T26-15 - Bid Specs.pdf

PDF 11 MB Posted

Attached to
SW Plymouth Ave from Wilson Springs Road to Jordan St - Sidewalk Improvements
Solicitation number
T26-15
Issued by
Florida

About this file

This is a bid specification document for Columbia County, Florida, for sidewalk improvement construction on SW Plymouth Avenue from Wilson Springs Road to Jordan Street. The project scope includes installation of 5-foot-wide concrete sidewalk on the west side of SW Plymouth Avenue, along with signing, pavement markings, and associated work. The bid submission deadline is Friday, July 31, 2026, at 5:00 PM, with bid opening scheduled for Tuesday, August 6, 2026, at 2:00 PM local time. A pre-construction conference will be held prior to work commencement to review project schedules, submittal procedures, and establish working procedures between the County and Contractor. The estimated project timeline includes contract execution by August 20, 2026, project commencement by October 1, 2026, and project completion by December 10, 2026. The contractor must submit a Notice to Proceed within 60 days of contract execution and begin work within that timeframe.

Payment terms are net thirty (30) days unless otherwise specified. The County reserves the right to award items separately or on a lump-sum basis and may purchase more or less than estimated quantities. Contractors must obtain and maintain comprehensive general liability insurance with minimum limits of $1,000,000 per occurrence for bodily injury and property damage, comprehensive automobile liability insurance at the same limits, and worker's compensation insurance as required by Florida statute. Performance and payment bonds in the amount of 100% of the contract price are required, underwritten by sureties rated A- or better by A.M. Best Company. All contractors must be prequalified with the Florida Department of Transportation and provide proof of such qualification. The contractor must comply with E-Verify requirements, maintain a drug-free workplace as certified under Florida Statute 287.087, and provide detailed subcontractor information. All bids must include executed exhibits covering proposed subcontractors, drug-free workplace certification, bidder qualifications, and non-collusion statements, with unsigned or late bids subject to automatic rejection.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July

Officer ejones

July 1, 2026

T26-15

August 6, 2026 @ 2:00 PM

2026 @ 2:00 PM

GENERAL INSTRUCTIONS TO BIDDERS

These instructions will bind bidders and conditions herein set forth, except as specifically qualified in special bid and contract terms issued with any individual bid.

1. The following criteria are used in determining low responsible bidder:

The ability, capacity and skill of bidder to perform required service.

Whether the bidder can perform service promptly or within specified time.

The determined character, integrity, reputation, judgment, experience and efficiency of bidder.

The performance of previous contracts with Columbia County or entities similar to

Columbia County.

The suitability of equipment or material for County use.

The ability of bidder to provide future maintenance.

2. Payment Terms are net thirty (30) unless otherwise specified. Favorable terms, discounts, may be offered and will be considered in determining low bids if they are deemed by

Purchasing Department to be advantageous to the County.

3. All bids should be tabulated, totaled and checked for accuracy. Where applicable, the provided unit price will prevail in case of discrepancies or other errors.

4. All requested information shall be included in the envelope. All desired information must be included for your bid to receive full consideration.

5. If anything on the bid request is not clear, you should contact the Purchasing Director immediately.

6. A bidders list is available at the Purchasing Office.

7. Quote all prices F.O.B. our warehouse or as specified in bid documents.

8. Each proposal shall be clearly marked on the outside of the envelope including Fed Ex, UPS or other delivery service envelopes, as a sealed bid. The name of the item being bid shall be shown on the outside in full.

9. The County shall not be liable for any bid opened prematurely if that bid was not sealed in a properly marked envelope.

10. If only one (1) bid is received, the bid may be rejected and re-advertised or excepted if determined to be in the counties best interest.

11. Bids received late will not be accepted. It is the bidder’s sole responsibility to ensure proposals are timely delivered and received before the deadline.

12. Telephone and facsimile bids will not be accepted under any circumstances. Should a timely delivered bid be misplaced by the County but later found before ranking occurs, the

(Unless otherwise specified in the ITB/RFP/RFQ) bid will be considered. A bidder may request a receipt showing the day and time a bid envelope is delivered to the appropriate office of the County.

13. Bids requiring bid bonds will not be accepted if bond is not enclosed. Cash or certified check will be accepted in lieu of bond except on construction projects with a project budget exceeding $40,000.

14. Upon request of the Purchasing Office or County Manager, a bidder must provide proof that the bidder has the requisite organization, capital, plant, stock, ability, and experience to perform the contract contemplated by the Request for Proposals/Qualifications or

Invitation to Bid.

15. Any alterations, erasures, additions, or omissions of required information or any changes to specifications or bidding schedule are done at the risk of the bidder. Any bid will be rejected that has a substantial variation, that is; a variation that affects price, quantity, and quality or delivery date (when delivery is required by a specific time).

16. When requested, samples will be furnished to the County free of expense, properly marked for identification and accompanied by a list where there is more than one (1) sample. The

County reserves the right to mutilate or destroy any sample submitted whenever it may be to the best interest of the County to do so for the purpose of testing.

17. The County will reject any material, supplies or equipment that did not meet the specifications, even though the bidder lists the trade names or names of such material on the bid or price quotation form.

