Tabulation of Bids - FW TREM 10(1).pdf
PDF 1 MB Posted
- Attached to
- Trempealeau National Wildlife Refuge
- Solicitation number
- 693C73-24-C-000008
About this file
This document is a Tabulation of Bids for the Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road (Route 100) at the Trempealeau National Wildlife Refuge in Wisconsin. The solicitation number is 693C73-24-B-000007 under the Department of Transportation Federal Highway Administration. The project includes roadway excavation, concrete pavement, box culvert, guardrail, and other related items. Five contractors submitted bids, with the lowest responsive bid of $2,191,878.30 from Norcon Corporation. The Government's estimate was $2,740,000. The document also includes bid details for an optional Schedule B and C with additional work items. The contract was awarded to Construction Solutions Group, LLC on April 18, 2024 for a total of $3,452,916.42 covering all three schedules.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tabulation of Bids Report Date: 03/21/24
1 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Contractor Responsive?
Engineer's Estimate
Central Southern Construction Corp.
Construction Solutions Group, LLC
Kovilic Construction Company, Inc.
Norcon Corporation
Pavkov Contracting Co., Inc.
Base Schedule A
$2,740,000.00
$3,120,361.60
$2,464,451.12
$2,855,000.00
$2,191,878.30
$3,787,950.00
Option: B
$450,000.00
$816,124.00
$407,952.54
$602,550.00
$524,932.60
$651,920.00
Option: C
$1,050,000.00
$798,978.55
$580,512.76
$1,487,025.00
$830,831.99
$1,366,380.00
Contractor Responsive?
Engineer's Estimate
Central Southern Construction Corp.
Construction Solutions Group, LLC
Kovilic Construction Company, Inc.
Norcon Corporation
Pavkov Contracting Co., Inc.
Total Base Schedule A and Option(s): B
$3,190,000.00
$3,936,485.60
$2,872,403.66
$3,457,550.00
$2,716,810.90
$4,439,870.00
Total Base Schedule A and Option(s): BC
$4,240,000.00
$4,735,464.15
$3,452,916.42
$4,944,575.00
$3,547,642.89
$5,806,250.00
Total Base Schedule A and Option(s): C
$3,790,000.00
$3,919,340.15
$3,044,963.88
$4,342,025.00
$3,022,710.29
$5,154,330.00
2 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Solcitation No: 693C73-24-B-000007
Division: Eastern Federal Lands
State: WI County: Buffalo, Trempealeau
Federal Land: TREMPEALEAU NATIONAL WILDLIFE REFUGE Opened at: Ashburn, Virginia
Opened by: Emily McCleary
Date: 03/21/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Norcon Corporation $2,191,878.30 5600 Municipal Street Schofield Wisconsin 54476
Construction Solutions Group, LLC $2,464,451.12 425 Highland Ave St. Louis Missouri 63122
Kovilic Construction Company, Inc. $2,855,000.00 3721 N. Carnation Street Franklin Park Illinois 60131
Central Southern Construction Corp. $3,120,361.60 119 Sewald Street Jacksonville Florida 32204
Pavkov Contracting Co., Inc. $3,787,950.00 55 S. Guignard Drive Sumter South Carolina 29150
Engineer's Estimate $2,740,000.00
21 March 2024
Contract Specialist
Emily McCleary
Construction Solutions Group, LLC 18 April 2024
3 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1000 15101-0000 MOBILIZATION
Norcon Corporation Lump Sum $385,091.05 Construction Solutions Group, LLC Lump Sum $879,200.00 Kovilic Construction Company, Inc. Lump Sum $200,000.00 Central Southern Construction Corp. Lump Sum $851,475.00 Pavkov Contracting Co., Inc. Lump Sum $377,000.00 Engineer's Estimate ALL LPSM Lump Sum $352,675.00
A1010 15201-0000 CONSTRUCTION SURVEY AND STAKING
Norcon Corporation Lump Sum $37,700.00 Construction Solutions Group, LLC Lump Sum $73,000.00 Kovilic Construction Company, Inc. Lump Sum $30,000.00 Central Southern Construction Corp. Lump Sum $350,000.00 Pavkov Contracting Co., Inc. Lump Sum $67,000.00 Engineer's Estimate ALL LPSM Lump Sum $75,000.00
A1020 15401-0000 CONTRACTOR TESTING
Norcon Corporation Lump Sum $40,033.75 Construction Solutions Group, LLC Lump Sum $51,800.00 Kovilic Construction Company, Inc. Lump Sum $30,000.00 Central Southern Construction Corp. Lump Sum $350,000.00 Pavkov Contracting Co., Inc. Lump Sum $43,400.00 Engineer's Estimate ALL LPSM Lump Sum $55,000.00
A1030 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Norcon Corporation $4.60 $10,120.00 Construction Solutions Group, LLC $5.52 $12,144.00 Kovilic Construction Company, Inc. $10.00 $22,000.00 Central Southern Construction Corp. $4.60 $10,120.00 Pavkov Contracting Co., Inc. $18.00 $39,600.00 Engineer's Estimate 2,200 LNFT $9.50 $20,900.00
A1040 15705-2000 SOIL EROSION CONTROL, FLOATING TURBIDITY CURTAIN
Norcon Corporation $50.00 $2,500.00 Construction Solutions Group, LLC $270.00 $13,500.00 Kovilic Construction Company, Inc. $250.00 $12,500.00 Central Southern Construction Corp. $250.00 $12,500.00 Pavkov Contracting Co., Inc. $66.00 $3,300.00 Engineer's Estimate 50 LNFT $140.00 $7,000.00
4 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1050 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT
Norcon Corporation $32,663.00 $32,663.00 Construction Solutions Group, LLC $114,195.60 $114,195.60 Kovilic Construction Company, Inc. $500.00 $500.00 Central Southern Construction Corp. $32,663.00 $32,663.00 Pavkov Contracting Co., Inc. $13,100.00 $13,100.00 Engineer's Estimate 1 EACH $120,000.00 $120,000.00
