Tabulation of Bids Report Date: 07/26/19
1 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Contractor Responsive?
Engineer's Estimate
Construction Solutions Group, LLC
GC Works, Inc.
Stormwater Plans, LLC dba SWP Contracting and Paving
Base Schedule A
$2,200,000.00
$2,842,677.48
$3,512,746.40
$2,531,659.00
Base Schedule B
$1,220,000.00
$1,601,299.51
$2,870,103.78
$1,738,042.00
2 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Solcitation No: 693C73-19-B-000026
Division: Eastern Federal Lands
State: AZ County: Pima
Federal Land: Buenos Aires National Wildlife Refuge Opened at: Sterling, Va
Opened by: Shirley Anderson
Date: 07/25/19
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Stormwater Plans, LLC dba SWP Contracting and Paving $2,531,659.00 5624 N. 54th Avenue Glendale Arizona 85301
Construction Solutions Group, LLC $2,842,677.48 5512 Elk Valley Estates Dr St. Louis Missouri 63128
GC Works, Inc. $3,512,746.40 5933 NE Win Sivers Dr. Ste 205 Portland Oregon 97220
Engineer's Estimate $2,200,000.00
Shirley A. Anderson
Contract Specialist
07/25/2019
SWP Contracting & Paving 9/5/2019 Stormwater Plans, LLC
3 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0010 15101-0000 MOBILIZATION
Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $720,000.00 Construction Solutions Group, LLC Lump Sum $381,694.31 GC Works, Inc. Lump Sum $1,007,262.83 Engineer's Estimate ALL LPSM Lump Sum $248,990.00
A0020 15201-0000 CONSTRUCTION SURVEY AND STAKING
Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $155,000.00 Construction Solutions Group, LLC Lump Sum $22,050.00 GC Works, Inc. Lump Sum $28,704.00 Engineer's Estimate ALL LPSM Lump Sum $55,000.00
A0030 15401-0000 CONTRACTOR TESTING
Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $85,000.00 Construction Solutions Group, LLC Lump Sum $14,700.00 GC Works, Inc. Lump Sum $28,704.00 Engineer's Estimate ALL LPSM Lump Sum $54,000.00
A0040 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Stormwater Plans, LLC dba SWP Contracting and Paving $5.00 $7,000.00 Construction Solutions Group, LLC $22.05 $30,870.00 GC Works, Inc. $5.74 $8,036.00 Engineer's Estimate 1,400 LNFT $8.00 $11,200.00
A0050 15720-0000 STORM WATER POLLUTION PREVENTION PLAN
Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $15,000.00 Construction Solutions Group, LLC Lump Sum $7,350.00 GC Works, Inc. Lump Sum $7,176.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00
A0060 20103-0000 CLEARING AND GRUBBING
Stormwater Plans, LLC dba SWP Contracting and Paving $0.60 $13,800.00 Construction Solutions Group, LLC $2.57 $59,110.00 GC Works, Inc. $1.25 $28,750.00 Engineer's Estimate 23,000 SQYD $12.00 $276,000.00
4 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0070 20301-2400 REMOVAL OF SIGN
Stormwater Plans, LLC dba SWP Contracting and Paving $85.00 $765.00 Construction Solutions Group, LLC $183.75 $1,653.75 GC Works, Inc. $93.29 $839.61 Engineer's Estimate 9 EACH $150.00 $1,350.00
A0080 20301-3400 REMOVAL OF WHEELSTOP
Stormwater Plans, LLC dba SWP Contracting and Paving $105.00 $1,260.00 Construction Solutions Group, LLC $142.59 $1,711.08 GC Works, Inc. $114.82 $1,377.84 Engineer's Estimate 12 EACH $40.00 $480.00
A0090 20401-0000 ROADWAY EXCAVATION
Stormwater Plans, LLC dba SWP Contracting and Paving $15.00 $15,900.00 Construction Solutions Group, LLC $35.87 $38,022.20 GC Works, Inc. $18.72 $19,843.20 Engineer's Estimate 1,060 CUYD $45.00 $47,700.00
A0100 30101-4000 AGGREGATE BASE GRADING C OR D