18. The unauthorized use of patented articles is done entirely at the risk of the successful bidder.

19. The ESTIMATED QUANTITY given in the specifications or advertisements is for the purpose of bidding only. The County may purchase more or less than the estimated quantity and the vendor must not assume that such estimated quantity is part of the contract.

20. Only the latest model equipment as evidenced by the manufacture’s current published literature will be considered. Obsolete models of equipment not in production will not be acceptable. The equipment shall be composed of new parts and materials. Any unit containing used parts or having seen any service other than the necessary tests will be rejected. In addition to the equipment specifically called for in the specification, all equipment catalogued by the manufacturer as standard or required by the State of Florida shall be furnished with the equipment. Where required by the State of Florida Motor

Vehicle Code, vehicles shall be inspected and bear the latest inspection sticker of the

Florida Department of Revenue.

21. The successful bidder on motor vehicle equipment shall be required to furnish with delivery of vehicle, certificate of origin and any other appropriate documentation as required by the

Florida Motor Vehicle Department.

22. Prospective bidders are required to examine the location of the proposed work or delivery and determine, in their own way, the difficulties, which are likely to be encountered in the prosecution of the same.

23. All materials, equipment and supplies shall be subject to rigid inspection, under the immediate supervision of the Purchasing Department, its designee and /or the department to which they are delivered. If defective material, equipment, or supplies are discovered, the contractor, upon being instructed by the Purchasing Department or designee, shall remove, or make good such material, equipment, or supplies without extra compensation.

It is expressly understood and agreed that the inspection of materials by the County will in no way lessen the responsibility of the Contractor release him from his obligation to perform and deliver to the County Sound and satisfactory materials, equipment, or supplies.

The Contractor agrees to pay the costs of all tests upon defective material, equipment, or supplies or allow the costs to be deducted from any monies due him from the County.

24. Unless otherwise specified by the Purchasing Department all materials, supplies, or equipment quoted herein must be delivered within thirty (30) days from the day of notification or exceptions noted on bid sheets.

25. A contract will not be awarded to any corporation, firm, or individual who is, from any cause, in arrears to the County or who has failed in former contracts with the County to perform work satisfactorily, either to the character of the work, the fulfillment or guarantee, or the time consumed in completing the work.

26. Reasonable grounds for supposing that any bidder is interested in more than one proposal for the same item will be considered sufficient cause for rejection of all proposals in which he is interested.

27. Submitting a proposal when the bidder intends to sublet the contract may be a cause for rejection of bids or cancellation of the contract by the County Manager.

28. Unless otherwise specified, the County reserves the right to award each items separately or on a lump sum basis whichever is in the best interest of the County.

29. Respondents to this solicitation or persons acting on their behalf may not contact, between the release of the solicitation and the end of the 72-hour period following the agency posting the notice of intended award, excluding Saturdays, Sundays, and state holidays, any employee or officer of the executive or legislative branch concerning any aspect of this solicitation, except in writing to the procurement officer or as provided in the solicitation documents. Violation of this provision may be grounds for rejecting a response.

30. The County reserves the right to reject any quotations or specifications and the right to waive minor discrepancies as to all bidders equally, when such rejection or waiver is deemed to be in the best interest of the County. For unit priced items, the County may elect to purchase part, all, or none of the materials, supplies, or equipment specified in a bid.

31. The bidder or the bidder's authorized representative or agent must sign the bid in the space provided. Unsigned bids will be rejected. Signature must be "wet" signatures in ink.

Typewritten or printed signatures will not be accepted.

32. Any bidder may withdraw his/her bid at any time before the time set for the opening of the bids.

33. It is mutually understood and agreed that if at any time the Purchasing Department or designee shall be of the opinion that the contract or any part thereof is unnecessarily delayed or that the rate of progress or delivery is unsatisfactory, or that the contractor is willfully violating any of the conditions or covenants of the agreement, or executing the same in bad faith, the Purchasing Department or his/her designee shall have the power to notify the contractor of the nature of the complaint. Notification shall constitute delivery of notice, or letter to address given in the proposal. If after three (3) working days of notification the conditions are not corrected to the satisfaction of the Purchasing Officer, he shall have the power to take whatever action necessary to complete the work or delivery and the expense shall be deducted from any paid by the County out of such monies as may become due to the said contractor. In case such expense shall exceed the last said sum, then and in that event, the bondsman or the contractor, his/her executors, administrators, successors, or assigns, shall pay the amounts of such excess to the County on notice made by the Purchasing Department or his/her designee of the excess due.

34. If the bidder proposes to furnish any item of foreign make or product, he shall write

“foreign” together with the name of the originating country opposite such item on a proposal.

35. Any complaint from bidders relative to the invitation to bid or attached specifications shall be made prior to the time of opening bids; otherwise, the bidder waives any such complaint.

36. Contracts may be cancelled by the County with or without cause on thirty- (30) days advance written notice.

37. All contractors submitting bids for road projects in excess of $250,000 must be pre-qualified with the Florida Department of Transportation and shall provide proof of such qualification.