A1060 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Norcon Corporation Lump Sum $40,960.00 Construction Solutions Group, LLC Lump Sum $12,000.00 Kovilic Construction Company, Inc. Lump Sum $20,000.00 Central Southern Construction Corp. Lump Sum $15,000.00 Pavkov Contracting Co., Inc. Lump Sum $49,900.00 Engineer's Estimate ALL LPSM Lump Sum $5,500.00
A1070 20120-1000 REMOVAL, INDIVIDUAL TREE
Norcon Corporation $1,297.20 $6,486.00 Construction Solutions Group, LLC $1,556.64 $7,783.20 Kovilic Construction Company, Inc. $1,000.00 $5,000.00 Central Southern Construction Corp. $1,297.00 $6,485.00 Pavkov Contracting Co., Inc. $1,800.00 $9,000.00 Engineer's Estimate 5 EACH $2,100.00 $10,500.00
A1080 20302-1200 REMOVAL OF GUARDRAIL
Norcon Corporation $5.00 $1,000.00 Construction Solutions Group, LLC $36.00 $7,200.00 Kovilic Construction Company, Inc. $25.00 $5,000.00 Central Southern Construction Corp. $150.00 $30,000.00 Pavkov Contracting Co., Inc. $62.00 $12,400.00 Engineer's Estimate 200 LNFT $20.50 $4,100.00
A1090 20302-2100 REMOVAL OF PIPE CULVERT
Norcon Corporation $39.50 $9,875.00 Construction Solutions Group, LLC $12.12 $3,030.00 Kovilic Construction Company, Inc. $100.00 $25,000.00 Central Southern Construction Corp. $31.00 $7,750.00 Pavkov Contracting Co., Inc. $88.00 $22,000.00 Engineer's Estimate 250 LNFT $38.00 $9,500.00
5 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1100 20401-0000 ROADWAY EXCAVATION
Norcon Corporation $20.50 $24,395.00 Construction Solutions Group, LLC $24.60 $29,274.00 Kovilic Construction Company, Inc. $100.00 $119,000.00 Central Southern Construction Corp. $20.50 $24,395.00 Pavkov Contracting Co., Inc. $146.00 $173,740.00 Engineer's Estimate 1,190 CUYD $55.00 $65,450.00
A1110 20426-1000 DITCH, EXCAVATION
Norcon Corporation $22.05 $9,040.50 Construction Solutions Group, LLC $26.46 $10,848.60 Kovilic Construction Company, Inc. $100.00 $41,000.00 Central Southern Construction Corp. $22.05 $9,040.50 Pavkov Contracting Co., Inc. $141.00 $57,810.00 Engineer's Estimate 410 CUYD $90.00 $36,900.00
A1120 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
Norcon Corporation $1.55 $3,100.00 Construction Solutions Group, LLC $1.86 $3,720.00 Kovilic Construction Company, Inc. $5.00 $10,000.00 Central Southern Construction Corp. $1.55 $3,100.00 Pavkov Contracting Co., Inc. $24.00 $48,000.00 Engineer's Estimate 2,000 SQYD $6.80 $13,600.00
A1130 20801-0000 STRUCTURE EXCAVATION
Norcon Corporation $80.00 $34,400.00 Construction Solutions Group, LLC $84.00 $36,120.00 Kovilic Construction Company, Inc. $100.00 $43,000.00 Central Southern Construction Corp. $70.00 $30,100.00 Pavkov Contracting Co., Inc. $157.00 $67,510.00 Engineer's Estimate 430 CUYD $55.00 $23,650.00
A1140 20815-0000 COFFERDAMS
Norcon Corporation Lump Sum $267,270.00 Construction Solutions Group, LLC Lump Sum $215,000.00 Kovilic Construction Company, Inc. Lump Sum $200,000.00 Central Southern Construction Corp. Lump Sum $39,700.00 Pavkov Contracting Co., Inc. Lump Sum $938,800.00 Engineer's Estimate ALL LPSM Lump Sum $105,000.00
6 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1150 25102-0400 PLACED RIPRAP, METHOD A, CLASS 4
Norcon Corporation $89.00 $22,250.00 Construction Solutions Group, LLC $53.46 $13,365.00 Kovilic Construction Company, Inc. $250.00 $62,500.00 Central Southern Construction Corp. $44.55 $11,137.50 Pavkov Contracting Co., Inc. $195.00 $48,750.00 Engineer's Estimate 250 TON $170.00 $42,500.00
A1160 30101-4000 AGGREGATE BASE GRADING C OR D
Norcon Corporation $30.75 $24,600.00 Construction Solutions Group, LLC $36.90 $29,520.00 Kovilic Construction Company, Inc. $85.00 $68,000.00 Central Southern Construction Corp. $30.75 $24,600.00 Pavkov Contracting Co., Inc. $179.00 $143,200.00 Engineer's Estimate 800 TON $65.00 $52,000.00
A1170 50101-0800 MINOR CONCRETE PAVEMENT, REINFORCED, 8-INCH DEPTH
Norcon Corporation $158.00 $331,800.00 Construction Solutions Group, LLC $88.56 $185,976.00 Kovilic Construction Company, Inc. $180.00 $378,000.00 Central Southern Construction Corp. $215.00 $451,500.00 Pavkov Contracting Co., Inc. $348.00 $730,800.00 Engineer's Estimate 2,100 SQYD $240.00 $504,000.00
A1180 55201-0200 STRUCTURAL CONCRETE, CLASS A (AE)
Norcon Corporation $1,875.00 $187,500.00 Construction Solutions Group, LLC $585.60 $58,560.00 Kovilic Construction Company, Inc. $3,600.00 $360,000.00 Central Southern Construction Corp. $488.00 $48,800.00 Pavkov Contracting Co., Inc. $1,800.00 $180,000.00 Engineer's Estimate 100 CUYD $4,000.00 $400,000.00
A1190 55401-1000 REINFORCING STEEL
Norcon Corporation $2.80 $33,600.00 Construction Solutions Group, LLC $1.92 $23,040.00 Kovilic Construction Company, Inc. $3.00 $36,000.00 Central Southern Construction Corp. $1.60 $19,200.00 Pavkov Contracting Co., Inc. $5.20 $62,400.00 Engineer's Estimate 12,000 LB $2.25 $27,000.00
15 April 2024
7 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1200 58202-0000 HELICAL PILE, IN PLACE
