Tabulation of Bids - MS ERFO NP VICK 2020-1(2).pdf
PDF 921 KB Posted
- Attached to
- Vicksburg National Military Park
- Solicitation number
- 693C73-25-C-000007
About this file
This is a bid tabulation report for a construction project at Vicksburg National Military Park for Grant Avenue and Union Avenue slide repairs. The project consists of a base Schedule A and optional Schedule B, with bids opened on December 12, 2024 in Ashburn, Virginia.
The contract was awarded to Central Southern Construction Corp. on January 9, 2025, who submitted the lowest combined bid of $7,438,460 ($3,789,630 for Schedule A and $3,648,830 for Schedule B). Other bidders included Eclipse Companies LLC ($8,468,086 total), Kovilic Construction Company Inc. ($11,233,200 total), and McKenzie Construction & Site Development LLC ($14,413,735.29 total). The Engineer's Estimate was $8,221,500 total. The work includes mobilization, construction survey and staking, erosion control, excavation, asphalt pavement, drilled shafts, drainage systems, concrete work, and traffic control. Eclipse Companies LLC had a bid error in Schedule B where their computed bid amount ($4,859,324) differed from their submitted amount ($4,863,604).
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 01/09/25
1 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Contractor Responsive?
Engineer's Estimate
Central Southern Construction Corp.
Eclipse Companies, LLC
Kovilic Construction Company, Inc.
McKenzie Construction & Site Development, LLC
Base Schedule A
$3,315,500.00
$3,789,630.00
$3,608,762.00
$3,952,950.00
$6,438,149.28
Option: B
$4,906,000.00
$3,648,830.00
$4,859,324.00
$7,280,250.00
$7,975,586.01
Contractor Responsive?
Engineer's Estimate
Central Southern Construction Corp.
Eclipse Companies, LLC
Kovilic Construction Company, Inc.
McKenzie Construction & Site Development, LLC
Total Base Schedule A and Option(s): B
$8,221,500.00
$7,438,460.00
$8,468,086.00
$11,233,200.00
$14,413,735.29
2 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Solcitation No: 693C73-25-B-000002
Division: Eastern Federal Lands
State: MS County: Warren
Federal Land: Vicksburg National Military Park Opened at: Ashburn, Virginia
Opened by: Emily McCleary
Date: 12/12/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Eclipse Companies, LLC $3,608,762.00 11554 East Washington Street Chagrin Falls Ohio 44023
Central Southern Construction Corp. Low bidder $3,789,630.00 119 Sewald Street Jacksonville Florida 32204
Kovilic Construction Company, Inc. $3,952,950.00 3721 N. Carnation Street Franklin Park Illinois 60131
McKenzie Construction & Site Development, LLC $6,438,149.28 2301 Calvert Street NW Washington District of Columbia 20008
Engineer's Estimate $3,315,500.00
Emily McCleary
Contract Specialist
12 December 2024
Central Southern Construction Corp. 9 January 2025
3 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0100 15101-0000 MOBILIZATION
Eclipse Companies, LLC Lump Sum $985,255.00 Central Southern Construction Corp. Lump Sum $675,000.00 Kovilic Construction Company, Inc. Lump Sum $300,000.00 McKenzie Construction & Site Development, LLC Lump Sum $983,446.00 Engineer's Estimate ALL LPSM Lump Sum $335,780.00
A0110 15201-0000 CONSTRUCTION SURVEY AND STAKING
Eclipse Companies, LLC Lump Sum $57,486.00 Central Southern Construction Corp. Lump Sum $450,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 McKenzie Construction & Site Development, LLC Lump Sum $516,976.26 Engineer's Estimate ALL LPSM Lump Sum $42,000.00
A0120 15401-0000 CONTRACTOR TESTING
Eclipse Companies, LLC Lump Sum $150,820.00 Central Southern Construction Corp. Lump Sum $350,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 McKenzie Construction & Site Development, LLC Lump Sum $182,267.27 Engineer's Estimate ALL LPSM Lump Sum $37,500.00