38. Any bidder affected adversely by an intended decision with respect to the award of any bid, shall file with the Purchasing Department for Columbia County, a written notice of intent to file a protest not later than seventy-two (72) hours (excluding Saturdays, Sundays and legal holidays), after the posting of the bid tabulation. Protest procedures may be obtained in the Purchasing Department.

39. A person or affiliate who has been placed on the convicted vendor's list following a conviction for a public entity crime may not submit a bid on a contract to provide any goods or services to Columbia County, may not submit a bid on a contract with Columbia County for the construction or repair of a public building or public work, may not submit bids on leases of real property to Columbia County, may not be awarded or perform work as a contractor, supplier, subcontractor, or consultant under a contract with Columbia County, and may not transact business with Columbia County for a period of 36 months from the date of being placed on the convicted vendor list.

40. Vendor/Contractor shall utilize the U.S. Department of Homeland Security’s E-Verify system, in accordance with the terms governing use of the system, to confirm the employment eligibility of;

All persons employed by the Vendor/Contractor during the term of the Contract to perform employment duties within Florida; and

All persons, including subcontractors, assigned by the Vendor/Contractor to perform work pursuant to the contract with the County.

41. Contractor shall register on line at https://www.columbiacountyfla.com/PurchasingBids.asp for this specific project. All addendums are delivered via email through this website, and it is the contractor’s responsibility to ensure all addendums are used in the bid submittal.

https://www.columbiacountyfla.com/PurchasingBids.asp

July 1, 2026

T26-15

August 6, 2026 @ 2:00 PM Local Time

T26-15

:00 PM on July 7, 2026 2:00 PM on August 6, 2026

Tuesday, August 6, 2026 @ 2:00 PM f

Friday, July 31, 2026 @ 5:00 PM

August 6, 2026 @ 2:00 PM Local Time

T26-15

August 6, 2026 @ 2:00 PM Local Time ejones r than Friday, July 31, 2026 @5:00 PM. Any and all interpretations and any s

Friday, July 31, 2026 @ 5:00 PM.

August 20, 2026 (Estimated) October 1, 2026 (Estimated)

December 10, 2026 (Estimated)

SECTION C – BIDDERS CHECKLIST

Bidders may use the boxes to the left to check off items when completed.

The checklist is intended as a reminder for certain important items and is not necessarily a complete list of what must be included in your BID submission.

Bid Form (EXHIBIT A) (Remember to fill this form out completely) THIS FORM MUST

BE SIGNED.

Acknowledge all Addendum(s) issued with this solicitation must be included in your BID submission. A place to check off acknowledgement is on the bid form.

Submit the appropriate number of copies.

MANDATORY, all of the following EXHIBITS must be SUBMITTED:

EXHIBIT B – PROPOSED SUBCONTRACTOR FORM

EXHIBIT C – BID OPPORTUNITY LIST

EXHIBIT D – DRUG FREE WORKPLACE

EXHIBIT C – BIDDER’S QUESTIONNAIRE

EXHIBIT N – LAP CERTIFICATION OF CURRENT CAPACITY

EXHIBIT O – NON-COLLUSION

EXHIBIT P – DEBARMENT/SUSPENSION

EXHIBIT Q & R – DISCLOSURE OF LOBBYING

Include any insurance requirements.

Include any payment, performance and/or bid bonds that may be applicable.

Remember to submit your Bid prior to the submittal deadline.

LATE BIDS WILL NOT BE CONSIDERED.

Make sure that your bid package has been clearly marked and sealed. The bid number and name along with the vendor’s company name should be clearly marked on the outside of the envelope.

It is the vendor’s responsibility when using courier services, such as Fed Ex, UPS, etc., to make sure that the bid arrives on time. LATE BIDS WILL NOT BE CONSIDERED.

If you have questions concerning these items or other sections of the bid solicitation please contact the County for clarification prior to submitting your bid.

SECTION D – GENERAL CONDITIONS

1.0 STARTING THE WORK

1.1 Schedule

Within ten (10) days after execution of the Agreement, the Contractor will submit to the County for approval an estimated progress schedule indicating the starting and completion dates of the various stages of the Work and a schedule of Shop Drawings submissions.

1.2 Pre-Construction Conference

Before starting Work, a conference will be held to review the above schedules and Submittal package (See 1.5 Submittals), to establish procedures for handling Shop Drawings and other submissions, to establish procedures for processing applications for payment and to establish a working understanding between the parties as to the project.

Present at the conference will be County Project Representatives, the Contractor and utility company representatives.

1.3 Notice to Proceed

Upon execution and delivery of the Agreement, the Engineer will give the Contractor a written Notice to Proceed stating date by which the Contractor must start the Work; but such date shall not be more than sixty (60) days after the date of execution and delivery of the Agreement. No work shall be done prior to receipt of the Notice to Proceed.

1.4 Commencement of Time

The Contract Time shall commence on the date when the Work is actually started but no later than the date provided in the Notice to Proceed.

1.5 Submittals

The Contractor’s submittal package for the Pre-Construction meeting shall include: Exhibit Y, Surveyor’s license confirmation, Maintenance of Traffic Plan, Erosion & Sedimentation Control Plan and Quality Control Plan to be approved by County Project Representatives prior to any construction activities along with any other requirements as outlined in this document.

