,500.00 McKenzie Construction & Site Development, LLC $25.82 $11,619.00 Engineer's Estimate 450 GAL $6.50 $2,925.00

B0420 41301-0000 ASPHALT PAVEMENT MILLING (MICRO MILLING)

Central Southern Construction Corp. $20.00 $5,000.00 Eclipse Companies, LLC $26.00 $6,500.00 Kovilic Construction Company, Inc. $50.00 $12,500.00 McKenzie Construction & Site Development, LLC $129.14 $32,285.00 Engineer's Estimate 250 SQYD $31.50 $7,875.00

B0430 41301-0600 ASPHALT PAVEMENT MILLING, 2-INCH DEPTH

Central Southern Construction Corp. $10.00 $1,500.00 Eclipse Companies, LLC $79.00 $11,850.00 Kovilic Construction Company, Inc. $27.00 $4,050.00 McKenzie Construction & Site Development, LLC $172.19 $25,828.50 Engineer's Estimate 150 SQYD $21.00 $3,150.00

15 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0440 60501-0000 STANDARD UNDERDRAIN SYSTEM

Central Southern Construction Corp. $100.00 $95,000.00 Eclipse Companies, LLC $51.00 $48,450.00 Kovilic Construction Company, Inc. $50.00 $47,500.00 McKenzie Construction & Site Development, LLC $172.19 $163,580.50 Engineer's Estimate 950 LNFT $94.00 $89,300.00

B0450 60521-0000 GRANULAR BACKFILL (#57 STONE)

Central Southern Construction Corp. $80.00 $960,000.00 Eclipse Companies, LLC $77.00 $924,000.00 Kovilic Construction Company, Inc. $125.00 $1,500,000.00 McKenzie Construction & Site Development, LLC $137.75 $1,653,000.00 Engineer's Estimate 12,000 TON $72.75 $873,000.00

B0460 60801-0400 PAVED WATERWAY, TYPE 4

Central Southern Construction Corp. $350.00 $5,250.00 Eclipse Companies, LLC $451.00 $6,765.00 Kovilic Construction Company, Inc. $180.00 $2,700.00 McKenzie Construction & Site Development, LLC $1,033.16 $15,497.40 Engineer's Estimate 15 SQYD $156.00 $2,340.00

B0470 60801-0400 PAVED WATERWAY, TYPE 4 (V-DITCH)

Central Southern Construction Corp. $125.00 $56,250.00 Eclipse Companies, LLC $304.00 $136,800.00 Kovilic Construction Company, Inc. $180.00 $81,000.00 McKenzie Construction & Site Development, LLC $602.68 $271,206.00 Engineer's Estimate 450 SQYD $156.00 $70,200.00

B0480 60811-0000 DRAINAGE CHUTE

Central Southern Construction Corp. $5,000.00 $5,000.00 Eclipse Companies, LLC $3,839.00 $3,839.00 Kovilic Construction Company, Inc. $5,000.00 $5,000.00 McKenzie Construction & Site Development, LLC $34,438.96 $34,438.96 Engineer's Estimate 1 EACH $3,650.00 $3,650.00

B0490 60901-1700 CURB, CONCRETE, 18-INCH DEPTH (NON-MOUNTABLE)

Central Southern Construction Corp. $80.00 $16,000.00 Eclipse Companies, LLC $122.00 $24,400.00 Kovilic Construction Company, Inc. $100.00 $20,000.00 McKenzie Construction & Site Development, LLC $68.87 $13,774.00 Engineer's Estimate 200 LNFT $75.00 $15,000.00

16 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0500 61401-0000 LEAN CONCRETE BACKFILL (FLOWABLE FILL)

Central Southern Construction Corp. $1,000.00 $5,000.00 Eclipse Companies, LLC $1,008.00 $5,040.00 Kovilic Construction Company, Inc. $2,500.00 $12,500.00 McKenzie Construction & Site Development, LLC $1,377.55 $6,887.75 Engineer's Estimate 5 CUYD $3,200.00 $16,000.00