A0130 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Eclipse Companies, LLC $13.00 $13,650.00 Central Southern Construction Corp. $5.00 $5,250.00 Kovilic Construction Company, Inc. $10.00 $10,500.00 McKenzie Construction & Site Development, LLC $17.23 $18,091.50 Engineer's Estimate 1,050 LNFT $15.60 $16,380.00
A0140 15705-0300 SOIL EROSION CONTROL, SLOPE DRAINS
Eclipse Companies, LLC $136.00 $13,600.00 Central Southern Construction Corp. $50.00 $5,000.00 Kovilic Construction Company, Inc. $150.00 $15,000.00 McKenzie Construction & Site Development, LLC $861.62 $86,162.00 Engineer's Estimate 100 LNFT $104.00 $10,400.00
A0150 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Eclipse Companies, LLC $13.00 $2,600.00 Central Southern Construction Corp. $5.00 $1,000.00 Kovilic Construction Company, Inc. $50.00 $10,000.00 McKenzie Construction & Site Development, LLC $172.32 $34,464.00 Engineer's Estimate 200 LNFT $9.50 $1,900.00
4 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0160 15706-0400 SOIL EROSION CONTROL, SEDIMENT TRAP
Eclipse Companies, LLC $30,953.00 $30,953.00 Central Southern Construction Corp. $20,000.00 $20,000.00 Kovilic Construction Company, Inc. $5,000.00 $5,000.00 McKenzie Construction & Site Development, LLC $8,616.27 $8,616.27 Engineer's Estimate 1 EACH $10,400.00 $10,400.00
A0170 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
Eclipse Companies, LLC $17,714.00 $17,714.00 Central Southern Construction Corp. $15,000.00 $15,000.00 Kovilic Construction Company, Inc. $7,500.00 $7,500.00 McKenzie Construction & Site Development, LLC $25,848.81 $25,848.81 Engineer's Estimate 1 EACH $10,400.00 $10,400.00
A0180 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Eclipse Companies, LLC Lump Sum $6,720.00 Central Southern Construction Corp. Lump Sum $25,000.00 Kovilic Construction Company, Inc. Lump Sum $15,000.00 McKenzie Construction & Site Development, LLC Lump Sum $172,325.42 Engineer's Estimate ALL LPSM Lump Sum $15,000.00
A0190 20103-0000 CLEARING AND GRUBBING
Eclipse Companies, LLC $20.00 $72,000.00 Central Southern Construction Corp. $8.00 $28,800.00 Kovilic Construction Company, Inc. $5.00 $18,000.00 McKenzie Construction & Site Development, LLC $25.84 $93,024.00 Engineer's Estimate 3,600 SQYD $52.00 $187,200.00
A0200 20301-1400 REMOVAL OF INLET
Eclipse Companies, LLC $1,361.00 $1,361.00 Central Southern Construction Corp. $3,000.00 $3,000.00 Kovilic Construction Company, Inc. $1,000.00 $1,000.00 McKenzie Construction & Site Development, LLC $5,169.76 $5,169.76 Engineer's Estimate 1 EACH $1,600.00 $1,600.00
A0210 20302-0500 REMOVAL OF CURB, CONCRETE
Eclipse Companies, LLC $22.00 $4,950.00 Central Southern Construction Corp. $15.00 $3,375.00 Kovilic Construction Company, Inc. $25.00 $5,625.00 McKenzie Construction & Site Development, LLC $34.46 $7,753.50 Engineer's Estimate 225 LNFT $31.20 $7,020.00
5 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Eclipse Companies, LLC $26.00 $10,400.00 Central Southern Construction Corp. $10.00 $4,000.00 Kovilic Construction Company, Inc. $27.00 $10,800.00 McKenzie Construction & Site Development, LLC $17.23 $6,892.00 Engineer's Estimate 400 SQYD $26.00 $10,400.00
A0230 20420-0000 EMBANKMENT CONSTRUCTION
Eclipse Companies, LLC $66.00 $514,800.00 Central Southern Construction Corp. $45.00 $351,000.00 Kovilic Construction Company, Inc. $100.00 $780,000.00 McKenzie Construction & Site Development, LLC $51.69 $403,182.00 Engineer's Estimate 7,800 CUYD $22.35 $174,330.00
A0240 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
Eclipse Companies, LLC $8.00 $17,600.00 Central Southern Construction Corp. $5.00 $11,000.00 Kovilic Construction Company, Inc. $10.00 $22,000.00 McKenzie Construction & Site Development, LLC $25.84 $56,848.00 Engineer's Estimate 2,200 SQYD $8.35 $18,370.00