2.0 INTENT OF CONTRACT DOCUMENTS

2.1 It is the intent of the Specifications and Drawings to describe a complete project to be constructed in accordance with the Contract Documents.

2.2 The Contract Documents comprise the entire Agreement between the County and the Contractor. They may be amended only by approval of a Change Order.

3.0 OWNERSHIP AND COPIES OF DOCUMENTS; RECORD DOCUMENTS

3.1 All Specifications, Drawings and copies thereof furnished by Columbia County shall remain the property of Columbia County. They shall not be used on another project, and with the exception of those sets of Contract Documents which have been signed in connection with the execution of the Agreement, shall be returned to the County on request upon completion of the project.

3.2 The County will furnish to the Contractor three (3) copies of the Drawings as are reasonably necessary for the execution of the Work. Additional copies will be furnished, upon request, at the cost of reproduction.

3.3 The Contractor will keep one record copy of all Specifications, Drawings, Addenda, Modifications, and Shop Drawings at the site in good order and annotated to show all changes made during the construction process. These shall be available to the County and/or County Project Representatives.

4.0 WORK BY OTHERS

4.1 The County may perform additional work related to the project by itself, or the County may let other direct contracts therefore, which shall contain General Conditions similar to these. The Contractor shall afford the other Contractors who are parties to such direct contracts (or the County, if it is performing the additional work) reasonable opportunity for the introduction and storage of materials and equipment and the execution of work and shall properly connect and coordinate his work with theirs.

4.2 If any part of the Contractor's Work depends for proper execution or results upon the work of any such other Contractor (or the County), the Contractor will inspect and promptly report to the Engineer in writing any defects or deficiencies in such work that render it unsuitable for such proper execution and results. His failure to so report shall constitute an acceptance of the other work as to be fit and proper for the relationship of his Work, except as to defects and deficiencies which may appear in the other work after the execution of his Work.

4.3 The Contractor will do all cutting, fitting and patching of his Work that may be required to make its several parts come together properly and fit it to receive or be received by such other work. The Contractor will not endanger any work of others by cutting, excavating or otherwise altering their work and will only cut or alter their work with the written consent of the Engineer.

4.4 If the performance of additional work by other contractors or the County is not noted in the Contract Documents prior to the award of the contract, written notice thereof shall be given to the Contractor prior to starting any such additional work. Contractor work schedules shall be adjusted to allow for any necessary utility adjustments identified prior to start of work. If the Contractor believes that the performance of such additional work by the County or others involves him in additional expense or entitles him to an extension of the Contract Time, he may make a claim therefore as provided in Section D, Paragraphs 15-17.

5.0 RESPONSIBLE AGENT

5.1 The Contractor shall designate and submit a responsible agent and alternate as necessary, for all dealings, communications, or notices or contracts between the County and the contractor, Section H, Exhibit G.

5.2 The Engineer will be the responsible agent for the County. Any notice or communication to or from the responsible agent shall be deemed to be a communication to the contractor.

5.3 A letter when addressed and sent by certified list mail to either part, at its business herein, will constitute notice required in this bid or contract.

6.0 ACCIDENT PREVENTION

6.1 Precaution shall be exercised at all times for the protection of employees, other persons and property.

6.2 Contractor's employees shall report to their superintendent any hazardous conditions or items in need of repair noted during the performance of work. Said superintendent shall thereupon notify the responsible agent or his designee of such conditions.

7.0 SUBCONTRACTS

7.1 With the Bid Proposal, the successful Bidder will have submitted to the County and the Engineer for acceptance, a list of the names of proposed Subcontractors and suppliers. Prior to the execution and delivery of the Agreement, the Engineer will notify the successful Bidder in writing if either the County or the Engineer, after due investigation, has reasonable objection to any Subcontractor, person or organization on such list. The failure of the County or the Engineer to make objection to any Subcontractor, person or organization on the list prior to the execution and delivery of the Agreement shall constitute an acceptance of such Subcontractor, person or organization. Acceptance of any such Subcontractor, person or organization shall not constitute a waiver of any right of the County or the Engineer to reject Work, material or equipment that is either defective or not in conformance with the requirements of the Contract Documents.

7.2 If, prior to the execution and delivery of the Agreement, the County or the Engineer has reasonable objection to and refuses to accept any Subcontractor, person or organization on such list, the successful Bidder may, prior to such execution and delivery, either (i) submit an acceptable substitute without an increase in his Bid price, or (ii) withdraw his Bid and forfeit any Bid security. If, after the execution and delivery of the Agreement, the County or the Engineer refuses to accept any Subcontractor, person or organization on such list, the Contractor will submit an acceptable substitute, the Contract Price shall be increased or decreased by the difference in cost occasioned by such substitution and an appropriate Change Order shall be issued. No such increase in the Contract Price shall be allowed if the disputed Subcontractor was not identified on the Subcontractor list submitted prior to award of the Contract.

7.3 The Contractor will not employ any Subcontractor (whether initially or as a substitute) against whom the County or the Engineer may have reasonable objection, nor will the Contractor be required to employ any Subcontractor against whom he has reasonable objection. The Contractor will not make any substitution for any Subcontractor who has been accepted by the County and the Engineer, prior to written concurrence by the Engineer.