Stormwater Plans, LLC dba SWP Contracting and Paving $60.00 $180,000.00 Construction Solutions Group, LLC $88.45 $265,350.00 GC Works, Inc. $81.12 $243,360.00 Engineer's Estimate 3,000 TON $45.00 $135,000.00
A0120 30303-3000 ROADWAY RECONDITIONING
Stormwater Plans, LLC dba SWP Contracting and Paving $1.40 $1,134.00 Construction Solutions Group, LLC $9.80 $7,938.00 GC Works, Inc. $2.50 $2,025.00 Engineer's Estimate 810 SQYD $3.00 $2,430.00
A0130 30402-1000 FULL DEPTH RECLAMATION, METHOD 1 (4-INCHES)
Stormwater Plans, LLC dba SWP Contracting and Paving $2.00 $50,400.00 Construction Solutions Group, LLC $4.81 $121,212.00 GC Works, Inc. $3.12 $78,624.00 Engineer's Estimate 25,200 SQYD $4.00 $100,800.00
5 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0140 40101-0600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3
MILLION ESAL (PG 70-10) (ROUGHNESS TYPE III B OR TYPE IV)
Stormwater Plans, LLC dba SWP Contracting and Paving $130.00 $910,000.00 Construction Solutions Group, LLC $241.08 $1,687,560.00 GC Works, Inc. $243.36 $1,703,520.00 Engineer's Estimate 7,000 TON $160.00 $1,120,000.00
A0170 40601-0000 FOG SEAL
Stormwater Plans, LLC dba SWP Contracting and Paving $675.00 $10,125.00 Construction Solutions Group, LLC $2,131.50 $31,972.50 GC Works, Inc. $936.00 $14,040.00 Engineer's Estimate 15 TON $700.00 $10,500.00
A0180 41101-1000 PRIME COAT, METHOD 1
Stormwater Plans, LLC dba SWP Contracting and Paving $675.00 $10,125.00 Construction Solutions Group, LLC $2,572.50 $38,587.50 GC Works, Inc. $936.00 $14,040.00 Engineer's Estimate 15 TON $1,000.00 $15,000.00
A0190 41201-0000 TACK COAT
Stormwater Plans, LLC dba SWP Contracting and Paving $675.00 $10,125.00 Construction Solutions Group, LLC $2,572.50 $38,587.50 GC Works, Inc. $936.00 $14,040.00 Engineer's Estimate 15 TON $700.00 $10,500.00
A0200 50101-2600 MINOR CONCRETE PAVEMENT, PLAIN, 6-INCH DEPTH (COLORED CONCRETE)
Stormwater Plans, LLC dba SWP Contracting and Paving $2,250.00 $33,750.00 Construction Solutions Group, LLC $302.92 $4,543.80 GC Works, Inc. $14.35 $215.25 Engineer's Estimate 15 SQYD $100.00 $1,500.00
A0210 60901-0000 CURB, CONCRETE
Stormwater Plans, LLC dba SWP Contracting and Paving $250.00 $17,500.00 Construction Solutions Group, LLC $53.92 $3,774.40 GC Works, Inc. $71.76 $5,023.20 Engineer's Estimate 70 LNFT $50.00 $3,500.00
6 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0220 60915-1000 WHEELSTOP, CONCRETE
Stormwater Plans, LLC dba SWP Contracting and Paving $125.00 $3,125.00 Construction Solutions Group, LLC $170.64 $4,266.00 GC Works, Inc. $140.65 $3,516.25 Engineer's Estimate 25 EACH $120.00 $3,000.00
A0230 61501-0200 SIDEWALK, COLORED CONCRETE
Stormwater Plans, LLC dba SWP Contracting and Paving $400.00 $74,000.00 Construction Solutions Group, LLC $128.70 $23,809.50 GC Works, Inc. $717.60 $132,756.00 Engineer's Estimate 185 SQYD $130.00 $24,050.00
A0240 61509-0000 DETECTABLE WARNING PANELS
Stormwater Plans, LLC dba SWP Contracting and Paving $5,000.00 $10,000.00 Construction Solutions Group, LLC $926.22 $1,852.44 GC Works, Inc. $143.52 $287.04 Engineer's Estimate 2 SQYD $400.00 $800.00
A0250 63302-0000 SIGN SYSTEM
Stormwater Plans, LLC dba SWP Contracting and Paving $130.00 $9,100.00 Construction Solutions Group, LLC $147.00 $10,290.00 GC Works, Inc. $146.39 $10,247.30 Engineer's Estimate 70 SQFT $60.00 $4,200.00
A0260 63316-1000 REMOVE AND RESET SIGN
Stormwater Plans, LLC dba SWP Contracting and Paving $450.00 $900.00 Construction Solutions Group, LLC $367.50 $735.00 GC Works, Inc. $502.32 $1,004.64 Engineer's Estimate 2 EACH $400.00 $800.00