Norcon Corporation $3,100.00 $124,000.00 Construction Solutions Group, LLC $2,248.80 $89,952.00 Kovilic Construction Company, Inc. $10,000.00 $400,000.00 Central Southern Construction Corp. $1,874.00 $74,960.00 Pavkov Contracting Co., Inc. $3,600.00 $144,000.00 Engineer's Estimate 40 EACH $4,000.00 $160,000.00
A1210 60220-0000 PRECAST REINFORCED CONCRETE BOX CULVERT (20 FEET SPAN, 4 FEET RISE)
Norcon Corporation $4,370.00 $227,240.00 Construction Solutions Group, LLC $3,952.80 $205,545.60 Kovilic Construction Company, Inc. $10,000.00 $520,000.00 Central Southern Construction Corp. $3,294.00 $171,288.00 Pavkov Contracting Co., Inc. $4,400.00 $228,800.00 Engineer's Estimate 52 LNFT $8,000.00 $416,000.00
A1220 60901-1300 CURB, CONCRETE, 15-INCH DEPTH
Norcon Corporation $165.00 $15,675.00 Construction Solutions Group, LLC $60.00 $5,700.00 Kovilic Construction Company, Inc. $100.00 $9,500.00 Central Southern Construction Corp. $50.00 $4,750.00 Pavkov Contracting Co., Inc. $38.00 $3,610.00 Engineer's Estimate 95 LNFT $65.00 $6,175.00
A1230 60901-1900 CURB, CONCRETE, 20-INCH DEPTH AND VARIES
Norcon Corporation $185.00 $16,650.00 Construction Solutions Group, LLC $90.00 $8,100.00 Kovilic Construction Company, Inc. $150.00 $13,500.00 Central Southern Construction Corp. $75.00 $6,750.00 Pavkov Contracting Co., Inc. $41.00 $3,690.00 Engineer's Estimate 90 LNFT $130.00 $11,700.00
A1240 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
Norcon Corporation $60.00 $7,500.00 Construction Solutions Group, LLC $180.00 $22,500.00 Kovilic Construction Company, Inc. $100.00 $12,500.00 Central Southern Construction Corp. $350.00 $43,750.00 Pavkov Contracting Co., Inc. $190.00 $23,750.00 Engineer's Estimate 125 LNFT $160.00 $20,000.00
Emily McCleary
8 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1250 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Norcon Corporation $4,250.00 $8,500.00 Construction Solutions Group, LLC $12,000.00 $24,000.00 Kovilic Construction Company, Inc. $5,000.00 $10,000.00 Central Southern Construction Corp. $12,000.00 $24,000.00 Pavkov Contracting Co., Inc. $6,600.00 $13,200.00 Engineer's Estimate 2 EACH $4,500.00 $9,000.00
A1260 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM
Norcon Corporation $275.00 $6,050.00 Construction Solutions Group, LLC $360.00 $7,920.00 Kovilic Construction Company, Inc. $250.00 $5,500.00 Central Southern Construction Corp. $350.00 $7,700.00 Pavkov Contracting Co., Inc. $345.00 $7,590.00 Engineer's Estimate 22 LNFT $210.00 $4,620.00
A1270 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGICAL MONITORING)
Norcon Corporation Lump Sum $21,225.00 Construction Solutions Group, LLC Lump Sum $38,400.00 Kovilic Construction Company, Inc. Lump Sum $20,000.00 Central Southern Construction Corp. Lump Sum $75,000.00 Pavkov Contracting Co., Inc. Lump Sum $64,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A1280 62501-0000 TURF ESTABLISHMENT
Norcon Corporation $7,500.00 $3,750.00 Construction Solutions Group, LLC $24,354.24 $12,177.12 Kovilic Construction Company, Inc. $20,000.00 $10,000.00 Central Southern Construction Corp. $20,295.20 $10,147.60 Pavkov Contracting Co., Inc. $8,400.00 $4,200.00 Engineer's Estimate 0.5 ACRE $11,000.00 $5,500.00
A1290 62901-1200 ROLLED EROSION CONTROL PRODUCT, TYPE 5.A
Norcon Corporation $6.80 $3,400.00 Construction Solutions Group, LLC $8.16 $4,080.00 Kovilic Construction Company, Inc. $10.00 $5,000.00 Central Southern Construction Corp. $6.80 $3,400.00 Pavkov Contracting Co., Inc. $13.00 $6,500.00 Engineer's Estimate 500 SQYD $15.00 $7,500.00
9 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A1300 63316-1000 REMOVE AND RESET SIGN
Norcon Corporation $250.00 $750.00 Construction Solutions Group, LLC $600.00 $1,800.00 Kovilic Construction Company, Inc. $500.00 $1,500.00 Central Southern Construction Corp. $350.00 $1,050.00 Pavkov Contracting Co., Inc. $300.00 $900.00 Engineer's Estimate 3 EACH $410.00 $1,230.00
A1310 63501-0000 TEMPORARY TRAFFIC CONTROL
Norcon Corporation Lump Sum $31,000.00 Construction Solutions Group, LLC Lump Sum $80,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Central Southern Construction Corp. Lump Sum $150,000.00 Pavkov Contracting Co., Inc. Lump Sum $36,000.00 Engineer's Estimate ALL LPSM Lump Sum $15,000.00
A1320 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION
Norcon Corporation Lump Sum $100,000.00 Construction Solutions Group, LLC Lump Sum $100,000.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 Central Southern Construction Corp. Lump Sum $100,000.00 Pavkov Contracting Co., Inc. Lump Sum $100,000.00 Engineer's Estimate ALL CTSM Lump Sum $100,000.00
A1330 63701-0000 FIELD OFFICE
Norcon Corporation $111,354.00 $111,354.00 Construction Solutions Group, LLC $30,000.00 $30,000.00 Kovilic Construction Company, Inc. $20,000.00 $20,000.00 Central Southern Construction Corp. $90,000.00 $90,000.00 Pavkov Contracting Co., Inc. $42,000.00 $42,000.00 Engineer's Estimate 1 EACH $40,000.00 $40,000.00
A1340 64501-0000 LOCATE UTILITIES
Norcon Corporation Lump Sum $10,400.00 Construction Solutions Group, LLC Lump Sum $55,000.00 Kovilic Construction Company, Inc. Lump Sum $10,000.00 Central Southern Construction Corp. Lump Sum $30,000.00 Pavkov Contracting Co., Inc. Lump Sum $22,000.00 Engineer's Estimate ALL LPSM Lump Sum $3,000.00