7.4 The Contractor will be fully responsible for all acts and omissions of his Subcontractors and of persons directly or indirectly employed by them and of persons for whose acts any of them may be liable to the same extent that he is responsible for the acts and omissions of persons directly employed by him. Nothing in the Contract Documents shall create any contractual relationship between any Subcontractor and the County or the Engineer or any obligation on the part of the County or the Engineer to pay or to see to the payment of any monies due any Subcontractor, except as may otherwise be required by law. The Director may furnish to any Subcontractor, to the extent practicable, evidence of amounts paid to the Contractor as compensation for specific Work performed.

7.5 The divisions and sections of the Specifications and the identifications of any Drawings shall not control the Contractor in dividing the Work among Subcontractors or delineating the Work to be performed by any trade.

7.6 The Contractor agrees to specifically bind every Subcontractor to all of the applicable terms and conditions of the Contract Documents. Every Subcontractor, by undertaking to perform any of the Work, will thereby automatically be deemed to be bound by such terms and conditions.

8.0 CONFLICT OF INTEREST

8.1 Neither the Contractor or their subcontractors shall enter into any contract, subcontract or arrangement in connection with the Project or any property included or planned to be included in the Project in which any member, officer or employee of the Contractor or the locality during tenure or for 2 years thereafter has any interest, direct or indirect. If any such present or former member, officer or employee involuntarily acquires or had acquired prior to the beginning of tenure any such interest, and if such interest is immediately disclosed to the Contractor, the Contractor, with prior approval of the County, may waive the prohibition contained in this paragraph provided that any such present member, officer or employee shall not participate in any action by the Contractor or the locality relating to such contract, subcontract or arrangement. The Contractor shall insert in each of their subcontracts, the following provision:

8.1.1 "No member, officer or employee of the Subcontractor or of the locality during his tenure or for 2 years thereafter shall have any interest, direct or indirect, in this contract or the proceeds thereof."

The provisions of this paragraph shall not be applicable to any agreement between the Recipient and its fiscal depositories or to any agreement for utility services the rates for which are fixed or controlled by a governmental agency.

9.0 PHYSICAL AND SUBSURFACE CONDITIONS

9.1 The Engineer will, upon request, furnish to the Contractor copies of all available boundary surveys and subsurface tests.

9.2 The Contractor will promptly notify the Engineer in writing of any subsurface or latent physical conditions at the site differing materially from those indicated in the Contract Documents. The Engineer will promptly investigate those conditions and determine if further surveys or subsurface tests are necessary. Promptly thereafter, the Engineer will obtain the necessary additional surveys and tests and furnish copies to the Contractor. If the Engineer finds that the results of such surveys or tests indicate subsurface or latent physical conditions differing significantly from those indicated in the Contract Documents, a Change Order shall be issued incorporating the necessary revisions.

10.0 ENGINEER’S STATUS DURING CONSTRUCTION

10.1 The Engineer shall be the County's representative during the construction period. All instructions of the County to the Contractor shall be issued through the Engineer.

10.2 The Engineer will make periodic visits to the site to observe the progress and quality of the executed Work and to determine, in general, if the Work is proceeding in accordance with the Contract Documents. He will not be required to make exhaustive or continuous on-site inspections to check the quality or quantity of the Work, nor will he be responsible for the construction means, methods, techniques, sequences, procedures or the safety precautions incident thereto. His efforts will be directed toward providing assurance for the County that the completed project will conform to the requirements of the Contract Documents, but he will not be responsible for the Contractor's failure to perform the Work in accordance with the Contract Documents. On the basis of his on-site observations as an experienced and qualified design professional, he will keep the County informed of the progress of the Work and will endeavor to guard the County against defects and deficiencies in the Work of the Contractor.

10.3 The Engineer will have authority to disapprove of or reject Work which is defective; i.e., it is unsatisfactory, faulty or defective, does not conform to the requirements of the Contract Documents or does not meet the requirements of any inspection, test or approval referred to in Section D, Paragraph 11. He will also have authority to require special inspection or testing of the Work as provided in Section D, Paragraph 13.2, whether or not the Work is fabricated, installed or completed.

10.4 Neither the Engineer’s authority to act under this Section D, Paragraph 9 nor any decision made by him in good faith either to exercise or not exercise such authority shall give rise to any duty or responsibility of the Engineer to the Contractor and Subcontractor, any of their agents or employees or any other person performing any of the Work.

11.0 ENGINEER’S INTERPRETATIONS AND DECISIONS

11.1 The Engineer will issue with reasonable promptness such written clarifications or interpretations (in the form of drawings or otherwise) as he may determine necessary for the proper execution of the Work. Such clarifications and interpretations are to be consistent with or reasonably inferable from the overall intent of the Contract Documents. If the Contractor believes that a written clarification and interpretation entitles him to an increase in the Contract Price, he may make a claim therefore as provided in Section D, Paragraph 16.

11.2 The Engineer will be the initial interpreter of the terms and conditions of the Contract Documents and the judge of the performance there under. In his capacity as interpreter and judge he will exercise his best efforts to insure faithful performance by both the County and the Contractor. He will not show partiality to either and shall not be liable for the result of any interpretation or decision rendered in good faith. Claims, disputes and other matters relating to the execution and progress of the Work or the interpretation of or performance under the Contract Documents shall be referred initially to the Engineer for decisions, which he shall render in writing within a reasonable time.