B0510 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH

Central Southern Construction Corp. $25.00 $125,000.00 Eclipse Companies, LLC $15.00 $75,000.00 Kovilic Construction Company, Inc. $10.00 $50,000.00 McKenzie Construction & Site Development, LLC $5.29 $26,450.00 Engineer's Estimate 5,000 SQYD $21.00 $105,000.00

B0520 62502-0000 TURF ESTABLISHMENT

Central Southern Construction Corp. $10.00 $50,000.00 Eclipse Companies, LLC $14.00 $70,000.00 Kovilic Construction Company, Inc. $5.00 $25,000.00 McKenzie Construction & Site Development, LLC $8.43 $42,150.00 Engineer's Estimate 5,000 SQYD $26.00 $130,000.00

B0530 62901-0300 ROLLED EROSION CONTROL PRODUCT, TYPE 1.C

Central Southern Construction Corp. $8.00 $40,000.00 Eclipse Companies, LLC $11.00 $55,000.00 Kovilic Construction Company, Inc. $10.00 $50,000.00 McKenzie Construction & Site Development, LLC $25.82 $129,100.00 Engineer's Estimate 5,000 SQYD $10.40 $52,000.00

B0540 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID

Central Southern Construction Corp. $4.00 $8,000.00 Eclipse Companies, LLC $5.00 $10,000.00 Kovilic Construction Company, Inc. $5.00 $10,000.00 McKenzie Construction & Site Development, LLC $3.31 $6,620.00 Engineer's Estimate 2,000 LNFT $2.10 $4,200.00

B0550 63501-0000 TEMPORARY TRAFFIC CONTROL

Central Southern Construction Corp. Lump Sum $25,000.00 Eclipse Companies, LLC Lump Sum $7,391.00 Kovilic Construction Company, Inc. Lump Sum $25,000.00 McKenzie Construction & Site Development, LLC Lump Sum $86,097.40 Engineer's Estimate ALL LPSM Lump Sum $16,000.00

17 out of 17

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

B0560 66702-0000 NEGOTIATED PAY ITEM (WILDLIFE BIOLOGIST)

Central Southern Construction Corp. Lump Sum $5,200.00 Eclipse Companies, LLC Lump Sum $5,200.00 Kovilic Construction Company, Inc. Lump Sum $5,200.00 McKenzie Construction & Site Development, LLC Lump Sum $5,200.00 Engineer's Estimate ALL CTSM Lump Sum $5,200.00

Total Schedule - All Items

Central Southern Construction Corp. $3,648,830.00 Eclipse Companies, LLC $4,859,324.00 Kovilic Construction Company, Inc. $7,280,250.00 McKenzie Construction & Site Development, LLC $7,975,586.01 Engineer's Estimate $4,906,000.00

Bid Error Report Report Date: 12/12/24

1 out of 4

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Bid Item Check Pass

Bidder Line Item Number Bidder's Extension Computed Extension

No Line Item Errors Found

2 out of 4

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: A

Schedule Type: Base

Bid Total Check Pass

Bidder Bidder's Bid Amount Computed Bid Amount Error

Central Southern Construction Corp. $3,789,630.00 $3,789,630.00

McKenzie Construction & Site Development, LLC $6,438,149.28 $6,438,149.28

Eclipse Companies, LLC $3,608,762.00 $3,608,762.00

Kovilic Construction Company, Inc. $3,952,950.00 $3,952,950.00

The apparent low bidder is 8.85% above the engineer's estimate.

3 out of 4

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Bid Item Check Pass

Bidder Line Item Number Bidder's Extension Computed Extension

No Line Item Errors Found

4 out of 4

Project No: MS ERFO NPS VICK 2020-1(2)

Project Name: Grant Avenue and Union Avenue Slide Repairs

Schedule: B

Schedule Type: Options

Bid Total Check Pass

Bidder Bidder's Bid Amount Computed Bid Amount Error

Central Southern Construction Corp. $3,648,830.00 $3,648,830.00

McKenzie Construction & Site Development, LLC $7,975,586.01 $7,975,586.01

Eclipse Companies, LLC $4,863,604.00 $4,859,324.00 X

Kovilic Construction Company, Inc. $7,280,250.00 $7,280,250.00

The apparent low bidder is 25.63% below the engineer's estimate.