10 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
Total Schedule - All Items
Norcon Corporation $2,191,878.30 Construction Solutions Group, LLC $2,464,451.12 Kovilic Construction Company, Inc. $2,855,000.00 Central Southern Construction Corp. $3,120,361.60 Pavkov Contracting Co., Inc. $3,787,950.00 Engineer's Estimate $2,740,000.00
11 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Solcitation No: 693C73-24-B-000007
Division: Eastern Federal Lands
State: WI County: Buffalo, Trempealeau
Federal Land: TREMPEALEAU NATIONAL WILDLIFE REFUGE Opened at: Ashburn, Virginia
Opened by: Emily McCleary
Date: 03/21/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Construction Solutions Group, LLC $407,952.54 425 Highland Ave St. Louis Missouri 63122
Norcon Corporation $524,932.60 5600 Municipal Street Schofield Wisconsin 54476
Kovilic Construction Company, Inc. $602,550.00 3721 N. Carnation Street Franklin Park Illinois 60131
Pavkov Contracting Co., Inc. $651,920.00 55 S. Guignard Drive Sumter South Carolina 29150
Central Southern Construction Corp. $816,124.00 119 Sewald Street Jacksonville Florida 32204
Engineer's Estimate $450,000.00
Emily McCleary
Contract Specialist
21 March 2024
12 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B2000 15101-0000 MOBILIZATION
Construction Solutions Group, LLC Lump Sum $6,380.94 Norcon Corporation Lump Sum $135,239.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Pavkov Contracting Co., Inc. Lump Sum $66,000.00 Central Southern Construction Corp. Lump Sum $105,317.00 Engineer's Estimate ALL LPSM Lump Sum $74,530.00
B2010 15201-0000 CONSTRUCTION SURVEY AND STAKING
Construction Solutions Group, LLC Lump Sum $1,200.00 Norcon Corporation Lump Sum $23,370.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Pavkov Contracting Co., Inc. Lump Sum $11,000.00 Central Southern Construction Corp. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
B2020 15401-0000 CONTRACTOR TESTING
Construction Solutions Group, LLC Lump Sum $1,200.00 Norcon Corporation Lump Sum $3,112.50 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Pavkov Contracting Co., Inc. Lump Sum $9,000.00 Central Southern Construction Corp. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $9,000.00
B2030 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Construction Solutions Group, LLC $5.52 $3,036.00 Norcon Corporation $4.60 $2,530.00 Kovilic Construction Company, Inc. $10.00 $5,500.00 Pavkov Contracting Co., Inc. $18.00 $9,900.00 Central Southern Construction Corp. $4.60 $2,530.00 Engineer's Estimate 550 LNFT $9.50 $5,225.00
B2040 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Construction Solutions Group, LLC Lump Sum $3,600.00 Norcon Corporation Lump Sum $14,360.00 Kovilic Construction Company, Inc. Lump Sum $10,000.00 Pavkov Contracting Co., Inc. Lump Sum $8,600.00 Central Southern Construction Corp. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
13 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B2050 20301-0100 REMOVAL OF BOLLARD
Construction Solutions Group, LLC $70.68 $2,968.56 Norcon Corporation $25.00 $1,050.00 Kovilic Construction Company, Inc. $100.00 $4,200.00 Pavkov Contracting Co., Inc. $110.00 $4,620.00 Central Southern Construction Corp. $58.90 $2,473.80 Engineer's Estimate 42 EACH $250.00 $10,500.00
B2060 20301-2400 REMOVAL OF SIGN
Construction Solutions Group, LLC $60.00 $180.00 Norcon Corporation $40.00 $120.00 Kovilic Construction Company, Inc. $250.00 $750.00 Pavkov Contracting Co., Inc. $300.00 $900.00 Central Southern Construction Corp. $350.00 $1,050.00 Engineer's Estimate 3 EACH $240.00 $720.00
B2070 20302-0700 REMOVAL OF FENCE
Construction Solutions Group, LLC $9.36 $1,778.40 Norcon Corporation $5.00 $950.00 Kovilic Construction Company, Inc. $10.00 $1,900.00 Pavkov Contracting Co., Inc. $12.00 $2,280.00 Central Southern Construction Corp. $7.80 $1,482.00 Engineer's Estimate 190 LNFT $21.00 $3,990.00
B2080 20302-1200 REMOVAL OF GUARDRAIL
Construction Solutions Group, LLC $18.00 $7,920.00 Norcon Corporation $5.00 $2,200.00 Kovilic Construction Company, Inc. $20.00 $8,800.00 Pavkov Contracting Co., Inc. $62.00 $27,280.00 Central Southern Construction Corp. $150.00 $66,000.00 Engineer's Estimate 440 LNFT $20.00 $8,800.00
B2090 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Construction Solutions Group, LLC $8.76 $3,504.00 Norcon Corporation $7.30 $2,920.00 Kovilic Construction Company, Inc. $27.00 $10,800.00 Pavkov Contracting Co., Inc. $39.00 $15,600.00 Central Southern Construction Corp. $7.30 $2,920.00 Engineer's Estimate 400 SQYD $32.00 $12,800.00
14 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B2100 20315-0000 SAWCUTTING PAVEMENT
Construction Solutions Group, LLC $6.42 $706.20 Norcon Corporation $12.00 $1,320.00 Kovilic Construction Company, Inc. $10.00 $1,100.00 Pavkov Contracting Co., Inc. $20.00 $2,200.00 Central Southern Construction Corp. $5.35 $588.50 Engineer's Estimate 110 LNFT $15.00 $1,650.00
B2110 20401-0000 ROADWAY EXCAVATION