12.0 TESTS AND INSPECTIONS

12.1 If the Contract Documents, laws, ordinances, rules, regulations or orders of any public authority having jurisdiction require any Work to specifically be inspected, tested or approved by someone other than the Contractor, the Contractor will give the Engineer timely notice of readiness therefore. The Contractor will furnish the Engineer the required certificates of inspection, testing or approval. All such tests will be in accordance with the methods prescribed by the American Society for Testing and Materials or such other applicable organization as may be required by law or the Contract Documents. If any such Work required so to be inspected, tested or approved is covered up without written approval or consent of the Engineer, it must, if directed by the Engineer, be uncovered for observation at the Contractor's expense. The cost of all such inspections, tests and approvals shall be borne by the Contractor unless otherwise provided.

12.2 Any Work which fails to meet the requirements of any such test, inspection or approval and any Work which meets the requirements of any such test or approval but does not meet the requirements of the Contract Documents shall be considered defective. Such defective Work may be rejected, corrected or accepted as provided in Section D, Paragraph 19.

12.3 Neither observations by the Engineer nor inspections, tests, or approvals by persons other than the Contractor shall relieve the Contractor from his obligations to perform the Work in accordance with the requirements of the Contract

13.0 CONTRACTOR’S SUPERVISION AND SUPERINTENDENCE

13.1 The Contractor will supervise and direct the Work efficiently and with his best skill and attention. He will be solely responsible for the means, methods, techniques, sequences and procedures of construction. Before undertaking the Work, he will carefully study and compare the Contract Documents and check and verify all figures shown thereon and all field measurements. He will at once report in writing to the Engineer any conflict, error or discrepancy which he may discover. The Contractor will be responsible to see that the finished Work complies accurately with the Contract Documents.

13.2 The Contractor will keep on the Work, at all times during its progress, a resident superintendent satisfactory to the

Engineer. The superintendent shall not be replaced without the consent of the Engineer, except under extraordinary circumstances. The superintendent will be the Contractor's representative at the site and shall have authority to act on behalf of the Contractor. All communications given to the superintendent shall be as binding as if given to the Contractor.

13.3 The Contractor will provide competent, suitably qualified personnel and perform construction as required by the Contract Documents. Survey and layout work shall be performed under direction of a Florida Registered Land Surveyor. Surveyor is required to sign, seal and return the form provided in Section I Exhibit Z. He will at all times maintain good discipline and order among his employees at the site.

13.4 The Engineer will not be responsible for the acts or omissions of the Contractor, any Subcontractors, any of his or their agents or employees or any other persons performing any of the Work.

13.5 The Contractor shall have a responsible person or persons available on a 24-hour basis seven (7) days a week in order that contact can be made in emergencies and in cases where immediate action must be taken to maintain traffic or to overcome any other problem that might arise. The furnishing of a telephone number where such person or persons can be reached outside of normal working hours will constitute compliance with this provision.

14.0 ACCESS TO THE WORK: UNCOVERING FINISHED WORK

14.1 The Engineer and his representatives and other representatives of the County will at all times have access to the Work.

The Contractor will provide proper facilities for such access and observation of the Work and also for any inspection or testing thereof by others.

14.2 If any Work is covered contrary to the request of the Engineer, it must, if requested by the Engineer, be uncovered for his observation and replaced at the Contractor's expense.

14.3 If any Work has been covered which the Engineer has not specifically requested to observe prior to its being covered, or if the Engineer considers it necessary or advisable that covered Work be inspected or tested by others, the Contractor, at the Director's request, will uncover, expose or otherwise make available for observation, inspection or testing, that portion of Work in question, furnishing all necessary labor, material and equipment. If it is found that such Work is defective or does not meet the requirements of the Contract Documents, the Contractor will bear all the expenses of such uncovering, exposure, observation, inspection and testing and of satisfactory reconstruction, including compensation for additional professional services. If, however, such Work is found to be non-defective and meets the requirements of the Contract Documents, the Contractor will be allowed an increase in the Contract Price or extension of the Contract Time directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction if he makes a claim therefore as provided in Section D, Paragraph 16 and 17.

15.0 MODIFICATIONS

15.1 This agreement constitutes the entire agreement and understanding between the parties hereto, and it shall not be considered modified, altered, changed or amended in any respect unless in writing and signed by the parties hereto.

15.2 The County will not be bound under this agreement for similar or like services being provided by County agencies or for services entered into by the County under a separate agreement.

16.0 CHANGES IN THE WORK

16.1 Without invalidating the Agreement, the County may, at any time or from time to time, order additions, deletions, or revisions in the Work. These will be authorized by Change Order or Field Change Order as appropriate. Upon receipt of written authorization, the Contractor will proceed with the Work involved. All such Work shall be executed under the applicable conditions of the Contract Documents. If any changes in the Work cause an increase or decrease in the Contract Amount, addition of Pay Items, or an extension or shortening of the Contract Time, an equitable adjustment will be made as provided in Section D, Paragraphs 15-17.

