Tab 04 3 SOW.pdf

PDF 201 KB Posted

Attached to
High Pressure Industrial Water (HPIW) Facility Auxiliary Supply Pump Package and Installation
Solicitation number
80NSSC25914556Q
Issued by

About this file

This Statement of Work details the procurement and installation of an auxiliary supply pump package for NASA's Stennis Space Center High-Pressure Industrial Water (HPIW) Facility. The project requires a contractor to provide and install one Goulds 3409S Split Case Auxiliary Supply Pump (Model 8x12-22L) with a 600 HP, 4160V, 3-phase motor, along with associated valves, flanges, and pipe spools. Field installation services are mandatory, including removing existing equipment, preparing foundations, installing new equipment, performing final alignment, and cleaning the site.

The project timeline spans 24 weeks, beginning with purchase order award (Week 0) and concluding with documentation and site acceptance (Week 24). Key contractor responsibilities include providing all equipment, performing installation tasks, supplying labor and materials, conducting alignment and stress analysis, and providing component conformance certificates. The government will provide worksite access, an electrician for electrical connections, and review submittals within 10 business days. Delivery will be to Building 4400 at Stennis Space Center in Mississippi, with fabrication occurring between weeks 0-20, delivery in week 20, installation in weeks 21-22, and final completion by week 23.

View the file

Other files

File Type Posted
Tab 07 Capability Statement SAM.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

Auxiliary Supply Pump Package and Installation NASA Stennis Space Center – High-Pressure Industrial Water (HPIW) Facility

1. Objectives

Procure and deliver one (1) auxiliary supply pump package and associated components, including valves and spools, and provide field installation services at NASA Stennis Space Center (SSC). This procurement supports ongoing upgrades to the High-Pressure Industrial Water Facility systems.

The awarded contractor shall:

Provide one (1) Goulds 3409S Split Case Auxiliary Supply Pump – Model 8x12-22L with 600 HP, 4160V, 3-phase, 60Hz motor.

Provide all associated valves, flanges, and pipe spools, per specifications.

Provide field installation services, including removal of existing equipment, foundation prep, new installation, final alignment, and site cleanup.

Adhere to all safety, quality, and cleanliness standards required at NASA SSC.

Coordinate with government-provided electrician for all electrical connections.

2. Equipment & Materials

Line Item

Description Quantity Notes

Pump Package – Goulds 3409 S, 8x12-22L, 600 HP, 1800 RPM, 4160V/3PH/60HZ motor with baseplate, RTDs, space heaters, couplings, and grease-lubricated bronze fitted construction

Includes TEFC motor, trim to 21.300", channel steel baseplate with drip pan

Spool Piece – 10” 300# x 12” 150# x 6” 150# (branch), carbon steel painted

Includes carbon steel tee and 8” 300# spool

12" 150# Powell Gate Valve (RFF, A216 Body, API Trim 8)

1 Painted

12" 300# Powell Gate Valve (Bolted Bonnet, Graphite Packing, API Trim 8)

5 Field Installation Services 1

Includes removal, anchor bolt work, epoxy grout, installation, alignment, and cleanup. See Section 3.2 below

3. Scope of Services

3.1 Field Installation Tasks

The contractor shall perform the following:

Remove old pump, baseplate, and anchor bolts.

Prepare existing concrete pad and install new anchor bolts.

Set and level new stainless steel baseplate to required elevation.

Mix and apply epoxy grout under baseplate.

Install all new equipment, valves, and spools.

Conduct final shaft alignment and piping stress checks.

Clean and chamfer grout forms and return site to clean condition.

3.2 Responsibilities

Contractor Responsibilities:

o Provide all equipment listed above.

o Perform all installation tasks.

o Supply all labor, tools, rigging, and materials (except as noted).

o Conduct alignment and stress analysis as needed.

o Provide Certificates of Conformance for major components.

Government Responsibilities:

o Provide access to the worksite.

o Provide an electrician for motor wiring and electrical connections.

o Review and approve submittals within 10 business days.

4. Deliverables

One (1) complete pump package installed and aligned

One (1) spool piece, two (2) gate valves installed

Epoxy grouted and leveled baseplate

Final alignment report and stress check summary

Material certification documentation

Site cleaned and cleared of debris

5. Timeline

Milestone Description Timeline

Purchase Order Award Authorization to proceed Week 0

Fabrication Pump, valves, spools 0–20 Weeks ARO

Delivery Ship to NASA SSC Week 20 ARO

Installation Start on-site services Week 21–22

Completion Install and final alignment By Week 23

Closeout Documentation, site acceptance Week 24

6. Delivery Location

High Pressure Industrial Water (HPIW) Facility Building 4400 Stennis Space Center, MS 39529