A0270 63401-0300 PAVEMENT MARKINGS, TYPE B, SOLID
Stormwater Plans, LLC dba SWP Contracting and Paving $0.80 $21,600.00 Construction Solutions Group, LLC $0.74 $19,980.00 GC Works, Inc. $4.31 $116,370.00 Engineer's Estimate 27,000 LNFT $0.25 $6,750.00
7 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
A0280 63405-0850 PAVEMENT MARKINGS, TYPE B, ACCESSIBILITY SYMBOL
Stormwater Plans, LLC dba SWP Contracting and Paving $350.00 $1,050.00 Construction Solutions Group, LLC $1,102.50 $3,307.50 GC Works, Inc. $574.08 $1,722.24 Engineer's Estimate 3 EACH $150.00 $450.00
A0290 63501-0000 TEMPORARY TRAFFIC CONTROL
Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $50,000.00 Construction Solutions Group, LLC Lump Sum $14,700.00 GC Works, Inc. Lump Sum $29,780.40 Engineer's Estimate ALL LPSM Lump Sum $36,000.00
A0300 63701-0000 FIELD OFFICE
Stormwater Plans, LLC dba SWP Contracting and Paving $125,000.00 $125,000.00 Construction Solutions Group, LLC $7,050.00 $7,050.00 GC Works, Inc. $11,481.60 $11,481.60 Engineer's Estimate 1 EACH $20,000.00 $20,000.00
Total Schedule - All Items
Stormwater Plans, LLC dba SWP Contracting and Paving $2,531,659.00 Construction Solutions Group, LLC $2,842,677.48 GC Works, Inc. $3,512,746.40 Engineer's Estimate $2,200,000.00
8 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: B
Schedule Type: Base
Solcitation No: 693C73-19-B-000026
Division: Eastern Federal Lands
State: AZ County: Pima
Federal Land: Buenos Aires National Wildlife Refuge Opened at: Sterling, Va
Opened by: Shirley Anderson
Date: 07/25/19
I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.
Signed: _______________________________
Title: _______________________________
Date: _______________________________
Contract Awarded to: ____________________ Award Date: ____________________
Contractor Comment Bid Amount Responsive
Construction Solutions Group, LLC $1,601,299.51 5512 Elk Valley Estates Dr St. Louis Missouri 63128
Stormwater Plans, LLC dba SWP Contracting and Paving $1,738,042.00 5624 N. 54th Avenue Glendale Arizona 85301
GC Works, Inc. $2,870,103.78 5933 NE Win Sivers Dr. Ste 205 Portland Oregon 97220
Engineer's Estimate $1,220,000.00
Shirley A. Anderson
Contract Specialist
07/25/2019
Stormwater Plans, LLC dba SWP Contracting & Paving 09/05/2019
9 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: B
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0010 15101-0000 MOBILIZATION
Construction Solutions Group, LLC Lump Sum $28,953.41 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $270,000.00 GC Works, Inc. Lump Sum $1,007,262.83 Engineer's Estimate ALL LPSM Lump Sum $144,560.00
B0020 15201-0000 CONSTRUCTION SURVEY AND STAKING
Construction Solutions Group, LLC Lump Sum $2,940.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $150,000.00 GC Works, Inc. Lump Sum $28,704.00 Engineer's Estimate ALL LPSM Lump Sum $77,000.00
B0030 15401-0000 CONTRACTOR TESTING
Construction Solutions Group, LLC Lump Sum $7,350.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $50,000.00 GC Works, Inc. Lump Sum $28,704.00 Engineer's Estimate ALL LPSM Lump Sum $34,000.00
B0040 15705-1400 SOIL EROSION CONTROL, FIBER ROLL
Construction Solutions Group, LLC $8.40 $11,760.00 Stormwater Plans, LLC dba SWP Contracting and Paving $5.00 $7,000.00 GC Works, Inc. $5.74 $8,036.00 Engineer's Estimate 1,400 LNFT $8.00 $11,200.00
B0050 20103-0000 CLEARING AND GRUBBING