A0250 20703-0000 GEOGRID (TYPE VI)
Eclipse Companies, LLC $5.00 $60,000.00 Central Southern Construction Corp. $6.00 $72,000.00 Kovilic Construction Company, Inc. $10.00 $120,000.00 McKenzie Construction & Site Development, LLC $25.84 $310,080.00 Engineer's Estimate 12,000 SQYD $13.00 $156,000.00
A0260 20803-0000 STRUCTURAL BACKFILL
Eclipse Companies, LLC $106.00 $10,600.00 Central Southern Construction Corp. $100.00 $10,000.00 Kovilic Construction Company, Inc. $250.00 $25,000.00 McKenzie Construction & Site Development, LLC $86.16 $8,616.00 Engineer's Estimate 100 CUYD $125.00 $12,500.00
A0270 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2
Eclipse Companies, LLC $152.00 $60,800.00 Central Southern Construction Corp. $200.00 $80,000.00 Kovilic Construction Company, Inc. $150.00 $60,000.00 McKenzie Construction & Site Development, LLC $430.81 $172,324.00 Engineer's Estimate 400 TON $208.00 $83,200.00
6 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0280 25302-1000 GABIONS, GALVANIZED OR ALUMINIZED COATED
Eclipse Companies, LLC $382.00 $171,900.00 Central Southern Construction Corp. $465.00 $209,250.00 Kovilic Construction Company, Inc. $500.00 $225,000.00 McKenzie Construction & Site Development, LLC $2,067.90 $930,555.00 Engineer's Estimate 450 CUYD $286.00 $128,700.00
A0290 25501-1000 MECHANICALLY STABILIZED EARTH WALL, WELDED WIRE FACE (FULL DEPTH PATCH)
Eclipse Companies, LLC $76.00 $26,600.00 Central Southern Construction Corp. $40.00 $14,000.00 Kovilic Construction Company, Inc. $20.00 $7,000.00 McKenzie Construction & Site Development, LLC $258.48 $90,468.00 Engineer's Estimate 350 SQFT $52.00 $18,200.00
A0300 30101-4000 AGGREGATE BASE GRADING C OR D
Eclipse Companies, LLC $96.00 $14,400.00 Central Southern Construction Corp. $75.00 $11,250.00 Kovilic Construction Company, Inc. $100.00 $15,000.00 McKenzie Construction & Site Development, LLC $430.81 $64,621.50 Engineer's Estimate 150 TON $109.20 $16,380.00
A0310 30201-1000 ROADWAY AGGREGATE, METHOD 1 (#3 STONE)
Eclipse Companies, LLC $184.00 $78,200.00 Central Southern Construction Corp. $175.00 $74,375.00 Kovilic Construction Company, Inc. $175.00 $74,375.00 McKenzie Construction & Site Development, LLC $387.73 $164,785.25 Engineer's Estimate 425 CUYD $130.00 $55,250.00
A0320 30302-1000 DITCH RECONDITIONING
Eclipse Companies, LLC $37.00 $3,700.00 Central Southern Construction Corp. $50.00 $5,000.00 Kovilic Construction Company, Inc. $50.00 $5,000.00 McKenzie Construction & Site Development, LLC $258.48 $25,848.00 Engineer's Estimate 100 LNFT $22.00 $2,200.00
A0330 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA)
Eclipse Companies, LLC $258.00 $79,980.00 Central Southern Construction Corp. $218.00 $67,580.00 Kovilic Construction Company, Inc. $300.00 $93,000.00 McKenzie Construction & Site Development, LLC $430.81 $133,551.10 Engineer's Estimate 310 TON $286.00 $88,660.00
7 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0340 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (3/4-INCH NMSA)
Eclipse Companies, LLC $377.00 $28,275.00 Central Southern Construction Corp. $205.00 $15,375.00 Kovilic Construction Company, Inc. $300.00 $22,500.00 McKenzie Construction & Site Development, LLC $430.81 $32,310.75 Engineer's Estimate 75 TON $286.00 $21,450.00
A0350 41102-0000 PRIME COAT
Eclipse Companies, LLC $9.00 $4,050.00 Central Southern Construction Corp. $10.00 $4,500.00 Kovilic Construction Company, Inc. $5.00 $2,250.00 McKenzie Construction & Site Development, LLC $17.23 $7,753.50 Engineer's Estimate 450 SQYD $2.10 $945.00
A0360 41202-0000 TACK COAT