Construction Solutions Group, LLC $57.30 $3,438.00 Norcon Corporation $47.75 $2,865.00 Kovilic Construction Company, Inc. $100.00 $6,000.00 Pavkov Contracting Co., Inc. $146.00 $8,760.00 Central Southern Construction Corp. $47.75 $2,865.00 Engineer's Estimate 60 CUYD $55.00 $3,300.00
B2120 25125-0000 BOULDER (3' DIAMETER)
Construction Solutions Group, LLC $355.02 $7,810.44 Norcon Corporation $295.85 $6,508.70 Kovilic Construction Company, Inc. $500.00 $11,000.00 Pavkov Contracting Co., Inc. $2,200.00 $48,400.00 Central Southern Construction Corp. $295.85 $6,508.70 Engineer's Estimate 22 EACH $1,600.00 $35,200.00
B2130 30101-4000 AGGREGATE BASE GRADING C OR D
Construction Solutions Group, LLC $45.36 $5,896.80 Norcon Corporation $37.80 $4,914.00 Kovilic Construction Company, Inc. $100.00 $13,000.00 Pavkov Contracting Co., Inc. $179.00 $23,270.00 Central Southern Construction Corp. $37.80 $4,914.00 Engineer's Estimate 130 TON $60.00 $7,800.00
B2145 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA, <0.3 MILLION ESAL, PG 64-22, TYPE IV PAVEMENT
ROUGHNESS)
Construction Solutions Group, LLC $190.46 $41,901.20 Norcon Corporation $158.72 $34,918.40 Kovilic Construction Company, Inc. $500.00 $110,000.00 Pavkov Contracting Co., Inc. $490.00 $107,800.00 Central Southern Construction Corp. $450.00 $99,000.00 Engineer's Estimate 220 TON $230.00 $50,600.00
15 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B2155 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (3/4-INCH NMSA, <0.3 MILLION ESAL, PG 64-22)
Construction Solutions Group, LLC $317.70 $28,593.00 Norcon Corporation $264.75 $23,827.50 Kovilic Construction Company, Inc. $250.00 $22,500.00 Pavkov Contracting Co., Inc. $490.00 $44,100.00 Central Southern Construction Corp. $425.00 $38,250.00 Engineer's Estimate 90 TON $220.00 $19,800.00
B2160 41201-0000 TACK COAT
Construction Solutions Group, LLC $619.50 $1,239.00 Norcon Corporation $516.25 $1,032.50 Kovilic Construction Company, Inc. $1,000.00 $2,000.00 Pavkov Contracting Co., Inc. $400.00 $800.00 Central Southern Construction Corp. $2,500.00 $5,000.00 Engineer's Estimate 2 TON $1,400.00 $2,800.00
B2170 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS
Construction Solutions Group, LLC $180.00 $41,400.00 Norcon Corporation $60.00 $13,800.00 Kovilic Construction Company, Inc. $100.00 $23,000.00 Pavkov Contracting Co., Inc. $190.00 $43,700.00 Central Southern Construction Corp. $350.00 $80,500.00 Engineer's Estimate 230 LNFT $150.00 $34,500.00
B2180 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT
Construction Solutions Group, LLC $12,000.00 $24,000.00 Norcon Corporation $4,250.00 $8,500.00 Kovilic Construction Company, Inc. $5,000.00 $10,000.00 Pavkov Contracting Co., Inc. $6,600.00 $13,200.00 Central Southern Construction Corp. $12,000.00 $24,000.00 Engineer's Estimate 2 EACH $4,000.00 $8,000.00
B2190 61707-4000 STRUCTURE TRANSITION RAILING, MGS SYSTEM
Construction Solutions Group, LLC $360.00 $7,920.00 Norcon Corporation $275.00 $6,050.00 Kovilic Construction Company, Inc. $250.00 $5,500.00 Pavkov Contracting Co., Inc. $345.00 $7,590.00 Central Southern Construction Corp. $350.00 $7,700.00 Engineer's Estimate 22 LNFT $210.00 $4,620.00
16 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B2200 61902-0000 GATE (REPLACEMENT OF GATE OPENING SYSTEMS)
Construction Solutions Group, LLC $42,000.00 $42,000.00 Norcon Corporation $22,830.00 $22,830.00 Kovilic Construction Company, Inc. $10,000.00 $10,000.00 Pavkov Contracting Co., Inc. $8,500.00 $8,500.00 Central Southern Construction Corp. $15,000.00 $15,000.00 Engineer's Estimate 1 EACH $6,500.00 $6,500.00
B2210 61902-1700 GATE, METAL, 22 FEET WIDTH
Construction Solutions Group, LLC $18,000.00 $18,000.00 Norcon Corporation $21,925.00 $21,925.00 Kovilic Construction Company, Inc. $15,000.00 $15,000.00 Pavkov Contracting Co., Inc. $13,000.00 $13,000.00 Central Southern Construction Corp. $9,500.00 $9,500.00 Engineer's Estimate 1 EACH $6,500.00 $6,500.00
B2220 62617-1400 QUERCUS MACROCARPA, BUR OAK, 7 GALLON, CONTAINER GROWN
Construction Solutions Group, LLC $600.00 $600.00 Norcon Corporation $1,200.00 $1,200.00 Kovilic Construction Company, Inc. $1,000.00 $1,000.00 Pavkov Contracting Co., Inc. $600.00 $600.00 Central Southern Construction Corp. $5,000.00 $5,000.00 Engineer's Estimate 1 EACH $440.00 $440.00
B2230 63301-0000 SIGN SYSTEM (SIGN POSTS WITH STONE MASONRY SIGN BASE)
Construction Solutions Group, LLC $43,680.00 $43,680.00 Norcon Corporation $77,465.00 $77,465.00 Kovilic Construction Company, Inc. $25,000.00 $25,000.00 Pavkov Contracting Co., Inc. $47,770.00 $47,770.00 Central Southern Construction Corp. $36,400.00 $36,400.00 Engineer's Estimate 1 EACH $13,000.00 $13,000.00
B2240 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
Construction Solutions Group, LLC $120.00 $6,600.00 Norcon Corporation $55.00 $3,025.00 Kovilic Construction Company, Inc. $100.00 $5,500.00 Pavkov Contracting Co., Inc. $90.00 $4,950.00 Central Southern Construction Corp. $75.00 $4,125.00 Engineer's Estimate 55 SQFT $95.00 $5,225.00
17 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B2250 63501-0000 TEMPORARY TRAFFIC CONTROL