16.2 The Director may authorize minor changes or alterations in the Work not involving extra cost and not inconsistent with the overall intent of the Contract Documents. These may be accomplished by a Field Change Order. If the Contractor believes that any minor change or alteration authorized by the Director entitles him to an increase in the Contract Price, he may make a claim therefore as provided in Section D, Paragraph 16.

16.3 Additional work performed by the Contractor prior to written authorization will not automatically entitle him to additional compensation, an increase in the Contract Price, or an extension of the Contract Time.

16.4 It is the Contractor's responsibility to notify his surety of any changes affecting the general scope of the Work or change in the Contract Price, and the amount of the applicable Bonds shall be adjusted accordingly. The Contractor will furnish proof of such adjustment to the County.

17.0 CHANGE OF CONTRACT PRICE

17.1 The Contract Price constitutes the total compensation payable to the Contractor for performing the Work. All duties, responsibilities and obligations assigned to or undertaken by the Contractor shall be at his expense without change in the Contract Price.

17.2 The Contract Price may only be changed by a Change Order or Field Change Order. If the Contractor is entitled by the Contract Documents to make a claim for an increase in the Contract Price his notice of intent to file a claim shall be in writing delivered to the Engineer within ten (10) days of the occurrence of the event giving rise to the claim. The claim shall then be delivered to the Engineer in writing within fifteen (15) days after the elimination of the event giving rise to the claims. Change orders and field change orders will be approved by the following procedure:

17.2.1 The County Manager may approve change orders and field change orders that, either cumulatively or individually, increase the contract price up to ten percent of the original contract price or $50,000.00, whichever is less. The board shall approve change orders that, either individually or cumulatively, increase the contract price by more than ten percent of the original contract price or $50,000.00, whichever is less.

17.2.2 The County Manager may approve all change orders and field change orders that do not increase the cost to the County

17.2.3 Only the board may approve a change order and field change order that expands the size, function, or intended use of the project from that stated in the contract documents, regardless of cost.

17.3 All change orders approved by the County Manager shall be reported to the board as information items to be included in its consent agenda.

17.4 The value of any Work covered by a Change Order, for any claim for an increase in the Contract Price, shall be determined in one of the following ways:

17.4.1 Where the Work involved is covered by unit prices contained in the Contract Documents, by application of unit prices to the quantities of the items involved.

17.4.2 Mutual acceptance of a lump sum or unit price.

17.4.3 Cost and a mutually acceptable fixed amount for overhead and profit.

17.4.4 If none of the above methods is agreed upon, the value shall be determined on the basis of costs and a percentage for overhead and profit. Costs shall only include labor (payroll, payroll taxes, fringe benefits, workman's compensation, etc.) materials, equipment, and other incidentals directly related to the Work involved. The maximum percentage which shall be allowed for the Contractor's combined overhead and profit, shall be as follows:

17.4.4.1 for all such Work done by his own organization, the Contractor may add up to 10% (ten percent) of his actual increase in cost; and

17.4.4.2 for all such Work done by Subcontractors, each Subcontractor may add up to 10% (ten percent) of his actual net increase in cost for combined overhead and profit; and the Contractor may add up to 5% (five percent) of the Subcontractor's total for his combined overhead and profit, provided that no overhead or profit shall be allowed on costs incurred in connection with premiums for public liability insurance or other special insurance directly related to such Work. In such case and also under paragraph 16.4.4.1, the Contractor will submit in a form prescribed by the Director an itemized cost breakdown together with supporting data

17.4.5 Pay factor adjustments will be adjusted in accordance with details outlined in Section F, Special Conditions.

17.5 The amount of credit to be allowed by the Contractor to the County for any such change which results in a net decrease in cost, will be in the amount of the actual net decrease as determined in Section D, Paragraph 16.4 and processed by Change Order or Field Change Order.

18.0 CHANGE OF THE CONTRACT TIME

18.1 The Contract Time may be changed by a Change Order. Contract Time may be changed for Weather Days only in a Field Change Order. If the Contractor is entitled by the Contract Documents to make a claim for an extension in the Contract Time his notice of intent to file a claim shall be in writing delivered to the Engineer within ten (10) days of the occurrence of the event giving rise to the claim. The claim shall then be delivered to the Engineer in writing within fifteen (15) days after the elimination of the event giving rise to the claim. The County Manager may approve any other extension in Contract Time. Contract Time shall not be extended for County designated holidays. Any change in the Contract Time resulting from any such claim shall be incorporated in a Change Order.

18.2 The Contract Time will be extended in an amount equal to time lost due to delays beyond the control of the Contractor, if he makes a claim therefore as provided in Section D, Paragraph 17.1. Such delays shall include, but not be restricted to, acts of neglect by any separate contractor employed by the County, fires, floods, labor disputes, epidemics, abnormal weather conditions or acts of God.

18.3 All time limits stated in the Contract Documents are of essence in the Agreement. The provisions of this Section D, Paragraph 17 shall not exclude recovery for damages (including compensation for additional professional services) for delay by either party.