Eclipse Companies, LLC $8.00 $3,200.00 Central Southern Construction Corp. $5.00 $2,000.00 Kovilic Construction Company, Inc. $10.00 $4,000.00 McKenzie Construction & Site Development, LLC $17.23 $6,892.00 Engineer's Estimate 400 GAL $6.50 $2,600.00
A0370 41301-0600 ASPHALT PAVEMENT MILLING, 2-INCH DEPTH
Eclipse Companies, LLC $14.00 $32,900.00 Central Southern Construction Corp. $10.00 $23,500.00 Kovilic Construction Company, Inc. $27.00 $63,450.00 McKenzie Construction & Site Development, LLC $34.46 $80,981.00 Engineer's Estimate 2,350 SQYD $21.00 $49,350.00
A0380 56501-0200 DRILLED SHAFT, 24-INCH DIAMETER
Eclipse Companies, LLC $515.00 $412,000.00 Central Southern Construction Corp. $500.00 $400,000.00 Kovilic Construction Company, Inc. $1,065.00 $852,000.00 McKenzie Construction & Site Development, LLC $569.99 $455,992.00 Engineer's Estimate 800 LNFT $1,405.00 $1,124,000.00
A0390 60501-0000 STANDARD UNDERDRAIN SYSTEM
Eclipse Companies, LLC $75.00 $7,500.00 Central Southern Construction Corp. $100.00 $10,000.00 Kovilic Construction Company, Inc. $50.00 $5,000.00 McKenzie Construction & Site Development, LLC $258.48 $25,848.00 Engineer's Estimate 100 LNFT $94.00 $9,400.00
8 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0400 60521-0000 GRANULAR BACKFILL (#57 STONE)
Eclipse Companies, LLC $79.00 $592,500.00 Central Southern Construction Corp. $80.00 $600,000.00 Kovilic Construction Company, Inc. $125.00 $937,500.00 McKenzie Construction & Site Development, LLC $137.86 $1,033,950.00 Engineer's Estimate 7,500 TON $72.75 $545,625.00
A0410 60811-0000 DRAINAGE CHUTE
Eclipse Companies, LLC $4,584.00 $13,752.00 Central Southern Construction Corp. $5,000.00 $15,000.00 Kovilic Construction Company, Inc. $5,000.00 $15,000.00 McKenzie Construction & Site Development, LLC $25,848.81 $77,546.43 Engineer's Estimate 3 EACH $3,650.00 $10,950.00
A0420 60901-1700 CURB, CONCRETE, 18-INCH DEPTH (NON-MOUNTABLE)
Eclipse Companies, LLC $122.00 $27,450.00 Central Southern Construction Corp. $80.00 $18,000.00 Kovilic Construction Company, Inc. $100.00 $22,500.00 McKenzie Construction & Site Development, LLC $86.16 $19,386.00 Engineer's Estimate 225 LNFT $75.00 $16,875.00
A0430 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH
Eclipse Companies, LLC $22.00 $11,550.00 Central Southern Construction Corp. $25.00 $13,125.00 Kovilic Construction Company, Inc. $10.00 $5,250.00 McKenzie Construction & Site Development, LLC $17.36 $9,114.00 Engineer's Estimate 525 SQYD $21.00 $11,025.00
A0440 62502-0000 TURF ESTABLISHMENT
Eclipse Companies, LLC $23.00 $12,075.00 Central Southern Construction Corp. $10.00 $5,250.00 Kovilic Construction Company, Inc. $5.00 $2,625.00 McKenzie Construction & Site Development, LLC $24.93 $13,088.25 Engineer's Estimate 525 SQYD $26.00 $13,650.00
A0450 62901-0300 ROLLED EROSION CONTROL PRODUCT, TYPE 1.C
Eclipse Companies, LLC $28.00 $2,100.00 Central Southern Construction Corp. $8.00 $600.00 Kovilic Construction Company, Inc. $25.00 $1,875.00 McKenzie Construction & Site Development, LLC $86.16 $6,462.00 Engineer's Estimate 75 SQYD $10.40 $780.00
9 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0460 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
Eclipse Companies, LLC $4.00 $11,200.00 Central Southern Construction Corp. $4.00 $11,200.00 Kovilic Construction Company, Inc. $5.00 $14,000.00 McKenzie Construction & Site Development, LLC $3.31 $9,268.00 Engineer's Estimate 2,800 LNFT $2.10 $5,880.00
A0470 63501-0000 TEMPORARY TRAFFIC CONTROL
Eclipse Companies, LLC Lump Sum $15,522.00 Central Southern Construction Corp. Lump Sum $150,000.00 Kovilic Construction Company, Inc. Lump Sum $25,000.00 McKenzie Construction & Site Development, LLC Lump Sum $86,162.71 Engineer's Estimate ALL LPSM Lump Sum $16,000.00
A0480 63701-0000 FIELD OFFICE