Construction Solutions Group, LLC Lump Sum $1,200.00 Norcon Corporation Lump Sum $3,500.00 Kovilic Construction Company, Inc. Lump Sum $40,000.00 Pavkov Contracting Co., Inc. Lump Sum $12,200.00 Central Southern Construction Corp. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $7,000.00
B2260 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION
Construction Solutions Group, LLC Lump Sum $100,000.00 Norcon Corporation Lump Sum $100,000.00 Kovilic Construction Company, Inc. Lump Sum $100,000.00 Pavkov Contracting Co., Inc. Lump Sum $100,000.00 Central Southern Construction Corp. Lump Sum $100,000.00 Engineer's Estimate ALL CTSM Lump Sum $100,000.00
B2270 64501-0000 LOCATE UTILITIES
Construction Solutions Group, LLC Lump Sum $1,200.00 Norcon Corporation Lump Sum $5,400.00 Kovilic Construction Company, Inc. Lump Sum $10,000.00 Pavkov Contracting Co., Inc. Lump Sum $9,900.00 Central Southern Construction Corp. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $2,500.00
Total Schedule - All Items
Construction Solutions Group, LLC $407,952.54 Norcon Corporation $524,932.60 Kovilic Construction Company, Inc. $602,550.00 Pavkov Contracting Co., Inc. $651,920.00 Central Southern Construction Corp. $816,124.00 Engineer's Estimate $450,000.00
18 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Solcitation No: 693C73-24-B-000007
Division: Eastern Federal Lands
State: WI County: Buffalo, Trempealeau
Federal Land: TREMPEALEAU NATIONAL WILDLIFE REFUGE Opened at: Ashburn, Virginia
Opened by: Emily McCleary
Date: 03/21/24
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Construction Solutions Group, LLC $580,512.76 425 Highland Ave St. Louis Missouri 63122
Central Southern Construction Corp. $798,978.55 119 Sewald Street Jacksonville Florida 32204
Norcon Corporation $830,831.99 5600 Municipal Street Schofield Wisconsin 54476
Pavkov Contracting Co., Inc. $1,366,380.00 55 S. Guignard Drive Sumter South Carolina 29150
Kovilic Construction Company, Inc. $1,487,025.00 3721 N. Carnation Street Franklin Park Illinois 60131
Engineer's Estimate $1,050,000.00
Emily McCleary
Contract Specialist 21 March 2024
19 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3000 15101-0000 MOBILIZATION
Construction Solutions Group, LLC Lump Sum $34,806.10 Central Southern Construction Corp. Lump Sum $108,171.75 Norcon Corporation Lump Sum $255,556.44 Pavkov Contracting Co., Inc. Lump Sum $120,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $73,686.00
C3010 15201-0000 CONSTRUCTION SURVEY AND STAKING
Construction Solutions Group, LLC Lump Sum $26,200.00 Central Southern Construction Corp. Lump Sum $50,000.00 Norcon Corporation Lump Sum $93,670.00 Pavkov Contracting Co., Inc. Lump Sum $29,000.00 Kovilic Construction Company, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $26,000.00
C3020 15401-0000 CONTRACTOR TESTING
Construction Solutions Group, LLC Lump Sum $21,200.00 Central Southern Construction Corp. Lump Sum $50,000.00 Norcon Corporation Lump Sum $15,320.00 Pavkov Contracting Co., Inc. Lump Sum $14,000.00 Kovilic Construction Company, Inc. Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $24,000.00
C3030 15705-0100 SOIL EROSION CONTROL, SILT FENCE
Construction Solutions Group, LLC $5.52 $9,936.00 Central Southern Construction Corp. $4.60 $8,280.00 Norcon Corporation $4.60 $8,280.00 Pavkov Contracting Co., Inc. $18.00 $32,400.00 Kovilic Construction Company, Inc. $10.00 $18,000.00 Engineer's Estimate 1,800 LNFT $9.50 $17,100.00
C3040 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Construction Solutions Group, LLC Lump Sum $1,200.00 Central Southern Construction Corp. Lump Sum $10,000.00 Norcon Corporation Lump Sum $28,720.00 Pavkov Contracting Co., Inc. Lump Sum $8,000.00 Kovilic Construction Company, Inc. Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $6,000.00
20 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3050 20103-0000 CLEARING AND GRUBBING
Construction Solutions Group, LLC $3.48 $9,396.00 Central Southern Construction Corp. $2.90 $7,830.00 Norcon Corporation $2.90 $7,830.00 Pavkov Contracting Co., Inc. $4.00 $10,800.00 Kovilic Construction Company, Inc. $5.00 $13,500.00 Engineer's Estimate 2,700 SQYD $6.55 $17,685.00
C3060 20301-2400 REMOVAL OF SIGN
Construction Solutions Group, LLC $60.00 $1,020.00 Central Southern Construction Corp. $350.00 $5,950.00 Norcon Corporation $30.00 $510.00 Pavkov Contracting Co., Inc. $90.00 $1,530.00 Kovilic Construction Company, Inc. $250.00 $4,250.00 Engineer's Estimate 17 EACH $240.00 $4,080.00
C3070 20302-0700 REMOVAL OF FENCE
Construction Solutions Group, LLC $19.86 $595.80 Central Southern Construction Corp. $16.55 $496.50 Norcon Corporation $6.00 $180.00 Pavkov Contracting Co., Inc. $20.00 $600.00 Kovilic Construction Company, Inc. $10.00 $300.00 Engineer's Estimate 30 LNFT $21.00 $630.00
C3080 20303-1600 REMOVAL OF PAVEMENT, ASPHALT
Construction Solutions Group, LLC $3.84 $2,304.00 Central Southern Construction Corp. $3.20 $1,920.00 Norcon Corporation $3.20 $1,920.00 Pavkov Contracting Co., Inc. $39.00 $23,400.00 Kovilic Construction Company, Inc. $27.00 $16,200.00 Engineer's Estimate 600 SQYD $30.00 $18,000.00
C3090 20401-0000 ROADWAY EXCAVATION