Construction Solutions Group, LLC $10.36 $4,869.20 Stormwater Plans, LLC dba SWP Contracting and Paving $0.60 $282.00 GC Works, Inc. $1.25 $587.50 Engineer's Estimate 470 SQYD $12.00 $5,640.00
B0060 20301-2400 REMOVAL OF SIGN
Construction Solutions Group, LLC $183.65 $1,101.90 Stormwater Plans, LLC dba SWP Contracting and Paving $85.00 $510.00 GC Works, Inc. $93.29 $559.74 Engineer's Estimate 6 EACH $150.00 $900.00
10 out of 10
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: B
Schedule Type: Base
Line Item Pay Item No. Description Quantity Unit Unit Price Amount
Number
B0080 30110-0000 AGGREGATE SURFACE COURSE
Construction Solutions Group, LLC $62.92 $1,195,480.00 Stormwater Plans, LLC dba SWP Contracting and Paving $58.00 $1,102,000.00 GC Works, Inc. $81.12 $1,541,280.00 Engineer's Estimate 19,000 TON $35.00 $665,000.00
B0090 30303-3000 ROADWAY RECONDITIONING
Construction Solutions Group, LLC $3.68 $334,880.00 Stormwater Plans, LLC dba SWP Contracting and Paving $1.40 $127,400.00 GC Works, Inc. $2.50 $227,500.00 Engineer's Estimate 91,000 SQYD $3.00 $273,000.00
B0100 63302-0000 SIGN SYSTEM
Construction Solutions Group, LLC $147.00 $6,615.00 Stormwater Plans, LLC dba SWP Contracting and Paving $130.00 $5,850.00 GC Works, Inc. $146.39 $6,587.55 Engineer's Estimate 45 SQFT $60.00 $2,700.00
B0110 63501-0000 TEMPORARY TRAFFIC CONTROL
Construction Solutions Group, LLC Lump Sum $7,350.00 Stormwater Plans, LLC dba SWP Contracting and Paving Lump Sum $25,000.00 GC Works, Inc. Lump Sum $20,882.16 Engineer's Estimate ALL LPSM Lump Sum $6,000.00
Total Schedule - All Items
Construction Solutions Group, LLC $1,601,299.51 Stormwater Plans, LLC dba SWP Contracting and Paving $1,738,042.00 GC Works, Inc. $2,870,103.78 Engineer's Estimate $1,220,000.00
Bid Error Report
1 out of 4
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
GC Works, Inc. A0040 $8,037.12 $8,036.00
GC Works, Inc. A0270 $116,251.20 $116,370.00
GC Works, Inc. A0200 $215.28 $215.25
GC Works, Inc. A0220 $3,516.24 $3,516.25
GC Works, Inc. A0070 $839.59 $839.61
GC Works, Inc. A0060 $28,704.00 $28,750.00
GC Works, Inc. A0120 $2,021.76 $2,025.00
GC Works, Inc. A0080 $1,377.79 $1,377.84
GC Works, Inc. A0250 $10,247.33 $10,247.30
2 out of 4
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: A
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Construction Solutions Group, LLC $2,842,677.48 $2,842,677.48
Stormwater Plans, LLC dba SWP Contracting and Paving $2,531,659.00 $2,531,659.00
GC Works, Inc. $3,512,579.46 $3,512,746.40 X
The apparent low bidder is 15.08% above the engineer's estimate.
3 out of 4
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: B
Schedule Type: Base
Bid Item Check Pass
Bidder Line Item Number Bidder's Extension Computed Extension
GC Works, Inc. B0060 $559.73 $559.74
GC Works, Inc. B0040 $8,037.12 $8,036.00
GC Works, Inc. B0090 $227,136.00 $227,500.00
GC Works, Inc. B0100 $6,587.57 $6,587.55
GC Works, Inc. B0050 $586.56 $587.50
4 out of 4
Project No: AZ FTFW BUAI 10(3), 11(1)
Project Name: Rehabilitation of Refuge Entrance Road, Pronghorn Tour Loop Road, and Visitor Center
Parking Area, and construction of new Overflow Parking Area
Schedule: B
Schedule Type: Base
Bid Total Check Pass
Bidder Bidder's Bid Amount Computed Bid Amount Error
Construction Solutions Group, LLC $1,601,299.51 $1,601,299.51
Stormwater Plans, LLC dba SWP Contracting and Paving $1,738,042.00 $1,738,042.00
GC Works, Inc. $2,869,739.42 $2,870,103.78 X
The apparent low bidder is 31.25% above the engineer's estimate.