Synopsis-Presolicitation Notice FY21- IOI Rehab PH1-3.pdf
PDF 28 KB Posted
- Attached to
- Trunkline and IOI Rehabilitation Phases 1-3
- Solicitation number
- 191BWC21R0002
About this file
This presolicitation notice is for the rehabilitation of approximately 19,730 linear feet of existing sewer pipelines known as the Trunkline and International Outfall Interceptor in Nogales, Arizona. The United States Section of the International Boundary and Water Commission will issue a solicitation to rehabilitate the pipelines in three phases, with an option to rehabilitate an additional 8,634 linear feet in Phase 3. Phase 1 covers 8,556 linear feet from Manhole No. 85 to Manhole No. 99 by the wastewater treatment plant. Phase 2 covers 11,174 linear feet from Manhole No. 1 to Manhole No. 37. Work includes bypass pumping, cleaning, inspection, cured-in-place piping, manhole rehabilitation, and repairs. The contract will be firm-fixed price, with a period of performance of 750 calendar days for Phases 1 and 2, extending an additional 210 days if Phase 3 is awarded. The solicitation is expected to post on December 31, 2020 for a minimum of 30 days on beta.Sam.gov.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Trunkline and IOI Rehabilitation Phases 1-3
Pre-Solicitation Notice
General Description of Work The United States Section of the International Boundary and Water Commission (USIBWC) is issuing a solicitation (negotiated) for the purpose of rehabilitating approximately 19,730 linear feet of the existing sewer pipeline known as the Trunkline and International Outfall Interceptor (IOI) in Nogales, Arizona with an option to rehabilitate an additional 8,634 linear feet.
The existing sewer pipeline, consisting of the Trunkline and the IOI, was installed between 1970 and 1971 and is comprised of unlined, reinforced and unreinforced concrete pipe that ranges in size between 24 inches and 42 inches in diameter. The Trunkline extends approximately 8,146 linear feet from Manhole No. 1 at the United States/Mexico border to almost Manhole No. 27, from which the IOI begins and extends about 38,290 linear feet to Manhole No. 99 at the Nogales International Wastewater Treatment Plant (NIWTP). The pipeline is approximately 46,436 linear feet in total length and has over one hundred (100) manholes within its alignment.
Currently, domestic and industrial wastewater generated in Nogales, Sonora is conveyed north through the main collector line in Mexico and across the border into Nogales, Arizona, where Mexican wastewater is eventually combined with Arizona wastewater in the Trunkline and the IOI for treatment at the NIWTP and discharge into the Santa Cruz River.
The rehabilitation of the Trunkline and IOI is subdivided in to five phases. The work under this Contract is limited to the Phases 1 and 2 of the project with an option to perform Phase 3 and includes rehabilitation of the sewer pipeline and manholes within these segments only. Phase 1 extends from Manhole No. 85 to Manhole No. 99 adjacent to the NIWTP and is approximately 8,556 linear feet with 16 manholes requiring rehabilitation within its alignment. Phase 2 extends from Manhole No. 1 to Manhole No. 37 and is approximately 11,174 linear feet with 22 existing manholes requiring rehabilitation within its alignment. Phase 3 option extends from Manhole No.
37 to Manhole No. 51 and is approximately 8,634 linear feet with 18 manholes requiring rehabilitation within its alignment.
The work is located in Santa Cruz County, Arizona. A site visit date will be listed in the solicitation. The work will be performed under NAICS Code 237110. The contract will be firm-fixed price.
Major Construction Tasks The major construction efforts for rehabilitation include the following tasks:
1. Bypass pumping to maintain sewerage conveyance during rehabilitation;
2. Sewer line cleaning;
3. Television inspection of sewer line;
4. Installation of Cured-in-Place Pipe (CIPP);
5. Installation of Protective Lining Systems in concrete manholes;
6. Rehabilitation of manholes using Carbon Fiber Composite;
7. Installation of new sanitary sewer manholes; and
8. Raising of existing manholes to grade by the use of grade rings or new precast concrete manhole sections.
The magnitude of the project is more than $10,000,000.
The work is located within various Right-of-Ways (ROWs), including the Union Pacific Railroad, City of Nogales, the Arizona Department of Transportation, and Santa Cruz County, and also located within private property. The Contractor shall be responsible for coordinating the work within the various ROWs and private property, and for obtaining all necessary permits and rights of entry for all work required under this Contract before beginning construction within each respective ROW or private property.
The work is located completely within the United States, but a portion of the work is directly adjacent to the international border with Mexico. The Trunkline/IOI is periodically used for illegal drug trafficking across the border. The Contractor shall fully cooperate with the directions of the staff of the U.S. Customs and Border Patrol (CBP) in the event of a security alert and may be required to stop work for any security reasons in the area. Additionally, the Trunkline between Manhole Nos. 1-13 within the existing covered floodway is restricted and Contractor shall have to coordinate with the City of Nogales and CBP for access.
This project requires work to be conducted in the vicinity of or within the Potrero Creek and Nogales Wash. Both the Potrero Creek and Nogales Wash, as well as their tributaries, are listed by the ADEQ as 303[d] Impaired Waters. The Contractor shall comply with the requirements and conditions of the USACE Nationwide Permit (NWP) No. 12, Utility Line Activities and the ADEQ Clean Water Act 401 Water Quality Certification (WQC). Additionally, overflows of the existing sanitary sewer and storm systems in Nogales, Sonora result in increased flows in the Nogales Wash and other waterbodies downstream, which may affect the Contractor’s work.
These flow increases are unexpected, occur throughout the year, and the duration of the event may be unknown. Since the overflows occur in Mexico, there may be no advance warning to the Contractor. The Contractor shall use its judgment on how to handle the sewage and how to proceed with the work when these overflows occur.
Performance Period All Contract work shall be completed within seven hundred fifty (750) calendar days after the Notice to Proceed. An additional two hundred ten (210) calendar days shall be provided for construction if the option for Phase 3 is also awarded.
• Five hundred seventy (570) calendar days for construction of Phases 1 and 2.
• An additional two hundred ten (210) calendar days for construction of Phase 3, if option is awarded.
• The final paperwork for closeout of the Contract shall be completed within one hundred eighty (180) calendar days of completion of the construction.
The time for completion of final paperwork is included in the seven hundred fifty (750) calendar days, or nine hundred sixty (960) calendar days if the option for Phase 3 is also awarded. The time stated for construction completion shall include final cleanup of the premises.
The work located within the Potrero Creek and Nogales Wash, as well as their tributaries, shall not take place during the monsoon season. Monsoon season typically runs from June 15 to
September 30.
The solicitation, plans, and specifications are expected to be posted on or about December 31, 2020 (this is a target date which may slip or change; if the solicitation is not posted on beta.Sam.gov by December 31, 2020 that is because the solicitation is not available for posting).
The solicitation will be available for a minimum of thirty (30) calendar days.
This is a Presolicitation Notice. The Solicitation will include information on how to obtain the plans and specifications. All responsible sources may submit a bid to be considered by the Agency.