Construction Solutions Group, LLC $24.48 $23,256.00 Central Southern Construction Corp. $20.40 $19,380.00 Norcon Corporation $20.40 $19,380.00 Pavkov Contracting Co., Inc. $114.00 $108,300.00 Kovilic Construction Company, Inc. $100.00 $95,000.00 Engineer's Estimate 950 CUYD $55.00 $52,250.00
Construction Solutions Group, LLC
21 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3100 20701-1000 SEPARATION-STABILIZATION GEOTEXTILE, CLASS 2, TYPE E
Construction Solutions Group, LLC $1.86 $48,360.00 Central Southern Construction Corp. $1.55 $40,300.00 Norcon Corporation $1.55 $40,300.00 Pavkov Contracting Co., Inc. $9.00 $234,000.00 Kovilic Construction Company, Inc. $5.00 $130,000.00 Engineer's Estimate 26,000 SQYD $6.80 $176,800.00
C3110 21101-1000 ROADWAY OBLITERATION, METHOD 1
Construction Solutions Group, LLC $7.26 $4,719.00 Central Southern Construction Corp. $6.05 $3,932.50 Norcon Corporation $6.05 $3,932.50 Pavkov Contracting Co., Inc. $23.00 $14,950.00 Kovilic Construction Company, Inc. $27.00 $17,550.00 Engineer's Estimate 650 SQYD $23.00 $14,950.00
C3120 30101-4000 AGGREGATE BASE GRADING C OR D
Construction Solutions Group, LLC $39.06 $3,906.00 Central Southern Construction Corp. $32.55 $3,255.00 Norcon Corporation $32.55 $3,255.00 Pavkov Contracting Co., Inc. $179.00 $17,900.00 Kovilic Construction Company, Inc. $85.00 $8,500.00 Engineer's Estimate 100 TON $60.00 $6,000.00
C3140 30110-0000 AGGREGATE SURFACE COURSE
Construction Solutions Group, LLC $30.48 $198,120.00 Central Southern Construction Corp. $25.40 $165,100.00 Norcon Corporation $25.40 $165,100.00 Pavkov Contracting Co., Inc. $82.00 $533,000.00 Kovilic Construction Company, Inc. $110.00 $715,000.00 Engineer's Estimate 6,500 TON $65.00 $422,500.00
C3155 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1 (1/2-INCH NMSA, <0.3 MILLION ESAL, PG 64-22, TYPE IV PAVEMENT
ROUGHNESS)
Construction Solutions Group, LLC $378.70 $26,509.00 Central Southern Construction Corp. $450.00 $31,500.00 Norcon Corporation $315.58 $22,090.60 Pavkov Contracting Co., Inc. $490.00 $34,300.00 Kovilic Construction Company, Inc. $250.00 $17,500.00 Engineer's Estimate 70 TON $230.00 $16,100.00
22 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3160 41201-0000 TACK COAT
Construction Solutions Group, LLC $619.50 $619.50 Central Southern Construction Corp. $2,500.00 $2,500.00 Norcon Corporation $516.25 $516.25 Pavkov Contracting Co., Inc. $400.00 $400.00 Kovilic Construction Company, Inc. $1,000.00 $1,000.00 Engineer's Estimate 1 TON $1,400.00 $1,400.00
C3170 60201-0800 24-INCH PIPE CULVERT (CMP)
Construction Solutions Group, LLC $105.66 $5,283.00 Central Southern Construction Corp. $88.05 $4,402.50 Norcon Corporation $88.05 $4,402.50 Pavkov Contracting Co., Inc. $140.00 $7,000.00 Kovilic Construction Company, Inc. $250.00 $12,500.00 Engineer's Estimate 50 LNFT $200.00 $10,000.00
C3180 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (CMP)
Construction Solutions Group, LLC $820.62 $1,641.24 Central Southern Construction Corp. $683.85 $1,367.70 Norcon Corporation $683.85 $1,367.70 Pavkov Contracting Co., Inc. $310.00 $620.00 Kovilic Construction Company, Inc. $1,500.00 $3,000.00 Engineer's Estimate 2 EACH $3,000.00 $6,000.00
C3190 60915-1000 WHEELSTOP, CONCRETE
Construction Solutions Group, LLC $360.00 $2,520.00 Central Southern Construction Corp. $300.00 $2,100.00 Norcon Corporation $570.00 $3,990.00 Pavkov Contracting Co., Inc. $110.00 $770.00 Kovilic Construction Company, Inc. $500.00 $3,500.00 Engineer's Estimate 7 EACH $490.00 $3,430.00
C3195 61501-0100 SIDEWALK, CONCRETE
Construction Solutions Group, LLC $360.00 $41,400.00 Central Southern Construction Corp. $120.00 $13,800.00 Norcon Corporation $134.00 $15,410.00 Pavkov Contracting Co., Inc. $198.00 $22,770.00 Kovilic Construction Company, Inc. $135.00 $15,525.00 Engineer's Estimate 115 SQYD $170.00 $19,550.00
23 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3200 61902-0000 GATE (AUTOMATIC)
Construction Solutions Group, LLC $30,000.00 $30,000.00 Central Southern Construction Corp. $14,550.00 $14,550.00 Norcon Corporation $44,755.00 $44,755.00 Pavkov Contracting Co., Inc. $11,900.00 $11,900.00 Kovilic Construction Company, Inc. $35,000.00 $35,000.00 Engineer's Estimate 1 EACH $12,000.00 $12,000.00
C3210 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGICAL MONITORING)
Construction Solutions Group, LLC Lump Sum $1,200.00 Central Southern Construction Corp. Lump Sum $75,000.00 Norcon Corporation Lump Sum $12,241.00 Pavkov Contracting Co., Inc. Lump Sum $13,000.00 Kovilic Construction Company, Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
C3220 62501-0000 TURF ESTABLISHMENT
Construction Solutions Group, LLC $24,354.24 $12,177.12 Central Southern Construction Corp. $20,295.20 $10,147.60 Norcon Corporation $7,500.00 $3,750.00 Pavkov Contracting Co., Inc. $6,000.00 $3,000.00 Kovilic Construction Company, Inc. $20,000.00 $10,000.00 Engineer's Estimate 0.5 ACRE $11,000.00 $5,500.00
C3230 62901-1200 ROLLED EROSION CONTROL PRODUCT, TYPE 5.A