Eclipse Companies, LLC $23,399.00 $23,399.00 Central Southern Construction Corp. $25,000.00 $25,000.00 Kovilic Construction Company, Inc. $50,000.00 $50,000.00 McKenzie Construction & Site Development, LLC $66,279.00 $66,279.00 Engineer's Estimate 1 EACH $42,000.00 $42,000.00
A0490 66702-0000 NEGOTIATED PAY ITEM (WILDLIFE BIOLOGIST)
Eclipse Companies, LLC Lump Sum $5,200.00 Central Southern Construction Corp. Lump Sum $5,200.00 Kovilic Construction Company, Inc. Lump Sum $5,200.00 McKenzie Construction & Site Development, LLC Lump Sum $5,200.00 Engineer's Estimate ALL CTSM Lump Sum $5,200.00
Total Schedule - All Items
Eclipse Companies, LLC $3,608,762.00 Central Southern Construction Corp. $3,789,630.00 Kovilic Construction Company, Inc. $3,952,950.00 McKenzie Construction & Site Development, LLC $6,438,149.28 Engineer's Estimate $3,315,500.00
10 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Solcitation No: 693C73-25-B-000002
Division: Eastern Federal Lands
State: MS County: Warren
Federal Land: Vicksburg National Military Park Opened at: Ashburn, Virginia
Opened by: Emily McCleary
Date: 12/12/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Central Southern Construction Corp. Low bidder $3,648,830.00 119 Sewald Street Jacksonville Florida 32204
Eclipse Companies, LLC $4,859,324.00 11554 East Washington Street Chagrin Falls Ohio 44023
Kovilic Construction Company, Inc. $7,280,250.00 3721 N. Carnation Street Franklin Park Illinois 60131
McKenzie Construction & Site Development, LLC $7,975,586.01 2301 Calvert Street NW Washington District of Columbia 20008
Engineer's Estimate $4,906,000.00
Emily McCleary
Contract Specialist
12 December 2024
Central Southern Construction Corp. 9 January 2025
11 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0200 15101-0000 MOBILIZATION
Central Southern Construction Corp. Lump Sum $250,000.00 Eclipse Companies, LLC Lump Sum $923,000.00 Kovilic Construction Company, Inc. Lump Sum $300,000.00 McKenzie Construction & Site Development, LLC Lump Sum $718,392.79 Engineer's Estimate ALL LPSM Lump Sum $460,625.00
B0210 15201-0000 CONSTRUCTION SURVEY AND STAKING
Central Southern Construction Corp. Lump Sum $200,000.00 Eclipse Companies, LLC Lump Sum $69,929.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 McKenzie Construction & Site Development, LLC Lump Sum $338,270.09 Engineer's Estimate ALL LPSM Lump Sum $42,000.00
B0220 15401-0000 CONTRACTOR TESTING
Central Southern Construction Corp. Lump Sum $75,000.00 Eclipse Companies, LLC Lump Sum $199,820.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 McKenzie Construction & Site Development, LLC Lump Sum $129,146.11 Engineer's Estimate ALL LPSM Lump Sum $37,500.00
B0230 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Central Southern Construction Corp. $5.00 $5,500.00 Eclipse Companies, LLC $17.00 $18,700.00 Kovilic Construction Company, Inc. $10.00 $11,000.00 McKenzie Construction & Site Development, LLC $17.21 $18,931.00 Engineer's Estimate 1,100 LNFT $15.60 $17,160.00
B0240 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Central Southern Construction Corp. $5.00 $4,500.00 Eclipse Companies, LLC $18.00 $16,200.00 Kovilic Construction Company, Inc. $25.00 $22,500.00 McKenzie Construction & Site Development, LLC $154.97 $139,473.00 Engineer's Estimate 900 LNFT $9.50 $8,550.00
B0250 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
Central Southern Construction Corp. $15,000.00 $15,000.00 Eclipse Companies, LLC $17,714.00 $17,714.00 Kovilic Construction Company, Inc. $7,500.00 $7,500.00 McKenzie Construction & Site Development, LLC $25,829.22 $25,829.22 Engineer's Estimate 1 EACH $5,200.00 $5,200.00