19.0 NEGLECTED WORK

19.1 If the Contractor should neglect to prosecute the Work in accordance with the Contract Documents, including any requirements of the progress schedule, after three (3) days written notice to the Contractor, the Engineer may, without prejudice to any other remedy he may have, make good such deficiencies, and the cost thereof (including compensation for additional professional services) shall be charged against the Contractor. In this case a Change Order shall be issued incorporating the necessary revisions in the Contract Documents, including an appropriate reduction in the Contract Price. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor will pay the difference to the County.

20.0 WARRANTY AND GUARANTEE; CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK

20.1 The Contractor warrants and guarantees to the County and the Engineer that all materials and equipment will be new unless otherwise specified; that all Work will be of good quality and free from faults or defects and in accordance with the requirements of the Contract Documents. All unsatisfactory Work, all faulty or defective Work and all Work not conforming to the requirements of the Contract Documents or of such inspections, tests or approvals shall be considered defective. Prompt notice of all defects shall be given to the Contractor. All defective Work, whether or not in place, may be rejected.

20.2 If required by either the Director or the Engineer prior to approval of final payment, the Contractor will promptly, without cost to the County and as required by either the Director or the Engineer, either correct any defective Work, whether or not fabricated, installed or completed, or, if the Work has been rejected by the Engineer, remove it from the site and replace it with nondefective Work. If the Contractor does not correct such defective Work or remove and replace such rejected Work within a reasonable time, all as required by written notice from either the Director or the Engineer, the County may have the deficiency corrected or the rejected Work removed and replaced. All direct or indirect cost of such correction or removal and replacement, including compensation for additional professional services, shall be paid by the Contractor, and an appropriate Change Order shall be issued deducting all such costs from the Contract Price. The Contractor will also bear the expenses of making good all Work of others destroyed or damaged by his correction, removal or replacement of his defective Work.

20.3 If, after the approval of final payment and prior to the expiration of one year after the date of substantial completion or such longer period of time as may be prescribed by law or by the terms of any applicable special guarantee required by the Contract Documents, any Work is found to be defective, the Contractor will promptly without cost to the County and in accordance with the County's written instructions either correct such defective Work, or, if it has been rejected by the County, remove it from the site and replace it with nondefective Work. If the Contractor does not promptly comply with the terms of such instructions, the County may have the defective Work corrected or the rejected Work removed and replaced, and all direct and indirect costs of such removal and replacement, including compensation for additional professional services, will be paid by the Contractor.

20.4 If, instead of requiring correction or removal and replacement of defective Work, the County prefers to accept it, the

County may do so. In such case, the appropriate reduction in the bid item amount shall be negotiated with the Contractor by the Engineer with the appropriate reductions submitted in the application for final payment. In the event the appropriate reduction cannot be negotiated, the provisions of Section D, Paragraph 33 shall prevail.

21.0 APPLICATIONS FOR PROGRESS PAYMENTS

21.1 Not more than once a month, the Engineer will submit to the Contractor for review the application for payment, covering the Work completed as of the date of the application. If payment is requested by the Contractor on the basis of materials and equipment not incorporated in the Work but delivered and suitably stored at the site or at another location agreed to in writing, the request for payment shall also be accompanied by such supporting data, satisfactory to the Engineer, as will establish 100% of invoice cost. Such payment to the Contractor shall not exceed seventy-five percent (75%) of the Unit Bid Price. Materials missing or damaged, for which partial or total payment has been made, shall be replaced by the Contractor at his expense.

21.2 The Contractor warrants and guarantees that title to all Work, materials and equipment covered by an application for payment, whether incorporated in the project or not, will have passed to the County prior to the making of the application for payment, free and clear of all liens, claims, security interests and encumbrances (hereafter in these General Conditions referred to as "liens"). The Contractor further warrants and guarantees that no Work, materials or equipment covered by an application for payment will have been acquired by the Contractor or by any other person performing the Work at the site or furnishing materials and equipment for the Project subject to an agreement under which an interest therein or encumbrance thereon is retained by the seller or otherwise imposed by the Contractor or such other person. Non-payment of subcontractors and suppliers will be referred to the Contractor's Surety for resolution. The contractor shall certify compliance with equal employment opportunity provisions and certify disbursements of pervious periodic payment to subcontractors with each application on the forms provided.

21.3 The Engineer will, within ten (10) days after Contractor concurrence of each application for payment, indicate in writing his approval of payment, less any retainage as specified by contract, and present the application to the Clerk of the Court for payment. The Clerk of the Court will within twenty-five (25) days of receipt of an approved application for payment, pay the Contractor the amount approved by the Engineer in accordance with the Prompt Payment Act.

22.0 APPROVAL OF PAYMENTS

22.1 The Engineer’s approval of any payment requested in an application for payment shall constitute a representation by him to the County, based on the Engineer’s on-site observations of the work in progress as an experienced and qualified design professional and on his review of the application for payment and the supporting data, that the Work has progressed to the point indicated; to the best of his knowledge, information and belief, that the quality of the Work is in accordance with the Contract Documents (subject to an evaluation of the Work as a functioning project upon substantial completion, to the results of any subsequent tests called for in the Contract Document and any qualifications stated in his approval); and that the Contractor is entitled to payment of the amount approved.

This is the start of the file's text. The full file is on GovTribe.