Construction Solutions Group, LLC $8.16 $5,304.00 Central Southern Construction Corp. $6.80 $4,420.00 Norcon Corporation $6.80 $4,420.00 Pavkov Contracting Co., Inc. $9.00 $5,850.00 Kovilic Construction Company, Inc. $10.00 $6,500.00 Engineer's Estimate 650 SQYD $15.00 $9,750.00
C3240 63301-1000 SIGN SYSTEM, GOVERNMENT FURNISHED SIGN
Construction Solutions Group, LLC $600.00 $600.00 Central Southern Construction Corp. $10,000.00 $10,000.00 Norcon Corporation $400.00 $400.00 Pavkov Contracting Co., Inc. $1,800.00 $1,800.00 Kovilic Construction Company, Inc. $500.00 $500.00 Engineer's Estimate 1 EACH $750.00 $750.00
24 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3250 63304-0900 SIGNS, ALUMINUM PANELS, TYPE 3 SHEETING
Construction Solutions Group, LLC $120.00 $11,400.00 Central Southern Construction Corp. $75.00 $7,125.00 Norcon Corporation $55.00 $5,225.00 Pavkov Contracting Co., Inc. $90.00 $8,550.00 Kovilic Construction Company, Inc. $100.00 $9,500.00 Engineer's Estimate 95 SQFT $95.00 $9,025.00
C3260 63316-1000 REMOVE AND RESET SIGN
Construction Solutions Group, LLC $600.00 $1,200.00 Central Southern Construction Corp. $350.00 $700.00 Norcon Corporation $250.00 $500.00 Pavkov Contracting Co., Inc. $300.00 $600.00 Kovilic Construction Company, Inc. $500.00 $1,000.00 Engineer's Estimate 2 EACH $390.00 $780.00
C3270 63401-1500 PAVEMENT MARKINGS, TYPE H, SOLID
Construction Solutions Group, LLC $12.00 $2,640.00 Central Southern Construction Corp. $50.00 $11,000.00 Norcon Corporation $22.00 $4,840.00 Pavkov Contracting Co., Inc. $7.00 $1,540.00 Kovilic Construction Company, Inc. $10.00 $2,200.00 Engineer's Estimate 220 LNFT $2.20 $484.00
C3280 63405-3250 PAVEMENT MARKINGS, TYPE H, ACCESSIBILITY SYMBOL
Construction Solutions Group, LLC $600.00 $600.00 Central Southern Construction Corp. $750.00 $750.00 Norcon Corporation $2,200.00 $2,200.00 Pavkov Contracting Co., Inc. $400.00 $400.00 Kovilic Construction Company, Inc. $1,000.00 $1,000.00 Engineer's Estimate 1 EACH $550.00 $550.00
C3290 63501-0000 TEMPORARY TRAFFIC CONTROL
Construction Solutions Group, LLC Lump Sum $1,200.00 Central Southern Construction Corp. Lump Sum $75,000.00 Norcon Corporation Lump Sum $5,370.00 Pavkov Contracting Co., Inc. Lump Sum $33,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00
25 out of 25
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
C3300 63603-0100 SYSTEM INSTALLATION, ELECTRICAL COMPANY COMPENSATION
Construction Solutions Group, LLC Lump Sum $50,000.00 Central Southern Construction Corp. Lump Sum $50,000.00 Norcon Corporation Lump Sum $50,000.00 Pavkov Contracting Co., Inc. Lump Sum $50,000.00 Kovilic Construction Company, Inc. Lump Sum $50,000.00 Engineer's Estimate ALL CTSM Lump Sum $50,000.00
C3310 64501-0000 LOCATE UTILITIES
Construction Solutions Group, LLC Lump Sum $1,200.00 Central Southern Construction Corp. Lump Sum $10,000.00 Norcon Corporation Lump Sum $5,400.00 Pavkov Contracting Co., Inc. Lump Sum $23,000.00 Kovilic Construction Company, Inc. Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $5,000.00
Total Schedule - All Items
Construction Solutions Group, LLC $580,512.76 Central Southern Construction Corp. $798,978.55 Norcon Corporation $830,831.99 Pavkov Contracting Co., Inc. $1,366,380.00 Kovilic Construction Company, Inc. $1,487,025.00 Engineer's Estimate $1,050,000.00
Bid Error Report
1 out of 6
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
No Line Item Errors Found
2 out of 6
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: A
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Norcon Corporation $2,191,878.30 $2,191,878.30
Central Southern Construction Corp. $3,120,361.60 $3,120,361.60
Construction Solutions Group, LLC $2,464,451.12 $2,464,451.12
Kovilic Construction Company, Inc. $2,859,500.00 $2,855,000.00 X
V. Pavkov Contracting Co., Inc. $3,782,950.00 $3,787,950.00 X
The apparent low bidder is 20.00% below the engineer's estimate.
3 out of 6
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Bid Item Check Pass
4 out of 6
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: B
Schedule Type: Options
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Norcon Corporation $524,932.60 $524,932.60
Central Southern Construction Corp. $816,124.00 $816,124.00
Construction Solutions Group, LLC $407,952.54 $407,952.54
Kovilic Construction Company, Inc. $602,550.00 $602,550.00
V. Pavkov Contracting Co., Inc. $651,920.00 $651,920.00
The apparent low bidder is 9.34% below the engineer's estimate.
5 out of 6
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Bid Item Check Pass
6 out of 6
Project No: FW-TREM 10(1)
Project Name: Rehabilitation of Entrance Road (Route 10) and Reconstruction of Marshland Road
(Route 100)
Schedule: C
Schedule Type: Options
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Norcon Corporation $830,831.99 $830,831.99
Central Southern Construction Corp. $798,978.55 $798,978.55
Construction Solutions Group, LLC $580,512.76 $580,512.76
Kovilic Construction Company, Inc. $1,487,125.00 $1,487,025.00 X
V. Pavkov Contracting Co., Inc. $1,366,380.00 $1,366,380.00
The apparent low bidder is 44.71% below the engineer's estimate.
15 April 2024
File details come from the government source that posted it. Updated .