12 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0260 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Central Southern Construction Corp. Lump Sum $25,000.00 Eclipse Companies, LLC Lump Sum $6,720.00 Kovilic Construction Company, Inc. Lump Sum $15,000.00 McKenzie Construction & Site Development, LLC Lump Sum $172,194.81 Engineer's Estimate ALL LPSM Lump Sum $13,600.00
B0270 20103-0000 CLEARING AND GRUBBING
Central Southern Construction Corp. $8.00 $62,400.00 Eclipse Companies, LLC $4.00 $31,200.00 Kovilic Construction Company, Inc. $5.00 $39,000.00 McKenzie Construction & Site Development, LLC $30.99 $241,722.00 Engineer's Estimate 7,800 SQYD $26.00 $202,800.00
B0280 20301-1400 REMOVAL OF INLET
Central Southern Construction Corp. $3,000.00 $6,000.00 Eclipse Companies, LLC $3,473.00 $6,946.00 Kovilic Construction Company, Inc. $1,000.00 $2,000.00 McKenzie Construction & Site Development, LLC $5,165.84 $10,331.68 Engineer's Estimate 2 EACH $1,600.00 $3,200.00
B0290 20302-0500 REMOVAL OF CURB, CONCRETE
Central Southern Construction Corp. $15.00 $15,000.00 Eclipse Companies, LLC $16.00 $16,000.00 Kovilic Construction Company, Inc. $25.00 $25,000.00 McKenzie Construction & Site Development, LLC $43.04 $43,040.00 Engineer's Estimate 1,000 LNFT $31.20 $31,200.00
B0300 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Central Southern Construction Corp. $10.00 $29,000.00 Eclipse Companies, LLC $23.00 $66,700.00 Kovilic Construction Company, Inc. $27.00 $78,300.00 McKenzie Construction & Site Development, LLC $17.21 $49,909.00 Engineer's Estimate 2,900 SQYD $26.00 $75,400.00
B0310 20401-0000 ROADWAY EXCAVATION
Central Southern Construction Corp. $30.00 $204,000.00 Eclipse Companies, LLC $42.80 $291,040.00 Kovilic Construction Company, Inc. $100.00 $680,000.00 McKenzie Construction & Site Development, LLC $43.04 $292,672.00 Engineer's Estimate 6,800 CUYD $52.00 $353,600.00
13 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0320 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
Central Southern Construction Corp. $5.00 $50,000.00 Eclipse Companies, LLC $5.00 $50,000.00 Kovilic Construction Company, Inc. $10.00 $100,000.00 McKenzie Construction & Site Development, LLC $25.82 $258,200.00 Engineer's Estimate 10,000 SQYD $8.35 $83,500.00
B0330 20703-0000 GEOGRID (TYPE VI)
Central Southern Construction Corp. $6.00 $81,000.00 Eclipse Companies, LLC $6.00 $81,000.00 Kovilic Construction Company, Inc. $10.00 $135,000.00 McKenzie Construction & Site Development, LLC $25.82 $348,570.00 Engineer's Estimate 13,500 SQYD $13.00 $175,500.00
B0340 20704-0000 GEOMEMBRANE
Central Southern Construction Corp. $12.00 $42,000.00 Eclipse Companies, LLC $7.00 $24,500.00 Kovilic Construction Company, Inc. $25.00 $87,500.00 McKenzie Construction & Site Development, LLC $60.26 $210,910.00 Engineer's Estimate 3,500 SQYD $16.65 $58,275.00
B0350 25102-0200 PLACED RIPRAP, METHOD A, CLASS 2
Central Southern Construction Corp. $200.00 $20,000.00 Eclipse Companies, LLC $152.00 $15,200.00 Kovilic Construction Company, Inc. $250.00 $25,000.00 McKenzie Construction & Site Development, LLC $430.48 $43,048.00 Engineer's Estimate 100 TON $208.00 $20,800.00
B0360 30101-4000 AGGREGATE BASE GRADING C OR D
Central Southern Construction Corp. $75.00 $75,000.00 Eclipse Companies, LLC $83.00 $83,000.00 Kovilic Construction Company, Inc. $100.00 $100,000.00 McKenzie Construction & Site Development, LLC $301.34 $301,340.00 Engineer's Estimate 1,000 TON $109.20 $109,200.00
B0370 30211-0000 MECHANICALLY COMPACTED AGGREGATE COLUMN (IMPACT (DISPLACEMENT) RAMMED AGGREGATE
PIER)
Central Southern Construction Corp. $35.00 $875,000.00 Eclipse Companies, LLC $54.00 $1,350,000.00 Kovilic Construction Company, Inc. $133.00 $3,325,000.00 McKenzie Construction & Site Development, LLC $67.59 $1,689,750.00 Engineer's Estimate 25,000 LNFT $62.40 $1,560,000.00
14 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0380 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (3/4-INCH NMSA)
Central Southern Construction Corp. $205.00 $102,500.00 Eclipse Companies, LLC $213.00 $106,500.00 Kovilic Construction Company, Inc. $300.00 $150,000.00 McKenzie Construction & Site Development, LLC $430.48 $215,240.00 Engineer's Estimate 500 TON $286.00 $143,000.00
B0390 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA)
Central Southern Construction Corp. $218.00 $78,480.00 Eclipse Companies, LLC $227.00 $81,720.00 Kovilic Construction Company, Inc. $300.00 $108,000.00 McKenzie Construction & Site Development, LLC $430.48 $154,972.80 Engineer's Estimate 360 TON $286.00 $102,960.00
B0400 41102-0000 PRIME COAT
Central Southern Construction Corp. $10.00 $29,000.00 Eclipse Companies, LLC $3.00 $8,700.00 Kovilic Construction Company, Inc. $5.00 $14,500.00 McKenzie Construction & Site Development, LLC $17.21 $49,909.00 Engineer's Estimate 2,900 SQYD $2.10 $6,090.00
B0410 41202-0000 TACK COAT
Central Southern Construction Corp. $5.00 $2,250.00 Eclipse Companies, LLC $10.00 $4,500.00 Kovilic Construction Company, Inc. $10.00 $4,500.00 McKenzie Construction & Site Development, LLC $25.82 $11,619.00 Engineer's Estimate 450 GAL $6.50 $2,925.00
B0420 41301-0000 ASPHALT PAVEMENT MILLING (MICRO MILLING)
Central Southern Construction Corp. $20.00 $5,000.00 Eclipse Companies, LLC $26.00 $6,500.00 Kovilic Construction Company, Inc. $50.00 $12,500.00 McKenzie Construction & Site Development, LLC $129.14 $32,285.00 Engineer's Estimate 250 SQYD $31.50 $7,875.00
B0430 41301-0600 ASPHALT PAVEMENT MILLING, 2-INCH DEPTH
Central Southern Construction Corp. $10.00 $1,500.00 Eclipse Companies, LLC $79.00 $11,850.00 Kovilic Construction Company, Inc. $27.00 $4,050.00 McKenzie Construction & Site Development, LLC $172.19 $25,828.50 Engineer's Estimate 150 SQYD $21.00 $3,150.00
15 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0440 60501-0000 STANDARD UNDERDRAIN SYSTEM
Central Southern Construction Corp. $100.00 $95,000.00 Eclipse Companies, LLC $51.00 $48,450.00 Kovilic Construction Company, Inc. $50.00 $47,500.00 McKenzie Construction & Site Development, LLC $172.19 $163,580.50 Engineer's Estimate 950 LNFT $94.00 $89,300.00
B0450 60521-0000 GRANULAR BACKFILL (#57 STONE)
Central Southern Construction Corp. $80.00 $960,000.00 Eclipse Companies, LLC $77.00 $924,000.00 Kovilic Construction Company, Inc. $125.00 $1,500,000.00 McKenzie Construction & Site Development, LLC $137.75 $1,653,000.00 Engineer's Estimate 12,000 TON $72.75 $873,000.00
B0460 60801-0400 PAVED WATERWAY, TYPE 4
Central Southern Construction Corp. $350.00 $5,250.00 Eclipse Companies, LLC $451.00 $6,765.00 Kovilic Construction Company, Inc. $180.00 $2,700.00 McKenzie Construction & Site Development, LLC $1,033.16 $15,497.40 Engineer's Estimate 15 SQYD $156.00 $2,340.00
B0470 60801-0400 PAVED WATERWAY, TYPE 4 (V-DITCH)
Central Southern Construction Corp. $125.00 $56,250.00 Eclipse Companies, LLC $304.00 $136,800.00 Kovilic Construction Company, Inc. $180.00 $81,000.00 McKenzie Construction & Site Development, LLC $602.68 $271,206.00 Engineer's Estimate 450 SQYD $156.00 $70,200.00
B0480 60811-0000 DRAINAGE CHUTE
Central Southern Construction Corp. $5,000.00 $5,000.00 Eclipse Companies, LLC $3,839.00 $3,839.00 Kovilic Construction Company, Inc. $5,000.00 $5,000.00 McKenzie Construction & Site Development, LLC $34,438.96 $34,438.96 Engineer's Estimate 1 EACH $3,650.00 $3,650.00
B0490 60901-1700 CURB, CONCRETE, 18-INCH DEPTH (NON-MOUNTABLE)
Central Southern Construction Corp. $80.00 $16,000.00 Eclipse Companies, LLC $122.00 $24,400.00 Kovilic Construction Company, Inc. $100.00 $20,000.00 McKenzie Construction & Site Development, LLC $68.87 $13,774.00 Engineer's Estimate 200 LNFT $75.00 $15,000.00
16 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0500 61401-0000 LEAN CONCRETE BACKFILL (FLOWABLE FILL)
Central Southern Construction Corp. $1,000.00 $5,000.00 Eclipse Companies, LLC $1,008.00 $5,040.00 Kovilic Construction Company, Inc. $2,500.00 $12,500.00 McKenzie Construction & Site Development, LLC $1,377.55 $6,887.75 Engineer's Estimate 5 CUYD $3,200.00 $16,000.00
B0510 62401-0300 FURNISHING AND PLACING TOPSOIL, 4-INCH DEPTH
Central Southern Construction Corp. $25.00 $125,000.00 Eclipse Companies, LLC $15.00 $75,000.00 Kovilic Construction Company, Inc. $10.00 $50,000.00 McKenzie Construction & Site Development, LLC $5.29 $26,450.00 Engineer's Estimate 5,000 SQYD $21.00 $105,000.00
B0520 62502-0000 TURF ESTABLISHMENT
Central Southern Construction Corp. $10.00 $50,000.00 Eclipse Companies, LLC $14.00 $70,000.00 Kovilic Construction Company, Inc. $5.00 $25,000.00 McKenzie Construction & Site Development, LLC $8.43 $42,150.00 Engineer's Estimate 5,000 SQYD $26.00 $130,000.00
B0530 62901-0300 ROLLED EROSION CONTROL PRODUCT, TYPE 1.C
Central Southern Construction Corp. $8.00 $40,000.00 Eclipse Companies, LLC $11.00 $55,000.00 Kovilic Construction Company, Inc. $10.00 $50,000.00 McKenzie Construction & Site Development, LLC $25.82 $129,100.00 Engineer's Estimate 5,000 SQYD $10.40 $52,000.00
B0540 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
Central Southern Construction Corp. $4.00 $8,000.00 Eclipse Companies, LLC $5.00 $10,000.00 Kovilic Construction Company, Inc. $5.00 $10,000.00 McKenzie Construction & Site Development, LLC $3.31 $6,620.00 Engineer's Estimate 2,000 LNFT $2.10 $4,200.00
B0550 63501-0000 TEMPORARY TRAFFIC CONTROL
Central Southern Construction Corp. Lump Sum $25,000.00 Eclipse Companies, LLC Lump Sum $7,391.00 Kovilic Construction Company, Inc. Lump Sum $25,000.00 McKenzie Construction & Site Development, LLC Lump Sum $86,097.40 Engineer's Estimate ALL LPSM Lump Sum $16,000.00
17 out of 17
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0560 66702-0000 NEGOTIATED PAY ITEM (WILDLIFE BIOLOGIST)
Central Southern Construction Corp. Lump Sum $5,200.00 Eclipse Companies, LLC Lump Sum $5,200.00 Kovilic Construction Company, Inc. Lump Sum $5,200.00 McKenzie Construction & Site Development, LLC Lump Sum $5,200.00 Engineer's Estimate ALL CTSM Lump Sum $5,200.00
Total Schedule - All Items
Central Southern Construction Corp. $3,648,830.00 Eclipse Companies, LLC $4,859,324.00 Kovilic Construction Company, Inc. $7,280,250.00 McKenzie Construction & Site Development, LLC $7,975,586.01 Engineer's Estimate $4,906,000.00
Bid Error Report Report Date: 12/12/24
1 out of 4
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
No Line Item Errors Found
2 out of 4
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: A
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Central Southern Construction Corp. $3,789,630.00 $3,789,630.00
McKenzie Construction & Site Development, LLC $6,438,149.28 $6,438,149.28
Eclipse Companies, LLC $3,608,762.00 $3,608,762.00
Kovilic Construction Company, Inc. $3,952,950.00 $3,952,950.00
The apparent low bidder is 8.85% above the engineer's estimate.
3 out of 4
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
No Line Item Errors Found
4 out of 4
Project No: MS ERFO NPS VICK 2020-1(2)
Project Name: Grant Avenue and Union Avenue Slide Repairs
Schedule: B
Schedule Type: Options
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Central Southern Construction Corp. $3,648,830.00 $3,648,830.00
McKenzie Construction & Site Development, LLC $7,975,586.01 $7,975,586.01
Eclipse Companies, LLC $4,863,604.00 $4,859,324.00 X
Kovilic Construction Company, Inc. $7,280,250.00 $7,280,250.00
The apparent low bidder is 25.63% below the engineer's estimate.